Applicable Charges for Group Captive Open access- UP (SOLAR)
Details ChargesforFY2018-19
TransmissionLoss 3.67%
TransmissionCharge (Rs/kWh) 0.1185
WheelingChargeabove11KVSubstation (Rsin
kWh)
0.215
WheelingLoss(DrawlofVoltageabove11KV) 4.00%
CrossSubsidyCharges Nil
AdditionalSurcharge Nil
ElectricityDuty Electricity duty for ten years shall be
exempted for sale to Distribution
licensee, captive/Group captive
consumption and third party sale in
respect of all solar projects set up
within the state.
Banking Banking of energy in every financial
year shall be permitted
Document necessary for Open Access
Registration
Documents to (Injecting Entity)
1. Connectivity Agreement the Enclosure of Format ST-11 duly signed and
properly dispatched by concerned Transmission/Distribution Licensee.
2. Certified copy of Single Line Diagram issued by concerned
Transmission/Distribution Licensee which clearly mentions the position of
interface ABT Meter details i.e., ABT Meter Number,CTR, PTR and overall MF
3. The certified copy of Interface ABT Meter sealing Certificates/Documents
issued by Transmission and / or Distribution Licensee, as applicable.
4. The Loading Pattern of last one year on monthly basis i.e., Maximum,
Minimum and Average values of MW & MVAR of Lines and Transformers of
connected Transmission/Distribution Substation issued by concerned
Transmission/Distribution Licensee.
5. Last DSM bill issued by UPSLDC in case of Intra-state entity whose ABT
Scheduling and DSM billing is being carried out by UPSLDC. In such cases,
document of Sl. No. 3 and 4 need not be ed unless there is a change in the
ABT metering status / configuration.
Documents to (Drawee Entity)
1. Connectivity agreement in case of STU connected consumers. However, if
consumer is connected with Distribution network, the latest bill issued by
Discom may be ed.
2. Certificate for validation of Discom Consumer details along with
concurrence/ NOC for distribution system, in case of Discom consumer is
beneficiary/drawee entity. Please refer UPSLDC website for Format.
3. The Enclosure of Format ST-11 duly signed and properly dispatched by
concerned Transmission Licensee (Transmission Substation end)
4. The Enclosure of Format ST-11 duly signed and properly dispatched by
concerned Distribution Licensee (Distribution
Substation/DiscoConsumer/Beneficiary end)
5. Certified copy of Single Line Diagram issued by concerned
Transmission/Distribution Licensee which clearly mentions the position of
interface ABT Meter details i.e., ABT Meter Number, CTR, PTR and overall
MF
6. The certified copy of Interface ABT Meter sealing Certificates/Documents
issued by Transmission and / or Distribution Licensee, as applicable.
7. The Loading Pattern of last one year on monthly basis i.e., Maximum,
Minimum and Average values of MW & MVAR of Lines and Transformers of
connected Transmission/Distribution Substation issued by concerned
Transmission/Distribution Licensee.
8. Last DSM bill issued by UPSLDC in case of Intra-state entity whose ABT
Scheduling and DSM billing is being carried out by UPSLDC. In such cases,
document of Sl. No. 5 and 6 need not be ed unless there is a change in the
ABT metering status / configuration.
Incentives:-
For grid connectivity of Solar projects of capacity 5 MW and above proposed to be
set up in Bundelkhand and Purvanchal region, State Government will bear the cost
for construction of maximum transmission line length as follows:-
 For 05 to 10 Megawatt capacity-10 Kilometer
 For >10 megawatt to 50 megawatt capacity -15 Kilometer
 For >50 megawatt capacity - 20 Kilometer.

