Aurum Villas Progress Pictures
- 1. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS – Photo Report
• Key Plan showing the Camera positions, Click on the Icon to review respective status:
1
2
3
4
5
6
7
8
9
10 11
12 13 14
15
1617
18
19
- 2. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 01
• Finishing works in progress
Key Plan
1
2
3
4
5
6
- 3. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 02
• Package I – Block work, Plastering and Painting in progress
Key Plan
1
2
3
4
5
6
- 4. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 03
• Package I – Block work and Plastering in progress
Key Plan
1
2
3
4
5
6
- 5. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 04
• Package I – Plastering and Tiling in progress
Key Plan
1
2
3
4
5
6
- 6. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 05
• Package I – Tiling work in progress.
Key Plan
1
2
3
4
5
6
- 7. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 06
• LEFT – Package 02 RIGHT – Package 01
Key Plan
1
2
3
4
5
6
- 8. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 07
• Package II – Finishing activities going on.
Key Plan
7
8
9
10 11
12
- 9. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 08
• Package I – UPVC window and Door shutter fixing in progress
Key Plan
7
8
9
10 11
12
- 10. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 09
• LOGON work in progress
Key Plan
7
8
9
10 11
12
- 11. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 10
• Package II – Internal Wall Putty work in progress
Key Plan
7
8
9
10 11
12
- 12. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 11
• Package II – Finishing activities going on.
Key Plan
7
8
9
10 11
12
- 13. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 12
• Package II – Tiling work in progress
Key Plan
7
8
9
10 11
12
- 14. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 13
• Package II – Waterproofing work in progress
Key Plan
13 14
15
1617
18
- 15. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 14
• Package II – Plastering in progress
Key Plan
13 14
15
1617
18
- 16. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 15
• Package II – Plastering in progress
Key Plan
13 14
15
1617
18
- 17. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 16
• Package II – Plastering in progress
Key Plan
13 14
15
1617
18
- 18. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 17
• Package II – Plastering in progress
Key Plan
13 14
15
1617
18
- 19. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 18
• Package II – Block work and Plastering in progress
Key Plan
13 14
15
1617
18
- 20. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 19
• Package II – Finishing work in progress
Key Plan
- 21. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group A Villas – OHT & Block work in progress
- 22. AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group B Villas – Plumbing work in progress