SlideShare a Scribd company logo
1 of 17
OVERVIEW OF THE JULY & AUGUST
Cutover RMS
Month Target Planned Actual % Achieved Planned Actual % Achieved
July 70 70 67 95.7142857 70 59 84.28571429
August 70 70 34 48.5714286 70 24 34.28571429
OVERVIEW OF THE JULY & AUGUST SUPERVISOR’S
MONTHLY DELIVERY
JULY AUGUST
Supervisor
Power
cutover
RMS
commissioning Supervisor
Power
cutover
RMS
commissioning
Henry 21 17 Henry 7 4
Emeka/Sadiq 16 16 Emeka 7 4
Wasiu 14 13 Wasiu 9 8
Ebuka 16 13 Ebuka 5 3
Sadiq 4 3
SBC RESOURCE PLAN
The Region is currently having 7nos SBCs with an average of 2 Teams
Each.
In most cases, the acclaimed SBC Team is constituted by just a single
personnel.
This has placed a significantly negative weight on the region’s target and
overall deliverables.
See the SBC’s resources…
SUPERVISOR’S SEPTEMBER ALLOCATION
TENTATIVE SITE ALLOCATION TO SUPERVISORS
SUPERVISOR LOCATION NUMBER OF SITES
EBUKA JOS 31
EMEKA KADUNA/ABUJA 28
HENRY KADUNA 32
WASIU JOS 31
SADIQ KADUNA/ABUJA 23
145
See site clustering…
ES & CIVILS AVAILABILITY
Region
September
Target
Civils required
Civil
completed
Complete
system in
the region
Complete
system in
the regional
warehouse
Complete
system
deployed
to site
Complete
system on site
Number of
commissioners
in the region
Remark
NC 145 145 53 18 0 18 18 5
10 ES Installations on new
deployment; 8 ES on
restricted Hub sites
EQUIPMENT & CIVIL WORKS AVAILABILITY
MATERIAL & LOGISTICS PLAN
ES IN Stock REQUIRED ES REQUEST
0KW 0 16 16
3KW 0 60 60
6KW 0 58 58
9KW 0 11 11
TOTAL 0 145 145
MATERIAL & LOGISTICS PLAN
Week 1
Week 1
Request
Tenants Battery Rating
Solar
Stand
DCDB
1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required
10 0 8 2 0 8 2
30 2 16 10 2 20 10
10 0 5 5 0 10 0
0 0 0 0 0 0 0
50 2 29 17 2 38 12
MATERIAL & LOGISTICS PLAN
Week 2
Week 2
Request
Tenants Battery Rating
Solar
Stand
DCDB
1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required
6 0 3 3 0 3 3
14 0 7 3 4 10 4
25 0 15 9 1 15 10
5 0 3 1 1 3 2
50 0 28 16 6 31 19
MATERIAL & LOGISTICS PLAN
Week 3
Week 2
Request
Tenants Battery Rating
Solar
Stand
DCDB
1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required
0 0 0 0 0 0 0
16 0 5 5 6 10 6
23 0 23 0 0 13 10
6 0 6 0 0 6 0
45 0 34 5 6 29 16
DEPENDENCIES FOR DELIVERY
► ADDITIONAL SUPERVISOR
► CONVERSION OF SADIQ FROM RMS COMMISSIONER TO POWER/RMS COMMISSIONER
► 2Nos PROJECT VEHICLE FOR SADIQ & THE ADDITIONAL SUPERVISOR
► 2Nos DRIVERS FOR THE TWO RESOURCES
► ADDITIONAL WAREHOUSE SUPPORT WITH PROJECT LIFE CYCLE CAPABILITY
► PROVISION OF 5LTRS DIESEL @N1,000/SITE TO THE COMMISIONERS FOR ES TESTING
PRIOR TO CUTOVER.
KEY RISKS AND ISSUES
ACCESS ROAD
COMMUNITY RESTIVENESS & SECURITY ISSUES ( E.G DUE TO ES NOISE
LEVEL)
ES STABILITY AND COMFORT LEVEL
WEATHER & CLIMATIC CONDITIONS
EQUIPMENT SHIPMENT DELAY
ETC
FACTORS AFFECTING THE SUCCESS OF THIS
PROJECT
SIMPLICITY OF DESIGN
TECHNICAL PROBLEMS ON ES PARTS – CONTROLLER & SPARES
INSUFFICIENT INVOLVEMENT OF BENEFICIARIES – OPERATIONS TEAM
SEPTEMBER REQUEST & REGIONAL FLOAT
THANK YOU

More Related Content

Similar to POWER SWAP Presentation

2016 third-quarter-earnings-update (1)
2016 third-quarter-earnings-update (1)2016 third-quarter-earnings-update (1)
2016 third-quarter-earnings-update (1)SandRidgeIR
 
2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master PlanCityofKilleen
 
Water Management Strategies - Ryan Kelso
Water Management Strategies - Ryan KelsoWater Management Strategies - Ryan Kelso
Water Management Strategies - Ryan KelsoTWCA
 
Business review
Business review Business review
Business review RecJOTG
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Company Presentation October 2014
Company Presentation October 2014Company Presentation October 2014
Company Presentation October 2014AnteroResources
 
Company website presentation october 2014
Company website presentation   october 2014Company website presentation   october 2014
Company website presentation october 2014AnteroResources
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshoppublicinvolvement
 

Similar to POWER SWAP Presentation (10)

2016 third-quarter-earnings-update (1)
2016 third-quarter-earnings-update (1)2016 third-quarter-earnings-update (1)
2016 third-quarter-earnings-update (1)
 
