PROPOSAL
BY: TAN MIN CHUEN
0322938
2
Content
No. Title Page no.
1 Cover 1
2 Content 2
3 Rationale 3
4 Project Concept 3
5 Proposal 4-7
Rice Factory 4
Rice Shop 4
Products 5-6
Rice Café 7
6 Bubble Diagram 8
7 Details 9-13
Factory 9
Café 9
Shop 10
Alley 10
Carpark 11
Loading bay 12
Distribution of vegetation 13
8 Benefits and Impacts 14
9 BuildingProcedure 15-16
10 Sample Documents 17-22
3
Rationale
My proposalis a combination of commercial and industrialarea. After
conducting site analysis, I decided to proposea projectthat will benefits the
surrounding community and create a new tourist spotin Sekinchan. Through
analysis I havepinpointed the following issues to proposethis project.
1. Small public library in Sekinchan
Sekinchan has only one public library, which is small and can’t satisfy
many people who wanted a peaceful place to study or read books.
2. Less variety of rice inthe market
3. Lack of rice products inthe market
Rice products can’tbe found in the market. Rice products arehealthier
than other similar products in the market, for instance, multigrain snacks
contain lesser fats compared to other snacks in the market.
4. Uniqueness of food
In this place that full of paddy field, special dishes and beveragemade of
rice will be a uniqueness of this projectand attract touristto this place.
Project Concept
Concept of this projectwill be a combination of industrialand commercial
area. The proposalincludes a rice factory, a rice café and a rice shop. The
factory works as a producer, who processes thepaddy and provides goods for
the café and the shop. This proposalis required to
1. Providea harmony spacefor reading and studying
2. Producedifferent types of rice for customers
3. Producehealthy rice products for customers
4. Provideunique foods and beverages
4
Proposal
The Rice Factory (Light Industry)
Itwill be a rice factory, producing various typeof rice by processing the paddy
planted in Sekinchan. Other rice products will also be manufactured. Every
type of rice will be wholesale to rice shops across peninsular Malaysia. Yetrice
products will be selling together with the rice in the rice shop beside the
factory.
The Rice shop (commercial)
Different type of rice and rice products produced fromthe factory will be
selling in this rice shop. Providing the consumers various choices of ricebeyond
the ordinary whiterice selling in supermarkets. Somehealthy rice products will
also be selling here.
5
Pearl white rice
Pearl white rice is round shortgrain white rice, which is
delicious and fond by Japaneseand Koreans
Brownrice
Brown rice is whole grain rice. Ithas a mild, nutty flavor, and
is chewier and more nutritious than white rice, but goes
rancid more quickly
Embryo rice
Embryo rice is the result of removing the bran frombrown
rice. This makes Embryo rice contains the goodness of brown
rice with its full nutrients but in white rice softand smooth
texture
White sticky rice
White sticky rice will be sticky when cooked. Itcan used to
make various types of dishes.
Black sticky rice
Black sticky rice is usually in sweetened formand seldom
served as main dish, it usually used to make dessert.
Products produced by the factory that will be selling in the rice shop
6
Pearl rice lollipop
This is a lollipop made of pearl rice with rice syrup and
some naturalflavoring.
Rice BranOil
Extracted from the outer layer on the brown rice kernel.
A high quality, delicate tasting cooking oil. Studies have
shown that it is effective in lowering blood cholesterol
levels.
Rice and Seasoning Mixes
Rice syrup
Multigrainsnacks
Rice Syrup lightly sweetand smooth in texture. It is a
nutritive sweetener that is a tasty alternative for those
who watch their sugar intake
This is a “guilt-free” snack, it is made of organic brown rice.
Itcontains 40% lesser fats than other snacks. It’s a tasty
alternative for those who like snacking and afraid of gaining
weight.
This is a mix of rice and seasonings to make it more
delicious. Available in different flavors .
7
Rice café (commercial)
This café will serves special dishes and beverage made fromrice. It will be
divided into indoor and outdoor area, there will be some vegetation planted
outdoor to provide a better environmentfor customers. The café consistof 2
floors, providing morespaces for customers. A study corner will be setup in the
café.
8
Bubble Diagram
FACTORY
Shop
Café
Carpark
LOADINGBAY
40m
85m
9
Details
Factory
Land occupied: 40m× 40m
n 1600m2
The factory has 3 entrance. The main
entrance is located on the south of the
factory. The second entrance can be
accessed through the loading bay. The
third entrance in facing the café and
shop, goods can be transferred to café
and shop through the third entrance.
Café
Land occupied: 35m× 20m
n 700m2
The café has 4 entrance, main entrance leads to the indoor seating area, the
sub entrance leads to the outdoor seating area. People can also access the café
fromthe shop through the third entrance that connects the shop and the café.
The fourth entrance is for stock replenishing purpose. Besides, there are also
two entrance to the indoor seating area fromthe outdoor seating area.
FACTORY2 3
.
1
Café
Outdoor
seating
1
3
Connecting
the shop
2
Indoor
seating
4
.
10
Shop
The shop has 3 entrance main entrance in on the east of the shop. Second
entrance is connecting the café, people can access the shop fromthe café