More Related Content

What's hot

Home Value DFW CBS C Corson 9-21-2015
Home Value DFW  CBS  C Corson 9-21-2015Home Value DFW  CBS  C Corson 9-21-2015
Home Value DFW CBS C Corson 9-21-2015CBS/KLUV Radio
 
Vehicles tracking and braking system in traffic
Vehicles tracking and braking system in trafficVehicles tracking and braking system in traffic
Vehicles tracking and braking system in trafficEcwayt
 
Us wireless cable television
Us wireless cable televisionUs wireless cable television
Us wireless cable televisionPoojith Chowdhary
 
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...Fingrid Oyj
 
Overview of REC Mechanism in India
Overview of REC Mechanism in IndiaOverview of REC Mechanism in India
Overview of REC Mechanism in IndiaVedant Sonkhiya
 
Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)Jay Ranvir
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policyJay Ranvir
 

What's hot (10)

Home Value DFW CBS C Corson 9-21-2015
Home Value DFW  CBS  C Corson 9-21-2015Home Value DFW  CBS  C Corson 9-21-2015
Home Value DFW CBS C Corson 9-21-2015
 
Vehicles tracking and braking system in traffic
Vehicles tracking and braking system in trafficVehicles tracking and braking system in traffic
Vehicles tracking and braking system in traffic
 
Us wireless cable television
Us wireless cable televisionUs wireless cable television
Us wireless cable television
 
Epira ra9136
Epira ra9136Epira ra9136
Epira ra9136
 
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...
Electricity Market Day 2015 - Jouni Mäenpää, Power-Deriva - Comments from mar...
 
netsci15_UP1
netsci15_UP1netsci15_UP1
netsci15_UP1
 
Overview of REC Mechanism in India
Overview of REC Mechanism in IndiaOverview of REC Mechanism in India
Overview of REC Mechanism in India
 
Igor Rozkladai
Igor RozkladaiIgor Rozkladai
Igor Rozkladai
 
Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policy
 

Similar to Applicable charges for group captive open access up solar

Protocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateProtocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateJay Ranvir
 
Open access charges chhattisgarh
Open access charges chhattisgarhOpen access charges chhattisgarh
Open access charges chhattisgarhJay Ranvir
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access MaharashtraJay Ranvir
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9Manoj kumar Rana
 
Power procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationPower procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationAmitava Nag
 
Public consultation on access deficit contribution
Public consultation on access deficit contributionPublic consultation on access deficit contribution
Public consultation on access deficit contributiontraoman
 
Transmission congestion management effects on reducing cost of bilateral mark...
Transmission congestion management effects on reducing cost of bilateral mark...Transmission congestion management effects on reducing cost of bilateral mark...
Transmission congestion management effects on reducing cost of bilateral mark...IRJET Journal
 
Contract Availability for LRET Development
Contract Availability for LRET DevelopmentContract Availability for LRET Development
Contract Availability for LRET DevelopmentSimon Mathis
 
Pre_consultation_paper_on_interoperablity_final
Pre_consultation_paper_on_interoperablity_finalPre_consultation_paper_on_interoperablity_final
Pre_consultation_paper_on_interoperablity_finalKanika Jain
 
2015 Connecticut Legislative Session Presentation (2)
2015 Connecticut Legislative Session Presentation (2)2015 Connecticut Legislative Session Presentation (2)
2015 Connecticut Legislative Session Presentation (2)Nicholas Cicale
 
169 rules&proc
169 rules&proc169 rules&proc
169 rules&proctraoman
 
112/2009 1-
112/2009 1-112/2009 1-
112/2009 1-traoman
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyJay Ranvir
 
Forecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forForecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forJay Ranvir
 

Similar to Applicable charges for group captive open access up solar (20)

test E4.pptx
test E4.pptxtest E4.pptx
test E4.pptx
 
Protocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateProtocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificate
 
Power Market regulation
Power Market regulationPower Market regulation
Power Market regulation
 
Erpc pres 100810
Erpc pres 100810Erpc pres 100810
Erpc pres 100810
 
TBCB_29032019.pptx
TBCB_29032019.pptxTBCB_29032019.pptx
TBCB_29032019.pptx
 
Cerc
CercCerc
Cerc
 
Open access charges chhattisgarh
Open access charges chhattisgarhOpen access charges chhattisgarh
Open access charges chhattisgarh
 
Distribution open access Maharashtra
Distribution open access  MaharashtraDistribution open access  Maharashtra
Distribution open access Maharashtra
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9
 
Power procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationPower procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle Generation
 
Public consultation on access deficit contribution
Public consultation on access deficit contributionPublic consultation on access deficit contribution
Public consultation on access deficit contribution
 
Transmission congestion management effects on reducing cost of bilateral mark...
Transmission congestion management effects on reducing cost of bilateral mark...Transmission congestion management effects on reducing cost of bilateral mark...
Transmission congestion management effects on reducing cost of bilateral mark...
 
