SlideShare a Scribd company logo
1 of 7
An overview on the processes to perform
                Maintenance QA for Citi
MRFs
–     MRFs are triggered when either a partner or someone within the organization finds a discrepancy on the retail partner pages which
      requires correction. It can also be created when the retail partner desires to implement new features or change the ones already in
      production.
–     There are three types of MRFs:
•     The ones that are content only handled by CMS
•     AMS (Approval Management System). This is for the Sears marketing page.
•     IT which requires code change.


EMRFs
–     These are very similar to the ones above with the exception on the implementation time. The “E” stands for emergency which changes the
      dynamic and flow of the MRF as it needs to be implemented in the next possible release. As there are several people involved in this type of
      request; the communication and coordination of all parties is vital to complete the task properly.


TRs
–     A TR can be opened at any time, but usually they are open on implementation day or few days later when an issue is found. These are
      categorized by severity.
Documentation, assets, and scheduling

–    Once the document is created, it is send to the production support team who will start assemble the assets required (images, URLs, legal
     sign off, translation, and screenshots) for its implementation.
–    A meeting will be held to determine which would be the most available release to implement the MRF.
–    Teams like CMS and IT will be engaged to start working on the changes requested.
–    At this point the tester can start looking at the assets to analyze the request and secure test accounts, conditioning, or test data.
–    Tester is also responsible to supply the VA team with accounts for their own testing.
1st Round of testing
–        The production support specialist would communicate to the tester when the MRF is ready for testing.
–        Tester would verify the server to be used depending on the type of MRF ( UATxx, BAU, content dropbox and checkbox, or jvssdz0xx)
–        If defects are found during this stage, the tester would send those to the CMS, IT or AMS person in charge to complete the fixes.
–        Tester would also support VA testing in case they need orientation or extra test accounts.


2nd Round of testing
–        Once defects are ready to retest, the tester will go ahead the revalidate and approved if that is the case.
–        Screenshots are taking at all times reflecting the date to avoid any conflict.
Implementation
–      Tester is responsible for defining which MRF can be PRVd. A list will be delivered prior to implementation weekend with the list of MRFs
–      On implementation day, tester would verify in production once is advised by release managers.
–      Tester will reply to the distribution list if the MRFs are approved or not. He/she will also send screenshots when an issue is found, and wait
       for confirmation for retesting.
Deliverables
–       Tester is responsible for taking screenshots during both UAT and PRV stages. Those should be uploaded to their respective folder within the
        Maintenance SP.
–       Power Point is the tool used to save the screenshots.
–       Maintenance log should be updated regularly with the MRF’s status.

More Related Content

Viewers also liked

Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Dr. Joy Kenneth Sala Biasong
 
How to create a quality management plan
How to create a quality management planHow to create a quality management plan
How to create a quality management planQuality Management
 
Components of a quality management system
Components of a quality management systemComponents of a quality management system
Components of a quality management systemselinasimpson311
 
Facilitating Workshop on Quality Assurance Program for MBFI - SW1
Facilitating Workshop on Quality Assurance Program for MBFI - SW1Facilitating Workshop on Quality Assurance Program for MBFI - SW1
Facilitating Workshop on Quality Assurance Program for MBFI - SW1Reynaldo Joson
 
Elements of a Quality System for Medical Devices
Elements of a Quality System for Medical DevicesElements of a Quality System for Medical Devices
Elements of a Quality System for Medical DevicesRaul Soto
 
Quality of maintenance
Quality of maintenanceQuality of maintenance
Quality of maintenanceOdai Assaf
 
Designing a quality management system
Designing a quality management systemDesigning a quality management system
Designing a quality management systemQuality Management
 
Elements Of An Effective Quality Management System
Elements Of An Effective Quality Management SystemElements Of An Effective Quality Management System
Elements Of An Effective Quality Management Systemgauravdhupar
 
