SlideShare a Scribd company logo
1 of 57
ASSET LIFE CYCLE, COST
ESTIMATING AND THE CCRG
Alberta Assessors’ Association
2015 Pre-Conference Course
Salvador Hernandez, Verus Capital Assessments
Dan Driscoll, A.M.A.A.
John Elzinga, A.M.A.A.
Carol Zukiwski, Reynolds Mirth Richards & Farmer LLP
1
INTRODUCTION
• Introduce panel
• Review course outline
• Review course objectives
• Identify industry terminology and practice
• Show how the assessment legislation overlays industry
terminology and practice
2
CCRG BACKGROUND
• Previous document Special Purpose Property
Assessment Guide (SPAG)
• SPAG in use under MTA
• CCRG Working Group 1999 - ______
• CCRG is a regulation
• When is the CCRG used?
• Legislation chart - handout
3
CCRG OVERVIEW –
Basic Principles
• Dan to work on hypotetical project with multiple
components hitting different assessment methodologies:
Linear properties, buildings, land, M&E, CCRG
4
CCRG OVERVIEW –
Basic Principles
• Terminology – included costs – excluded costs
• The term non-assessable can have multiple meanings:
(i) s. 298, (ii) s. 291, and (iii) excluded cost under the
CCRG
• Project cost
• Construction cost
5
CCRG OVERVIEW –
Basic Principles
• How the CCRG is laid out
• Obligation on property owner to prove claims for
excluded costs
• Limited number of categories of excluded costs
6
CCRG OVERVIEW –
Main Areas of Dispute
• Section 1.000 – costs to be included
• Do the project costs include feasibility studies?
• Do the project costs include those incurred by the general
contractor(s) plus those incurred by the owner?
• Do the project costs include the cost of bidding and
tendering?
• Do the project costs include the cost incurred by the owner
to supervise the contractor, or to do quality control in the
factory?
• When do construction costs start being incurred?
• What is a construction cost?
7
CCRG OVERVIEW –
Main Areas of Dispute
• Section 2.000 – costs to be excluded
• Is there a section which allows for the exclusion of the cost
of the DBM and EDS?
• Are all design changes or re-work an excluded cost?
• At what point in time do you measure an abnormal cost?
• What is the benchmark of a normal cost against which an
abnormal claim is made?
• Do you measure abnormal claims against what is typical for
the municipality? Or do you measure against what is typical
or normal in the Edmonton area?
• Are all delays or schedule slippage an abnormal cost?
8
ASSET LIFE CYCLE –
Expenditures Over Time
9
Business
Planning
Definition
Optimization
Execution
Operations
Handover
Life of
the Asset
Early
Funding
Advanced
Commitment
Appropriation
For Expenditure
Tax Bills
EBITDA
Capital Expenditure Operational Expenditure
Concept
Selection
Assessment
Tax
Notice
ASSET LIFE CYCLE –
Phases Over Time
Project Life Cycle – Major Project Phases
10
Field
Execution
Engineering 6%
Procurement 32%
Field Execution 53%
C&SU 4%
Early Funding 2%
Optimizations 3%
ASSET LIFE CYCLE –
Phases Over Time
11
CEO’s Vision What Operations What Major Projects What Procurement CEO promise
Understood asked EPCs Purchased to
shareholders
What was documented What Operations What Owner paid for EPC’s support What the company
Received really needed
DBM / EDS / FEED
12
• Design Basis Memorandum (DBM) – FEL 1 or Pre-Feed
• Defines basis for further development of a main idea. Possibly includes a narrowed
down list of alternatives previously evaluated as well as descriptions of main
processes with high-level flow diagrams and general and/or special conditions for
continuous operations of facility. Results in a definitive alternative. Class 5 Estimate.
• Engineering Design Specifications (EDS) – FEL 2
• Includes design specificacions to increase definition what project should do/be.
Opportunity to optimize selected alternative. Includes preliminary plot plan,
preliminary size equipment list and major equipment list. Class 4 Estimate.
• Front End Engineering Design (FEED) – FEL 3
• The purpose is to further define project facilities to produce the Project
Specifications and Standards, and the Job Specification that serve as the basis for
Detailed Engineering. Deliverables of FEED are used to prepare bid/tender
packages for long leads items. Class 3 Estimate.
PROJECT MANAGEMENT
TEAM
(Owner’s Team)
13
• Purpose
• To build a team with the range and reach of skillsets in key competencies required to
meet project expectations. This group as a whole is responsible for overall project
performance.
• Expectation - Designed to ensure alignment in 3 dimensions:
•Vertical among company, project team & 3rd
parties: contractors and subcontractors.
•Horizonal among business functions, technical, and operational organizations.
•Time to maintain continuity of key personnel throughout project life cycle.
PROJECT MANAGEMENT
TEAM
(Owner’s Team)
14
• Management PMT Support
• 15% 60% 25%
Vicepresidents
Project Champions
Gatekeepers
Executives
Project Advisors
General Managers
Project Directors
Area Directors
PMO
Procurement Directors
Executive Assistants
Admin Assistants
Engineering Disciplines
Scheduling, Planning
Quality, Risk
Cost Estimating
Forecasting
Change Management
Business Services
Procurement
Construction
C&SU
Health, Safety & Envir.
Document Control
Human Rresources
Information Technology
Finance
Media Relations
Strategy
Accounts Payable
Real Estate
Travel Coordination
Security
Career Development
Regulatory Compliance
Shareholders Relations
TRANSITION TO
ASSESSMENT
• Assessors are concerned with CapEx (project costs)
• Municipalities are concerned with OpEx
• OPEX may be applicable for Schedule D additional
depreciation.
OpEx is the source of tax bills and a source to finance
municipalities expenditure operational and growth needs.
15
16
CCRG Overlay on Project Phases
16
Construction Cost
Field
Execution
Pre-Construction Cost Post-Construction Cost
Engineering 6%
Procurement 32%
Field Execution 53%
C&SU 4%
Early Funding 2%
Optimizations 3%
ASSET LIFE CYCLE –
Expenditures Over Time
1717
Business
Planning
Definition
Optimization
Execution
Operations
Handover
Life of
the Asset
Early
Funding
Advanced
Commitment
Appropriation
For Expenditure
CCRG Cost
Rendition
Tax Bills
EBITDA
Capital Expenditure Operational Expenditure
Concept
Selection
Assessment
Tax
Notice
Property
Tax
Rendition
Program
Multiple
Assessor
Reviews
ASSET LIFE CYCLE –
Expenditures Over Time – Assessment Timeline
Schedule D
CCRG ISSUES WHICH ARISE
• When does construction begin? When do construction
costs start?
• What are the differences between a feasibility study and
the DBM and EDS?
• Does the CCRG view of a construction cost differ from