through this entrance. The third is for stock replenishing purpose.
Alley between factory and shop+café
The alley connects the factory to the shop and café. Workers willtransfer
goods to shop and café through this alley. Vegetation is planted along the alley
to beautify that place.
Shop
1
.
3
.
Land occupied: 15m× 20m
n 300m2
2
Connecting
the café
FACTORY
Shop
Café
Carp
ark
Alley
11
Carpark
Land occupied: 20m× 20m
n 400m2
The carpark consistof 14 parking lot, each parking lot is 5m × 3m in size. There
is only an entrance and an exit for this carpark. Vehiclecan only movein one
way inside the carpark.
Entrance
Exit
Entrance of café Entrance of outdoor
seatingarea
Entrance of
shop
12
Loading bay
Land occupied: 5m× 20m
n 100m2
The space of the loading bay is only sufficient for one lorry to
go in at a time. A dock is built to load goods efficiently.
Dock
13
Distributionof vegetation
Legend
FACTORY
Shop
Café
Carpark
Vegetation
Vegetation planted in this project is shown above. Vegetation is planted in the
carpark, caféand the loading bay. Vegetation is planted in the café to make a
good atmosphere. In the carpark, vegetation is planted on the edge to emphasis
wherethe entrance is. Vegetation is also planted along the alley to beautify that
place.
14
Benefits & Impacts
Benefits
Sekinchan as a fastdeveloping tourist spot, touristnumber is increasing. By
producing various types of rice and rice products that can’t get easily from
ordinary shops, this projecthas potential to become one of the touristspot in
Sekinchan.
Special rice-related dishes and beverages served in the café is also a
uniqueness that may help this place to become a tourist spotin Sekinchan,
attracting tourist and bring advantages to the client.
By attracting tourist to this place, this place will become more crowded and
this will benefits nearby shop lots.
The factory, shop and café require sufficientmanpower to ensure everything
operate well. Therefore, this project will bring working opportunities for
residents nearby.
Besides, the café provides a place for nearby residents and tourist for
relaxation and gathering.
The public library in Sekinchan has a smallcapacity. The Rice Café can solve the
problem as it can also function as a study place for students nearby, due to its
peaceful environment.
By producing various typeof rice, consumers willhave different choices of rice.
Consumers can chooserice according their needs. For instance, black sticky
rice that serves as dessert, pearlrice that is more scrumptious, brown ricethat
contain more nutrients and so on.
Impacts
As tourist number increase in this place, Streets nearby will become congested
as the road in Sekinchan is not wide enough. This will cause traffic problem and
annoys the community nearby.
Only a little amount of vegetation is planted on site. This projectis not eco-
friendly.
Besides, Rice factory will produce somewaste products that might pollute the
environment.
15
Building procedure
1.Submit and obtain development approval
Submission requirements:
• Planning plan
• Building plan
• Engineering plan (earthwork, road & drainageplan, road excavation permit,
x and street lighting plan)
• Landscapeplan
• Water supply plan
• Sewerageplan
• Infrastructurecommunication plan
• Firesafety plan
Planning and building plans are prepared by the Architect. Including:
• Key and location plan
• Site plan
• Floor plans
• Roof plan
• Sections (longitudinal and cross-sections)
• Elevations
2. Submit pre-construction notifications
3. Request final utilities inspections
4. Receive roadanddrainage inspection (Agency: Engineering Departmentof
CHKL)
5. Receive sewagefinal inspection (Agency: SewerageCertifying Agency (IWK))
The Sewerage Certifying Agency (IWK) willcarry outan inspection of the
seweragesystemand issueBuildCo a clearance letter for sewerage.
6. Receive water final inspection (Agency: Water Authority SYABAS) TheWater
Authority (SYABAS) will conduct an on-site inspection of the works and make
the connection to the public pipe.
16
7. Obtain road and drainage clearance (Agency: Engineering Departmentof
CHKL ) A date for the inspection will be set prior to the issuanceof clearance
letter for the road and drainage work.
8. Obtain sewage clearance letter andsewerage
connection (Agency: SewerageCertifying Agency (IWK) ) Oncethe inspection
has been carried out, a clearance letter is issued. The sewage clearance letter
is needed in order for the engineer to issue the Certificate of Completion and
Compliance (CCC).
9. Submit water test andcommissioning (T&C) report (Agency: Water
Authority SYABAS) the water testing and commissioning reportwil be prepared
and submitit to SYABAS. This document is required to obtain the clearance
letter fromSYABAS.
10. Obtain water clearance letter andwater connection (Agency: Water
Authority SYABAS) The Water Authority (SYABAS) will issuea clearance letter
and install the water meter. This will complete the water connection process.
11. Receive fire safety inspection.(Agency: Fireand Rescue Department) Fire
and Rescue Department will carry out fire safety inspection
12. Obtain fire safety clearance letter (Agency: Fireand Rescue
Department). Fire and Rescue Department will issuethe fire clearance letter
13. Builder’s principal submitting person files the certificate of completion
and compliance (CCC) (Agency: Building Department and Board of Architect)