Example of quality management system
Example of quality management systemExample of quality management system
Example of quality management systemselinasimpson1701
 
Reliability and Maintenance in production Management
Reliability and Maintenance in production ManagementReliability and Maintenance in production Management
Reliability and Maintenance in production ManagementNazneen sheikh
 
Quality management slides
Quality management slidesQuality management slides
Quality management slidesSaba Afaq
 
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...Andre Barnarde
 
Quality Management System
Quality Management SystemQuality Management System
Quality Management SystemPeter van Dijk
 
Quality management
Quality managementQuality management
Quality managementvishal patel
 

Viewers also liked (20)

Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)Field Implementation Plan on Quality Management System (QMS)
Field Implementation Plan on Quality Management System (QMS)
 
Transferencia
TransferenciaTransferencia
Transferencia
 
How to create a quality management plan
How to create a quality management planHow to create a quality management plan
How to create a quality management plan
 
Components of a quality management system
Components of a quality management systemComponents of a quality management system
Components of a quality management system
 
Facilitating Workshop on Quality Assurance Program for MBFI - SW1
Facilitating Workshop on Quality Assurance Program for MBFI - SW1Facilitating Workshop on Quality Assurance Program for MBFI - SW1
Facilitating Workshop on Quality Assurance Program for MBFI - SW1
 
Edge presentation cmm_final CMMI CSTE CSQA
Edge presentation cmm_final CMMI CSTE CSQAEdge presentation cmm_final CMMI CSTE CSQA
Edge presentation cmm_final CMMI CSTE CSQA
 
Developing quality program
Developing quality programDeveloping quality program
Developing quality program
 
TQM
TQMTQM
TQM
 
Elements of a Quality System for Medical Devices
Elements of a Quality System for Medical DevicesElements of a Quality System for Medical Devices
Elements of a Quality System for Medical Devices
 
Quality of maintenance
Quality of maintenanceQuality of maintenance
Quality of maintenance
 
Qms
QmsQms
Qms
 
Designing a quality management system
Designing a quality management systemDesigning a quality management system
Designing a quality management system
 
Elements Of An Effective Quality Management System
Elements Of An Effective Quality Management SystemElements Of An Effective Quality Management System
Elements Of An Effective Quality Management System
 
Example of quality management system
Example of quality management systemExample of quality management system
Example of quality management system
 
Reliability and Maintenance in production Management
Reliability and Maintenance in production ManagementReliability and Maintenance in production Management
Reliability and Maintenance in production Management
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
Quality management system
Quality management system Quality management system
Quality management system
 
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...
The Five Things You Must Do To Have A Bona Fide Quality Management System Tha...
 
Quality Management System
Quality Management SystemQuality Management System
Quality Management System
 
Quality management
Quality managementQuality management
Quality management
 

Similar to D3 quality assurance overview maintenance

Implementing Vulnerability Management
Implementing Vulnerability Management Implementing Vulnerability Management
Implementing Vulnerability Management Argyle Executive Forum
 
Asp Abstracts, Sample Copy 15+ Abstracts
Asp Abstracts, Sample Copy 15+ AbstractsAsp Abstracts, Sample Copy 15+ Abstracts
Asp Abstracts, Sample Copy 15+ Abstractsncct
 
On the nature of FMECA... An introduction
On the nature of FMECA... An introductionOn the nature of FMECA... An introduction
On the nature of FMECA... An introductionMartGerrand
 
Avoid firefighting: SaaS Based Shop Floor System Framework
Avoid firefighting: SaaS Based Shop Floor System FrameworkAvoid firefighting: SaaS Based Shop Floor System Framework
Avoid firefighting: SaaS Based Shop Floor System FrameworkSatish Nande
 
Preventive Maintenance System
Preventive Maintenance SystemPreventive Maintenance System
Preventive Maintenance Systemlittleb_77
 
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docx
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docxTEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docx
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docxmattinsonjanel
 
