RENEWABLE ENERGY PAKISTAN
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
 Established in 1960 – 53 Years of Effective Existence
 Operations throughout Pakistan & Middle East
 Current Strength: 500+ Professionals & Support Staff
 Extensive Experience with 4000+ completed projects in
Government, Multinational & Private sector
 Comprehensive range of Consultancy Services in Engineering,
Architecture, Planning, Mapping & Technology fields
 PKR 550+ billion (USD 5.5 billion) projects under execution
OSMANI & COMPANY (PVT.) LTD.
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
INFRASTRUCTURE SERVICES BY OSMANI
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
Project Size Infrastructure Energy Cost PRK
DHA City Karachi 11,600 acre Yes Yes 100 B
Hawksbay Scheme 42, Karachi 11,460 acre Yes Yes 65 B
Hyderabad Development Package & GIS 253,000 acre Yes Yes 8 B
Buddo-Bundal Island 12,000 acre Yes Yes 300 B
DHA Phase VIII, Karachi 4,140 acre Yes Yes 15 B
New Malir Housing Karachi 4,400 acre Yes Yes 10 B
M3 - Industrial City, Faisalabad 4,000 acre Yes Yes 6 B
Gulistan-e-Sarmast Housing, Hyderabad 4,800 acre Yes Yes 15 B
750 Water Filtration Plants in Sindh 750 towns Water only Yes 4 B
Islamabad Sewerage Treatment Project 60 MGD Water only Yes 6 B
K-IV Greater Karachi Bulk Water Supply 260 MGD Water only Yes 30 B
KPT Wetland Park Karachi 100 MGD Water only Yes 4 B
Combined Effluent Treatment Plants Karachi 80 MGD Water only Yes 7 B
ADB Flood Effected Roads Rehab 1000+ km Roads only Yes 10 B
INFRASTRUCTURE PROJECTS UNDER EXECUTION (PKR 550+ BILLION)
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
RENEWABLE ENERGY INITIATIVES IN PAKISTAN
 Except for some 50 MW wind farms, only small scale sustainability
initiatives taken in Pakistan, and no holistic initiative has been taken
for large scale Renewable Energy development
 Karachi, the largest city of Pakistan with a population of approx. 20
M people is facing the worst impacts of the Energy crisis
 DHA City Karachi (DCK) is the 1st ever large scale sustainable urban
development project utilizing 30% Renewable Energy i.e. 150 MW
 DCK is targeted to be a landmark urban development with a high
quality of living for 600,000 residents and to serve as a model
sustainable Pakistani city of the 21st century
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DHA City is located at the eastern border of Karachi
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DCK SCALE COMPARISION
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
SUSTAINABE PLANNING INITIATIVES IN PAKISTAN
 For incorporating latest Sustainability Technology transfer, an international
JV was formed:
 Lead Consultants: Osmani & Company (Pvt.) Ltd. Pakistan
 Chief Concept Planner: Prof. Spiro Pollalis, Harvard University USA
 Foreign Planning Associate: Doxiadis Associates Greece
 Foreign Architectural Associate: RMJM
 Chain of Events:
 Detailed Master planning completed in 1 year (Sep 2010 to Sep 2011)
 Conceptual Infrastructure Planning Reports completed (Dec 2011)
 Detailed Design of Immediate action completed & balance under progress
 On ground Execution started in Feb. 2012 – PKR 10 billion infrastructure projects
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
Planning, Design & Implementation of a world class 24/7 transportation
& utilities infrastructure. Emphasis on water & energy needs of city
The safest city suburb in Pakistan with safety features incorporated
through planning & information technology interventions
Facilities for work, education, healthcare, shopping, recreation
& community activities in close proximity
Provide a beautiful natural living environment with
highest quality of life in Pakistan