More Related Content

Similar to Individual proposal

FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYI
FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYIFNBE0115 - ICI PROJECT BRIEF CHANGHUEYYI
FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYIbarbaraxchang
 
Agri tech-investors-meet
Agri tech-investors-meetAgri tech-investors-meet
Agri tech-investors-meetAim Niabi
 
business studies project
business studies project business studies project
business studies project Gagan Jain
 
class 12 business studies project
class 12 business studies projectclass 12 business studies project
class 12 business studies projectGagan Jain
 
Organization study at coffee day
Organization study at coffee dayOrganization study at coffee day
Organization study at coffee dayProjects Kart
 
Raj mehta 04 sfimar
Raj mehta 04 sfimarRaj mehta 04 sfimar
Raj mehta 04 sfimarPravinsaraf
 
Nestle Nespresso Bus 400
Nestle Nespresso Bus 400Nestle Nespresso Bus 400
Nestle Nespresso Bus 400starsajeeb
 
Coffee Shop Customer Experiences #CX #CompellingExperiences
Coffee Shop Customer Experiences #CX #CompellingExperiencesCoffee Shop Customer Experiences #CX #CompellingExperiences
Coffee Shop Customer Experiences #CX #CompellingExperiencesGreen Room Design
 
spice-iii-150911200409-lva1-app6892_compressed (1).pptx
spice-iii-150911200409-lva1-app6892_compressed (1).pptxspice-iii-150911200409-lva1-app6892_compressed (1).pptx
spice-iii-150911200409-lva1-app6892_compressed (1).pptxAzizShaikh45
 
Organization Study at Coffee Day
Organization Study at Coffee DayOrganization Study at Coffee Day
Organization Study at Coffee DayProjects Kart
 
Genius farm partner - English
Genius farm partner - EnglishGenius farm partner - English
Genius farm partner - EnglishNgwe Tun
 
Marketing plan for new product.
Marketing plan for new product.Marketing plan for new product.
Marketing plan for new product.Tanweer Sudhan
 
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...GURUKRIPACOMMUNICATI1
 
10740253 829669857090191 1067850004_n-2
10740253 829669857090191 1067850004_n-210740253 829669857090191 1067850004_n-2
10740253 829669857090191 1067850004_n-2rachaelcheong
 
Principles of Business S.B.A
Principles of Business S.B.APrinciples of Business S.B.A
Principles of Business S.B.AAaron Skyers Jr
 
Marketing of new coffee
Marketing of new coffeeMarketing of new coffee
Marketing of new coffeeKhushal Teli
 