industry’s view?
• Are the costs of bidding and tendering an included cost?
18
CCRG ISSUES WHICH ARISE
• CARB Decision – Canadian Natural Resources Limited v
Regional Municipality of Wood Buffalo, CARB 001-2014
• “[182] The municipality understood the CARB’s decision
to interpret “construction costs” to mean costs with a
sufficient nexus to the construction of bricks and mortar
or that facilitates construction of machinery and
equipment. The municipality also believed the CARB’s
order supported the view that abnormal costs, including
productivity losses were not measured against what was
typical or normal in central Alberta or Edmonton, but
were measured against what was typical or normal within
the municipality.” 19
CCRG ISSUES WHICH ARISE –
Owners Costs
• Term used by industry but does not appear in the CCRG
• Can be a “catch all” category for the owner to record costs related to:
• Home office overhead for PMO, IT, Finance, HR, Corporate
Support, Media PR
• Perks and trinkets
• Bidding and tendering
• Parties and celebrations, recognitions
• Supervision of the general contractor(s)
• Material and Equipment surplus/damaged
• Quality control in the factory
• PMT – Non dedicated personnel (40% of PMT)
20
CCRG ISSUES WHICH ARISE –
DBM/EDS
• Design Basis Memorandum (DBM)
• Typical contents – COAA document
• Engineering Design Specifications (EDS)
• Typical contents – COAA document
• Front End Loading (FEL) / Front End Engineering Design (FEED)
• Are the costs to prepare the DBM/EDS included or
excluded?
21
GROUP EXERCISE
Owners Costs / FEED
• Working at your table, please consider whether the list of
items shown on slide 16 (owners costs) are: (i)
construction costs – refer to CCRG section, and (ii)
which costs are excluded costs – and identify the
applicable CCRG section which could allow for their
exclusion
• Complete your answers in the template provided
22
GROUP EXERCISE
Owners Costs / FEED – De-brief
• Exercise De-Brief
23
ASSET LIFE CYCLE
24
ESTIMATE CLASSIFICATION &
TYPES OF CONTRACTS
25
ESTIMATE CLASSIFICATION &
TYPES OF CONTRACTS
26
ESTIMATE CLASSIFICATION &
TYPES OF CONTRACTS
27
Fixed Price
Lump Sum
Cost Plus Incentive
Time & Materials
Cost Reimbursable
Unit Rates
Contractor’s Risk
100%
0%
0%
100%
Owner’s Risk
Few Change Orders Max Change Orders
ESTIMATE CLASSIFICATION &
TYPES OF CONTRACTS
28
CCRG ISSUES WHICH ARISE
Cost Estimating
• Information found on the Authorization for Expenditure (AFE)
is useful to understand the scope of the work. An AFE is
typically a class 3 estimate:
• Known technology industry accuracy -20% + 30% (Power)
• New technology industry accuracy –30% + 50% (Oil sands)
• CCRG requires final project costs, not even class 1 estimates
• Assessors need to ask for final project costs, commonly
called by industry: Total Installed Cost or Total Final Project
Cost
1. Make sure project has been de-supplemented (AFE removed)
29
CCRG ISSUES WHICH ARISE
Lump Sum Contracts
• Property owner cannot break out possible excluded costs
• Examples of how this is handled in practice:
• 1. Ask for details of the buildup of the LS contract
• 2. Apply the rest of the project factors to the LS contract
• 3. Calculate from a similar facility
• 4. Producing capacity comparable analisys
• Onus remains on the property Owner to segregate and
substantiate costs claims as per CCRG 2005 30
SECTION 2.500 ABNORMAL COSTS
Basic Principles
• Types of claims under this heading include: labour productivity
losses, schedule slippage, delays, inclement weather, work
slow down, accidents, natural disaster, a cost not normally
incurred in a balanced market, a cost excluded to maintain
consistency among regulated properties:
• This requires clear definition on a case by case basis because
there are multiple scenarios possible on each concept
mentioned above. Companies need to come forward with full
cost details and traceability to let the assessor decide on each
case as each project is different by deifnition.
31
SECTION 2.500 ABNORMAL COSTS
Basic Principles
• From a review of the section we can see several principles
• Labour force available – travel excluded s. 2.500.100
• Materials and parts are available – transportation past
Edmonton excluded s. 2.500.200
• Interest during construction is excluded – s. 2.500.300
• Premium payments for overtime are excluded – s. 2.500.400
32
SECTION 2.500 ABNORMAL COSTS
Basic Principles
• Typical or normal varies over time
• Typical or normal varies by location
• Typical or normal varies by industry
• Requirement to measure actual costs against typical or normal
• Obligation on the property owner to establish typical or normal,
time period, location and the industry constructed.
33
SECTION 2.500 ABNORMAL COSTS
Basic Principles
• How do you measure a balanced market?
• Back to basic principles – varies by location, industry and over
time
• Measure market during the period of construction
• If everyone in the industry/location is experiencing the same
pressure – is normal.
• Deviations from that normal can be abnormals.
34
SECTION 2.500 ABNORMAL COSTS
Basic Principles
• Cost excluded to maintain consistency among regulated
properties
• CCRG used by the Regulated Property Unit to prepare the
rates in the Minister’s Guidelines
35
CHANGE MANAGEMENT
A process whereby changes in the Scope of Work agreed to by the
Owner and Contractor are implemented via Change Orders.
Change Orders are additions, deletions of scope which alter the
original contract cost and/or completion date.
CO’s are common in large projects under cost reimbursable
contracts. Seldom seen in Lump Sum/Fixed Price contracts.
1.Project schedule/scope/cost incorrectly estimated.
2.Owner discovers possible efficiencies that require deviations from
original plans.
3.Contractor underestimated efficiencies and additional cost, time
or scope must be added to complete project
36
CHANGE MANAGEMENT
37
CHANGE MANAGEMENT
38
0%
25%
50%
75%
100%
Business
Planning
Feasibility
Studies
Concept
Optimization
Basic Design E&P Construction C&SU
Cost of Change
# of Changes
As projects progress, changes are more costly but fewer
CHANGE MANAGEMENT
Challenges for Owners
Cost Reimbursable: Contractors low ball bids seeking to turn it into
change management heavens.
Company Staff Turnover: A manager may approve a change that
his/her replacement may reject. And viceversa.
Company/EPC Change Management Culture: Change order forms
are poorly filled and no relevant info is avaliable to assess a change.
EPC does not adhere to company processes: Competing
