A sequence of four tasks is part of the project schedule. Each of the four activities has a finish-start relationship with the next. And each has one day of total float. Currently, activity one and two have been completed on schedule. How many days of float remain in the schedule of these tasks? a. One b. Two c. Four d. Zero .