2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan2012 Water & Wastewater Master Plan
2012 Water & Wastewater Master Plan
 
Water Management Strategies - Ryan Kelso
Water Management Strategies - Ryan KelsoWater Management Strategies - Ryan Kelso
Water Management Strategies - Ryan Kelso
 
Wp special master-plan[071113]
Wp special master-plan[071113]Wp special master-plan[071113]
Wp special master-plan[071113]
 
Business review
Business review Business review
Business review
 
Bupers 32 spouse brief fet norfolk_ updated_13 aug 2013
Bupers 32 spouse brief fet norfolk_ updated_13 aug 2013Bupers 32 spouse brief fet norfolk_ updated_13 aug 2013
Bupers 32 spouse brief fet norfolk_ updated_13 aug 2013
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Company Presentation October 2014
Company Presentation October 2014Company Presentation October 2014
Company Presentation October 2014
 
Company website presentation october 2014
Company website presentation   october 2014Company website presentation   october 2014
Company website presentation october 2014
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshop
 

POWER SWAP Presentation

  • 1.
  • 2.
  • 3. OVERVIEW OF THE JULY & AUGUST Cutover RMS Month Target Planned Actual % Achieved Planned Actual % Achieved July 70 70 67 95.7142857 70 59 84.28571429 August 70 70 34 48.5714286 70 24 34.28571429
  • 4. OVERVIEW OF THE JULY & AUGUST SUPERVISOR’S MONTHLY DELIVERY JULY AUGUST Supervisor Power cutover RMS commissioning Supervisor Power cutover RMS commissioning Henry 21 17 Henry 7 4 Emeka/Sadiq 16 16 Emeka 7 4 Wasiu 14 13 Wasiu 9 8 Ebuka 16 13 Ebuka 5 3 Sadiq 4 3
  • 5. SBC RESOURCE PLAN The Region is currently having 7nos SBCs with an average of 2 Teams Each. In most cases, the acclaimed SBC Team is constituted by just a single personnel. This has placed a significantly negative weight on the region’s target and overall deliverables. See the SBC’s resources…
  • 6. SUPERVISOR’S SEPTEMBER ALLOCATION TENTATIVE SITE ALLOCATION TO SUPERVISORS SUPERVISOR LOCATION NUMBER OF SITES EBUKA JOS 31 EMEKA KADUNA/ABUJA 28 HENRY KADUNA 32 WASIU JOS 31 SADIQ KADUNA/ABUJA 23 145 See site clustering…
  • 7. ES & CIVILS AVAILABILITY Region September Target Civils required Civil completed Complete system in the region Complete system in the regional warehouse Complete system deployed to site Complete system on site Number of commissioners in the region Remark NC 145 145 53 18 0 18 18 5 10 ES Installations on new deployment; 8 ES on restricted Hub sites
  • 8. EQUIPMENT & CIVIL WORKS AVAILABILITY
  • 9. MATERIAL & LOGISTICS PLAN ES IN Stock REQUIRED ES REQUEST 0KW 0 16 16 3KW 0 60 60 6KW 0 58 58 9KW 0 11 11 TOTAL 0 145 145
  • 10. MATERIAL & LOGISTICS PLAN Week 1 Week 1 Request Tenants Battery Rating Solar Stand DCDB 1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required 10 0 8 2 0 8 2 30 2 16 10 2 20 10 10 0 5 5 0 10 0 0 0 0 0 0 0 0 50 2 29 17 2 38 12
  • 11. MATERIAL & LOGISTICS PLAN Week 2 Week 2 Request Tenants Battery Rating Solar Stand DCDB 1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required 6 0 3 3 0 3 3 14 0 7 3 4 10 4 25 0 15 9 1 15 10 5 0 3 1 1 3 2 50 0 28 16 6 31 19
  • 12. MATERIAL & LOGISTICS PLAN Week 3 Week 2 Request Tenants Battery Rating Solar Stand DCDB 1Tenants 2Tenants 3Tenants 4Tenants 5*63AH 6*63AH Sets In stock Required 0 0 0 0 0 0 0 16 0 5 5 6 10 6 23 0 23 0 0 13 10 6 0 6 0 0 6 0 45 0 34 5 6 29 16
  • 13. DEPENDENCIES FOR DELIVERY ► ADDITIONAL SUPERVISOR ► CONVERSION OF SADIQ FROM RMS COMMISSIONER TO POWER/RMS COMMISSIONER ► 2Nos PROJECT VEHICLE FOR SADIQ & THE ADDITIONAL SUPERVISOR ► 2Nos DRIVERS FOR THE TWO RESOURCES ► ADDITIONAL WAREHOUSE SUPPORT WITH PROJECT LIFE CYCLE CAPABILITY ► PROVISION OF 5LTRS DIESEL @N1,000/SITE TO THE COMMISIONERS FOR ES TESTING PRIOR TO CUTOVER.
  • 14. KEY RISKS AND ISSUES ACCESS ROAD COMMUNITY RESTIVENESS & SECURITY ISSUES ( E.G DUE TO ES NOISE LEVEL) ES STABILITY AND COMFORT LEVEL WEATHER & CLIMATIC CONDITIONS EQUIPMENT SHIPMENT DELAY ETC
  • 15. FACTORS AFFECTING THE SUCCESS OF THIS PROJECT SIMPLICITY OF DESIGN TECHNICAL PROBLEMS ON ES PARTS – CONTROLLER & SPARES INSUFFICIENT INVOLVEMENT OF BENEFICIARIES – OPERATIONS TEAM
  • 16. SEPTEMBER REQUEST & REGIONAL FLOAT