WORKSHOP ON PROCUREMENT
NATIONAL AGRICULTURE HIGHER EDUCATION
PROJECT
July 16,2020
(virtual)
Official
NAHEP
This project was approved by Bank Board on August 3, 2017 with closing
date of November 30, 2022. The Project is being implemented by 61
agencies (universities) in several states.
The Project Agreement require that the PMU engage a Procurement
consultant to carry out procurement review .The selection process has
been initiated and we expect ICAR will have a consultant onboard within
next couple of months .
In FY19, over 427 contracts were awarded ( as per STEP DATA)and to
ensure compliance the Bank team sampled 12% contracts for PPR .
A number of non -compliances have been identified in the PPR.
All the IA must note that these possible noncompliance can lead to
declaration of mis procurement.
Official
STEP STATUS
July 15, 2020
 Number of Procurement plans in STEP :61
 Completed : $ 10 Million
 Signed : $9.6 Million
 Pending for Initiation : $16.70 Million
 Under Implementation: $8.00 Million
Official
NAHEP
Applicable Guidelines
of The World Bank
 – “Procurement Guidelines” means the “Guidelines:
Procurement of Goods, Works and Non-consulting
Services under IBRD Loans and IDA Credits and Grants
by World Bank Borrowers” dated January 2011
(revised July 2014).
 -Consultant Guidelines” means the “Guidelines:
Selection and Employment of Consultants under IBRD
Loans and IDA Credits and Grants by World Bank
Borrowers” dated January 2011 (revised July 2014).
Official
Prior Review
Thresholds
Category Prior Review threshold in US$
Works
10,000,000
Goods
2,000,000
Consulting firms
1,000,000
Individual consultants
300,000
Official
CONSIDERATIONS
THAT GUIDE
PROCUREMENT IN
BANK FINANCED
PROJECTS
PROCUREMENT PRINCIPLE :
 Need for economy and efficiency in the execution of the project.(Encourage open competition).
 All eligible bidders to get equal opportunity to compete.
 Make the procurement process transparent.
BANK GUIDELINE REQUIRES THAT HIGHEST STANDARD OF ETHICS ARE OBSERVED DURING THE PROCUREMENT AND
EXECUTION .
F&C DEFINITIONS:
 “CORRUPT PRACTICE” – OFFERING, GIVING, RECEIVING, SOLICITING ANYTHING OF VALUE TO INFLUENCE
A PUBLIC OFFICIAL IN THE PROCUREMENT PROCESS OR CONTRACT EXECUTION.
 “FRAUDULENT PRACTICE” – MISREPRESENTATION OR OMISSION OF FACTS IN ORDER TO INFLUENCE A
PROCUREMENT PROCESS OR CONTRACT EXECUTION.
 “COLLUSIVE PRACTICE” – ARRANGEMENT BETWEEN BIDDERS IN ORDER TO ESTABLISH BID PRICES AT
ARTIFICIAL NON-COMPETITIVE LEVELS.
 “COERCIVE PRACTICE” – HARMING OR THREATENING TO HARM PERSONS TO INFLUENCE THEIR
PARTICIPATION IN A PROCUREMENT PROCESS OR AFFECT THE EXECUTION OF A CONTRACT
 ‘OBSTRUCTIVE PRACTICE ‘-DELIBERATELY DESTROYING FALSIFYING ALTERING OR CONCEALING OF
EVIDENCEMATERIAL TO THE INVESTIGATION OR MAKING FALSE STATEMEMT TO INVESTIGATORS TO
MATERIALLY IMPEDE BANK INVESTIGATION INTO CORRUPT,FRAUDULENT,COERCIVE,COLLUSIVE
PRACTICE
6
Official
TYPES OF PROCUREMENT
PROCUREMENT
OF
CONSULTANT
SERVICES
“CONSULTANT SERVICES” INCLUDE SERVICES OF AN INTELLECTUAL AND
ADVISORY NATURE (SUCH AS POLICY ADVISE, INSTITUTIONAL REFORMS ADVICE,
SOCIAL AND ENVIRONMENTAL STUDIES, TECHNICAL ASSISTANCE–ENGINEERING
SERVICES AND CONSTRUCTION SUPERVISION, FINANCIAL SERVICES
PROCUREMENT
OF GOODS
“GOODS” INCLUDE: COMMODITIES, RAW MATERIAL, MACHINERY, EQUIPMENT
AND INDUSTRIAL PLANT.
PROCUREMENT
OF WORKS
“WORKS” INCLUDE SERVICES WHICH ARE BID AND CONTRACTED ON THE BASIS
OF PERFORMANCE OF A MEASURABLE PHYSICAL OUTPUT (SUCH AS
CONSTRUCTION OF WORKS, MANUFACTURE OF GOODS, OPERATION AND
MAINTENANCE OF FACILITIES OR PLANTS, DRILLING, MAPPING A.S.O.)
Official
PROCUREMEN
T PLANNING-
TAKE THE
FIRST STEP
Prior Agreed Procurement Plan to be the basis for any
procurement under the project.
FACTORS :
What? (Contract packages)
What Price ?($)
How? (Strategy)
Who? (Organization)
When? (Scheduling & Monitoring)
Official
PROCUREMENT CYCLE-Goods &Works
9
Steps to follow
Contract
performance
Prepare Bidding
document
Contract award
BID OPENING
Issue Bidding
Documents
Bid evaluation and
selection
Pre Bid conference (if
required)
Advertising in
National press
Bids Received
Official
General
Procurement
Notice
Contract
Performance
Adv. for
EOI with
TOR
Contract
Award
Financial
Evaluation
Short-listing
Tech.
Proposal
Opening
Issue of RFP
Documents
Tech.
Evaluation
Pre-proposal
Conference
Consultant Selection Cycle
10
Official
MISPROCUREMENT
THE BANK DOES NOT FINANCE
FOR CONSULTANT SERVICES, GOODS AND
WORKS WHICH HAVE NOT BEEN PROCURED
ACCORDANCE WITH AGREED PROCEDURES
THE LOAN AGREEMENT
IN CASE OF MISPROCUREMENT, IT IS THE
BANK POLICY TO CANCEL THAT PORTION
THE LOAN ALLOCATED TO SERVICES,
OR WORKS THAT HAVE BEEN
Official
Goods & WORKS
ICB
Some Aspects ICB NCB SHOPPING DIRECT CONTRACTING
ADVERTISE UNDB/National and
international
Newspapers
National Newspaper
and FREELY
ACCESSIBLE website
NA
BIDDING PERIOD Appx 45 days from date
of availability of
document
Minimum 30 days 7-14 days NA
MINIMUM
BIDDERS
1 1 3 1
Bidding Document SBD of WB Country specific as
agreed with
Government
Model RFQ Same as ICB/NCB/Shopping
Threshold  $3 million for goods
> $40 million for works
< $3 million for
<$40 million for
< $100,000 As per the provision of the
regulations
NA
12
Official
RISK &
Required
SYSTEMS
Procurement system risk
 Organization/Staffing: Organization of the procurement unit and allocation of functions; quality and
adequacy of procurement staff.
 Controls/Manuals: complaints handling, existence of dispute resolution systems, internal procedural