contractors blame each other for delays, availability of work fronts.
39
CHANGE MANAGEMENT
40
Queen Isabella Causeway near South Padre Island, Texas, September 15, 2001
United States Coast Guard, CWO2 Robert Wyman
CHANGE MANAGEMENT
41
Can you live with it as it is?
SECTION 2.500 ABNORMAL COSTS
Labour Productivity
42
Field labour productivity is the single greatest variable in any cost
estimate and it is extremely difficult to estimate.
Direct field labour constitutes a high percentage of the total cost
of a project from 15% to 25%.
Productivity variations are based on:
Type of project, world and regional location, contractor’s morale,
owner’s management, project’s culture, weather, technology, time
of the year, craft availability, labour mix (local vs expatriate vs
extra-provincial), degree of supervision and degree of skillset to
use equipmentm learning curve effect, job size, project change
orders.
SECTION 2.500 ABNORMAL COSTS
Engineering Productivity
43
Engineering productivity is also subject to variations similar to
labour productivity, but easier to estimate and quantify.
Engineering productivity range from 10% to 15%.
Variations are based on:
Type of project, world and regional location, contractor’s morale,
owner’s management, project’s culture, weather, technology,
engineers avalability and mix (local vs expatriate vs extra-
provincial), degree of supervision and job size.
SECTION 2.500 ABNORMAL COSTS
Labour Productivity
Process to establish the normal vs abnormals:
Projects establish a Base Productivity to define what can be
expected as a normal condition in that particular project.
Abnormals are deviations from Base Productivity
There are always abnormal conditions related to any project,
whether they were captured as such is another story.
44
SECTION 2.500 ABNORMAL COSTS
Labour Productivity
45
DFL Non-Productive Time
10 hr shift
6%
12%
10%
6%
16%
50%
Actual Work Time Idle/ Moving Instructions
Socializing Tools & Matls. Other
University of Calgary – Productivity in Construction Research Studies
SECTION 2.500 ABNORMAL COSTS
Labour Productivity
Overtime Premium – Day Shifts
46
Calculating Overtime Premium:
ST $70/hr & OT $97.5/hr
Delta ST vs OT = $27.5/hr
OT Premium = (27.5/70) = 39.2%
Days
On
Days
Off
One
Cycle
Hours
Worked
Standard
Time
Over
Time
Cost
Increase
Base
Productivity
4 3 7 40 40 0 0% 100%
5 2 7 50 40 10 3.9% 90%
6 1 7 60 40 20 7.9% 80%
10 4 14 100 70 30 11.8% 75%
21 7 28 210 120 90 35.4% 64%
35 21 56 350 200 150 58.9% 60%
Job Rotations in Remote Locations
SECTION 2.500 ABNORMAL COSTS
Labour Productivity
More than one way to calculate actual productivity depending info available
47
1. Productivity = QAB workhours
Actual workhours
2. Productivity = % physical completion
% of QAB workhours
3. Productivity = Budget Unit Rate
Actual Unit Rates
QAB – Quantity Adjusted Budget: Includes adjustment for actual conditions on site to reflect real productivity
SECTION 2.500 ABNORMAL COSTS
Delays / Schedule Slippage
The Schedule Control Basis, typically includes the following:
1.The Plan
2.Schedule Control Baseline
3.Planned Schedule
4.Schedule Basis
5.Schedule Control Plan
Schedule Basis covers assumptions, inclusions, exclusions, risk and
uncertainty as well as schedule contingencies, such as inclement
weather. Schedule slippage and delays are incorporated into the
schedule as they happen as they are usually EPC change orders.
48
SECTION 2.500 ABNORMAL COSTS
Edmonton Area
• Historically under SPAG, all abnormal costs were compared to
normal costs in the Edmonton area
• This was because prior to 1995 all assessments were
regulated based on cost manuals which reflected Edmonton
area costs
• There is a debate as to whether abnormal cost claims are still
measured against what is typical or normal in Edmonton
• Only mention of Edmonton area is in s. 2.500.200 with regard
to transportation costs
• If this is the case – conflicts with the basic principles under s.
2.500
49
DESIGN CHANGES s. 2.300.400
INTERFERENCE COSTS s. 2.300.500
• Most projects have some costs for re-work
• The allowance for re-work is often found in the following
documents:
• ___________________
• ___________________
• Generally interference costs are for brownfield sites
50
TRAVEL s. 2.500.100
TRANSPORTATION s. 2.500.200
• Travel to the site is excluded.
• Travel within the site would be an included cost.
• Transportation costs of materials within the site are an
included cost.
• The cost of loading and unloading the raw materials and
components is included.
51
TRANSPORTATION s. 2.500.200
IMPORT DUTIES & BROKER FEES S. 2.300.700
• Consider that nine countries shipped equipment worth $392M CAD
to a job site in RMWB in circa. 2006. Generating costs for
transportation and import duties and brokerage fees.
• Austria Canada Germany
• Holland Italy Mexico
• Spain Sweden USA
• Transportation cost to EDM included, from EDM to jobsite excluded
• Duties & Fees all excluded
52
SITE PREPARATION
Page 8 of the Interpretive Guide
• The cost to clear, level and finish the site is an included cost
• Except if the land assessment is based on the value of finished
industrial land (stripped or graded) – then the actual site
preparation costs for stripping and grading are excluded but
any other site preparation costs are included
53
CCRG BEST PRACTICES
Establish Expectations
• Recommend a meeting with the property owner early in the
construction process to set out expectations with regard to: (i)
types of documents required, (ii) interpretation and application
of the CCRG
• Have regular follow up meetings, steer conversations to have
cost-data discussions segregating included vs excluded.
• Cost reporting should comply with the requirements of the
CCRG
• Claims for excluded costs should be made under a section of
the CCRG
• Re-work your RFI to set out your expectations regarding the
CCRG, and the cost reporting
54
CCRG BEST PRACTICES
Documents
• Depending on the scope of the project, it is good practice to
request:
• Feasibility study
• DBM and EDS
• The sanction budget, and all updates to the budget
• AFE’s and final cost reconciliation documents
• Change orders – which relate to claims for abnormal costs
• Man power plan for the PMT
• ________________________________________________
55
COURSE WRAP UP
56
THANK YOU FOR YOUR ATTENTION
QUESTIONS ARE WELCOME
Salvador Hernandez, Verus Capital Assessments
email: salvador@vecaas.ca
phone: 1-403-690-3053
Dan Driscoll, A.M.A.A.
email: dandriscoll@shaw.ca
John Elzinga, A.M.A.A.
email: john.a.elzinga@gmail.ca
Carol Zukiwski, RMRF LLP
email: czukiwski@rmrf.com
phone: 1-780-497-3350
57