Most Energy efficient suburb of Pakistan with a sustainable
Infrastructure with Renewable Energy systems
The Vision
* Quality
Infrastructure
* Safety &
Security
* Proximity
* Environment
Sustainability
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DEVELOPMENT OF DHA CITY, KARACHI
Project Cost : USD 1 Billion PKR. 100+ Billion
Survey, Master Planning, Infrastructure Design, GIS & Supervision
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
THEME
PARK
DOWNTOWN
MARKET
GATEWAY
DISTRICT
EDUCATION
ZONE
SPORT CENTERS &
FACILITIES
C5 COMMUNITY
CENTERS
DOWNTOWN
BUSINESS ZONE
GOLF CLUB
RESORT
LAKEVIEW
PARK
WIND & SOLAR
ENERGY PARKS
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DHA City’s holistic plan for sustainable energy, with demand management
combined with renewable energy utilization
4. Reduce conventional energy
demand by 50%
3. Renewable energy usage to 30%
2. Increase efficiency of appliances 5%
1. Manage and reduce energy consumption by 15%
Passive Cooling & Shades
Reduce A/C loads
Mandatory LED based street
lights from Day 1 – Efficient
A/C
Wind + Solar + Biomass +
Waste-Energy
DCK Sustainable Energy Infrastructure
Conventional Energy = 350 MW
Renewable Energy = 150 MW
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DCK RENEWABLE ENERGY INTERVENTIONS
WIND FARM (50 MW)
SOLAR FARM & HOUSE LEVEL SOLAR (50-80 MW)
BIOMASS & RFO POWER PLANT (400 MW)
SMART GRID
ENERGY CONSERVATION
MANDATORY LED BASED STREET LIGHTS (WITH SOLAR PANELS)
MANDATORY SOLAR WATER HEATERS
SOLAR WATER PUMPING (50+ WELLS)
SOLAR STREET LIGHTING (1000s OF LIGHTS)
ELECTRIC BUSES
BIOFUELS PRODUCTION
ENVISION RATING SYSTEM
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
Biomass
Power
Plant
Wind
Farm
Solar
Farm
RFO
Power
Plant
132kV U/G
Cable
GIS 1
GIS 2
GIS 3
GIS 4
GIS 5
GIS 6
GIS 7
220 V to End User
5.5 MW 11 kV Feeder (11)
DCK ENERGY SYSTEM
132kV Bus Bar
Power House
Switchyard
Step down distribution
Transformer 630KVA or 400 KVA
5.5 MW 11 kV Feeder (14)
5.5 MW 11 kV Feeder (21)
5.5 MW 11 kV Feeder (8)
5.5 MW 11 kV Feeder (20)
5.5 MW 11 kV Feeder (11)
5.5 MW 11 kV Feeder (11)
Power Plants Transmission System Grid Stations Distribution System
132kV U/G
Cable
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DCK
50 MW
WIND FARM
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
NREL USA Map showing DCK is in
Good wind condition zone
GOOD
FAIR
EXCELLENT
MARGINAL
GOOD
6.9 to 7.4 m/s
EXCELLENT
7.4 to 7.9 m/s
FAIR
6.2 TO 6.8 m/s
REGIONAL WIND CORRIDOR & DCK
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
18
Wind Energy Park
Wind Energy Park
(65 Acres : 50 MW)
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
Wind Farm Area
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DCK
SOLAR POWER PROJECTS
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
21
Solar Energy Park
Solar Energy Park
(64 Acres : 12-15 MW)
Solar Short Term Dev 2012-15
1-2 MW functional plant
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
SOLAR ENERGY AT HOUSE LEVEL
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
Conventional & Biomass
Energy Plant
(197 Acres : 400 MW)
DCK BIOMASS POWER PLANT
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
BIO MASS MULTI FUEL POWER PLANT
BIO MASS FUEL:
 Wheat Husk
 Rice Husk
 Sugarcane Husk
 Solid Waste
 Sewage Sludge
 Kitchen Garbage
DCK BIOMASS POWER PLANT
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
 Reliable
 Secure
 Economic
 Efficient
 Environment friendly
 Safe
DCK SMART GRID SYSTEM
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
DCK SMART GRID CONCEPTUAL MODEL
Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved
Power & Alternate Energy Asia 2013 - Karachi
ENVISION Sustainability Rating pursued by DCK