Visit to city walk mall
Visit to city walk mallVisit to city walk mall
Visit to city walk mallaadi29045
 

Similar to Individual proposal (20)

FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYI
FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYIFNBE0115 - ICI PROJECT BRIEF CHANGHUEYYI
FNBE0115 - ICI PROJECT BRIEF CHANGHUEYYI
 
Agri tech-investors-meet
Agri tech-investors-meetAgri tech-investors-meet
Agri tech-investors-meet
 
business studies project
business studies project business studies project
business studies project
 
class 12 business studies project
class 12 business studies projectclass 12 business studies project
class 12 business studies project
 
Organization study at coffee day
Organization study at coffee dayOrganization study at coffee day
Organization study at coffee day
 
Business Plan - Amil Sabanadzovic
Business Plan - Amil SabanadzovicBusiness Plan - Amil Sabanadzovic
Business Plan - Amil Sabanadzovic
 
Raj mehta 04 sfimar
Raj mehta 04 sfimarRaj mehta 04 sfimar
Raj mehta 04 sfimar
 
Nestle Nespresso Bus 400
Nestle Nespresso Bus 400Nestle Nespresso Bus 400
Nestle Nespresso Bus 400
 
Coffee Shop Customer Experiences #CX #CompellingExperiences
Coffee Shop Customer Experiences #CX #CompellingExperiencesCoffee Shop Customer Experiences #CX #CompellingExperiences
Coffee Shop Customer Experiences #CX #CompellingExperiences
 
spice-iii-150911200409-lva1-app6892_compressed (1).pptx
spice-iii-150911200409-lva1-app6892_compressed (1).pptxspice-iii-150911200409-lva1-app6892_compressed (1).pptx
spice-iii-150911200409-lva1-app6892_compressed (1).pptx
 
Organization Study at Coffee Day
Organization Study at Coffee DayOrganization Study at Coffee Day
Organization Study at Coffee Day
 
Genius farm partner - English
Genius farm partner - EnglishGenius farm partner - English
Genius farm partner - English
 
Marketing plan for new product.
Marketing plan for new product.Marketing plan for new product.
Marketing plan for new product.
 
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...
Choices Of Baked Items In bakery a study on consumer preference IN BHOPAL (2)...
 
10740253 829669857090191 1067850004_n-2
10740253 829669857090191 1067850004_n-210740253 829669857090191 1067850004_n-2
10740253 829669857090191 1067850004_n-2
 
Principles of Business S.B.A
Principles of Business S.B.APrinciples of Business S.B.A
Principles of Business S.B.A
 
Marketing of new coffee
Marketing of new coffeeMarketing of new coffee
Marketing of new coffee
 
Visit to city walk mall
Visit to city walk mallVisit to city walk mall
Visit to city walk mall
 