More Related Content

What's hot

Business Architecture and Enterprise Planning
Business Architecture and Enterprise PlanningBusiness Architecture and Enterprise Planning
Business Architecture and Enterprise Planningi3 Technologies, Inc
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterScottMadden, Inc.
 
Architecture Series 5-1 EA As Corporate Strategy Introduction
Architecture Series 5-1   EA As Corporate Strategy   IntroductionArchitecture Series 5-1   EA As Corporate Strategy   Introduction
Architecture Series 5-1 EA As Corporate Strategy IntroductionFrankie Hsiang
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsAlan McSweeney
 
Ea As A Strategy M Veeraragaloo Approach
Ea As A Strategy   M Veeraragaloo ApproachEa As A Strategy   M Veeraragaloo Approach
Ea As A Strategy M Veeraragaloo ApproachMaganathin Veeraragaloo
 
Shah rakesh executive
Shah rakesh executiveShah rakesh executive
Shah rakesh executivershah1976
 
Agile Strategic Facilities Plan
Agile Strategic Facilities PlanAgile Strategic Facilities Plan
Agile Strategic Facilities PlanRobert Lambe, CFM
 
The Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor ViabilityThe Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor ViabilityProformative, Inc.
 
Enterprise architecture framework business case
Enterprise architecture framework business caseEnterprise architecture framework business case
Enterprise architecture framework business caseAlex Antonatos
 
Business Impact Analysis
Business Impact AnalysisBusiness Impact Analysis
Business Impact Analysisdlfrench
 
Capability based planning compressed
Capability based planning   compressedCapability based planning   compressed
Capability based planning compressedDavid Izzard
 
Practical BPM
Practical BPMPractical BPM
Practical BPMminorifh
 
Mega project not mega problems session 2
Mega project not mega problems session 2Mega project not mega problems session 2
Mega project not mega problems session 2Aconex
 
Dennis Batdorf resume
Dennis Batdorf resumeDennis Batdorf resume
Dennis Batdorf resumeDennis Batdorf
 
IFG Finance Accounting and Risk Solutions
IFG Finance Accounting and Risk SolutionsIFG Finance Accounting and Risk Solutions
IFG Finance Accounting and Risk SolutionsJames Hannan, CPA
 
Successful Outsourcing Transitions Webinar Presentation
Successful Outsourcing Transitions Webinar PresentationSuccessful Outsourcing Transitions Webinar Presentation
Successful Outsourcing Transitions Webinar PresentationNeo Group Inc
 
ITSM Academy Webinar - Establishing A Business Process Group
ITSM Academy Webinar - Establishing A Business Process GroupITSM Academy Webinar - Establishing A Business Process Group
ITSM Academy Webinar - Establishing A Business Process GroupITSM Academy, Inc.
 
G Holmes CV - BA-STA
G Holmes CV - BA-STAG Holmes CV - BA-STA
G Holmes CV - BA-STAGraham Holmes
 

What's hot (20)

Agile Paper Cutter
Agile Paper CutterAgile Paper Cutter
Agile Paper Cutter
 
Business Architecture and Enterprise Planning
Business Architecture and Enterprise PlanningBusiness Architecture and Enterprise Planning
Business Architecture and Enterprise Planning
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
 
Architecture Series 5-1 EA As Corporate Strategy Introduction
Architecture Series 5-1   EA As Corporate Strategy   IntroductionArchitecture Series 5-1   EA As Corporate Strategy   Introduction
Architecture Series 5-1 EA As Corporate Strategy Introduction
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation Solutions
 
Ea As A Strategy M Veeraragaloo Approach
Ea As A Strategy   M Veeraragaloo ApproachEa As A Strategy   M Veeraragaloo Approach
Ea As A Strategy M Veeraragaloo Approach
 
