SlideShare a Scribd company logo
1 of 9
Download to read offline
Balance Cost To Complete Report
Quantity Value
Actual
Quantity
Actual
Cost Quantity
forecast
Cost
A B C D E F G=D+F H=B - G
Remarks:
This report shows an expected outcome of a project in terms of meeting cost targets set at the bid level.
Any negative variations will be further analysed.
BOQ
Actual Progress upto
Sept-2010 Balance to CompleteBOQ
Item/WP/C
ost Center
Total
Projected
Cost
Diff in Bid Cost
and Actual
expected cost
Cash Operating Cycle of a Project Jan-10
No of Days required to receive Progress Invoices 80
No of days Material is in Stock 15
No of days to pay labour 35*14% -4.9
No of days to pay Subcontractors 50*60% -30
No of days to pay other expenses and purchases 35*26% -9.1
Cash Operating Cycle of a project 51 days
Remarks:
Developed by:
Abdul Kashif
This report shows that it takes 51 days to convert our periodic investments into the projects to be
returned back into our bank accounts with profit. Therefore, we must be able to finance 51 days
through our own capital or through external financing. An increase in Cash Operating Cycle due
to any reason e.g. Client is delaying payment, will require us to make arrangements of additional
financing.
Project wise return on Investments
Project-1 Project-2 Project-3 Project-4 Project-5 Project-6
(Millions)
Material on Site 80
Accounts Receivables 400
Advances to suppliers 150
Other current assets 300
Fixed Assets 600
Total Assets 1530
Accounts Payables 150
Net Investments 1380
Gross Profit 90
Return on Investments 6.52%
Remarks:
The solution can be:
Either increase profit margin by decreasing cost
Decrease investments such as reduction in receivables, obsolete materials
Increase Payables as an alternative of decrease in investments.
Through above three choices Return on Investment on a Project can be increased.
Any project which is earning less than the desired Return on Investment will be analysed further for
causes of lower profitability
Proportion of Cost Elements in Total Cost
Amount %age Amount %age Amount %age
Gen. Req. 13 15 11
Labor 4 15 16
Subcon (Apply
Only) 5 5 5
Material 14 20 25
Others
1 2 1
Equipment 2 2 2
Subcon (S&A) 61 41 40
Total Cost 100% 100% 100%
Remarks:
Actual amounts deleted from the original report
Developed by:
Abdul Kashif
Original Budget Jan-10 Sep-10
Cost Items
This table and accompanied graph shows how cost structure is deviating from the budget. In the above case
Subcontractor (S&A) is decreasing while Material cost is increasing-this means we are taking jobs from
Subcontractors and doing them ourselves.
0
10
20
30
40
50
60
70
1 2 3
General Requirements
Labor
Subcon (Apply Only)
Material
Others
Equipment
Subcon (S&A)
Historial analysis of Revenue and Cost
Periods Revenue Total Cost Gross Profit
Jan-10 700 735 -35
Feb-10 800 856 -56
Mar-10 850 807.5 42.5
May-10 900 819 81
Jun-10 950 883.5 66.5
Jul-10 1010 858.5 151.5
Aug-10 970 776 194
Sep-10 950 760 190
(Figures are hypothetical)
Remarks: This table highlights historical performance of a particular project and describe different phasis of its profitability cycle.
Management may be interested to explore more any sharp deviations in a particular period.
-200
0
200
400
600
800
1000
1200
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10
Revenue
Total Cost
Gross Profit
Historial analysis of Revenue and Cost
Periods Revenue Material Labour SubcontracTotal Cost Gross Profit
Jan-10 700 257.25 36.75 441 735 -35
Feb-10 800 299.6 128.4 428 856 -56
Mar-10 850 282.625 201.875 323 807.5 42.5
Apr-10 825 262.7625 225.225 262.7625 750.75 74.25
May-10 900 286.65 245.7 286.65 819 81
Jun-10 950 309.225 247.38 326.895 883.5 66.5
Jul-10 1010 300.475 214.625 343.4 858.5 151.5
Aug-10 970 271.6 186.24 318.16 776 194
Sep-10 950 266 197.6 296.4 760 190
Remarks:
This table and accompanied graph shows how components of Total Costs are moving during the period.
Subcontract cost decreased while labour cost increased.
Perhaps now project is coming down from its peak activity. Is there any chance to further reduce
the labour and over head expenses?
This and similar analysis will provide an opportunity to look into the future requirements of the project
-200
0
200
400
600
800
1000
1200
Revenue
Material
Labour
Subcontract
Gross Profit
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10
Cash Inflow
Cash Outflow
Excess (Shortfall)
Opening Balance
Closing Balance
Remarks:
This is a very simplified version of actual Rolling Cash Flow of a project. Based on future
Revenue and expenses, a projected Cash Statement is prepared to enable Management
to arrange necessary finances at appropriate time; or withdraw excess funds.
Planning Quantities
Assumptions
Working Hours/Day 16
Data
Crusher (O&M) 100 Rs/cum
Generator POL Consumption
Diesel Consumption 78.1 ltr/hr Rs
Deisel Rate 38.1 Rs/hr
Oil change 1 change per 550 hr 11,000
Oil filter change 1 change per 550 hr 2,100
Air filter change 1 change per 1000 hr 20,000
Fuel filter change 1 change per 1100 hr 1,835
Lease Cost 1,200,000 Rs/month
Manpower Crew Cost 1,010 Rs/hr
Other Equipment
Dumpers
Qty 20 Units
Rent 95,000 Rs/month
Diesel Consumption 10 ltr/hr
Excavator
Qty 2 Units
Rent 150,000 Rs/month
Diesel Consumption 10 ltr/hr
Loader
Qty 2 Units
Rent 160,000
Diesel Consumption 10 ltr/hr
Raw Material 275 Rs/dumper
Description Qty Units Remarks
Total Qty Required (Planning) 125,534 cum
Production 95 cum/hr
Hours Required 1,321 hr
Months 4 months 16 hrs/day
250 TPH Crusher Plant
Cost & Benefit Analysis
This Capex analysis were made to
establish Crush Plant for a road project.
In organizations where Capex decisions
are regularly made, this template can
expedite and improve decision-making
process
COSTS Rs
POL (500 KVA) 3,992,109
Other Equipment
Dumpers 7,600,381
Excavator 1,200,381
Loader 1,280,381
Lease 4,800,000 #REF!
Raw Material 3,797,404
Crusher (O&M) 12,553,400 6
Manpower 1,334,625 #REF!
Total 36,558,680
Decision:
291.23 Rs./cum We should
8.25 Rs./cft establish our
514.00 Rs./cum own plant
14.55 Rs./cft
Savings 27,965,796 Rs
DEL Rate
Market Rate