More Related Content

What's hot

Final Synopsis- Project on Construction of electric vehicle
Final Synopsis- Project on Construction of electric vehicleFinal Synopsis- Project on Construction of electric vehicle
Final Synopsis- Project on Construction of electric vehicleSourya Sanghan Basu
 
Report on electric rickshaw and case studies
Report on electric rickshaw and case studies Report on electric rickshaw and case studies
Report on electric rickshaw and case studies RuzaanKaranjia
 
Fabrication of Hybrid Petroelectric Vehicle
Fabrication of Hybrid Petroelectric VehicleFabrication of Hybrid Petroelectric Vehicle
Fabrication of Hybrid Petroelectric VehicleIJERA Editor
 
Solar EPC Services - Mahindra Susten
Solar EPC Services - Mahindra SustenSolar EPC Services - Mahindra Susten
Solar EPC Services - Mahindra SustenRaniDas6
 
IRJET-Smart Self Charging Batteries in Electric Vehicle
IRJET-Smart Self Charging Batteries in Electric VehicleIRJET-Smart Self Charging Batteries in Electric Vehicle
IRJET-Smart Self Charging Batteries in Electric VehicleIRJET Journal
 
IRJET- A Study on Campus-Friendly Solar Powered Electric Vehicle
IRJET-  	  A Study on Campus-Friendly Solar Powered Electric VehicleIRJET-  	  A Study on Campus-Friendly Solar Powered Electric Vehicle
IRJET- A Study on Campus-Friendly Solar Powered Electric VehicleIRJET Journal
 
Lohia Auto Solar Rickshaw - Press Release
Lohia Auto Solar Rickshaw - Press ReleaseLohia Auto Solar Rickshaw - Press Release
Lohia Auto Solar Rickshaw - Press ReleaseRushLane
 
solar roadway (solar power smart highways
 solar roadway (solar power smart highways solar roadway (solar power smart highways
solar roadway (solar power smart highwaysSahil Soni
 

What's hot (14)

Energy sector
Energy sectorEnergy sector
Energy sector
 
E-Rickshaw Presentation
E-Rickshaw PresentationE-Rickshaw Presentation
E-Rickshaw Presentation
 
Final Synopsis- Project on Construction of electric vehicle
Final Synopsis- Project on Construction of electric vehicleFinal Synopsis- Project on Construction of electric vehicle
Final Synopsis- Project on Construction of electric vehicle
 
Presentation By Rahul Galgate
Presentation By Rahul GalgatePresentation By Rahul Galgate
Presentation By Rahul Galgate
 
Report on electric rickshaw and case studies
Report on electric rickshaw and case studies Report on electric rickshaw and case studies
Report on electric rickshaw and case studies
 
Fabrication of Hybrid Petroelectric Vehicle
Fabrication of Hybrid Petroelectric VehicleFabrication of Hybrid Petroelectric Vehicle
Fabrication of Hybrid Petroelectric Vehicle
 
Presented by Munjal Rangwala
Presented by Munjal RangwalaPresented by Munjal Rangwala
Presented by Munjal Rangwala
 
Solar EPC Services - Mahindra Susten
Solar EPC Services - Mahindra SustenSolar EPC Services - Mahindra Susten
Solar EPC Services - Mahindra Susten
 
IRJET-Smart Self Charging Batteries in Electric Vehicle
IRJET-Smart Self Charging Batteries in Electric VehicleIRJET-Smart Self Charging Batteries in Electric Vehicle
IRJET-Smart Self Charging Batteries in Electric Vehicle
 
Ij3314291436
Ij3314291436Ij3314291436
Ij3314291436
 
Introduction
IntroductionIntroduction
Introduction
 
IRJET- A Study on Campus-Friendly Solar Powered Electric Vehicle
IRJET-  	  A Study on Campus-Friendly Solar Powered Electric VehicleIRJET-  	  A Study on Campus-Friendly Solar Powered Electric Vehicle
IRJET- A Study on Campus-Friendly Solar Powered Electric Vehicle
 
Lohia Auto Solar Rickshaw - Press Release
Lohia Auto Solar Rickshaw - Press ReleaseLohia Auto Solar Rickshaw - Press Release
Lohia Auto Solar Rickshaw - Press Release
 
solar roadway (solar power smart highways
 solar roadway (solar power smart highways solar roadway (solar power smart highways
solar roadway (solar power smart highways
 

Similar to 08-RENEWABLE-ENERGY-Arif-Osmani

Boond - SXSW Eco Startup Showcase Presentation
Boond - SXSW Eco Startup Showcase PresentationBoond - SXSW Eco Startup Showcase Presentation
Boond - SXSW Eco Startup Showcase PresentationRustam Sengupta
 
Boond - SXSW Presentation
Boond - SXSW PresentationBoond - SXSW Presentation
Boond - SXSW PresentationHelina Jolly
 
Boond - SXSW Eco 2015
Boond - SXSW Eco 2015Boond - SXSW Eco 2015
Boond - SXSW Eco 2015Helina Jolly
 
Ada power presentataion 30.03.2018
Ada  power presentataion  30.03.2018Ada  power presentataion  30.03.2018
Ada power presentataion 30.03.2018Avanindra Yadav
 
