Australia China Resources Symposium- Chinese Spotlight Presentation NT Chris Tonkin Arafura Resources -Chinese

  1. 1. 澳-中南北资源投资论坛Chris Tonkin首席执行官2012年7月11日
  2. 2. 免责声明Important NoticeThis presentation contains certain statements which may constitute “forward-looking statements”. Such statements are only expectations or beliefsand are subject to inherent risks and uncertainties which could cause actual values, results or performance achievements to differ materially fromthose expressed or implied in this presentation. No representation or warranty, express or implied is made by Arafura Resources Limited(“Arafura Resources”) that any forward-looking statement contained in this presentation will occur, be achieved or prove to be correct. You arecautioned against relying upon any forward looking statement.Except for statutory liability which cannot be excluded, each of Arafura Resources and its related body corporates and their officers, employees andadvisers expressly disclaims any responsibility for the accuracy or completeness of the material contained in this presentation and excludes all liabilitywhatsoever (including in negligence) for any loss or damage which may be suffered by any person as a consequence of any information in thispresentation or any error in it or omission from it. Arafura Resources accepts no responsibility to update any person regarding any inaccuracy,omission or change in information in this presentation or any other information made available to a person, nor any obligation to furnish the personwith any further information.This presentation does not constitute an offer of securities in Arafura Resources, nor an invitation to apply for such securities. This presentation doesnot provide investment advice or financial product advice. You should obtain professional advice and carry out your own independent investigationsand assessment of the information in this presentation (including any assumptions) before acting.Information in this presentation which is attributed to a third party source has not been checked or verified by Arafura Resources.The information in this presentation that relates to exploration results, mineral resources or ore reserves is based on information compiled byMr Richard Brescianini BSc(Hons). Mr Brescianini is a Member of the Australian Institute of Geoscientists and he has sufficient experience which isrelevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a CompetentPerson as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves(The JORC Code)”. Mr Brescianini consents to the inclusion in this presentation of the matters based on his information in the form and context inwhich it appears.Mr Brescianini is a full-time employee of Arafura Resources. Page 2
  3. 3. 内容摘要Arafura公司简介Nolans项目2011年 – 2012年近况Nolans 项目– 资源和加工2012 任务安排和下一步计划总结摘要 Page 3
  4. 4. Arafura公司简介公司概要 截止2012年6月26日• 是一家成立于1997年的澳大利 资金 3.96亿股股票 亚上市公司 1150万股董事会及员工期权• 2003年在澳洲股市上市 (交易代 市值 @ 0.22澳元/股 = 约8700万澳元 码 ARU)• Nolans氧化稀土项目 (REO) 主要股东 JP Morgan Nominees1 24.13% ECE2 16.97%• 在澳洲北省拥有广阔的土地开 负债 - 零 现金 2180万元澳币 (2012年5月31 展勘探工作 日)• 由澳大利亚专业人士设计的技 术 1. 2. 主要由德国股东控股 中国东部矿业开发与发展局 Page 4
  5. 5. Nolans 项目资源介绍Nolans 项目有着世界级规模并具有战略性意义• 最小的资源风险;• 目前完成了94公里的钻孔任务,平均孔距为40米;• 近期报告证明资源近期测明提升到52%;• 资源在220米深度下很开阔;• 适合低成本操作、属开口矿的开采和加工;• 标准的选矿技术;• 长于20年的矿藏寿命。 氧化稀土 氧化稀土 五氧化磷 铀 资源 吨 (百万) % (吨) (吨) (吨) 测量资源 4.3 3.3 144,000 13 0.57 指定资源 21 2.6 563,000 12 0.42 推断资源 22 2.4 511,000 10 0.37 总计 47 2.6 1,217,000 11 0.41 Page 5
  6. 6. Nolans 项目- 加工处理流程 商业模式 – 为澳大利亚做出贡献 原矿 精矿 中级加工稀土 (碳酸岩) 年产 氧化稀土 2万吨 金属/合金 元件 原始设备制造商 Page 6
  7. 7. 加工处理到终端产品 加工流程经过各种测试和验明 ……. 2009年小规模试验水漂 2009年硫酸盐烘烤 2011年示范工厂的盐酸洗后产生的石膏 ANSTO, 悉尼 ANSAC, Bunbury ALS-Ammtec 珀斯2011年示范工厂中盐酸盐再生石膏 2012年示范工厂中硫酸盐和纯化 2012 年Nolans 项目的氧化稀土样本 ALS-Ammtec, 珀斯 ANSTO,悉尼 ANSTO,悉尼 Page 7
  8. 8. Arafura 资源 – 2011年 ~ 2012年近况成就 • 在南澳Whyalla选好稀土加工厂厂址; • Nolans 项目矿物资源近期测明提升到52%; • 工艺流程证明在各种规模的矿场分离稀土氧化物; • 公司管理人员正致力于确定关键技术和策划工作; • Nolans氧化稀土生产纯度在99%的市场质量规范; • 同欧洲和韩国的承购合作伙伴达成联盟关系。挑战 • 全球资金市场疲弱,项目融资困难重重; • 项目进展由于资金紧张而延迟,裁员减支; • Nolans 项目的资金开支有所增加。 Page 8
  9. 9. 2012 年项目工作安排目前开展的基本工作 • 项目整体规划方案草稿/项目状态更新; • 项目工程方面经过独立性的审查; • 生产氧化镧为市场评估; • 在ANSTO的酸洗示范厂正在运作中; • 确定战略合作伙伴和承购合同; • 筹集资金以完成最后的可行性研究。改进加工工艺的研究 • 在初步酸洗中减少化学药剂用量; • 简化盐酸再生工艺; • 有可能使用成本较低的稀土回剂; • 减少滞留时间和酸洗及稀土回工厂的规模; • 通过减少硫化酸烘烤温度和时间来改进能源消耗; • 提高碳酸稀土的纯度可降低溶剂萃取工厂的规模和试剂消耗。 Page 9
  10. 10. 2012年 ~ 2013年的下一步技术方面 • 综合试点厂 • 进一步试点的稀土分离过程工程方面 • 开采规划 – 最后阶段 • 矿山和选矿厂工程 • 运输及物流 • 稀土加工厂的施工其它方面 • 环境影响研究的建议书 • 项目融资 • 战略合作伙伴最终的项目整体规划方案 Page 10
  11. 11. 总结归纳Arafura 和 Nolans项目: 尽管短期内有项目融资挑 战,但项目仍有引人注目的商业价值• 公司拥有深思熟虑的计划将Nolans项目的整体规规划方案完成;• Nolans项目是澳大利亚的一个先进项目,有可能成为近十年来少有 项目之一; - 世界级规模的资源,矿山寿命长而且深度有拓展潜力; - 最小的资源风险; - 加工生产设计灵活,为进一步增长保留余地; - 从Nolans矿分离的氧化稀土纯度可达99%;产品规格已通过潜在市场的 验证;• 公司同两家跨国公司达成承购意向书并得到在项目发展方面的支持;• 项目受到政府和社会各界的支持。 Page 11
  12. 12. 谢谢!Chris Tonkin – 首席执行官2012年7月11日

×