SlideShare a Scribd company logo
1 of 75
Download to read offline
JOINT VENTURE
PRESENTATION
Together we build something better
WELCOME TO OUR
WHO WE ARE?
SARI Consulting Ltd is a quality-driven, leading engineering company with over 18 years experience in the provision of independent professional
management, strategic advice, design of infrastructures and environmental engineering. SARI is a company participating in FG Tecnopolo Alliance. FG
Tecnopolo Alliance is an initiative of FG Tecnopolo Holding, a structured network of partner companies specialized in consulting services in the fields of
architecture, engineering, and information technology, delivering fully integrated design services for large scale projects. The FG Tecnopolo Alliance business
model is based on the integration of skills of the individual Companies participating in the coalition, which while preserving their independence, contribute
to the definition of integrated and harmonized design proposals. The scope is to provide integrated consultancy services characterized by the Maximum
Specialization in the disciplines, thanks to the excellent standard of all Partners, through the interface of the Structured Organization of FG Tecnopolo
Alliance.
SIMECO Spa is a leading mid-size engineering and contracting company, established in 1984, providing:
• qualified and competitive services from basic design & FEED to detail engineering and site services, for Oil & Gas plants (On-shore/Off-shore Upstream
Facilities, Refining), Pipelines, Petrochemical & Chemical Plants, Power Plants (including renewable energies), Plant Off-sites & Utility Generation Units;
• contracting for the execution of projects on turn key lump sum basis;
• design and supply of skid mounted plants.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
3
Sari Consulting Ltd (SARI) activity cover:
• Economic and financial analysis, feasibility
studies, and concessions of infrastructure
projects;
• Institutional strengthening and capacity-
building, assistance to program management, as
well as programming for operation and
maintenance of infrastructure and equipment;
• Irrigation/Agricultural planning, including
design and/or modernization of infrastructure;
• Technical assistance, planning, studies, design
and/or construction supervision of all types of
transport infrastructure, building technology,
water and environment, in projects ranging from
major infrastructure to small local projects.
SARI Clients include: Developing Aid Agencies,
Government Ministries Municipal Authorities,
Private Sector Companies.
SARI is registered with the majority of funding
agencies such as the European Union (EDF), and
International Financial Institutions such as the World
Bank Group (IBRD/IDA), the African Development
Bank (AfDB), and the Asian Development Bank.
Sari Consulting Ltd.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
4
Sari Consulting Ltd (SARI) has carried out projects
in the following countries:
Africa:
Tanzania, Uganda, Zambia, Mozambico, Gambia,
Guinea Bissau, Benin, Sierra Leone, Madagascar,
Ghana , Mauritius, Niger, Lesotho, Angola, Morocco,
Djibouti, Rwanda, Botswana, Angola, Seychelles ,
Nigeria, Burkina Faso, Republic of Congo
(Brazaville), Malawi, Somalia, Togo, Algeria,
Comore Islands , Egypt, Tunisia, Libya, Ivory Coast,
Guinea (Conakry), Liberia, Senegal
Central & South America:
Saint Lucie(West Indies), Haiti, Honduras, Ecuador,
Nicaragua, Venezuela, El Salvador, Guatemala
Asia
Pakistan, India, Philippines, Thailand, Indonesia,
Myanmar, Mongolia
Oceania
Vanuatu
Europe
Italy, Albania
Sari Consulting Ltd.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
5
Simeco S.p.A. possess the organization and the
skilled experienced staff to provide the following
services to the Oil & Gas, Petrochemical and
Chemical Industry:
• Feasibility Studies and Cost Estimates
• Conceptual Design
• Basic Engineering Design
• Front End Engineering and Design (FEED)
• Project Management
• Project Management Consultancy
• Owner’s Engineering Services
• Risk Analysis and HSE Reports
• Detail Engineering
• Procurement Services
• Expediting and Inspections
• Construction Management & Site Supervision
• Commissioning
• Assistance to Plant Start-up and Operation
• Operative Maintenance & Training
• Supply of equipment and skid mounted units on
EP/EPC basis
Simeco S.p.A.
