Développement Shigawake Development


                          Log Cabin & Camp Grounds
Development Plan Summary

As based on development committee meeting October 29, 2012 at the log cabin

Participants: Mayor Ken Duguay, Councillor Denzil Ross, Joanne Ross, Giselle Delarosbil, Nikki
Hayes, Jennifer Hayes

FINAL PLAN MUST BE SUBMITTED BY NOVEMBER 9th, 2012.

The Log Cabin and surrounding grounds and facilities support 2 key elements of Shigawake’s
development:

    1) Family & Seniors’ Policy
    2) Tourism Development

All investments undertaken must fulfill the town’s priorities with regards to these 2 sections of
our development plans.



PHASE 1 to be completed spring / summer 2013

New restroom facility: must be clean and accessible for all users. Must be secure. Must also
service needs of camp site users and tourists.

        -   Wheelchair accessible
        -   Multiple toilets in stalls
        -   Sink, soap, mirror area
        -   Constructed of materials easy to clean with a hose or pressure sprayer if necessary
        -   Unit to store and LIMIT use of toilet paper
        -   Baby change station
        -   Washer & dryer
        -   Shower stalls
        -   Heavy duty exterior door with key access

Ken & Denzil to collaborate on design and share with committee for questions or comments.
Also tasked to request quotation from contractor.




                                                                                                    1
Développement Shigawake Development

FUTURE PHASES under FAMILY & SENIORS’ POLICY

      -   More play equipment for young children to be purchased and installed
      -   A walking track suitable for walkers, joggers, baby carriages, wheelchairs will be
          constructed around the perimeter of play area
      -   An extension to the existing falls trail will allow hikers to access the falls directly
          from the Log Cabin
      -   Skating rink surface to be cemented, or asphalt; whichever is best for rink
          functionality
      -   Installation of snow fence on the west side of the skating rink, 8ft high
      -   New boards around the rink
      -   Installation of bleachers / players boxes at rink side so parents with children and
          spectators have a place to be seated.



FUTURE PHASES under TOURISM DEVELOPMENT

      -   Achieve direct access to the beach and wharf from camping site and walking trails
      -   Focus on completing the campsite to service non-motorized camping clientele
          (camping sauvage)
      -   Complete the yurt project as detailed in the development plan
      -   Install lighting along trails to campsites
      -   Establish an independent business to run a year round canteen at the cabin
      -   Build fire pits at the campsites, and a fire/bbq pit in the common area
      -   Establish an agreement with the local depanneur to carry sundry camping supplies
          and items (pegs, tarps, etc.)
      -   Coordinate an inter-municipal nature trail map of municipalities of Shigawake to
          Hope detailing trail locations, accessibility and skill levels for tourists.




                                                                                                    2

More Related Content

What's hot

Constructed landscape project 1
Constructed landscape project 1Constructed landscape project 1
Constructed landscape project 1Js Cheok
 
Adhiraj Samyama - Kharghar, Navi Mumbai
Adhiraj Samyama - Kharghar, Navi MumbaiAdhiraj Samyama - Kharghar, Navi Mumbai
Adhiraj Samyama - Kharghar, Navi Mumbaiinventors Realty
 
Portfolio_RobinMassingill_2015
Portfolio_RobinMassingill_2015Portfolio_RobinMassingill_2015
Portfolio_RobinMassingill_2015Robin Massingill
 
Parks District meeting - 04/25
Parks District meeting - 04/25Parks District meeting - 04/25
Parks District meeting - 04/25Grace Stainback
 
Unravelling Urban Design project 2
Unravelling Urban Design project 2Unravelling Urban Design project 2
Unravelling Urban Design project 2Ka Long Bryan Wong
 
Rk Site Master Plan Update
Rk Site Master Plan UpdateRk Site Master Plan Update
Rk Site Master Plan Updaterdekam
 
Housing Task Force Work Session Presentation #3
Housing Task Force Work Session Presentation #3Housing Task Force Work Session Presentation #3
Housing Task Force Work Session Presentation #3SharswoodBlumberg
 
Unravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategyUnravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategyKa Long Bryan Wong
 
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...AvantikaBadgujar
 

What's hot (13)

BUMC
BUMCBUMC
BUMC
 
Constructed landscape project 1
Constructed landscape project 1Constructed landscape project 1
Constructed landscape project 1
 
Adhiraj Samyama - Kharghar, Navi Mumbai
Adhiraj Samyama - Kharghar, Navi MumbaiAdhiraj Samyama - Kharghar, Navi Mumbai
Adhiraj Samyama - Kharghar, Navi Mumbai
 
