1. Ministry of Energy and
Natural Resources of Georgia
Steps for Investment in
Georgia’s hydro potential
2. Steps for Investment
STEP 1
Submit application form
STEP 2
Sign MOU with GoG
STEP 3
Obtain construction permit
• Feasibility, detailed project
design
• Land possession/ownership
document
(Ministry of Economic development )
STEP 4
Obtain generation license *
Environmental and social
impact assessment
(Ministry of Environment)
(GNEWRC)
STEP 5
Start electricity sales
* HPPs under 13 MW do not require generation license
2