manuals and instructions, oversight and auditing practices, and code of professional behavior and
ethics.
 Record-keeping: Availability, quality, security, and completeness of procurement records and files.
Procurement process risk
 Procurement Planning: adherence to the Procurement Plan, including any /updates.
 Publications: adhere to advertising and contract award publication requirements for applicable
contracts.
 Bidding: adhere to requirements for bidding documents, including RFPs, LOIs, shortlists, terms of
reference, invoices, and other applicable documents.
 Evaluation: adhere to bid evaluation requirements/criteria, including draft contracts, technical and
financial evaluation reports, and any bid amendments.
 Awards: adhere to contract award requirements, including complaints handling, amendments,
variation orders, and extensions
 Implementation: adhere to contract implementation criteria, including results of physical inspections.
Contract Administration risk
 Payments: adhere to contract payment schedules, including timeliness of payments to contractors.
 Compliance: adhere to all contractual provisions; adherence to all related anticorruption practices.
 Disputes: promptness and equity in resolving contractual disputes
Official
SOME PPR OBSERVATIONS
Supply Order and payment detail not available in the system.
Delay in contract completion by 3 weeks for which no amendment issued.
RFQ does not have provision for splitting of contract while the contract has been awarded to two bidders for the two items.
Delay in supply.
The item approved in PP and actual procured are different.
The Quotation request is undated. No last date for submission mentioned.
Comparison based on model /Brand which is not an acceptable method as per Bank norms.
The dates of quotation request and the roadmap dates do not match as the activity had been updated in the system after the same was carried out (contract /Work order issued)
plan being cleared by the Bank.
There is huge variation in estimated price and most of the bids that have been received for which no reason is amplified in the comparative statement to establish that the lowest
meets the technical requirement and the reason for such large variations.
While the completion period was three months, the contractor has been able to complete the same not before 8 months for which no extension / amendments has been carried
No Work Order/Contract Agreement available in STEP
There is no contract issued to the individual except for the draft Negotiated Contract. The value of contract captured in the system mention Rs 1 lac without specifying the unit or
contract which should be the complete period. No amendments issued
Official
SOME PPR OBSERVATION
From the document uploaded in STEP, AU has mentioned value which is inconsistent with the contract value
( with GST/without GST)
Supply order is issued beyond the quotation validity period
No communication to the supplier on contract termination available in STEP.Not clear if any payment has been made against this contract. The relevant documents not available in STEP
Delay in supply of materials for which there is no amendment or extension carried out. ( EgEM)
Two contracts awarded while this should have been awarded on single responsibility basis
While the chosen method is Single Stage- Single Envelope, the evaluation is based on two envelope.
BER does not have the complete information of the tender value.
RFQ was for larger number while the actual contract was awarded for lower numbers for which no prior indication was made in RFQ. (FQ and the final contract needs to be aligned. At the
25 Nos. while contract is for only 10 nos)
There is a contract Agreement which has been drawn on the letter head of SUPPLIER
There appears to be a complaint which is not properly captured in the system which needs to be updated .
Quotation received from an agent while the SO is placed on a foreign supplier. (No authorization document is in STEP)
Against requirement of 3 Quotation only one quotation received
There is no contract issued to the individual except for the draft Negotiated Contract. The value of contract captured in the system mention Rs 1 lac without specifying the unit or period
which should be the complete period. No amendments issued
The PP approved is for a lumpsum consultancy the contract signed is a time-Based consultancy.
Official
Procurement
compliance &
Review –
Way Forward-I
 Incorporating wrong methods /estimates/specs can lead to avoidable delays and transactions .
Prior to arriving at method and estimate in STEP do a market survey.
 The process as mentioned in STEP to be adhered to and documents to be promptly uploaded at
each stage.
 The contract value and value updated in STEP should be consistent .Do not skip steps in STEP .
 Minimum three quotations are required for RFQ method of procurement.
 RFQ needs to carry complete information in regard to date of submission; required specification,
quantity, quantity variation, if contracting will be based on individual items or all evaluated
together only, payment terms, delivery period, guarantee warrant requirements etc .
 Do not proceed with award before the last date of submission as mentioned in RFQ.
 Comparative should be based on the invited RFQ.
 For RFB procurement use standard BER format and duly upload it in STEP.
 No change in specification and terms can be made at the contract award stage. The RFQ and
contract to be consistent.
 All Contract should be awarded within the bid validity period.