Portfolio_RobinMassingill_2015
Portfolio_RobinMassingill_2015Portfolio_RobinMassingill_2015
Portfolio_RobinMassingill_2015
 
Ici final project
Ici final projectIci final project
Ici final project
 
Parks District meeting - 04/25
Parks District meeting - 04/25Parks District meeting - 04/25
Parks District meeting - 04/25
 
Water Works Design Update - 9.27.18 open house
Water Works Design Update - 9.27.18 open houseWater Works Design Update - 9.27.18 open house
Water Works Design Update - 9.27.18 open house
 
Unravelling Urban Design project 2
Unravelling Urban Design project 2Unravelling Urban Design project 2
Unravelling Urban Design project 2
 
Rk Site Master Plan Update
Rk Site Master Plan UpdateRk Site Master Plan Update
Rk Site Master Plan Update
 
Housing Task Force Work Session Presentation #3
Housing Task Force Work Session Presentation #3Housing Task Force Work Session Presentation #3
Housing Task Force Work Session Presentation #3
 
Unravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategyUnravelling Urban Design Project3 public artstrategy
Unravelling Urban Design Project3 public artstrategy
 
STA. BARBARA HEIGHTS
STA. BARBARA HEIGHTS STA. BARBARA HEIGHTS
STA. BARBARA HEIGHTS
 
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...
Community based tourism - Case study (Thanh Ha pottery village |Miso walai Ho...
 

Similar to Log cabin meeting summary

City of Salina Parks and Recreation Draft Master Plan-Section 2
City of Salina Parks and Recreation Draft Master Plan-Section 2City of Salina Parks and Recreation Draft Master Plan-Section 2
City of Salina Parks and Recreation Draft Master Plan-Section 2City of Salina
 
City of Salina Parks and Recreation Master Plan-Section 2
City of Salina Parks and Recreation Master Plan-Section 2City of Salina Parks and Recreation Master Plan-Section 2
City of Salina Parks and Recreation Master Plan-Section 2City of Salina
 
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...Au Dormitory, Sra Pou vocational school, sos children village, econef childre...
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...Sumaiya Islam
 
WunderHaus Bavarian Tourist Village (Family Involvement)
WunderHaus Bavarian Tourist Village (Family Involvement)WunderHaus Bavarian Tourist Village (Family Involvement)
WunderHaus Bavarian Tourist Village (Family Involvement)Doug Bertram
 
WunderHaus Bavarian Tourist Village (Direct Purchase)
WunderHaus Bavarian Tourist Village (Direct Purchase)WunderHaus Bavarian Tourist Village (Direct Purchase)
WunderHaus Bavarian Tourist Village (Direct Purchase)Doug Bertram
 
Grandview District analysis + frameworks
Grandview District analysis + frameworksGrandview District analysis + frameworks
Grandview District analysis + frameworksWigley and Associates
 
URA Task Force - PDNA
URA Task Force - PDNAURA Task Force - PDNA
URA Task Force - PDNAmazik
 
Nikola Dakic - Portfolio
Nikola Dakic - PortfolioNikola Dakic - Portfolio
Nikola Dakic - Portfolionikoladakic
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolionikoladakic
 
4 Skeppies Application Example 2 Of Supporting Photos Pof
4 Skeppies Application Example 2 Of Supporting Photos Pof4 Skeppies Application Example 2 Of Supporting Photos Pof
4 Skeppies Application Example 2 Of Supporting Photos Pofmelissagmoye
 
Irene Stern Butterfly and Pollinator Garden in Fulshear Texas
Irene Stern Butterfly and Pollinator Garden in Fulshear TexasIrene Stern Butterfly and Pollinator Garden in Fulshear Texas
Irene Stern Butterfly and Pollinator Garden in Fulshear TexasTajana Surlan
 
Nikola Dakic - Portfolio
Nikola Dakic - PortfolioNikola Dakic - Portfolio
Nikola Dakic - Portfolionikoladakic
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolionikoladakic
 

Similar to Log cabin meeting summary (13)

City of Salina Parks and Recreation Draft Master Plan-Section 2
City of Salina Parks and Recreation Draft Master Plan-Section 2City of Salina Parks and Recreation Draft Master Plan-Section 2
City of Salina Parks and Recreation Draft Master Plan-Section 2
 
City of Salina Parks and Recreation Master Plan-Section 2
City of Salina Parks and Recreation Master Plan-Section 2City of Salina Parks and Recreation Master Plan-Section 2
City of Salina Parks and Recreation Master Plan-Section 2
 
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...Au Dormitory, Sra Pou vocational school, sos children village, econef childre...
Au Dormitory, Sra Pou vocational school, sos children village, econef childre...
 