Shah rakesh executive
Shah rakesh executiveShah rakesh executive
Shah rakesh executive
 
Agile Strategic Facilities Plan
Agile Strategic Facilities PlanAgile Strategic Facilities Plan
Agile Strategic Facilities Plan
 
The Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor ViabilityThe Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor Viability
 
Enterprise architecture framework business case
Enterprise architecture framework business caseEnterprise architecture framework business case
Enterprise architecture framework business case
 
Roi Charts
Roi ChartsRoi Charts
Roi Charts
 
Business Impact Analysis
Business Impact AnalysisBusiness Impact Analysis
Business Impact Analysis
 
Capability based planning compressed
Capability based planning   compressedCapability based planning   compressed
Capability based planning compressed
 
Practical BPM
Practical BPMPractical BPM
Practical BPM
 
Mega project not mega problems session 2
Mega project not mega problems session 2Mega project not mega problems session 2
Mega project not mega problems session 2
 
Dennis Batdorf resume
Dennis Batdorf resumeDennis Batdorf resume
Dennis Batdorf resume
 
IFG Finance Accounting and Risk Solutions
IFG Finance Accounting and Risk SolutionsIFG Finance Accounting and Risk Solutions
IFG Finance Accounting and Risk Solutions
 
Successful Outsourcing Transitions Webinar Presentation
Successful Outsourcing Transitions Webinar PresentationSuccessful Outsourcing Transitions Webinar Presentation
Successful Outsourcing Transitions Webinar Presentation
 
ITSM Academy Webinar - Establishing A Business Process Group
ITSM Academy Webinar - Establishing A Business Process GroupITSM Academy Webinar - Establishing A Business Process Group
ITSM Academy Webinar - Establishing A Business Process Group
 
G Holmes CV - BA-STA
G Holmes CV - BA-STAG Holmes CV - BA-STA
G Holmes CV - BA-STA
 

Similar to CCRG 2005 Alberta Assessors Association Conference Seminar

4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motoraroosa khan
 
2.requirements management
2.requirements management2.requirements management
2.requirements managementPanos Fitsilis
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
24 Concepts LEED AP
24 Concepts LEED AP24 Concepts LEED AP
24 Concepts LEED APRob Freeman
 
The fact that your poject is agile is not (necessarily) a cost driver arlen...
The fact that your poject is agile is not (necessarily) a cost driver   arlen...The fact that your poject is agile is not (necessarily) a cost driver   arlen...
The fact that your poject is agile is not (necessarily) a cost driver arlen...Nesma
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIARichard Goins
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptxxego1
 
Structural Audit and Selection of Contractor for Building by Using Analytical...
Structural Audit and Selection of Contractor for Building by Using Analytical...Structural Audit and Selection of Contractor for Building by Using Analytical...
Structural Audit and Selection of Contractor for Building by Using Analytical...IRJET Journal
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
Unit viii preparation of project report
Unit viii preparation of project reportUnit viii preparation of project report
Unit viii preparation of project reporttaruian
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...Alberto Sanchez
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 

Similar to CCRG 2005 Alberta Assessors Association Conference Seminar (20)

4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motor
 
REEP[1]
REEP[1]REEP[1]
REEP[1]
 
2.requirements management
2.requirements management2.requirements management
2.requirements management
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
24 Concepts LEED AP
24 Concepts LEED AP24 Concepts LEED AP
24 Concepts LEED AP
 
The fact that your poject is agile is not (necessarily) a cost driver arlen...
The fact that your poject is agile is not (necessarily) a cost driver   arlen...The fact that your poject is agile is not (necessarily) a cost driver   arlen...
The fact that your poject is agile is not (necessarily) a cost driver arlen...
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIA
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
 
Structural Audit and Selection of Contractor for Building by Using Analytical...
Structural Audit and Selection of Contractor for Building by Using Analytical...Structural Audit and Selection of Contractor for Building by Using Analytical...
Structural Audit and Selection of Contractor for Building by Using Analytical...
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
Unit viii preparation of project report
Unit viii preparation of project reportUnit viii preparation of project report
Unit viii preparation of project report
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 

Recently uploaded

Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Sonam Pathan
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...saminamagar
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxHenryBriggs2
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...narwatsonia7
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfCharlynTorres1
 

Recently uploaded (20)

Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170Call Girls Near Surya International Hotel New Delhi 9873777170
Call Girls Near Surya International Hotel New Delhi 9873777170
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptx
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Laxmi Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Model Town  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Model Town DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Tilak Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdfMonastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
Monastic-Supremacy-in-the-Philippines-_20240328_092725_0000.pdf
 