 Civil work contracts to be awarded on single responsibility basis.
 Contract terms, contract amount and contract period are important aspects which need to be
captured in the contract .
 Cannot change method after the contract is signed.
 Payments to be made as per contract terms
Official
Procurement
compliance &
Review –
Way Forward-II
 No retendering if responsive bids have been received. For retendering
provide appropriate justification (refer to the guideline) and upload
in STEP.
 All complaints need to be updated in STEP and upon resolution
should be closed with all documentation fully uploaded else PMU
should review the complaints and escalate it, as appropriate.
 If the contract is likely to be delayed then issue EOT before contract
expiry with justification in files. Upload the addendum with
justification note in STEP
 If item in the RFQ is to be evaluated separately then same to be stated
in RFQ upfront.
 If there are delays in supplies (even if procured thru eGem) then
either issue an amendment or terminate the contract (record the
justification in both instances ).
 Timely amendment to be issued
 If the items need to be changed then update STEP before proceeding
with the activity.
 Use generic specification. Wherever unavoidable please add ‘or
equivalent’
 Backdated document not to be uploaded unless agreed with Bank
Official
eGem in Lieu of RFQ
eGem only for RFQ method i.e upto $100,000.
Not to be used for procurement above $100,000 (RFB)
up to INR 50,000 in catalog mode (viz. any available item could be selected by IA without
further competition), provided selected Item/Supplier meeting the requisite quality,
specification and delivery period.
up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers
meeting the requisite quality, specification and delivery period. The tools for online bidding
and online reverse auction available on GeM may be used by the Purchaser.
up to INR equivalent of US$ 100,000 from the Supplier having lowest price and meeting
the requisite quality, specification and delivery period after mandatorily obtaining bids from
at least three Suppliers, using online bidding or reverse auction tool provided on GeM.”
Official
REMEMBER
PREPARE Good Estimates
 Cost & time overruns can be arrested simply by making good estimates.
 Estimates should be proposed after proper ground survey and market rates.
 variations during execution reflects poor quality of estimation.
VERIFY Documents
 Due diligence in checking Documents such as completion certificates for past experience,
Bank Guarantees etc should be done independently to ensure authenticity.
EXAMINE Quality
 Some times forged records of testing are created. This results in execution of sub-standard
quality of works, which adversely affects the performance and life of the projects besides
undue benefit to the contractor. Third part inspection gives an unbiased confirmation on the
quality .
KEEP Records
 Records authenticate quality and quantity audits conducted by field staff and regulate
mandatory requirements. These become handy for fixing accountability also.
 Thus record generation, safe custody and authenticity of records need attention and
verification by Sr Officers.
Official
ACTION TO
BE TAKEN :
WAY
FORWARD
 PMU and IA to propose actions to minimize these occurrences.
 PMU and each AU must prepare a kit of most critical document which includes but not limited to –
Applicable Guidelines ,Project Procurement manual, Model Bid document, Formats for evaluation ,contract
format and PPR format and upload on website for easy access.
 Each IA shall have designated procurement person who have received training at ASCI Hyderabad or held by
PMU to carry out procurement. The names of officers to be shared with the PMU and Frequent change in the
procurement personnel to be avoided as it is an impediment in smooth functionality. Should that be
necessitated then ensure proper handover is done.
 PMU shall prepare an annual calendar of Regular clinics and workshops and disseminate to all AU’s and
ensure that each university has more than one official who is trained and familiar with Bank procurement
requirements . to disseminate the procurement guidance and findings and get commitment from implementing
agencies and PMU on actions that will be taken to mitigate these issues.
 An independent consultant to be onboarded without further delay for conducting regular procurement review
and sharing the report ever six months
 PMU to proactively disseminate regularly norms which are commonly applicable for all AU’s , Provide an update
in regard to FAQ, specific observations, guidance ,training material from time to time .
 All complaints to be closely monitored by PMU and ensure that they are duly addressed and closed in an
amicable manner .
 Bank standard/Model documents as agreed with Bank shall be used consistently across board. All agencies
need to ensure compliance to the agreed procedures and processes
 All IA must ensure that all the documents are uploaded in STEP in a timely manner .
 Regular internal Quality assurance by the AU’s and PMU by reviewing if the documents are uploaded in STEP
and if the procurement process are being correctly and consistently followed .
 Ensure procurement MIS is developed and information is updated on real time basis .
 Action to be initiated for large number of activities cleared in STEP. This will require proactive review and
engagement by PMU.
 Action plan should be updated by PMU and agreed with Bank in addition to the PPR report response.
Official
THANK
YOU