WunderHaus Bavarian Tourist Village (Family Involvement)
WunderHaus Bavarian Tourist Village (Family Involvement)WunderHaus Bavarian Tourist Village (Family Involvement)
WunderHaus Bavarian Tourist Village (Family Involvement)
 
WunderHaus Bavarian Tourist Village (Direct Purchase)
WunderHaus Bavarian Tourist Village (Direct Purchase)WunderHaus Bavarian Tourist Village (Direct Purchase)
WunderHaus Bavarian Tourist Village (Direct Purchase)
 
Grandview District analysis + frameworks
Grandview District analysis + frameworksGrandview District analysis + frameworks
Grandview District analysis + frameworks
 
URA Task Force - PDNA
URA Task Force - PDNAURA Task Force - PDNA
URA Task Force - PDNA
 
Nikola Dakic - Portfolio
Nikola Dakic - PortfolioNikola Dakic - Portfolio
Nikola Dakic - Portfolio
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolio
 
4 Skeppies Application Example 2 Of Supporting Photos Pof
4 Skeppies Application Example 2 Of Supporting Photos Pof4 Skeppies Application Example 2 Of Supporting Photos Pof
4 Skeppies Application Example 2 Of Supporting Photos Pof
 
Irene Stern Butterfly and Pollinator Garden in Fulshear Texas
Irene Stern Butterfly and Pollinator Garden in Fulshear TexasIrene Stern Butterfly and Pollinator Garden in Fulshear Texas
Irene Stern Butterfly and Pollinator Garden in Fulshear Texas
 
Nikola Dakic - Portfolio
Nikola Dakic - PortfolioNikola Dakic - Portfolio
Nikola Dakic - Portfolio
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolio
 

Log cabin meeting summary

  • 1. Développement Shigawake Development Log Cabin & Camp Grounds Development Plan Summary As based on development committee meeting October 29, 2012 at the log cabin Participants: Mayor Ken Duguay, Councillor Denzil Ross, Joanne Ross, Giselle Delarosbil, Nikki Hayes, Jennifer Hayes FINAL PLAN MUST BE SUBMITTED BY NOVEMBER 9th, 2012. The Log Cabin and surrounding grounds and facilities support 2 key elements of Shigawake’s development: 1) Family & Seniors’ Policy 2) Tourism Development All investments undertaken must fulfill the town’s priorities with regards to these 2 sections of our development plans. PHASE 1 to be completed spring / summer 2013 New restroom facility: must be clean and accessible for all users. Must be secure. Must also service needs of camp site users and tourists. - Wheelchair accessible - Multiple toilets in stalls - Sink, soap, mirror area - Constructed of materials easy to clean with a hose or pressure sprayer if necessary - Unit to store and LIMIT use of toilet paper - Baby change station - Washer & dryer - Shower stalls - Heavy duty exterior door with key access Ken & Denzil to collaborate on design and share with committee for questions or comments. Also tasked to request quotation from contractor. 1
  • 2. Développement Shigawake Development FUTURE PHASES under FAMILY & SENIORS’ POLICY - More play equipment for young children to be purchased and installed - A walking track suitable for walkers, joggers, baby carriages, wheelchairs will be constructed around the perimeter of play area - An extension to the existing falls trail will allow hikers to access the falls directly from the Log Cabin - Skating rink surface to be cemented, or asphalt; whichever is best for rink functionality - Installation of snow fence on the west side of the skating rink, 8ft high - New boards around the rink - Installation of bleachers / players boxes at rink side so parents with children and spectators have a place to be seated. FUTURE PHASES under TOURISM DEVELOPMENT - Achieve direct access to the beach and wharf from camping site and walking trails - Focus on completing the campsite to service non-motorized camping clientele (camping sauvage) - Complete the yurt project as detailed in the development plan - Install lighting along trails to campsites - Establish an independent business to run a year round canteen at the cabin - Build fire pits at the campsites, and a fire/bbq pit in the common area - Establish an agreement with the local depanneur to carry sundry camping supplies and items (pegs, tarps, etc.) - Coordinate an inter-municipal nature trail map of municipalities of Shigawake to Hope detailing trail locations, accessibility and skill levels for tourists. 2