More Related Content

What's hot

What's hot (19)

Bsec
BsecBsec
Bsec
 
Presentation 5
Presentation 5Presentation 5
Presentation 5
 
Depreciation Tax Shield | Finance
Depreciation Tax Shield | FinanceDepreciation Tax Shield | Finance
Depreciation Tax Shield | Finance
 
Xyz company
Xyz companyXyz company
Xyz company
 
Depreciation made easy !
Depreciation made easy !Depreciation made easy !
Depreciation made easy !
 
STRATERGIC COST MANAGEMENT
STRATERGIC COST MANAGEMENT STRATERGIC COST MANAGEMENT
STRATERGIC COST MANAGEMENT
 
Statistical Forecast - Business Case, Final
Statistical Forecast - Business Case, FinalStatistical Forecast - Business Case, Final
Statistical Forecast - Business Case, Final
 
Depreciation | Accounting
Depreciation | AccountingDepreciation | Accounting
Depreciation | Accounting
 
Target
TargetTarget
Target
 
OPERATION MANAGEMENT : Aggregate Planning for washing machine
OPERATION MANAGEMENT : Aggregate Planning for washing machineOPERATION MANAGEMENT : Aggregate Planning for washing machine
OPERATION MANAGEMENT : Aggregate Planning for washing machine
 
Depreciation
DepreciationDepreciation
Depreciation
 
Cost Segregation Studies
Cost Segregation StudiesCost Segregation Studies
Cost Segregation Studies
 
Boeing Case Study Competition
Boeing Case Study CompetitionBoeing Case Study Competition
Boeing Case Study Competition
 
Depreciation
DepreciationDepreciation
Depreciation
 
O&M Budgeting
O&M BudgetingO&M Budgeting
O&M Budgeting
 
Cushman & Wakefield Q1 2017 Industrial Calgary Marketbeat
Cushman & Wakefield Q1 2017 Industrial Calgary MarketbeatCushman & Wakefield Q1 2017 Industrial Calgary Marketbeat
Cushman & Wakefield Q1 2017 Industrial Calgary Marketbeat
 
Diamond Chemicals
Diamond ChemicalsDiamond Chemicals
Diamond Chemicals
 
Depreciation
DepreciationDepreciation
Depreciation
 
Depreciation accounting
Depreciation accountingDepreciation accounting
Depreciation accounting
 

Similar to Cost To Complete Report Shows Projection of Costs

Cost-benefit analysis -2
Cost-benefit analysis -2Cost-benefit analysis -2
Cost-benefit analysis -2Gashaw Abebe
 
SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )Peter Ezzat
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxKhaled Jomaa
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxSIBANJAN MISHRA
 
Capital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation SlidesCapital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation SlidesSlideTeam
 
Financial Forecasting & Planning
Financial Forecasting & PlanningFinancial Forecasting & Planning
Financial Forecasting & Planningtintin_leo
 
UTSFinmagecapitalbugproject
UTSFinmagecapitalbugprojectUTSFinmagecapitalbugproject
UTSFinmagecapitalbugprojectJoshua C
 
PPAM-AK PPT.pptx
PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptxShyam273559
 
Q3 2015 Investor Call Slides
Q3 2015 Investor Call Slides Q3 2015 Investor Call Slides
Q3 2015 Investor Call Slides broadwind
 
Checklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting CompanyChecklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting Companykashif khawja
 
Chapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsChapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsAKSHAYA0000
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economicsChirag Jain
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesSlideTeam
 
Q215 investor call slides final
Q215 investor call slides finalQ215 investor call slides final
Q215 investor call slides finalbroadwind
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisalDhwani Shah
 

Similar to Cost To Complete Report Shows Projection of Costs (20)

How to assess working capital requirement
How to assess working capital requirementHow to assess working capital requirement
How to assess working capital requirement
 
Cost-benefit analysis -2
Cost-benefit analysis -2Cost-benefit analysis -2
Cost-benefit analysis -2
 
SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
Capital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation SlidesCapital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation Slides
 
Introduction to project economics in oil and gas upstream industry
Introduction to project economics in oil and gas upstream industryIntroduction to project economics in oil and gas upstream industry
Introduction to project economics in oil and gas upstream industry
 
Planning Document.pptx
Planning Document.pptxPlanning Document.pptx
Planning Document.pptx
 
Financial Forecasting & Planning
Financial Forecasting & PlanningFinancial Forecasting & Planning
Financial Forecasting & Planning
 
UTSFinmagecapitalbugproject
UTSFinmagecapitalbugprojectUTSFinmagecapitalbugproject
UTSFinmagecapitalbugproject
 
Incurred_Cost_Submissions
Incurred_Cost_SubmissionsIncurred_Cost_Submissions
Incurred_Cost_Submissions
 
PPAM-AK PPT.pptx
PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptx
 
Q3 2015 Investor Call Slides
Q3 2015 Investor Call Slides Q3 2015 Investor Call Slides
Q3 2015 Investor Call Slides
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
 
Checklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting CompanyChecklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting Company
 
Chapter13 specialdecisionsituations
Chapter13 specialdecisionsituationsChapter13 specialdecisionsituations
Chapter13 specialdecisionsituations
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economics
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation Slides
 
Q215 investor call slides final
Q215 investor call slides finalQ215 investor call slides final
Q215 investor call slides final
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisal
 