More Related Content

Similar to FNAHEP-16072020.pptx

capaicty buidling program to make nation clean
capaicty buidling program to make nation cleancapaicty buidling program to make nation clean
capaicty buidling program to make nation clean
chiragvyas32
 
Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2a
Joy Irman
 
Construction business training
Construction business   trainingConstruction business   training
Construction business training
veritama
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
Vivek Srivastava
 

Similar to FNAHEP-16072020.pptx (20)

Good Contract Management;A municipality perspective
Good Contract Management;A municipality perspectiveGood Contract Management;A municipality perspective
Good Contract Management;A municipality perspective
 
Government procurement Act RA 9184
Government procurement Act  RA 9184Government procurement Act  RA 9184
Government procurement Act RA 9184
 
capaicty buidling program to make nation clean
capaicty buidling program to make nation cleancapaicty buidling program to make nation clean
capaicty buidling program to make nation clean
 
Purchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitbPurchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitb
 
2017 SLA Conference - Government Contracting - King
2017 SLA Conference - Government Contracting - King2017 SLA Conference - Government Contracting - King
2017 SLA Conference - Government Contracting - King
 
Understanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesUnderstanding Pre Qualification Questionnaires
Understanding Pre Qualification Questionnaires
 
Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2a
 
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
 
LSCTIG 2015 Session Materials - Managing your grant effectively
LSCTIG 2015 Session Materials -  Managing your grant effectively  LSCTIG 2015 Session Materials -  Managing your grant effectively
LSCTIG 2015 Session Materials - Managing your grant effectively
 