YKJain_Solar020915
YKJain_Solar020915YKJain_Solar020915
YKJain_Solar020915YK Jain
 
Adani power Practice School
Adani power Practice SchoolAdani power Practice School
Adani power Practice SchoolNemish Kanwar
 
Adani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportAdani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportNemish Kanwar
 
Introducing dayton solar power
Introducing dayton solar powerIntroducing dayton solar power
Introducing dayton solar powerBhaskar Mishra
 
SSAEL Utility Solar pre bid and post bid consulting services
SSAEL Utility Solar pre bid and post bid consulting servicesSSAEL Utility Solar pre bid and post bid consulting services
SSAEL Utility Solar pre bid and post bid consulting servicesSatya Kumar DV
 
Dayton power-cold storage final
Dayton power-cold storage finalDayton power-cold storage final
Dayton power-cold storage finalBhaskar Mishra
 
Indurti - Energy Efficiency may2016
Indurti - Energy Efficiency may2016Indurti - Energy Efficiency may2016
Indurti - Energy Efficiency may2016Ramesh Kumar
 
217332 renewable energy
217332 renewable energy217332 renewable energy
217332 renewable energyDhibiDas
 
ADA power high effeciency presentataion summary 02.05.2019
ADA  power high effeciency  presentataion summary  02.05.2019ADA  power high effeciency  presentataion summary  02.05.2019
ADA power high effeciency presentataion summary 02.05.2019Avanindra Yadav
 
Corporate profile baritech
Corporate profile baritechCorporate profile baritech
Corporate profile baritechPriyank jain
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdfsanjay vashishtha
 
Bus Karo: Smart Cities and Support Actions for Electromobility
Bus Karo: Smart Cities and Support Actions for ElectromobilityBus Karo: Smart Cities and Support Actions for Electromobility
Bus Karo: Smart Cities and Support Actions for ElectromobilityWRI India
 
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)WRI Ross Center for Sustainable Cities
 

Similar to 08-RENEWABLE-ENERGY-Arif-Osmani (20)

Boond - SXSW Eco Startup Showcase Presentation
Boond - SXSW Eco Startup Showcase PresentationBoond - SXSW Eco Startup Showcase Presentation
Boond - SXSW Eco Startup Showcase Presentation
 
Boond - SXSW Presentation
Boond - SXSW PresentationBoond - SXSW Presentation
Boond - SXSW Presentation
 
Boond - SXSW Eco 2015
Boond - SXSW Eco 2015Boond - SXSW Eco 2015
Boond - SXSW Eco 2015
 
Ada power presentataion 30.03.2018
Ada  power presentataion  30.03.2018Ada  power presentataion  30.03.2018
Ada power presentataion 30.03.2018
 
YKJain_Solar020915
YKJain_Solar020915YKJain_Solar020915
YKJain_Solar020915
 
AEPL-Profile-SW
AEPL-Profile-SWAEPL-Profile-SW
AEPL-Profile-SW
 
ertcc
ertccertcc
ertcc
 
Adani power Practice School
Adani power Practice SchoolAdani power Practice School
Adani power Practice School
 
Adani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportAdani Power, Tirora- Project Report
Adani Power, Tirora- Project Report
 
Introducing dayton solar power
Introducing dayton solar powerIntroducing dayton solar power
Introducing dayton solar power
 
SSAEL Utility Solar pre bid and post bid consulting services
SSAEL Utility Solar pre bid and post bid consulting servicesSSAEL Utility Solar pre bid and post bid consulting services
SSAEL Utility Solar pre bid and post bid consulting services
 
Dayton power-cold storage final
Dayton power-cold storage finalDayton power-cold storage final
Dayton power-cold storage final
 
Zorays Inc.
Zorays Inc.Zorays Inc.
Zorays Inc.
 
