1. OL3 PROJECT NEWS – December 4, 2015 - #163
OL3
Project
OL3 Project Communication 2015 - Contact : communication.ol3@areva.com
97% OF WELDS
SUCCESSFULLY COMPLETED!
On November 30, 2015 the piping team jointly with the subcontractor BPT based on an operational “plateau”
mode, has reached the goal of 97% of welds completed (8041 welds done for an expected total of 7958 welds)
as it was planned one year ago. This performance is a great achievement for Construction and contributes
to pave the way towards its completion scheduled for mid-2016. Piping team has successfully took-up the
challenge by being committed and showing its high motivation from the beginning.
8041welds
≈300people
involved
97%completed