SARI CONSULTING LTD and SIMECO SPA
PARTNERSHIP PRESENTATION
6
Our mission is to operate in different fields of
engineering and architecture on behalf of private and
public customers, expressing their freedom of action
and choice in identifying the best solutions for each
project, in order to ensure the highest satisfaction of
our customers and the achievement of their targets.
Commitment, consistency and accountability are the
fundamental values through which we build the
confidence of our customers during the execution of
each project.
VISION AND MISSION
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
7
Oil & Gas
FIELD OF ACTIVITIES
Water Infrastructures Environmental
Architecture,
Civil Engineeering
Environmental Engineering
Hydraulic & Coastal Engineering
Geology & Geotechnical Engineering
Town & Regional Planning
Roads & Highways
Railroads
Bridges & Structures
Water, Drainage & Sewerage Systems
Sari Consulting Ltd.
Oil & Gas Plants
Refineries
Petrochemical Plants
Chemical Plants
Power Plants
Tank Farms
Pipelines
Renewable Energies
Simeco S.p.A.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
8
YEARLY TURNOVER
$15M
2015
$7M
2014
$5M
2013
$15M
2015
$17M
2014
$19M
2013
Sari Consulting Ltd. Simeco S.p.A.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
9
JOINT VENTURE OFFICES WORLDWIDE
Milano, Italy
Rome, Italy
Sarajevo, Bosnia and Herzegovina
Kingdom of Bahrain
Lusaka, ZambiaKampala, Uganda
Maputo, MozambiqueCape Town, South Africa
Harare, ZimbabweNairobi, Kenya
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
10
50+
CLIENTS
500+
ITEMS DELIVERED
500+
PROJECTS
JOINT VENTURE WORKFORCE
More than 250 engineers and technicians to develop your ideas and support your business
BUSINESS PRESENTATION 11
MEET OUR TEAM
Pierfranco FORLANI
President
Goffredo DEPASCALE
CEO
Antonio GNISCI
COO *
Lorenzo TAGLIABUE
New Business
Development
Mirella REGGIANI
CFO
Alfonso PANTALENA
Relations with Oil
Companies
Giuseppe PEDATA
Communication & Relations
with Middle East countries
Pietro FONTANA
Oil & Gas Technical
Director
Gianluca GASPERINI
O&G Process
Technologies Director
Marco FORLANI
O&G Operations
Director
Francesco GALLI **
Transportation & Water
Technical Director
Francis BYARUHANGA
Executive Director
Uganda
Jacob SIKAZWE
Executive Director
Zambia
Nico BEZUIDENHOUT
Executive Director
S.A
• Managing Director of FG Tecnopolo Holding Srl
** Africa Director of SGI – Studio Galli Ingegneria Srl
BUSINESS PRESENTATION 12
Our Quality Management System is certified by D.N.V. (Det Norske
Veritas) for conformity to the Requirements of ISO 9001:2008 for:
Multidisciplinary basic and detailed design of chemical, petrochemical,
refinery, power generation and of gas and oil pipelines. Equipment and
material procurement.
QUALITY MANAGEMENT SYSTEM
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
13
WRc Group Stoat 4.01
Modelling of Waste Water Treatment Plants
LEDA FLOW
Flow Assurance, Dynamic Multiphase Flow
HTRI / MICROTECH / PV ELITE
Design of heat exchangers, aircoolers, pressure vessels
PDS / SMART PLAN / PDMS
CAD 3D of industrial plants
CAESAR II
Piping stress analysis
SPI (former INTOOLS), AVEVA Instrumentation
Instrumentation Database
PLC 2005
Software to design and plan PLC inputs-outputs
NEPLAN / AMPERE / ETAP
Design, optimization and simulation of electrical systems
MS PROJECT /PRIMAVERA P6
Project management (planning and control)
ASPEN ONE ENGINEERING DESKTOP / HYSYS / PRO II
Process simulators
BIOWIN 3
Analysis, testing and design of wastewater treatment plants
ANOVA Swater
Modelling of suspended-biomass wastewater treatment plant
AFT Arrow / Fathom / Impulse
Steady state & dynamic simulation of pipeline networks
DHI Mike
Integrated modelling of the entire water cycle (storm and waste
waters, open channels, urban water networks,…).