Construction business training
Construction business   trainingConstruction business   training
Construction business training
 
vigilanceawarenesswee.pdf
vigilanceawarenesswee.pdfvigilanceawarenesswee.pdf
vigilanceawarenesswee.pdf
 
Vigilance awareness
Vigilance awareness Vigilance awareness
Vigilance awareness
 
Procurement of works
Procurement of worksProcurement of works
Procurement of works
 
Striking The Balance
Striking The BalanceStriking The Balance
Striking The Balance
 
Procurement mca-compact-ii-presentation-bcm
Procurement mca-compact-ii-presentation-bcmProcurement mca-compact-ii-presentation-bcm
Procurement mca-compact-ii-presentation-bcm
 
ICT-Grant-ContractProcess
ICT-Grant-ContractProcessICT-Grant-ContractProcess
ICT-Grant-ContractProcess
 
Winning Government Business in Canada
Winning Government Business in CanadaWinning Government Business in Canada
Winning Government Business in Canada
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
 
Procurement Procedures Manual for Public Procurement in Ekiti State
Procurement Procedures Manual for Public Procurement in Ekiti StateProcurement Procedures Manual for Public Procurement in Ekiti State
Procurement Procedures Manual for Public Procurement in Ekiti State
 

More from robert mota (7)

Comunicaciones_20181024110421_0.pptx
Comunicaciones_20181024110421_0.pptxComunicaciones_20181024110421_0.pptx
Comunicaciones_20181024110421_0.pptx
 
Qué es APB.pptx
Qué es APB.pptxQué es APB.pptx
Qué es APB.pptx
 
Essential_Skills_of_a_Site_Reliability_E.pdf
Essential_Skills_of_a_Site_Reliability_E.pdfEssential_Skills_of_a_Site_Reliability_E.pdf
Essential_Skills_of_a_Site_Reliability_E.pdf
 
10.a guide-to-facebook-security
10.a guide-to-facebook-security10.a guide-to-facebook-security
10.a guide-to-facebook-security
 
certificate-Q6UJ909684MY
certificate-Q6UJ909684MYcertificate-Q6UJ909684MY
certificate-Q6UJ909684MY
 
20411 d enu-trainerhandbook
20411 d enu-trainerhandbook20411 d enu-trainerhandbook
20411 d enu-trainerhandbook
 
Central telefonica
Central telefonicaCentral telefonica
Central telefonica
 

Recently uploaded

一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
bd2c5966a56d
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
JosephCanama
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
A AA
 
一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
Airst S
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
mahikaanand16
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
CssSpamx
 
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.pptCorporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
RRR Chambers
 
一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书
irst
 

Recently uploaded (20)

Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 
The Main Steps on Starting a Business in Spain
The Main Steps on Starting a Business in SpainThe Main Steps on Starting a Business in Spain
The Main Steps on Starting a Business in Spain
 
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
 
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
一比一原版(UM毕业证书)美国密歇根大学安娜堡分校毕业证如何办理
 
一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
 
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.pptCorporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
Corporate Governance (Indian Scenario, Legal frame work in India ) - PPT.ppt
 