Contract Availability for LRET Development
Contract Availability for LRET DevelopmentContract Availability for LRET Development
Contract Availability for LRET Development
 
Pre_consultation_paper_on_interoperablity_final
Pre_consultation_paper_on_interoperablity_finalPre_consultation_paper_on_interoperablity_final
Pre_consultation_paper_on_interoperablity_final
 
2015 Connecticut Legislative Session Presentation (2)
2015 Connecticut Legislative Session Presentation (2)2015 Connecticut Legislative Session Presentation (2)
2015 Connecticut Legislative Session Presentation (2)
 
169 rules&proc
169 rules&proc169 rules&proc
169 rules&proc
 
112/2009 1-
112/2009 1-112/2009 1-
112/2009 1-
 
AFCS_PQConference.pdf
AFCS_PQConference.pdfAFCS_PQConference.pdf
AFCS_PQConference.pdf
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind Energy
 
Forecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forForecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling for
 

More from Jay Ranvir

Open access mp
Open access mpOpen access mp
Open access mpJay Ranvir
 
Profile on the production retreaded tyre
Profile on the production retreaded tyreProfile on the production retreaded tyre
Profile on the production retreaded tyreJay Ranvir
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessJay Ranvir
 
Open Access Charges Rajasthan
Open Access Charges RajasthanOpen Access Charges Rajasthan
Open Access Charges RajasthanJay Ranvir
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demandsJay Ranvir
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015Jay Ranvir
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draftJay Ranvir
 
Notified f &s regulations 2018
Notified f &s  regulations 2018Notified f &s  regulations 2018
Notified f &s regulations 2018Jay Ranvir
 
Detailed comparison of capex vs opex
Detailed comparison of capex vs opexDetailed comparison of capex vs opex
Detailed comparison of capex vs opexJay Ranvir
 
Plastics to oil report
Plastics to oil reportPlastics to oil report
Plastics to oil reportJay Ranvir
 
Detail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantDetail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantJay Ranvir
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sourcesJay Ranvir
 
Verification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationVerification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationJay Ranvir
 
Short term open access status for march 17
Short term open access status for march 17Short term open access status for march 17
Short term open access status for march 17Jay Ranvir
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)Jay Ranvir
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)Jay Ranvir
 
Ppa model presentation
Ppa model presentationPpa model presentation
Ppa model presentationJay Ranvir
 
Sbi rooftop program
Sbi rooftop programSbi rooftop program
Sbi rooftop programJay Ranvir
 

More from Jay Ranvir (20)

Open access mp
Open access mpOpen access mp
Open access mp
 
Profile on the production retreaded tyre
Profile on the production retreaded tyreProfile on the production retreaded tyre
Profile on the production retreaded tyre
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading Process
 
Ch21
Ch21Ch21
Ch21
 
Open Access Charges Rajasthan
Open Access Charges RajasthanOpen Access Charges Rajasthan
Open Access Charges Rajasthan
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demands
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draft
 
Notified f &s regulations 2018
Notified f &s  regulations 2018Notified f &s  regulations 2018
Notified f &s regulations 2018
 
Detailed comparison of capex vs opex
Detailed comparison of capex vs opexDetailed comparison of capex vs opex
Detailed comparison of capex vs opex
 
Plastics to oil report
Plastics to oil reportPlastics to oil report
Plastics to oil report
 
Detail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantDetail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plant
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sources
 
Verification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationVerification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligation
 