CCRG 2005 Alberta Assessors Association Conference Seminar

  • 1. ASSET LIFE CYCLE, COST ESTIMATING AND THE CCRG Alberta Assessors’ Association 2015 Pre-Conference Course Salvador Hernandez, Verus Capital Assessments Dan Driscoll, A.M.A.A. John Elzinga, A.M.A.A. Carol Zukiwski, Reynolds Mirth Richards & Farmer LLP 1
  • 2. INTRODUCTION • Introduce panel • Review course outline • Review course objectives • Identify industry terminology and practice • Show how the assessment legislation overlays industry terminology and practice 2
  • 3. CCRG BACKGROUND • Previous document Special Purpose Property Assessment Guide (SPAG) • SPAG in use under MTA • CCRG Working Group 1999 - ______ • CCRG is a regulation • When is the CCRG used? • Legislation chart - handout 3
  • 4. CCRG OVERVIEW – Basic Principles • Dan to work on hypotetical project with multiple components hitting different assessment methodologies: Linear properties, buildings, land, M&E, CCRG 4
  • 5. CCRG OVERVIEW – Basic Principles • Terminology – included costs – excluded costs • The term non-assessable can have multiple meanings: (i) s. 298, (ii) s. 291, and (iii) excluded cost under the CCRG • Project cost • Construction cost 5
  • 6. CCRG OVERVIEW – Basic Principles • How the CCRG is laid out • Obligation on property owner to prove claims for excluded costs • Limited number of categories of excluded costs 6
  • 7. CCRG OVERVIEW – Main Areas of Dispute • Section 1.000 – costs to be included • Do the project costs include feasibility studies? • Do the project costs include those incurred by the general contractor(s) plus those incurred by the owner? • Do the project costs include the cost of bidding and tendering? • Do the project costs include the cost incurred by the owner to supervise the contractor, or to do quality control in the factory? • When do construction costs start being incurred? • What is a construction cost? 7
  • 8. CCRG OVERVIEW – Main Areas of Dispute • Section 2.000 – costs to be excluded • Is there a section which allows for the exclusion of the cost of the DBM and EDS? • Are all design changes or re-work an excluded cost? • At what point in time do you measure an abnormal cost? • What is the benchmark of a normal cost against which an abnormal claim is made? • Do you measure abnormal claims against what is typical for the municipality? Or do you measure against what is typical or normal in the Edmonton area? • Are all delays or schedule slippage an abnormal cost? 8
  • 9. ASSET LIFE CYCLE – Expenditures Over Time 9 Business Planning Definition Optimization Execution Operations Handover Life of the Asset Early Funding Advanced Commitment Appropriation For Expenditure Tax Bills EBITDA Capital Expenditure Operational Expenditure Concept Selection Assessment Tax Notice
  • 10. ASSET LIFE CYCLE – Phases Over Time Project Life Cycle – Major Project Phases 10 Field Execution Engineering 6% Procurement 32% Field Execution 53% C&SU 4% Early Funding 2% Optimizations 3%
  • 11. ASSET LIFE CYCLE – Phases Over Time 11 CEO’s Vision What Operations What Major Projects What Procurement CEO promise Understood asked EPCs Purchased to shareholders What was documented What Operations What Owner paid for EPC’s support What the company Received really needed
  • 12. DBM / EDS / FEED 12 • Design Basis Memorandum (DBM) – FEL 1 or Pre-Feed • Defines basis for further development of a main idea. Possibly includes a narrowed down list of alternatives previously evaluated as well as descriptions of main processes with high-level flow diagrams and general and/or special conditions for continuous operations of facility. Results in a definitive alternative. Class 5 Estimate. • Engineering Design Specifications (EDS) – FEL 2 • Includes design specificacions to increase definition what project should do/be. Opportunity to optimize selected alternative. Includes preliminary plot plan, preliminary size equipment list and major equipment list. Class 4 Estimate. • Front End Engineering Design (FEED) – FEL 3 • The purpose is to further define project facilities to produce the Project Specifications and Standards, and the Job Specification that serve as the basis for Detailed Engineering. Deliverables of FEED are used to prepare bid/tender packages for long leads items. Class 3 Estimate.
  • 13. PROJECT MANAGEMENT TEAM (Owner’s Team) 13 • Purpose • To build a team with the range and reach of skillsets in key competencies required to meet project expectations. This group as a whole is responsible for overall project performance. • Expectation - Designed to ensure alignment in 3 dimensions: •Vertical among company, project team & 3rd parties: contractors and subcontractors. •Horizonal among business functions, technical, and operational organizations. •Time to maintain continuity of key personnel throughout project life cycle.
  • 14. PROJECT MANAGEMENT TEAM (Owner’s Team) 14 • Management PMT Support • 15% 60% 25% Vicepresidents Project Champions Gatekeepers Executives Project Advisors General Managers Project Directors Area Directors PMO Procurement Directors Executive Assistants Admin Assistants Engineering Disciplines Scheduling, Planning Quality, Risk Cost Estimating Forecasting Change Management Business Services Procurement Construction C&SU Health, Safety & Envir. Document Control Human Rresources Information Technology Finance Media Relations Strategy Accounts Payable Real Estate Travel Coordination Security Career Development Regulatory Compliance Shareholders Relations
  • 15. TRANSITION TO ASSESSMENT • Assessors are concerned with CapEx (project costs) • Municipalities are concerned with OpEx • OPEX may be applicable for Schedule D additional depreciation. OpEx is the source of tax bills and a source to finance municipalities expenditure operational and growth needs. 15
  • 16. 16 CCRG Overlay on Project Phases 16 Construction Cost Field Execution Pre-Construction Cost Post-Construction Cost Engineering 6% Procurement 32% Field Execution 53% C&SU 4% Early Funding 2% Optimizations 3% ASSET LIFE CYCLE – Expenditures Over Time
  • 17. 1717 Business Planning Definition Optimization Execution Operations Handover Life of the Asset Early Funding Advanced Commitment Appropriation For Expenditure CCRG Cost Rendition Tax Bills EBITDA Capital Expenditure Operational Expenditure Concept Selection Assessment Tax Notice Property Tax Rendition Program Multiple Assessor Reviews ASSET LIFE CYCLE – Expenditures Over Time – Assessment Timeline Schedule D