一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 

FNAHEP-16072020.pptx

  • 1. Official WORKSHOP ON PROCUREMENT NATIONAL AGRICULTURE HIGHER EDUCATION PROJECT July 16,2020 (virtual)
  • 2. Official NAHEP This project was approved by Bank Board on August 3, 2017 with closing date of November 30, 2022. The Project is being implemented by 61 agencies (universities) in several states. The Project Agreement require that the PMU engage a Procurement consultant to carry out procurement review .The selection process has been initiated and we expect ICAR will have a consultant onboard within next couple of months . In FY19, over 427 contracts were awarded ( as per STEP DATA)and to ensure compliance the Bank team sampled 12% contracts for PPR . A number of non -compliances have been identified in the PPR. All the IA must note that these possible noncompliance can lead to declaration of mis procurement.
  • 3. Official STEP STATUS July 15, 2020  Number of Procurement plans in STEP :61  Completed : $ 10 Million  Signed : $9.6 Million  Pending for Initiation : $16.70 Million  Under Implementation: $8.00 Million
  • 4. Official NAHEP Applicable Guidelines of The World Bank  – “Procurement Guidelines” means the “Guidelines: Procurement of Goods, Works and Non-consulting Services under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” dated January 2011 (revised July 2014).  -Consultant Guidelines” means the “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” dated January 2011 (revised July 2014).
  • 5. Official Prior Review Thresholds Category Prior Review threshold in US$ Works 10,000,000 Goods 2,000,000 Consulting firms 1,000,000 Individual consultants 300,000
  • 6. Official CONSIDERATIONS THAT GUIDE PROCUREMENT IN BANK FINANCED PROJECTS PROCUREMENT PRINCIPLE :  Need for economy and efficiency in the execution of the project.(Encourage open competition).  All eligible bidders to get equal opportunity to compete.  Make the procurement process transparent. BANK GUIDELINE REQUIRES THAT HIGHEST STANDARD OF ETHICS ARE OBSERVED DURING THE PROCUREMENT AND EXECUTION . F&C DEFINITIONS:  “CORRUPT PRACTICE” – OFFERING, GIVING, RECEIVING, SOLICITING ANYTHING OF VALUE TO INFLUENCE A PUBLIC OFFICIAL IN THE PROCUREMENT PROCESS OR CONTRACT EXECUTION.  “FRAUDULENT PRACTICE” – MISREPRESENTATION OR OMISSION OF FACTS IN ORDER TO INFLUENCE A PROCUREMENT PROCESS OR CONTRACT EXECUTION.  “COLLUSIVE PRACTICE” – ARRANGEMENT BETWEEN BIDDERS IN ORDER TO ESTABLISH BID PRICES AT ARTIFICIAL NON-COMPETITIVE LEVELS.  “COERCIVE PRACTICE” – HARMING OR THREATENING TO HARM PERSONS TO INFLUENCE THEIR PARTICIPATION IN A PROCUREMENT PROCESS OR AFFECT THE EXECUTION OF A CONTRACT  ‘OBSTRUCTIVE PRACTICE ‘-DELIBERATELY DESTROYING FALSIFYING ALTERING OR CONCEALING OF EVIDENCEMATERIAL TO THE INVESTIGATION OR MAKING FALSE STATEMEMT TO INVESTIGATORS TO MATERIALLY IMPEDE BANK INVESTIGATION INTO CORRUPT,FRAUDULENT,COERCIVE,COLLUSIVE PRACTICE 6
  • 7. Official TYPES OF PROCUREMENT PROCUREMENT OF CONSULTANT SERVICES “CONSULTANT SERVICES” INCLUDE SERVICES OF AN INTELLECTUAL AND ADVISORY NATURE (SUCH AS POLICY ADVISE, INSTITUTIONAL REFORMS ADVICE, SOCIAL AND ENVIRONMENTAL STUDIES, TECHNICAL ASSISTANCE–ENGINEERING SERVICES AND CONSTRUCTION SUPERVISION, FINANCIAL SERVICES PROCUREMENT OF GOODS “GOODS” INCLUDE: COMMODITIES, RAW MATERIAL, MACHINERY, EQUIPMENT AND INDUSTRIAL PLANT. PROCUREMENT OF WORKS “WORKS” INCLUDE SERVICES WHICH ARE BID AND CONTRACTED ON THE BASIS OF PERFORMANCE OF A MEASURABLE PHYSICAL OUTPUT (SUCH AS CONSTRUCTION OF WORKS, MANUFACTURE OF GOODS, OPERATION AND MAINTENANCE OF FACILITIES OR PLANTS, DRILLING, MAPPING A.S.O.)
  • 8. Official PROCUREMEN T PLANNING- TAKE THE FIRST STEP Prior Agreed Procurement Plan to be the basis for any procurement under the project. FACTORS : What? (Contract packages) What Price ?($) How? (Strategy) Who? (Organization) When? (Scheduling & Monitoring)
  • 9. Official PROCUREMENT CYCLE-Goods &Works 9 Steps to follow Contract performance Prepare Bidding document Contract award BID OPENING Issue Bidding Documents Bid evaluation and selection Pre Bid conference (if required) Advertising in National press Bids Received
  • 11. Official MISPROCUREMENT THE BANK DOES NOT FINANCE FOR CONSULTANT SERVICES, GOODS AND WORKS WHICH HAVE NOT BEEN PROCURED ACCORDANCE WITH AGREED PROCEDURES THE LOAN AGREEMENT IN CASE OF MISPROCUREMENT, IT IS THE BANK POLICY TO CANCEL THAT PORTION THE LOAN ALLOCATED TO SERVICES, OR WORKS THAT HAVE BEEN
  • 12. Official Goods & WORKS ICB Some Aspects ICB NCB SHOPPING DIRECT CONTRACTING ADVERTISE UNDB/National and international Newspapers National Newspaper and FREELY ACCESSIBLE website NA BIDDING PERIOD Appx 45 days from date of availability of document Minimum 30 days 7-14 days NA MINIMUM BIDDERS 1 1 3 1 Bidding Document SBD of WB Country specific as agreed with Government Model RFQ Same as ICB/NCB/Shopping Threshold  $3 million for goods > $40 million for works < $3 million for <$40 million for < $100,000 As per the provision of the regulations NA 12
