1. ID Task Task Name Duration Start Finish September 1 October 1 November 1
Mode 9/4 9/18 10/2 10/16 10/30 11/13
1 Idea & features 6 days Sat 10/1/11 Fri 10/7/11 Task#1
2 begin idea collecting tools 7 days Sat 10/8/11 Mon 10/17/11 Task#2
3 cloud building search 7 days Mon 10/10/11 Tue 10/18/11 Task#3
4 begin cloud server building 14 days Sat 10/15/11 Wed 11/2/11 Task#4
5 Andriod Study 7 days Sun 10/30/11 Sun 11/6/11 Task#5
6 build UI with Andriod 14 days Mon 11/7/11 Thu 11/24/11 Ta
7 Link Andriod With Cloud 10 days Fri 11/25/11 Thu 12/8/11
8 build map with its feature 11 days Fri 12/9/11 Fri 12/23/11
9 Exams Cut 26 days Sat 12/24/11 Fri 1/27/12 C
10 build map with its feature 11 days Sat 1/28/12 Fri 2/10/12
11 Feature 2 build & test 20 days Sat 2/11/12 Thu 3/8/12
12 Features 3 & Test 20 days Sat 3/10/12 Thu 4/5/12
13 project Test & maintanance 17 days Fri 4/6/12 Mon 4/30/12
14 Project Documentation 23 days Tue 5/1/12 Thu 5/31/12
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Project: Project10 Milestone Inactive Milestone Start-only
Date: Wed 11/16/11 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress
Page 1