Maveric - Automation of Release & Deployment Management
Maveric -  Automation of Release & Deployment ManagementMaveric -  Automation of Release & Deployment Management
Maveric - Automation of Release & Deployment ManagementMaveric Systems
 
Run time Verification using formal methods
Run time Verification using formal methodsRun time Verification using formal methods
Run time Verification using formal methodsSulman Ahmed
 
Running head  SIMPLIFIED PROJECT PLAN .docx
Running head  SIMPLIFIED PROJECT PLAN                          .docxRunning head  SIMPLIFIED PROJECT PLAN                          .docx
Running head  SIMPLIFIED PROJECT PLAN .docxrtodd599
 
Pwc systems-implementation-lessons-learned
Pwc systems-implementation-lessons-learnedPwc systems-implementation-lessons-learned
Pwc systems-implementation-lessons-learnedAvi Kumar
 
IS-1 Short Report [Muhammad Akram Abbasi]
IS-1 Short Report [Muhammad Akram Abbasi]IS-1 Short Report [Muhammad Akram Abbasi]
IS-1 Short Report [Muhammad Akram Abbasi]Akram Abbasi
 
Testing in multiplatform environment
Testing in multiplatform environmentTesting in multiplatform environment
Testing in multiplatform environmentshivanichauhan1953
 
The Complete Web Application Security Testing Checklist
The Complete Web Application Security Testing ChecklistThe Complete Web Application Security Testing Checklist
The Complete Web Application Security Testing ChecklistCigital
 
Ignyte assurance platform NIST RMF datasheet.
Ignyte assurance platform NIST RMF datasheet.Ignyte assurance platform NIST RMF datasheet.
Ignyte assurance platform NIST RMF datasheet.Ignyte Assurance Platform
 
Framework for Evaluating Martech
Framework for Evaluating Martech Framework for Evaluating Martech
Framework for Evaluating Martech Blue Leopard LLC
 

Similar to D3 quality assurance overview maintenance (20)

Asset Tracking Systems for Meter Services
Asset Tracking Systems for Meter ServicesAsset Tracking Systems for Meter Services
Asset Tracking Systems for Meter Services
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
Implementing Vulnerability Management
Implementing Vulnerability Management Implementing Vulnerability Management
Implementing Vulnerability Management
 
Asp Abstracts, Sample Copy 15+ Abstracts
Asp Abstracts, Sample Copy 15+ AbstractsAsp Abstracts, Sample Copy 15+ Abstracts
Asp Abstracts, Sample Copy 15+ Abstracts
 
Meter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni'sMeter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni's
 
On the nature of FMECA... An introduction
On the nature of FMECA... An introductionOn the nature of FMECA... An introduction
On the nature of FMECA... An introduction
 
Avoid firefighting: SaaS Based Shop Floor System Framework
Avoid firefighting: SaaS Based Shop Floor System FrameworkAvoid firefighting: SaaS Based Shop Floor System Framework
Avoid firefighting: SaaS Based Shop Floor System Framework
 
Preventive Maintenance System
Preventive Maintenance SystemPreventive Maintenance System
Preventive Maintenance System
 
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docx
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docxTEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docx
TEAM CAPSTONESECTIONS VI & VIIPROJECT MANAGE.docx
 
Vivek G
Vivek GVivek G
Vivek G
 
Maveric - Automation of Release & Deployment Management
Maveric -  Automation of Release & Deployment ManagementMaveric -  Automation of Release & Deployment Management
Maveric - Automation of Release & Deployment Management
 
Run time Verification using formal methods
Run time Verification using formal methodsRun time Verification using formal methods
Run time Verification using formal methods
 
Meter Asset Tracking and the Power of Analytics in an AMI System
Meter Asset Tracking and the Power of Analytics in an AMI SystemMeter Asset Tracking and the Power of Analytics in an AMI System
Meter Asset Tracking and the Power of Analytics in an AMI System
 
