Unit 7 example
1. An Example: Lemonade
Make 1,000 cups over 50 days
Steady rate of 20 cups per day
Budgeted cost per cup is $0.50
Total project budget is $500
2. Lemonade Progress
At end of day 10:
150 cups have been made
Total actual cost is $90 (ACWP)
3. Lemonade Status
BCWS = $100
10 days x 20 cups per day x .50/cup budget
BCWP = $75 (Earned Value)
150 cups x .50/cup budget
SV = BCWP - BCWS = -$25
SPI = BCWP / BCWS = 0.75
CV = BCWP - ACWP = $75 - $90 = -$15
CPI = BCWP / ACWP = 0.833