CSdU Urbis Pro
Hydraulic simulation of flood waves in water basins
SANEX 2.0
Design and planning of septic tanks and sewers
EMS-I SMS (RMA2-RMA4)
2D hydro-dynamic modelling of waste waters
SOFTWARE TOOLS
Plant Design
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
14
ESRI Arc View
Geographic Information System (GIS)
MAT 3D / FOUNDATION 3D
Design of foundations
STAAD PRO / SAP 2000
Structural Design
TEKLA
3D Modelling of steel structures
DIGICORP CIVIL DESIGN
AUTOCAD add-on for civil works, topography, road and railways
design
MX Road Design / AutoTURN/ Civil 3D
Road Design
HDM-4
Economic analysis for roads and highways
ESRI Arc View
Geographic information system (GIS)
Sierrasoft ProST
Planning and accounting of civil works
SOFTWARE TOOLS
Civil Works & Infrastructures:
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
15
2 Hanna Instruments photometers for analysis of free and total chlorine
2 two-channel Spectralog with incorporated 10 bar pressure transducer
9 one-channel Spectralog with incorporated 10 bar pressure transducer
2 Spectrascan bi-directional quadrina to gauge flow
2 Spectrascan gauge poles (for quadrina)
1 Palmer MC5 model micro-correlator
1 stetophon Sewerin listening poles with extensions
EQUIPMENT FOR ANALYSIS AND MONITORING OF
WATER AND DRAINAGE SYSTEMS
1 Sewerin AQUAPHON model geophone
1 Sewerin manhole cover detector
4 Casella Rain Gauges
1 MONTEC DETECT 3013 portable level-speedometer to gauge water
speed
1 ISCO sampler
1 SIGMA sampler
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
16
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Pacific Future Energy (Canada)
Year: 2014
Project : British Columbia Greenfield Refinery, Canada (Feasibility Study)
Description: Pacific Future Energy Co. is committed to build and operate the world’s
greenest refinery on British Columbia’s north coast.
PFEC believes it is in Canada’s national strategic interest to gain access to international
markets for Alberta’s oil, especially the fast growing Asian market.
The company believes it should not be done at the sacrifice of BC’s coast or broader
environment and must be done in full partnership with First Nations.
The $10 Billion refinery will be built in modules (each phase having a process capacity
of 200,000 BPSD).
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
17
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Milazzo Refinery (RaM)
Year: 2014-2015
Project : New Naphtha Hydrotreating Unit, Italy (Basic Design)
Description:
The scope of the Basic Design Package is a new naphtha hydrotreating unit named
HDT-3.
HDT-3 will produce 450,000 tons per year of hydrotreated Naphtha containing less
than 0.5 ppmw of sulphur and 24,000 tons per year of olefin saturated LPG with target
specification Pro Isomerization.
The plant will include a refurbished hydrotreating reactor and new pumps, heat
exchangers in the preheating trains, fired heater, three-phase separators, reboiled
stripper distillation tower, associated utilities, LPG and off-gas amine gas treating
packages, recycle / make-up gas compressor package and control systems.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
18
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Milazzo Refinery (RaM)
Year: 2014-in progress
Contract Value (LSTK): 15M€
Project : Revamping of Kerosene Desulphurization Unit, Italy (EPC)
Description :
Project scope is a major revamping of the existing Kerosene Hydrodesulphurization
Unit (HDS-1) to expand the capacity from 2,400 to 4,000 t/d.
Improvement of product quality to target specification Pro Clear and Bright and
maximum S content of 10 ppm are also foreseen.
New feed pumps, stripper, kero dryer and heat exchange train are being installed.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
19
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Eni R&M Division (Italy)
Year: 2011-2013
Contract Value (LSTK): 14M€
Project : Vacuum Column & Filtration System for FCC Slurry Oil (EPC)
Description :
Project scope is the installation of a new Vacuum Column & Automatic Filtration
System on the Slurry Oil stream produced by the existing FCC Plant of the Refinery.
The purpose of the new Unit is:
1) to recover additional LVGO as feed for the Hydrocracking Unit
2) to increase Slurry Oil flash point
3) to remove the catalyst fines in order to feed the Clarified Oil (CLO) stream to the
existing Gasification Plant or to recycle it to the FCC riser .