Short term open access status for march 17
Short term open access status for march 17Short term open access status for march 17
Short term open access status for march 17
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)
 
Ppa model presentation
Ppa model presentationPpa model presentation
Ppa model presentation
 
Sbi rooftop program
Sbi rooftop programSbi rooftop program
Sbi rooftop program
 
Sldc
SldcSldc
Sldc
 

Recently uploaded

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 

Recently uploaded (20)

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 

Applicable charges for group captive open access up solar

  • 1. Applicable Charges for Group Captive Open access- UP (SOLAR) Details ChargesforFY2018-19 TransmissionLoss 3.67% TransmissionCharge (Rs/kWh) 0.1185 WheelingChargeabove11KVSubstation (Rsin kWh) 0.215 WheelingLoss(DrawlofVoltageabove11KV) 4.00% CrossSubsidyCharges Nil AdditionalSurcharge Nil ElectricityDuty Electricity duty for ten years shall be exempted for sale to Distribution licensee, captive/Group captive consumption and third party sale in respect of all solar projects set up within the state. Banking Banking of energy in every financial year shall be permitted Document necessary for Open Access Registration Documents to (Injecting Entity) 1. Connectivity Agreement the Enclosure of Format ST-11 duly signed and properly dispatched by concerned Transmission/Distribution Licensee. 2. Certified copy of Single Line Diagram issued by concerned Transmission/Distribution Licensee which clearly mentions the position of interface ABT Meter details i.e., ABT Meter Number,CTR, PTR and overall MF 3. The certified copy of Interface ABT Meter sealing Certificates/Documents issued by Transmission and / or Distribution Licensee, as applicable. 4. The Loading Pattern of last one year on monthly basis i.e., Maximum, Minimum and Average values of MW & MVAR of Lines and Transformers of connected Transmission/Distribution Substation issued by concerned Transmission/Distribution Licensee. 5. Last DSM bill issued by UPSLDC in case of Intra-state entity whose ABT Scheduling and DSM billing is being carried out by UPSLDC. In such cases, document of Sl. No. 3 and 4 need not be ed unless there is a change in the ABT metering status / configuration. Documents to (Drawee Entity) 1. Connectivity agreement in case of STU connected consumers. However, if consumer is connected with Distribution network, the latest bill issued by Discom may be ed. 2. Certificate for validation of Discom Consumer details along with concurrence/ NOC for distribution system, in case of Discom consumer is beneficiary/drawee entity. Please refer UPSLDC website for Format. 3. The Enclosure of Format ST-11 duly signed and properly dispatched by concerned Transmission Licensee (Transmission Substation end) 4. The Enclosure of Format ST-11 duly signed and properly dispatched by concerned Distribution Licensee (Distribution Substation/DiscoConsumer/Beneficiary end)
  • 2. 5. Certified copy of Single Line Diagram issued by concerned Transmission/Distribution Licensee which clearly mentions the position of interface ABT Meter details i.e., ABT Meter Number, CTR, PTR and overall MF 6. The certified copy of Interface ABT Meter sealing Certificates/Documents issued by Transmission and / or Distribution Licensee, as applicable. 7. The Loading Pattern of last one year on monthly basis i.e., Maximum, Minimum and Average values of MW & MVAR of Lines and Transformers of connected Transmission/Distribution Substation issued by concerned Transmission/Distribution Licensee. 8. Last DSM bill issued by UPSLDC in case of Intra-state entity whose ABT Scheduling and DSM billing is being carried out by UPSLDC. In such cases, document of Sl. No. 5 and 6 need not be ed unless there is a change in the ABT metering status / configuration. Incentives:- For grid connectivity of Solar projects of capacity 5 MW and above proposed to be set up in Bundelkhand and Purvanchal region, State Government will bear the cost for construction of maximum transmission line length as follows:-  For 05 to 10 Megawatt capacity-10 Kilometer  For >10 megawatt to 50 megawatt capacity -15 Kilometer  For >50 megawatt capacity - 20 Kilometer.