Running head  SIMPLIFIED PROJECT PLAN .docx
Running head  SIMPLIFIED PROJECT PLAN                          .docxRunning head  SIMPLIFIED PROJECT PLAN                          .docx
Running head  SIMPLIFIED PROJECT PLAN .docx
 
Pwc systems-implementation-lessons-learned
Pwc systems-implementation-lessons-learnedPwc systems-implementation-lessons-learned
Pwc systems-implementation-lessons-learned
 
IS-1 Short Report [Muhammad Akram Abbasi]
IS-1 Short Report [Muhammad Akram Abbasi]IS-1 Short Report [Muhammad Akram Abbasi]
IS-1 Short Report [Muhammad Akram Abbasi]
 
Testing in multiplatform environment
Testing in multiplatform environmentTesting in multiplatform environment
Testing in multiplatform environment
 
The Complete Web Application Security Testing Checklist
The Complete Web Application Security Testing ChecklistThe Complete Web Application Security Testing Checklist
The Complete Web Application Security Testing Checklist
 
Ignyte assurance platform NIST RMF datasheet.
Ignyte assurance platform NIST RMF datasheet.Ignyte assurance platform NIST RMF datasheet.
Ignyte assurance platform NIST RMF datasheet.
 
Framework for Evaluating Martech
Framework for Evaluating Martech Framework for Evaluating Martech
Framework for Evaluating Martech
 

D3 quality assurance overview maintenance

  • 1. An overview on the processes to perform Maintenance QA for Citi
  • 2.
  • 3. MRFs – MRFs are triggered when either a partner or someone within the organization finds a discrepancy on the retail partner pages which requires correction. It can also be created when the retail partner desires to implement new features or change the ones already in production. – There are three types of MRFs: • The ones that are content only handled by CMS • AMS (Approval Management System). This is for the Sears marketing page. • IT which requires code change. EMRFs – These are very similar to the ones above with the exception on the implementation time. The “E” stands for emergency which changes the dynamic and flow of the MRF as it needs to be implemented in the next possible release. As there are several people involved in this type of request; the communication and coordination of all parties is vital to complete the task properly. TRs – A TR can be opened at any time, but usually they are open on implementation day or few days later when an issue is found. These are categorized by severity.
  • 4. Documentation, assets, and scheduling – Once the document is created, it is send to the production support team who will start assemble the assets required (images, URLs, legal sign off, translation, and screenshots) for its implementation. – A meeting will be held to determine which would be the most available release to implement the MRF. – Teams like CMS and IT will be engaged to start working on the changes requested. – At this point the tester can start looking at the assets to analyze the request and secure test accounts, conditioning, or test data. – Tester is also responsible to supply the VA team with accounts for their own testing.
  • 5. 1st Round of testing – The production support specialist would communicate to the tester when the MRF is ready for testing. – Tester would verify the server to be used depending on the type of MRF ( UATxx, BAU, content dropbox and checkbox, or jvssdz0xx) – If defects are found during this stage, the tester would send those to the CMS, IT or AMS person in charge to complete the fixes. – Tester would also support VA testing in case they need orientation or extra test accounts. 2nd Round of testing – Once defects are ready to retest, the tester will go ahead the revalidate and approved if that is the case. – Screenshots are taking at all times reflecting the date to avoid any conflict.
  • 6. Implementation – Tester is responsible for defining which MRF can be PRVd. A list will be delivered prior to implementation weekend with the list of MRFs – On implementation day, tester would verify in production once is advised by release managers. – Tester will reply to the distribution list if the MRFs are approved or not. He/she will also send screenshots when an issue is found, and wait for confirmation for retesting.
  • 7. Deliverables – Tester is responsible for taking screenshots during both UAT and PRV stages. Those should be uploaded to their respective folder within the Maintenance SP. – Power Point is the tool used to save the screenshots. – Maintenance log should be updated regularly with the MRF’s status.