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
20
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Danieli Far East
Year: 2011-2012
Project : Carbon Dioxide Removal Unit (FEED + Detail Design + Procurement
Services)
Description:
Project scope was the Detail Design, the Equipment & Bulk Material Procurement and
the Home Office Project Management Services for the 10,000 Nm3/h Carbon Dioxide
Removal Unit at an iron ore reduction plant.
The Unit, based on Giammarco-Vetrocoke hot carbonate process, was extensively
modularized in order to facilitate the construction utilizing local labour.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
21
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Eni E&P Division
Year: 2010-2011
Project: Fauzia, Elettra & Benedetta Platforms, Adriatic Sea (FEED)
Description :
The project was carried out providing our Client with the EPC Tender Documents for
n.3 new gas platforms located offshore Adriatic Sea and the relevant ± 15% Cost
Estimate.
SIMECO developed the Front End Engineering Design according to the following main
specifications:
• FAUZIA PLATFORM: 12” export sealine; n° 2 wellheads double completion; 3-legs
jacket.
• ELETTRA PLATFORM: 8” export sealine; n° 1 wellhead double completion; 3-legs
jacket.
• BENEDETTA PLATFORM: 8” export sealine; n° 1 wellhead single completion;
monopode.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
22
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Saipem SES
Year: 2008-2010
Project : OLT Livorno FSRU, Italy (Detail Design)
Description:
The world’s first offshore Floating Storage and Regassification Unit (FSRU) was
constructed by converting the LNG Carrier Golar Frost.
The FSRU is permanently moored offshore Livorno, Italy, about 12 miles from the coast
in a water depth of about 120 meters and connected to shore through a gas export
pipeline.
Storage capacity is 137,000 cubic meters of LNG in four spheres.
Production capacity is 3,75 billion standard cubic meters year (bscmpa).
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
23
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Saipem (Iraq)
Year: 2010-2011
Project : Zubair Degassing Station, Iraq (FEED)
Description :
Project scope was the development of the Front End Engineering Design for a new Oil
Degassing Station (DGS) and rehabilitation of an existing one at Zubair field, Iraq.
The Zubair field - being developed by Eni with Occidental Oil Co., Korean Gas and
Missan Oil Company - with an estimated production capacity of 1,200,000 BOPD is one
of the few super giant oil field presently developed worldwide.
Zubair is a “brown field” project involving the realization of new plants as well as the
revamping of existing unit.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
24
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: ENI R&M Div.
Year: 2010-2011
Contract Value (LSTK) : 1.1 M€
Project : Electrically Traced Transfer Line for Liquid Sulfur at Eni’s Taranto
Refinery, Italy (EPC)
Description:
Project scope was the installation of a new 4’’ x 1 km Liquid Sulfur transfer line from
the Sulfur storage tanks to the flaker unit producing solid sulfur flakes.
The un-flanged transfer line is electrically heated by a skin effect tracing system
capable to re-melt the sulfur in case of in line solidification.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
25
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Saipem
Year: 2009-2012
Project : EST Project at Eni’s Sannazzaro Refinery, Italy (Detail Design)
Description: EST (Eni Slurry Technology) is a new deep hydrocracking technology
developed by Eni for the valorization of heavy and extra heavy oils, tar sands and
refinery residues.
Sannazzaro Plant, with a capacity of 20,000 BPSD, will be the first industrial application
of the EST technology, which has been extensively tested in a Commercial
Demonstration Unit in Italy.
EST plant features n.2 x 2,000 t hydro-cracking reactors made of CrMoV + SS 347 Weld
Overlay, supplied by GE-Nuovo Pignone, the largest built ever.
SIMECO has been in charge for the Technical Bid Evaluation and the follow-up of the
hydro-cracking reactors, hydro-treating reactors (400 t) and large HP Gas/Liquid
Separators (300 t) made of CrMoV (supplied by ATB).
