1. Republic of the Philippines
Province of Leyte
Tacloban City
PROVINCIAL AGRICULTURE
PROGRAM OF WORK
Brgy. Bunga Dam Rehabilitation
Brgy. Bunga, Abuyog, Leyte
Jan. 31, 2005
ITEM/ACTIVITY Quantity Unit Unit cost Amount Percent
PhP/unit PhP
I. CLEARING & GRUBBING 185.00 sq.m. 1.10 203.50 0.02
II. COFFERDAM 51.92 m 1,565.00 81,254.80 9.03
a. Water pump 120.00 hrs 336.25 40,350.00 4.48
III. EXCAVATION 740.00 cu.m. 27.78 20,557.20 2.28
IV. RETAINING WALL
a. Concrete Class "A" 82.70 cu.m. 4,945.05 408,967.50 45.44
b. RSB 3/4" dia. 5,983.22 kg 43.11 257,936.61 28.66
b.2 RSB 3/8" dia 1,590.32 kg 45.67 72,629.91 8.07
V. STRUCTURAL BACKFILL 431.42 cu.m. 28.75 12,403.33 1.38
VI. Administrative and supervision cost L.S. 5,697.14 0.63
TOTAL PROJECT COST 900,000.00 100.00
Prepared by: Recommending Approval:
RENATO N. PAYOD
Ag. Eng'g Staff ROGELIO O. PORTULA
Checked by: Acting Provincial Agriculturist
BUENAVENTURA L. PITAO
Ag. Eng'g Div. Chief, OPA WELL V. CAPANGPANGAN
Chief, RAEG, DA-RFU-8
Approved:
LEO P. CANEDA
Regional Executive Director
DA-RFU-8