SlideShare a Scribd company logo
1 of 2
Engineering a concrete pour
Anybodycanconcrete. Orderconcrete,place the pump& bam! Case closed. Thatis concrete
farming,gentlemen!
However, engineeringaconcrete pourisa totallydifferentball game.Here we wouldlike to
share the achievementof ahandful of Engineerswho planned, managed&executed apourof 3400
cu.m. A simple PDCA (Plan-Do-Check-Act)cycle shall putthingsinperspective.
Planningphase
The plan was to pour 3400 cu.m concrete for a raft of 1.8 m thick with the help of 3 pumps at a
rate of 150cu.m per hour.The methodstatementidentifiedthe rate of pour& the needfortemperature
control withthermocouplers.The labour was arranged in shifts and so were the Construction Manager
and Project Engineers. The checkpoint for concrete testing was set up & manned by the 3rd
party
technicianwiththe QCEngineerformonitoringthe slump,temp. & collecting cubes as per the regional
specification.All the supportteamnamelylogistics, Health, Safety and Environment (HSE), stores, land
surveyors&QA/QCwere representedthroughoutthe pour. There was backup material/equipment for
everything being used at site like the pump, vibrators etc.
The mass concrete was planned to be placed in successive even layers of 400mm thickness and 2.00m
setbacks. The stepped front progresses forward, across the full width of the module, from one end of
the module to the other until the raft form is filled and the lift placement is completed.
Approval wasobtainedforanepoxybondingagent,tobe usedif there isdelayinsupplyof concrete and
there is a cold joint and methodology for cold joints identified in the method statement.
400
400
Even setbacks @ 2.0m
400
Even layers @ 0.40m
2000 2000 2000 2000 2000
10000
Next layer
460 thick
Exposed pour face = 40.30mx6.00mx0.40m=96 m3
@a pour rate of 150 m3 per hour =45 min exposure
Just DID it
The actual pour startedat 0830AM inthe morningandthe Engineersatsite coordinatedwiththe
supplierregularlytoensure there wasnoshortage orbottle neckof concrete trucks at site,asthe site
access wasverynarrow. The supplier,Smeet, hadabatchingplantdedicatedforthe project andthe
supplywas smooth,withtheirrepresentative atsite.
The communicationamongstourEngineerswasveryeffectiveasa groupwas formedon the social
mediaplatform,‘WhatsApp’forconcrete pourlive updates,whichhelpedinteambuildingasmuchas it
didfor communication.
Logisticsarrangedforall the equipment’sandmachineries withsome extraasbackup.HSE ensuredall
environmental hazardsare addressed,likewashingbay forpumps,plasticsheetsforconcrete.Proper
trainingsandtool box talkswere providedtoall workersatsite.
With effective coordination the actual pour average was 180 cu.m per hour against the planned
150cu.m per hour and the total pour was completed in less than 23 hours.
Check
The trucks were routed insuch a waythat theycame to the checkpointwhere the temperature and
slumpwas measured,cubeswere takenandif foundsatisfactoryforwardedtothe pumplocation.
Also,thermocouplersinstalledin the massconcrete ensuredthatthe temperaturereadingsshall be
takenfor 7 consecutive daysfromthe dayof pour.
Act
The site teamwas fullyempoweredtotake anycorrective actiondeemednecessaryduringthe time of
pour.
Also,continuousmonitoringof concrete duringandafterthe pour(throughthermocouplers)ensured
that the material usedisas perspecification.
Lessonlearnedfromthispourwasthat a proper,smoothcommunicationchannel andteameffortgoes
a longway if it isbasedon a planned foundation.
QualityControl teamhelpedinbuildingastrongteamby providingthe backupandplatformonwhich
the Engineersatsite couldefficientlyandeffectivelyfinishthe concrete pour.

More Related Content

Viewers also liked

Viewers also liked (7)

Sky siren pcs
Sky siren pcsSky siren pcs
Sky siren pcs
 
Clase 06/11/2015
Clase 06/11/2015Clase 06/11/2015
Clase 06/11/2015
 
Letter of Recommendation; Bart Baird
Letter of Recommendation; Bart BairdLetter of Recommendation; Bart Baird
Letter of Recommendation; Bart Baird
 
Como vivir con Jesús
Como vivir con JesúsComo vivir con Jesús
Como vivir con Jesús
 
EBW Tension Link Load Cell
EBW Tension Link Load CellEBW Tension Link Load Cell
EBW Tension Link Load Cell
 
Prueba de computo
Prueba de computoPrueba de computo
Prueba de computo
 
Proyecto Legislación " Chipas Ña Chaki"
Proyecto Legislación " Chipas Ña Chaki"Proyecto Legislación " Chipas Ña Chaki"
Proyecto Legislación " Chipas Ña Chaki"
 