Corn COffee.pptx
Corn COffee.pptxCorn COffee.pptx
Corn COffee.pptx
 
business plan
business planbusiness plan
business plan
 

Individual proposal

  • 1. 1 PROPOSAL BY: TAN MIN CHUEN 0322938
  • 2. 2 Content No. Title Page no. 1 Cover 1 2 Content 2 3 Rationale 3 4 Project Concept 3 5 Proposal 4-7 Rice Factory 4 Rice Shop 4 Products 5-6 Rice Café 7 6 Bubble Diagram 8 7 Details 9-13 Factory 9 Café 9 Shop 10 Alley 10 Carpark 11 Loading bay 12 Distribution of vegetation 13 8 Benefits and Impacts 14 9 BuildingProcedure 15-16 10 Sample Documents 17-22
  • 3. 3 Rationale My proposalis a combination of commercial and industrialarea. After conducting site analysis, I decided to proposea projectthat will benefits the surrounding community and create a new tourist spotin Sekinchan. Through analysis I havepinpointed the following issues to proposethis project. 1. Small public library in Sekinchan Sekinchan has only one public library, which is small and can’t satisfy many people who wanted a peaceful place to study or read books. 2. Less variety of rice inthe market 3. Lack of rice products inthe market Rice products can’tbe found in the market. Rice products arehealthier than other similar products in the market, for instance, multigrain snacks contain lesser fats compared to other snacks in the market. 4. Uniqueness of food In this place that full of paddy field, special dishes and beveragemade of rice will be a uniqueness of this projectand attract touristto this place. Project Concept Concept of this projectwill be a combination of industrialand commercial area. The proposalincludes a rice factory, a rice café and a rice shop. The factory works as a producer, who processes thepaddy and provides goods for the café and the shop. This proposalis required to 1. Providea harmony spacefor reading and studying 2. Producedifferent types of rice for customers 3. Producehealthy rice products for customers 4. Provideunique foods and beverages
  • 4. 4 Proposal The Rice Factory (Light Industry) Itwill be a rice factory, producing various typeof rice by processing the paddy planted in Sekinchan. Other rice products will also be manufactured. Every type of rice will be wholesale to rice shops across peninsular Malaysia. Yetrice products will be selling together with the rice in the rice shop beside the factory. The Rice shop (commercial) Different type of rice and rice products produced fromthe factory will be selling in this rice shop. Providing the consumers various choices of ricebeyond the ordinary whiterice selling in supermarkets. Somehealthy rice products will also be selling here.
  • 5. 5 Pearl white rice Pearl white rice is round shortgrain white rice, which is delicious and fond by Japaneseand Koreans Brownrice Brown rice is whole grain rice. Ithas a mild, nutty flavor, and is chewier and more nutritious than white rice, but goes rancid more quickly Embryo rice Embryo rice is the result of removing the bran frombrown rice. This makes Embryo rice contains the goodness of brown rice with its full nutrients but in white rice softand smooth texture White sticky rice White sticky rice will be sticky when cooked. Itcan used to make various types of dishes. Black sticky rice Black sticky rice is usually in sweetened formand seldom served as main dish, it usually used to make dessert. Products produced by the factory that will be selling in the rice shop
  • 6. 6 Pearl rice lollipop This is a lollipop made of pearl rice with rice syrup and some naturalflavoring. Rice BranOil Extracted from the outer layer on the brown rice kernel. A high quality, delicate tasting cooking oil. Studies have shown that it is effective in lowering blood cholesterol levels. Rice and Seasoning Mixes Rice syrup Multigrainsnacks Rice Syrup lightly sweetand smooth in texture. It is a nutritive sweetener that is a tasty alternative for those who watch their sugar intake This is a “guilt-free” snack, it is made of organic brown rice. Itcontains 40% lesser fats than other snacks. It’s a tasty alternative for those who like snacking and afraid of gaining weight. This is a mix of rice and seasonings to make it more delicious. Available in different flavors .
  • 7. 7 Rice café (commercial) This café will serves special dishes and beverage made fromrice. It will be divided into indoor and outdoor area, there will be some vegetation planted outdoor to provide a better environmentfor customers. The café consistof 2 floors, providing morespaces for customers. A study corner will be setup in the café.
  • 9. 9 Details Factory Land occupied: 40m× 40m n 1600m2 The factory has 3 entrance. The main entrance is located on the south of the factory. The second entrance can be accessed through the loading bay. The third entrance in facing the café and shop, goods can be transferred to café and shop through the third entrance. Café Land occupied: 35m× 20m n 700m2 The café has 4 entrance, main entrance leads to the indoor seating area, the sub entrance leads to the outdoor seating area. People can also access the café fromthe shop through the third entrance that connects the shop and the café. The fourth entrance is for stock replenishing purpose. Besides, there are also two entrance to the indoor seating area fromthe outdoor seating area. FACTORY2 3 . 1 Café Outdoor seating 1 3 Connecting the shop 2 Indoor seating 4 .