  • 13. Official RISK & Required SYSTEMS Procurement system risk  Organization/Staffing: Organization of the procurement unit and allocation of functions; quality and adequacy of procurement staff.  Controls/Manuals: complaints handling, existence of dispute resolution systems, internal procedural manuals and instructions, oversight and auditing practices, and code of professional behavior and ethics.  Record-keeping: Availability, quality, security, and completeness of procurement records and files. Procurement process risk  Procurement Planning: adherence to the Procurement Plan, including any /updates.  Publications: adhere to advertising and contract award publication requirements for applicable contracts.  Bidding: adhere to requirements for bidding documents, including RFPs, LOIs, shortlists, terms of reference, invoices, and other applicable documents.  Evaluation: adhere to bid evaluation requirements/criteria, including draft contracts, technical and financial evaluation reports, and any bid amendments.  Awards: adhere to contract award requirements, including complaints handling, amendments, variation orders, and extensions  Implementation: adhere to contract implementation criteria, including results of physical inspections. Contract Administration risk  Payments: adhere to contract payment schedules, including timeliness of payments to contractors.  Compliance: adhere to all contractual provisions; adherence to all related anticorruption practices.  Disputes: promptness and equity in resolving contractual disputes
  • 14. Official SOME PPR OBSERVATIONS Supply Order and payment detail not available in the system. Delay in contract completion by 3 weeks for which no amendment issued. RFQ does not have provision for splitting of contract while the contract has been awarded to two bidders for the two items. Delay in supply. The item approved in PP and actual procured are different. The Quotation request is undated. No last date for submission mentioned. Comparison based on model /Brand which is not an acceptable method as per Bank norms. The dates of quotation request and the roadmap dates do not match as the activity had been updated in the system after the same was carried out (contract /Work order issued) plan being cleared by the Bank. There is huge variation in estimated price and most of the bids that have been received for which no reason is amplified in the comparative statement to establish that the lowest meets the technical requirement and the reason for such large variations. While the completion period was three months, the contractor has been able to complete the same not before 8 months for which no extension / amendments has been carried No Work Order/Contract Agreement available in STEP There is no contract issued to the individual except for the draft Negotiated Contract. The value of contract captured in the system mention Rs 1 lac without specifying the unit or contract which should be the complete period. No amendments issued
  • 15. Official SOME PPR OBSERVATION From the document uploaded in STEP, AU has mentioned value which is inconsistent with the contract value ( with GST/without GST) Supply order is issued beyond the quotation validity period No communication to the supplier on contract termination available in STEP.Not clear if any payment has been made against this contract. The relevant documents not available in STEP Delay in supply of materials for which there is no amendment or extension carried out. ( EgEM) Two contracts awarded while this should have been awarded on single responsibility basis While the chosen method is Single Stage- Single Envelope, the evaluation is based on two envelope. BER does not have the complete information of the tender value. RFQ was for larger number while the actual contract was awarded for lower numbers for which no prior indication was made in RFQ. (FQ and the final contract needs to be aligned. At the 25 Nos. while contract is for only 10 nos) There is a contract Agreement which has been drawn on the letter head of SUPPLIER There appears to be a complaint which is not properly captured in the system which needs to be updated . Quotation received from an agent while the SO is placed on a foreign supplier. (No authorization document is in STEP) Against requirement of 3 Quotation only one quotation received There is no contract issued to the individual except for the draft Negotiated Contract. The value of contract captured in the system mention Rs 1 lac without specifying the unit or period which should be the complete period. No amendments issued The PP approved is for a lumpsum consultancy the contract signed is a time-Based consultancy.
  • 16. Official Procurement compliance & Review – Way Forward-I  Incorporating wrong methods /estimates/specs can lead to avoidable delays and transactions . Prior to arriving at method and estimate in STEP do a market survey.  The process as mentioned in STEP to be adhered to and documents to be promptly uploaded at each stage.  The contract value and value updated in STEP should be consistent .Do not skip steps in STEP .  Minimum three quotations are required for RFQ method of procurement.  RFQ needs to carry complete information in regard to date of submission; required specification, quantity, quantity variation, if contracting will be based on individual items or all evaluated together only, payment terms, delivery period, guarantee warrant requirements etc .  Do not proceed with award before the last date of submission as mentioned in RFQ.  Comparative should be based on the invited RFQ.  For RFB procurement use standard BER format and duly upload it in STEP.  No change in specification and terms can be made at the contract award stage. The RFQ and contract to be consistent.  All Contract should be awarded within the bid validity period.  Civil work contracts to be awarded on single responsibility basis.  Contract terms, contract amount and contract period are important aspects which need to be captured in the contract .  Cannot change method after the contract is signed.  Payments to be made as per contract terms