Similar to Engineering a concrete pour

Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboAnton Ricalovskis
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)1000kv technologies
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concretethamand7
 
Dm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prDm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prTensar
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
Environment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingEnvironment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingkunal singh
 

Similar to Engineering a concrete pour (20)

Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in Colombo
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
Dm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prDm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-pr
 
Francisco Campos Almodovar Curriculum (1)
Francisco Campos Almodovar Curriculum (1)Francisco Campos Almodovar Curriculum (1)
Francisco Campos Almodovar Curriculum (1)
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Concreting work
Concreting workConcreting work
Concreting work
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
Park xpress presentation
Park xpress presentationPark xpress presentation
Park xpress presentation
 
Park xpress presentation
Park xpress presentationPark xpress presentation
Park xpress presentation
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
Environment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housingEnvironment friendly building_material_technologies_for_low_cost_housing
Environment friendly building_material_technologies_for_low_cost_housing
 

Engineering a concrete pour

  • 1. Engineering a concrete pour Anybodycanconcrete. Orderconcrete,place the pump& bam! Case closed. Thatis concrete farming,gentlemen! However, engineeringaconcrete pourisa totallydifferentball game.Here we wouldlike to share the achievementof ahandful of Engineerswho planned, managed&executed apourof 3400 cu.m. A simple PDCA (Plan-Do-Check-Act)cycle shall putthingsinperspective. Planningphase The plan was to pour 3400 cu.m concrete for a raft of 1.8 m thick with the help of 3 pumps at a rate of 150cu.m per hour.The methodstatementidentifiedthe rate of pour& the needfortemperature control withthermocouplers.The labour was arranged in shifts and so were the Construction Manager and Project Engineers. The checkpoint for concrete testing was set up & manned by the 3rd party technicianwiththe QCEngineerformonitoringthe slump,temp. & collecting cubes as per the regional specification.All the supportteamnamelylogistics, Health, Safety and Environment (HSE), stores, land surveyors&QA/QCwere representedthroughoutthe pour. There was backup material/equipment for everything being used at site like the pump, vibrators etc. The mass concrete was planned to be placed in successive even layers of 400mm thickness and 2.00m setbacks. The stepped front progresses forward, across the full width of the module, from one end of the module to the other until the raft form is filled and the lift placement is completed. Approval wasobtainedforanepoxybondingagent,tobe usedif there isdelayinsupplyof concrete and there is a cold joint and methodology for cold joints identified in the method statement. 400 400 Even setbacks @ 2.0m 400 Even layers @ 0.40m 2000 2000 2000 2000 2000 10000 Next layer 460 thick Exposed pour face = 40.30mx6.00mx0.40m=96 m3 @a pour rate of 150 m3 per hour =45 min exposure
  • 2. Just DID it The actual pour startedat 0830AM inthe morningandthe Engineersatsite coordinatedwiththe supplierregularlytoensure there wasnoshortage orbottle neckof concrete trucks at site,asthe site access wasverynarrow. The supplier,Smeet, hadabatchingplantdedicatedforthe project andthe supplywas smooth,withtheirrepresentative atsite. The communicationamongstourEngineerswasveryeffectiveasa groupwas formedon the social mediaplatform,‘WhatsApp’forconcrete pourlive updates,whichhelpedinteambuildingasmuchas it didfor communication. Logisticsarrangedforall the equipment’sandmachineries withsome extraasbackup.HSE ensuredall environmental hazardsare addressed,likewashingbay forpumps,plasticsheetsforconcrete.Proper trainingsandtool box talkswere providedtoall workersatsite. With effective coordination the actual pour average was 180 cu.m per hour against the planned 150cu.m per hour and the total pour was completed in less than 23 hours. Check The trucks were routed insuch a waythat theycame to the checkpointwhere the temperature and slumpwas measured,cubeswere takenandif foundsatisfactoryforwardedtothe pumplocation. Also,thermocouplersinstalledin the massconcrete ensuredthatthe temperaturereadingsshall be takenfor 7 consecutive daysfromthe dayof pour. Act The site teamwas fullyempoweredtotake anycorrective actiondeemednecessaryduringthe time of pour. Also,continuousmonitoringof concrete duringandafterthe pour(throughthermocouplers)ensured that the material usedisas perspecification. Lessonlearnedfromthispourwasthat a proper,smoothcommunicationchannel andteameffortgoes a longway if it isbasedon a planned foundation. QualityControl teamhelpedinbuildingastrongteamby providingthe backupandplatformonwhich the Engineersatsite couldefficientlyandeffectivelyfinishthe concrete pour.