Indurti - Energy Efficiency may2016
Indurti - Energy Efficiency may2016Indurti - Energy Efficiency may2016
Indurti - Energy Efficiency may2016
 
217332 renewable energy
217332 renewable energy217332 renewable energy
217332 renewable energy
 
ADA power high effeciency presentataion summary 02.05.2019
ADA  power high effeciency  presentataion summary  02.05.2019ADA  power high effeciency  presentataion summary  02.05.2019
ADA power high effeciency presentataion summary 02.05.2019
 
Corporate profile baritech
Corporate profile baritechCorporate profile baritech
Corporate profile baritech
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdf
 
Bus Karo: Smart Cities and Support Actions for Electromobility
Bus Karo: Smart Cities and Support Actions for ElectromobilityBus Karo: Smart Cities and Support Actions for Electromobility
Bus Karo: Smart Cities and Support Actions for Electromobility
 
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)
Bus Karo: Smart Cities and Support Actions for Electromobility (Session V)
 

08-RENEWABLE-ENERGY-Arif-Osmani

  • 1. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi
  • 2. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi OSMANI & COMPANY (PVT.) LTD. CONSULTING ENGINEERS – ARCHITECTS – PLANNERS www.osmani.com Karachi - Islamabad - Faisalabad - Lahore - Hyderabad Riyadh – Jeddah – Toronto – Boston - Athens RENEWABLE ENERGY PAKISTAN
  • 3. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi  Established in 1960 – 53 Years of Effective Existence  Operations throughout Pakistan & Middle East  Current Strength: 500+ Professionals & Support Staff  Extensive Experience with 4000+ completed projects in Government, Multinational & Private sector  Comprehensive range of Consultancy Services in Engineering, Architecture, Planning, Mapping & Technology fields  PKR 550+ billion (USD 5.5 billion) projects under execution OSMANI & COMPANY (PVT.) LTD.
  • 4. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi INFRASTRUCTURE SERVICES BY OSMANI
  • 5. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi Project Size Infrastructure Energy Cost PRK DHA City Karachi 11,600 acre Yes Yes 100 B Hawksbay Scheme 42, Karachi 11,460 acre Yes Yes 65 B Hyderabad Development Package & GIS 253,000 acre Yes Yes 8 B Buddo-Bundal Island 12,000 acre Yes Yes 300 B DHA Phase VIII, Karachi 4,140 acre Yes Yes 15 B New Malir Housing Karachi 4,400 acre Yes Yes 10 B M3 - Industrial City, Faisalabad 4,000 acre Yes Yes 6 B Gulistan-e-Sarmast Housing, Hyderabad 4,800 acre Yes Yes 15 B 750 Water Filtration Plants in Sindh 750 towns Water only Yes 4 B Islamabad Sewerage Treatment Project 60 MGD Water only Yes 6 B K-IV Greater Karachi Bulk Water Supply 260 MGD Water only Yes 30 B KPT Wetland Park Karachi 100 MGD Water only Yes 4 B Combined Effluent Treatment Plants Karachi 80 MGD Water only Yes 7 B ADB Flood Effected Roads Rehab 1000+ km Roads only Yes 10 B INFRASTRUCTURE PROJECTS UNDER EXECUTION (PKR 550+ BILLION)
  • 6. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi RENEWABLE ENERGY INITIATIVES IN PAKISTAN  Except for some 50 MW wind farms, only small scale sustainability initiatives taken in Pakistan, and no holistic initiative has been taken for large scale Renewable Energy development  Karachi, the largest city of Pakistan with a population of approx. 20 M people is facing the worst impacts of the Energy crisis  DHA City Karachi (DCK) is the 1st ever large scale sustainable urban development project utilizing 30% Renewable Energy i.e. 150 MW  DCK is targeted to be a landmark urban development with a high quality of living for 600,000 residents and to serve as a model sustainable Pakistani city of the 21st century
  • 7. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DHA City is located at the eastern border of Karachi
  • 8. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DCK SCALE COMPARISION
  • 9. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi SUSTAINABE PLANNING INITIATIVES IN PAKISTAN  For incorporating latest Sustainability Technology transfer, an international JV was formed:  Lead Consultants: Osmani & Company (Pvt.) Ltd. Pakistan  Chief Concept Planner: Prof. Spiro Pollalis, Harvard University USA  Foreign Planning Associate: Doxiadis Associates Greece  Foreign Architectural Associate: RMJM  Chain of Events:  Detailed Master planning completed in 1 year (Sep 2010 to Sep 2011)  Conceptual Infrastructure Planning Reports completed (Dec 2011)  Detailed Design of Immediate action completed & balance under progress  On ground Execution started in Feb. 2012 – PKR 10 billion infrastructure projects