  • 17. Official Procurement compliance & Review – Way Forward-II  No retendering if responsive bids have been received. For retendering provide appropriate justification (refer to the guideline) and upload in STEP.  All complaints need to be updated in STEP and upon resolution should be closed with all documentation fully uploaded else PMU should review the complaints and escalate it, as appropriate.  If the contract is likely to be delayed then issue EOT before contract expiry with justification in files. Upload the addendum with justification note in STEP  If item in the RFQ is to be evaluated separately then same to be stated in RFQ upfront.  If there are delays in supplies (even if procured thru eGem) then either issue an amendment or terminate the contract (record the justification in both instances ).  Timely amendment to be issued  If the items need to be changed then update STEP before proceeding with the activity.  Use generic specification. Wherever unavoidable please add ‘or equivalent’  Backdated document not to be uploaded unless agreed with Bank
  • 18. Official eGem in Lieu of RFQ eGem only for RFQ method i.e upto $100,000. Not to be used for procurement above $100,000 (RFB) up to INR 50,000 in catalog mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. up to INR equivalent of US$ 100,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM.”
  • 19. Official REMEMBER PREPARE Good Estimates  Cost & time overruns can be arrested simply by making good estimates.  Estimates should be proposed after proper ground survey and market rates.  variations during execution reflects poor quality of estimation. VERIFY Documents  Due diligence in checking Documents such as completion certificates for past experience, Bank Guarantees etc should be done independently to ensure authenticity. EXAMINE Quality  Some times forged records of testing are created. This results in execution of sub-standard quality of works, which adversely affects the performance and life of the projects besides undue benefit to the contractor. Third part inspection gives an unbiased confirmation on the quality . KEEP Records  Records authenticate quality and quantity audits conducted by field staff and regulate mandatory requirements. These become handy for fixing accountability also.  Thus record generation, safe custody and authenticity of records need attention and verification by Sr Officers.
  • 20. Official ACTION TO BE TAKEN : WAY FORWARD  PMU and IA to propose actions to minimize these occurrences.  PMU and each AU must prepare a kit of most critical document which includes but not limited to – Applicable Guidelines ,Project Procurement manual, Model Bid document, Formats for evaluation ,contract format and PPR format and upload on website for easy access.  Each IA shall have designated procurement person who have received training at ASCI Hyderabad or held by PMU to carry out procurement. The names of officers to be shared with the PMU and Frequent change in the procurement personnel to be avoided as it is an impediment in smooth functionality. Should that be necessitated then ensure proper handover is done.  PMU shall prepare an annual calendar of Regular clinics and workshops and disseminate to all AU’s and ensure that each university has more than one official who is trained and familiar with Bank procurement requirements . to disseminate the procurement guidance and findings and get commitment from implementing agencies and PMU on actions that will be taken to mitigate these issues.  An independent consultant to be onboarded without further delay for conducting regular procurement review and sharing the report ever six months  PMU to proactively disseminate regularly norms which are commonly applicable for all AU’s , Provide an update in regard to FAQ, specific observations, guidance ,training material from time to time .  All complaints to be closely monitored by PMU and ensure that they are duly addressed and closed in an amicable manner .  Bank standard/Model documents as agreed with Bank shall be used consistently across board. All agencies need to ensure compliance to the agreed procedures and processes  All IA must ensure that all the documents are uploaded in STEP in a timely manner .  Regular internal Quality assurance by the AU’s and PMU by reviewing if the documents are uploaded in STEP and if the procurement process are being correctly and consistently followed .  Ensure procurement MIS is developed and information is updated on real time basis .  Action to be initiated for large number of activities cleared in STEP. This will require proactive review and engagement by PMU.  Action plan should be updated by PMU and agreed with Bank in addition to the PPR report response.