Cost To Complete Report Shows Projection of Costs

  • 1. Balance Cost To Complete Report Quantity Value Actual Quantity Actual Cost Quantity forecast Cost A B C D E F G=D+F H=B - G Remarks: This report shows an expected outcome of a project in terms of meeting cost targets set at the bid level. Any negative variations will be further analysed. BOQ Actual Progress upto Sept-2010 Balance to CompleteBOQ Item/WP/C ost Center Total Projected Cost Diff in Bid Cost and Actual expected cost
  • 2. Cash Operating Cycle of a Project Jan-10 No of Days required to receive Progress Invoices 80 No of days Material is in Stock 15 No of days to pay labour 35*14% -4.9 No of days to pay Subcontractors 50*60% -30 No of days to pay other expenses and purchases 35*26% -9.1 Cash Operating Cycle of a project 51 days Remarks: Developed by: Abdul Kashif This report shows that it takes 51 days to convert our periodic investments into the projects to be returned back into our bank accounts with profit. Therefore, we must be able to finance 51 days through our own capital or through external financing. An increase in Cash Operating Cycle due to any reason e.g. Client is delaying payment, will require us to make arrangements of additional financing.
  • 3. Project wise return on Investments Project-1 Project-2 Project-3 Project-4 Project-5 Project-6 (Millions) Material on Site 80 Accounts Receivables 400 Advances to suppliers 150 Other current assets 300 Fixed Assets 600 Total Assets 1530 Accounts Payables 150 Net Investments 1380 Gross Profit 90 Return on Investments 6.52% Remarks: The solution can be: Either increase profit margin by decreasing cost Decrease investments such as reduction in receivables, obsolete materials Increase Payables as an alternative of decrease in investments. Through above three choices Return on Investment on a Project can be increased. Any project which is earning less than the desired Return on Investment will be analysed further for causes of lower profitability
  • 4. Proportion of Cost Elements in Total Cost Amount %age Amount %age Amount %age Gen. Req. 13 15 11 Labor 4 15 16 Subcon (Apply Only) 5 5 5 Material 14 20 25 Others 1 2 1 Equipment 2 2 2 Subcon (S&A) 61 41 40 Total Cost 100% 100% 100% Remarks: Actual amounts deleted from the original report Developed by: Abdul Kashif Original Budget Jan-10 Sep-10 Cost Items This table and accompanied graph shows how cost structure is deviating from the budget. In the above case Subcontractor (S&A) is decreasing while Material cost is increasing-this means we are taking jobs from Subcontractors and doing them ourselves. 0 10 20 30 40 50 60 70 1 2 3 General Requirements Labor Subcon (Apply Only) Material Others Equipment Subcon (S&A)
  • 5. Historial analysis of Revenue and Cost Periods Revenue Total Cost Gross Profit Jan-10 700 735 -35 Feb-10 800 856 -56 Mar-10 850 807.5 42.5 May-10 900 819 81 Jun-10 950 883.5 66.5 Jul-10 1010 858.5 151.5 Aug-10 970 776 194 Sep-10 950 760 190 (Figures are hypothetical) Remarks: This table highlights historical performance of a particular project and describe different phasis of its profitability cycle. Management may be interested to explore more any sharp deviations in a particular period. -200 0 200 400 600 800 1000 1200 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Revenue Total Cost Gross Profit
  • 6. Historial analysis of Revenue and Cost Periods Revenue Material Labour SubcontracTotal Cost Gross Profit Jan-10 700 257.25 36.75 441 735 -35 Feb-10 800 299.6 128.4 428 856 -56 Mar-10 850 282.625 201.875 323 807.5 42.5 Apr-10 825 262.7625 225.225 262.7625 750.75 74.25 May-10 900 286.65 245.7 286.65 819 81 Jun-10 950 309.225 247.38 326.895 883.5 66.5 Jul-10 1010 300.475 214.625 343.4 858.5 151.5 Aug-10 970 271.6 186.24 318.16 776 194 Sep-10 950 266 197.6 296.4 760 190 Remarks: This table and accompanied graph shows how components of Total Costs are moving during the period. Subcontract cost decreased while labour cost increased. Perhaps now project is coming down from its peak activity. Is there any chance to further reduce the labour and over head expenses? This and similar analysis will provide an opportunity to look into the future requirements of the project -200 0 200 400 600 800 1000 1200 Revenue Material Labour Subcontract Gross Profit
  • 7. Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Cash Inflow Cash Outflow Excess (Shortfall) Opening Balance Closing Balance Remarks: This is a very simplified version of actual Rolling Cash Flow of a project. Based on future Revenue and expenses, a projected Cash Statement is prepared to enable Management to arrange necessary finances at appropriate time; or withdraw excess funds.
  • 8. Planning Quantities Assumptions Working Hours/Day 16 Data Crusher (O&M) 100 Rs/cum Generator POL Consumption Diesel Consumption 78.1 ltr/hr Rs Deisel Rate 38.1 Rs/hr Oil change 1 change per 550 hr 11,000 Oil filter change 1 change per 550 hr 2,100 Air filter change 1 change per 1000 hr 20,000 Fuel filter change 1 change per 1100 hr 1,835 Lease Cost 1,200,000 Rs/month Manpower Crew Cost 1,010 Rs/hr Other Equipment Dumpers Qty 20 Units Rent 95,000 Rs/month Diesel Consumption 10 ltr/hr Excavator Qty 2 Units Rent 150,000 Rs/month Diesel Consumption 10 ltr/hr Loader Qty 2 Units Rent 160,000 Diesel Consumption 10 ltr/hr Raw Material 275 Rs/dumper Description Qty Units Remarks Total Qty Required (Planning) 125,534 cum Production 95 cum/hr Hours Required 1,321 hr Months 4 months 16 hrs/day 250 TPH Crusher Plant Cost & Benefit Analysis This Capex analysis were made to establish Crush Plant for a road project. In organizations where Capex decisions are regularly made, this template can expedite and improve decision-making process
  • 9. COSTS Rs POL (500 KVA) 3,992,109 Other Equipment Dumpers 7,600,381 Excavator 1,200,381 Loader 1,280,381 Lease 4,800,000 #REF! Raw Material 3,797,404 Crusher (O&M) 12,553,400 6 Manpower 1,334,625 #REF! Total 36,558,680 Decision: 291.23 Rs./cum We should 8.25 Rs./cft establish our 514.00 Rs./cum own plant 14.55 Rs./cft Savings 27,965,796 Rs DEL Rate Market Rate