  • 18. CCRG ISSUES WHICH ARISE • When does construction begin? When do construction costs start? • What are the differences between a feasibility study and the DBM and EDS? • Does the CCRG view of a construction cost differ from industry’s view? • Are the costs of bidding and tendering an included cost? 18
  • 19. CCRG ISSUES WHICH ARISE • CARB Decision – Canadian Natural Resources Limited v Regional Municipality of Wood Buffalo, CARB 001-2014 • “[182] The municipality understood the CARB’s decision to interpret “construction costs” to mean costs with a sufficient nexus to the construction of bricks and mortar or that facilitates construction of machinery and equipment. The municipality also believed the CARB’s order supported the view that abnormal costs, including productivity losses were not measured against what was typical or normal in central Alberta or Edmonton, but were measured against what was typical or normal within the municipality.” 19
  • 20. CCRG ISSUES WHICH ARISE – Owners Costs • Term used by industry but does not appear in the CCRG • Can be a “catch all” category for the owner to record costs related to: • Home office overhead for PMO, IT, Finance, HR, Corporate Support, Media PR • Perks and trinkets • Bidding and tendering • Parties and celebrations, recognitions • Supervision of the general contractor(s) • Material and Equipment surplus/damaged • Quality control in the factory • PMT – Non dedicated personnel (40% of PMT) 20
  • 21. CCRG ISSUES WHICH ARISE – DBM/EDS • Design Basis Memorandum (DBM) • Typical contents – COAA document • Engineering Design Specifications (EDS) • Typical contents – COAA document • Front End Loading (FEL) / Front End Engineering Design (FEED) • Are the costs to prepare the DBM/EDS included or excluded? 21
  • 22. GROUP EXERCISE Owners Costs / FEED • Working at your table, please consider whether the list of items shown on slide 16 (owners costs) are: (i) construction costs – refer to CCRG section, and (ii) which costs are excluded costs – and identify the applicable CCRG section which could allow for their exclusion • Complete your answers in the template provided 22
  • 23. GROUP EXERCISE Owners Costs / FEED – De-brief • Exercise De-Brief 23
  • 27. ESTIMATE CLASSIFICATION & TYPES OF CONTRACTS 27 Fixed Price Lump Sum Cost Plus Incentive Time & Materials Cost Reimbursable Unit Rates Contractor’s Risk 100% 0% 0% 100% Owner’s Risk Few Change Orders Max Change Orders
  • 29. CCRG ISSUES WHICH ARISE Cost Estimating • Information found on the Authorization for Expenditure (AFE) is useful to understand the scope of the work. An AFE is typically a class 3 estimate: • Known technology industry accuracy -20% + 30% (Power) • New technology industry accuracy –30% + 50% (Oil sands) • CCRG requires final project costs, not even class 1 estimates • Assessors need to ask for final project costs, commonly called by industry: Total Installed Cost or Total Final Project Cost 1. Make sure project has been de-supplemented (AFE removed) 29
  • 30. CCRG ISSUES WHICH ARISE Lump Sum Contracts • Property owner cannot break out possible excluded costs • Examples of how this is handled in practice: • 1. Ask for details of the buildup of the LS contract • 2. Apply the rest of the project factors to the LS contract • 3. Calculate from a similar facility • 4. Producing capacity comparable analisys • Onus remains on the property Owner to segregate and substantiate costs claims as per CCRG 2005 30
  • 31. SECTION 2.500 ABNORMAL COSTS Basic Principles • Types of claims under this heading include: labour productivity losses, schedule slippage, delays, inclement weather, work slow down, accidents, natural disaster, a cost not normally incurred in a balanced market, a cost excluded to maintain consistency among regulated properties: • This requires clear definition on a case by case basis because there are multiple scenarios possible on each concept mentioned above. Companies need to come forward with full cost details and traceability to let the assessor decide on each case as each project is different by deifnition. 31
  • 32. SECTION 2.500 ABNORMAL COSTS Basic Principles • From a review of the section we can see several principles • Labour force available – travel excluded s. 2.500.100 • Materials and parts are available – transportation past Edmonton excluded s. 2.500.200 • Interest during construction is excluded – s. 2.500.300 • Premium payments for overtime are excluded – s. 2.500.400 32
  • 33. SECTION 2.500 ABNORMAL COSTS Basic Principles • Typical or normal varies over time • Typical or normal varies by location • Typical or normal varies by industry • Requirement to measure actual costs against typical or normal • Obligation on the property owner to establish typical or normal, time period, location and the industry constructed. 33
  • 34. SECTION 2.500 ABNORMAL COSTS Basic Principles • How do you measure a balanced market? • Back to basic principles – varies by location, industry and over time • Measure market during the period of construction • If everyone in the industry/location is experiencing the same pressure – is normal. • Deviations from that normal can be abnormals. 34
  • 35. SECTION 2.500 ABNORMAL COSTS Basic Principles • Cost excluded to maintain consistency among regulated properties • CCRG used by the Regulated Property Unit to prepare the rates in the Minister’s Guidelines 35
  • 36. CHANGE MANAGEMENT A process whereby changes in the Scope of Work agreed to by the Owner and Contractor are implemented via Change Orders. Change Orders are additions, deletions of scope which alter the original contract cost and/or completion date. CO’s are common in large projects under cost reimbursable contracts. Seldom seen in Lump Sum/Fixed Price contracts. 1.Project schedule/scope/cost incorrectly estimated. 2.Owner discovers possible efficiencies that require deviations from original plans. 3.Contractor underestimated efficiencies and additional cost, time or scope must be added to complete project 36
  • 38. CHANGE MANAGEMENT 38 0% 25% 50% 75% 100% Business Planning Feasibility Studies Concept Optimization Basic Design E&P Construction C&SU Cost of Change # of Changes As projects progress, changes are more costly but fewer
  • 39. CHANGE MANAGEMENT Challenges for Owners Cost Reimbursable: Contractors low ball bids seeking to turn it into change management heavens. Company Staff Turnover: A manager may approve a change that his/her replacement may reject. And viceversa. Company/EPC Change Management Culture: Change order forms are poorly filled and no relevant info is avaliable to assess a change. EPC does not adhere to company processes: Competing contractors blame each other for delays, availability of work fronts. 39