  • 10. 10 Shop The shop has 3 entrance main entrance in on the east of the shop. Second entrance is connecting the café, people can access the shop fromthe café through this entrance. The third is for stock replenishing purpose. Alley between factory and shop+café The alley connects the factory to the shop and café. Workers willtransfer goods to shop and café through this alley. Vegetation is planted along the alley to beautify that place. Shop 1 . 3 . Land occupied: 15m× 20m n 300m2 2 Connecting the café FACTORY Shop Café Carp ark Alley
  • 11. 11 Carpark Land occupied: 20m× 20m n 400m2 The carpark consistof 14 parking lot, each parking lot is 5m × 3m in size. There is only an entrance and an exit for this carpark. Vehiclecan only movein one way inside the carpark. Entrance Exit Entrance of café Entrance of outdoor seatingarea Entrance of shop
  • 12. 12 Loading bay Land occupied: 5m× 20m n 100m2 The space of the loading bay is only sufficient for one lorry to go in at a time. A dock is built to load goods efficiently. Dock
  • 13. 13 Distributionof vegetation Legend FACTORY Shop Café Carpark Vegetation Vegetation planted in this project is shown above. Vegetation is planted in the carpark, caféand the loading bay. Vegetation is planted in the café to make a good atmosphere. In the carpark, vegetation is planted on the edge to emphasis wherethe entrance is. Vegetation is also planted along the alley to beautify that place.
  • 14. 14 Benefits & Impacts Benefits Sekinchan as a fastdeveloping tourist spot, touristnumber is increasing. By producing various types of rice and rice products that can’t get easily from ordinary shops, this projecthas potential to become one of the touristspot in Sekinchan. Special rice-related dishes and beverages served in the café is also a uniqueness that may help this place to become a tourist spotin Sekinchan, attracting tourist and bring advantages to the client. By attracting tourist to this place, this place will become more crowded and this will benefits nearby shop lots. The factory, shop and café require sufficientmanpower to ensure everything operate well. Therefore, this project will bring working opportunities for residents nearby. Besides, the café provides a place for nearby residents and tourist for relaxation and gathering. The public library in Sekinchan has a smallcapacity. The Rice Café can solve the problem as it can also function as a study place for students nearby, due to its peaceful environment. By producing various typeof rice, consumers willhave different choices of rice. Consumers can chooserice according their needs. For instance, black sticky rice that serves as dessert, pearlrice that is more scrumptious, brown ricethat contain more nutrients and so on. Impacts As tourist number increase in this place, Streets nearby will become congested as the road in Sekinchan is not wide enough. This will cause traffic problem and annoys the community nearby. Only a little amount of vegetation is planted on site. This projectis not eco- friendly. Besides, Rice factory will produce somewaste products that might pollute the environment.
  • 15. 15 Building procedure 1.Submit and obtain development approval Submission requirements: • Planning plan • Building plan • Engineering plan (earthwork, road & drainageplan, road excavation permit, x and street lighting plan) • Landscapeplan • Water supply plan • Sewerageplan • Infrastructurecommunication plan • Firesafety plan Planning and building plans are prepared by the Architect. Including: • Key and location plan • Site plan • Floor plans • Roof plan • Sections (longitudinal and cross-sections) • Elevations 2. Submit pre-construction notifications 3. Request final utilities inspections 4. Receive roadanddrainage inspection (Agency: Engineering Departmentof CHKL) 5. Receive sewagefinal inspection (Agency: SewerageCertifying Agency (IWK)) The Sewerage Certifying Agency (IWK) willcarry outan inspection of the seweragesystemand issueBuildCo a clearance letter for sewerage. 6. Receive water final inspection (Agency: Water Authority SYABAS) TheWater Authority (SYABAS) will conduct an on-site inspection of the works and make the connection to the public pipe.
  • 16. 16 7. Obtain road and drainage clearance (Agency: Engineering Departmentof CHKL ) A date for the inspection will be set prior to the issuanceof clearance letter for the road and drainage work. 8. Obtain sewage clearance letter andsewerage connection (Agency: SewerageCertifying Agency (IWK) ) Oncethe inspection has been carried out, a clearance letter is issued. The sewage clearance letter is needed in order for the engineer to issue the Certificate of Completion and Compliance (CCC). 9. Submit water test andcommissioning (T&C) report (Agency: Water Authority SYABAS) the water testing and commissioning reportwil be prepared and submitit to SYABAS. This document is required to obtain the clearance letter fromSYABAS. 10. Obtain water clearance letter andwater connection (Agency: Water Authority SYABAS) The Water Authority (SYABAS) will issuea clearance letter and install the water meter. This will complete the water connection process. 11. Receive fire safety inspection.(Agency: Fireand Rescue Department) Fire and Rescue Department will carry out fire safety inspection 12. Obtain fire safety clearance letter (Agency: Fireand Rescue Department). Fire and Rescue Department will issuethe fire clearance letter 13. Builder’s principal submitting person files the certificate of completion and compliance (CCC) (Agency: Building Department and Board of Architect)