  • 10. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi Planning, Design & Implementation of a world class 24/7 transportation & utilities infrastructure. Emphasis on water & energy needs of city The safest city suburb in Pakistan with safety features incorporated through planning & information technology interventions Facilities for work, education, healthcare, shopping, recreation & community activities in close proximity Provide a beautiful natural living environment with highest quality of life in Pakistan Most Energy efficient suburb of Pakistan with a sustainable Infrastructure with Renewable Energy systems The Vision * Quality Infrastructure * Safety & Security * Proximity * Environment Sustainability
  • 11. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DEVELOPMENT OF DHA CITY, KARACHI Project Cost : USD 1 Billion PKR. 100+ Billion Survey, Master Planning, Infrastructure Design, GIS & Supervision
  • 12. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi THEME PARK DOWNTOWN MARKET GATEWAY DISTRICT EDUCATION ZONE SPORT CENTERS & FACILITIES C5 COMMUNITY CENTERS DOWNTOWN BUSINESS ZONE GOLF CLUB RESORT LAKEVIEW PARK WIND & SOLAR ENERGY PARKS
  • 13. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DHA City’s holistic plan for sustainable energy, with demand management combined with renewable energy utilization 4. Reduce conventional energy demand by 50% 3. Renewable energy usage to 30% 2. Increase efficiency of appliances 5% 1. Manage and reduce energy consumption by 15% Passive Cooling & Shades Reduce A/C loads Mandatory LED based street lights from Day 1 – Efficient A/C Wind + Solar + Biomass + Waste-Energy DCK Sustainable Energy Infrastructure Conventional Energy = 350 MW Renewable Energy = 150 MW
  • 14. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DCK RENEWABLE ENERGY INTERVENTIONS WIND FARM (50 MW) SOLAR FARM & HOUSE LEVEL SOLAR (50-80 MW) BIOMASS & RFO POWER PLANT (400 MW) SMART GRID ENERGY CONSERVATION MANDATORY LED BASED STREET LIGHTS (WITH SOLAR PANELS) MANDATORY SOLAR WATER HEATERS SOLAR WATER PUMPING (50+ WELLS) SOLAR STREET LIGHTING (1000s OF LIGHTS) ELECTRIC BUSES BIOFUELS PRODUCTION ENVISION RATING SYSTEM
  • 15. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi Biomass Power Plant Wind Farm Solar Farm RFO Power Plant 132kV U/G Cable GIS 1 GIS 2 GIS 3 GIS 4 GIS 5 GIS 6 GIS 7 220 V to End User 5.5 MW 11 kV Feeder (11) DCK ENERGY SYSTEM 132kV Bus Bar Power House Switchyard Step down distribution Transformer 630KVA or 400 KVA 5.5 MW 11 kV Feeder (14) 5.5 MW 11 kV Feeder (21) 5.5 MW 11 kV Feeder (8) 5.5 MW 11 kV Feeder (20) 5.5 MW 11 kV Feeder (11) 5.5 MW 11 kV Feeder (11) Power Plants Transmission System Grid Stations Distribution System 132kV U/G Cable
  • 16. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DCK 50 MW WIND FARM
  • 17. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi NREL USA Map showing DCK is in Good wind condition zone GOOD FAIR EXCELLENT MARGINAL GOOD 6.9 to 7.4 m/s EXCELLENT 7.4 to 7.9 m/s FAIR 6.2 TO 6.8 m/s REGIONAL WIND CORRIDOR & DCK
  • 18. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi 18 Wind Energy Park Wind Energy Park (65 Acres : 50 MW)
  • 19. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi Wind Farm Area
  • 20. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DCK SOLAR POWER PROJECTS
  • 21. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi 21 Solar Energy Park Solar Energy Park (64 Acres : 12-15 MW) Solar Short Term Dev 2012-15 1-2 MW functional plant
  • 22. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi SOLAR ENERGY AT HOUSE LEVEL
  • 23. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi Conventional & Biomass Energy Plant (197 Acres : 400 MW) DCK BIOMASS POWER PLANT
  • 24. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi BIO MASS MULTI FUEL POWER PLANT BIO MASS FUEL:  Wheat Husk  Rice Husk  Sugarcane Husk  Solid Waste  Sewage Sludge  Kitchen Garbage DCK BIOMASS POWER PLANT
  • 25. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi  Reliable  Secure  Economic  Efficient  Environment friendly  Safe DCK SMART GRID SYSTEM
  • 26. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi DCK SMART GRID CONCEPTUAL MODEL
  • 27. Copyright © 2013 Osmani & Company (Pvt.) Ltd. All Rights Reserved Power & Alternate Energy Asia 2013 - Karachi ENVISION Sustainability Rating pursued by DCK