  • 40. CHANGE MANAGEMENT 40 Queen Isabella Causeway near South Padre Island, Texas, September 15, 2001 United States Coast Guard, CWO2 Robert Wyman
  • 41. CHANGE MANAGEMENT 41 Can you live with it as it is?
  • 42. SECTION 2.500 ABNORMAL COSTS Labour Productivity 42 Field labour productivity is the single greatest variable in any cost estimate and it is extremely difficult to estimate. Direct field labour constitutes a high percentage of the total cost of a project from 15% to 25%. Productivity variations are based on: Type of project, world and regional location, contractor’s morale, owner’s management, project’s culture, weather, technology, time of the year, craft availability, labour mix (local vs expatriate vs extra-provincial), degree of supervision and degree of skillset to use equipmentm learning curve effect, job size, project change orders.
  • 43. SECTION 2.500 ABNORMAL COSTS Engineering Productivity 43 Engineering productivity is also subject to variations similar to labour productivity, but easier to estimate and quantify. Engineering productivity range from 10% to 15%. Variations are based on: Type of project, world and regional location, contractor’s morale, owner’s management, project’s culture, weather, technology, engineers avalability and mix (local vs expatriate vs extra- provincial), degree of supervision and job size.
  • 44. SECTION 2.500 ABNORMAL COSTS Labour Productivity Process to establish the normal vs abnormals: Projects establish a Base Productivity to define what can be expected as a normal condition in that particular project. Abnormals are deviations from Base Productivity There are always abnormal conditions related to any project, whether they were captured as such is another story. 44
  • 45. SECTION 2.500 ABNORMAL COSTS Labour Productivity 45 DFL Non-Productive Time 10 hr shift 6% 12% 10% 6% 16% 50% Actual Work Time Idle/ Moving Instructions Socializing Tools & Matls. Other University of Calgary – Productivity in Construction Research Studies
  • 46. SECTION 2.500 ABNORMAL COSTS Labour Productivity Overtime Premium – Day Shifts 46 Calculating Overtime Premium: ST $70/hr & OT $97.5/hr Delta ST vs OT = $27.5/hr OT Premium = (27.5/70) = 39.2% Days On Days Off One Cycle Hours Worked Standard Time Over Time Cost Increase Base Productivity 4 3 7 40 40 0 0% 100% 5 2 7 50 40 10 3.9% 90% 6 1 7 60 40 20 7.9% 80% 10 4 14 100 70 30 11.8% 75% 21 7 28 210 120 90 35.4% 64% 35 21 56 350 200 150 58.9% 60% Job Rotations in Remote Locations
  • 47. SECTION 2.500 ABNORMAL COSTS Labour Productivity More than one way to calculate actual productivity depending info available 47 1. Productivity = QAB workhours Actual workhours 2. Productivity = % physical completion % of QAB workhours 3. Productivity = Budget Unit Rate Actual Unit Rates QAB – Quantity Adjusted Budget: Includes adjustment for actual conditions on site to reflect real productivity
  • 48. SECTION 2.500 ABNORMAL COSTS Delays / Schedule Slippage The Schedule Control Basis, typically includes the following: 1.The Plan 2.Schedule Control Baseline 3.Planned Schedule 4.Schedule Basis 5.Schedule Control Plan Schedule Basis covers assumptions, inclusions, exclusions, risk and uncertainty as well as schedule contingencies, such as inclement weather. Schedule slippage and delays are incorporated into the schedule as they happen as they are usually EPC change orders. 48
  • 49. SECTION 2.500 ABNORMAL COSTS Edmonton Area • Historically under SPAG, all abnormal costs were compared to normal costs in the Edmonton area • This was because prior to 1995 all assessments were regulated based on cost manuals which reflected Edmonton area costs • There is a debate as to whether abnormal cost claims are still measured against what is typical or normal in Edmonton • Only mention of Edmonton area is in s. 2.500.200 with regard to transportation costs • If this is the case – conflicts with the basic principles under s. 2.500 49
  • 50. DESIGN CHANGES s. 2.300.400 INTERFERENCE COSTS s. 2.300.500 • Most projects have some costs for re-work • The allowance for re-work is often found in the following documents: • ___________________ • ___________________ • Generally interference costs are for brownfield sites 50
  • 51. TRAVEL s. 2.500.100 TRANSPORTATION s. 2.500.200 • Travel to the site is excluded. • Travel within the site would be an included cost. • Transportation costs of materials within the site are an included cost. • The cost of loading and unloading the raw materials and components is included. 51
  • 52. TRANSPORTATION s. 2.500.200 IMPORT DUTIES & BROKER FEES S. 2.300.700 • Consider that nine countries shipped equipment worth $392M CAD to a job site in RMWB in circa. 2006. Generating costs for transportation and import duties and brokerage fees. • Austria Canada Germany • Holland Italy Mexico • Spain Sweden USA • Transportation cost to EDM included, from EDM to jobsite excluded • Duties & Fees all excluded 52
  • 53. SITE PREPARATION Page 8 of the Interpretive Guide • The cost to clear, level and finish the site is an included cost • Except if the land assessment is based on the value of finished industrial land (stripped or graded) – then the actual site preparation costs for stripping and grading are excluded but any other site preparation costs are included 53
  • 54. CCRG BEST PRACTICES Establish Expectations • Recommend a meeting with the property owner early in the construction process to set out expectations with regard to: (i) types of documents required, (ii) interpretation and application of the CCRG • Have regular follow up meetings, steer conversations to have cost-data discussions segregating included vs excluded. • Cost reporting should comply with the requirements of the CCRG • Claims for excluded costs should be made under a section of the CCRG • Re-work your RFI to set out your expectations regarding the CCRG, and the cost reporting 54
  • 55. CCRG BEST PRACTICES Documents • Depending on the scope of the project, it is good practice to request: • Feasibility study • DBM and EDS • The sanction budget, and all updates to the budget • AFE’s and final cost reconciliation documents • Change orders – which relate to claims for abnormal costs • Man power plan for the PMT • ________________________________________________ 55
  • 57. THANK YOU FOR YOUR ATTENTION QUESTIONS ARE WELCOME Salvador Hernandez, Verus Capital Assessments email: salvador@vecaas.ca phone: 1-403-690-3053 Dan Driscoll, A.M.A.A. email: dandriscoll@shaw.ca John Elzinga, A.M.A.A. email: john.a.elzinga@gmail.ca Carol Zukiwski, RMRF LLP email: czukiwski@rmrf.com phone: 1-780-497-3350 57