GBOP Beneficiary Update and Primary Project Summaries
1. Summary of Primary projects Description Duration
(months) Budget
General Board Of Pension & Health
Beneficiary Update This project was initiated because GBOP has records that are stored in various 12 $550,000.00
sources that cause inconsistency and create lags in processing benefits and a
risk that we may pay benefits to the wrong party. It is best practice to provide
participants with a confirmation of their current elections and a tool to update
them.
Some of the key scope items included:
Beneficiary Confirmation showing current designations
Solicitation of updates
New confirmations as we receive and enter updates
Overall strategy for ongoing process including periodic solicitation and confirms
Develop policies regarding beneficiary designations including how we get the
information, when we reject or override a designation, etc.
General Conference Implementation The purpose of this project was to implement the approved 2008 General 18 $300,000.00
Conference petitions. There were a total of 23 Petitions for the Health and
Welfare area. These do not include 7 that were deemed out of scope for this
project because they will be addressed in the Center for Health Project. Also
included in this project are 5 Petitions for Ministry Higher Ed & Superintendency
Petitions, 2 Petitions for Investments, and 37 Petitions for Retirement. Also within
the scope of this project are 13 Petitions that are included as GBOP and 1
Petition that is labeled as Miscellaneous Petitions. This project included the
migration of the current retirement plan for lay from a DB / DC to full DC plan
403B Regulations By January 1, 2009, the General Board needed to be in compliance with the final 7 $25,000.00
403(b) regulations
Hardship withdrawals will be made to eligible participants provided necessary
documentation is received by the participant.
The General Board will be ready to enforce contribution due dates.
By January 1, 2009, the General Board will also be ready to calculate contribution
limits under IRC 415 and 402(g).
2. Summary of Primary projects Description Duration
(months) Budget
Health Care Replacement System This project was initiated to replace the current Health plan system, initially the 6 $1,535,000.00
project was being developed by an outside vendor that didn't have any health
system experience. As the initial project I managed, I worked with GBOP Sr.
Management to identify the key risks and issues as we attempted to move
forward with this plan. The original project budget was over $2.5mil and I felt we
needed to stop throwing good money after bad. Additionally the more we
attempted to make this work, the more we were at risk of not being ready for our
A/E. Once the decision was made to move on, we contracted with another
vendor, who's core competency is health. By creating a small focused team and
working with the vendor, we accomplished this in a 4 month window, with a
greatly reduced budget . New vendor budget was $225,000.00
ITT RCW & McDonnell and Miller
Bigfoot Plant Consolidation This project involved closing down a $50mil facility and merging it into another 1 $8,530,000.00
plant. This program incorporated multiple projects, including cell moves, shipping
and inventory needs, environmental issues, system changes, and construction
needs. The original timeline for this effort was two years and it was completed in
one
Warehouse Management system Warehouse Management System, the major objective of this project was to 6 $140,000.00
purchase, install, and implement a radio frequency system to automate the flow
of data from our shipping department into our MRP system. The costs of the
project was 140K, and had 15 resources on the project, including members from
the business community, Six Sigma Black belt, Local IT department, vendors
and corporate level resources. The main scope of the first phase of this project
was to handle the shipment of finished goods, to include the completion of the
transfer of finished goods, though shipment and invoicing of the orders. The main
impact to the users was the elimination of invalid product shipment, at a first year
cost savings of 54K.
NAFTA Project was an in-house application used to maintain a record of Certificates of 7 Part of dept.
Origin as required under the Free trade agreement. development $
Kronos Timekeeper Upgrade This was the project to upgrade the Time keeping and Payroll interface system at 4 $13,000.00
our unit. While the project was small it was used as a Greenbelt project to create
a vendor selection process.
GroupWise - Outlook Migration McDonnell and Miller was the pilot plant used to migrate from GW to Outlook. 6 Corp. funded
Based on the sucees of this pilot I was also given the responsibility of managing
the migration for the entire Fluid Handling Division and coordinating that effort
with the Corporate project manager.
3. Summary of Primary projects Description Duration
(months) Budget
Novell to Windows 2003 Server Based on the success of using M&M at the pilot plant for the GW project, my 6 Corp. funded
plant was again targeted for that during this project. I assumed the same role
here as in the GW to Outlook project.
Trans Union
TAG System The TAG (Trans Union Attribute Generator) was developed to decrease the 7 $165,000.00
amount of time needed to develop customized attributes by building a repository
of customer attributes that can be utilized by the developers to pick and chose
needed attributes for a promotion. The savings with this was an average of 30%
per promotion, from 4 - 5 weeks to 2 - 3 weeks, with an approximate cost savings
of $6375 per job.
Marketing Service D/B and match update Project was a redevelopment of TU's old and edit match process. This process 24 $350,000.00
involved utilizing new technology to Marketing Services and was a major change
in the way Marketing Services performed its work.
Sears Catalogue
Returns Reporting System A client server based system used to track and report returns. Initial phase of 3 $290,000.00
project was a benchmarking to compare vendors. That phase is the duration
quoted and dollar amounts are for development and hardware for an RS/6000
and required software and licenses.
Moore Business Forms
New Order Management Systems Creation of a front end order system that feed the plant inventory systems and 12 $370,000.00
maintained plant inventory levels and confirmation of shipments