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
26
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Eni SpA
Year: 2008-2009
Contract Value (LSTK): 8.5 M€
Project : C4 Dryers Package at Eni’s Sannazzaro Refinery, Italy (EPC)
Description:
The new C4 Dryer Package was designed to remove impurities (water, acetone,
acetonitryle) from a C4 Olefinic Stream , feeding the existing Isomerization Unit.
The purification is obtained throughout adsorbents continuously regenerated. The
regeneration unit includes a hydrogenation reactor to remove to reduce olefins content
from the adsorbent regeneration stream.
The Unit is entirely installed on a steel structure “straddling” an existing pipe-way in a
very congested area of the Refinery.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
27
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Saipem Energy Services
Year: 2009
Project : GOSP at Burun Oil Field, Turkmenistan (BDP review and assessment)
Description:
The Gas Oil Separation Plant (GOSP) at Burun Oil Field had some trouble operations,
i.e. sand carry over, clogging of filters by paraffines contained in the crude oil and HSE
issues.
The Scope of Work was to carry out, on a very tight schedule, a review of the existing
BDP developed by the previous Owner of the Oil Field in order to solve the operating
problems.
Each document of the BDP was reviewed and several inconsistencies were identified.
For each document a Comment Sheet was produced.
Eventually, recommendations have been provided to Company regarding the
possibility to use the BDP as a basis for an EPC bid to de-bottleneck the Plant.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
28
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Bonatti
Year: 2008-2009
Project : Underground Gas Storage, Italy (Detail Design)
Description: Bordolano is a depleted gas field, 50 km from Milan (Italy), owned by
SNAM Rete Gas/STOGIT (Stoccaggi Gas Italia).
STOGIT intended to convert the existing reservoir into an Underground Gas Storage.
The Plant consisted of a temporary gas compression and Injection station, called Early
Injection Station, withdrawing natural gas from the national pipeline network owned
by Snam Rete Gas. Natural Gas was collected and delivered to the reservoir through 2
new pipelines.
The Early Injection Station was dismantled once completed the injection phase of the
cushion gas in the reservoir.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
29
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Saipem
Year: 2008-2009
Project : QAFCO V Ammonia Plant, Qatar (Detail Design)
Description:
The Project include N. 2 complete Ammonia Plants (Licensor Haldor Topsoe A/S -
design capacity 2 x 2,200 t/d) based on Steam Reforming of Natural Gas consisting of
the following process systems:
Natural gas desulphurization; Process Air Compression; Steam Reforming of Natural
Gas and Waste Heat Recovery; HT & LT Shift Converters; CO2 removal by MDEA;
Methanation; Syngas Compression; Ammonia Synthesis Loop; Ammonia Refrigeration;
Purge Gas Scrubbing & Hydrogen Recovery; Process Condensate Stripper; Deaerator
& BFW pumps.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
30
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Snamprogetti
Year: 2007-2008
Project : ENVEN 1.3 Project - Ammonia / Urea Plant, Pakistan (Detail Design)
Description : N.1 complete Ammonia Plant (Licensor Haldor Topsoe A/S; 2184 MTPD)
based on Steam Reforming of Natural Gas consisting of the following process systems:
Natural gas desulphurization; Process Air Compression; Steam Reforming of Natural
Gas and Waste Heat Recovery; HT & LT Shift Converters; CO2 removal by MDEA;
Methanation; Syngas Compression; Ammonia Synthesis Loop; Ammonia Refrigeration;
Purge Gas Scrubbing & Hydrogen Recovery; Process Condensate Stripper; Deaerator
& BFW pumps. Urea Plant (Licensor Snamprogetti; 3835 MTPD) Process units have
been connected to existing Facilities as: Instrument Air, Plant Air, Steam Generation,
Power Generation, Raw Water, Potable Water, Natural Gas Treatment.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
31
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Tecnimont
Year: 2006-2007
Project: NKNK LLDPE/HDPE Plant, Russia (Detail Design)
Description: NKNK (Nizhnekamsk Neftekhim) LLDPE/HDPE is a Polyethylene Plant
based on the Spherilene Process Technology from Basell Italia.
The plant annual capacity is 230,000 MTPY of polyethylene in pallets, HDPE, MDPE
and LLDPR type.
The units included in the engineering activities were: Polymerization Area, Extrusion
Area, Alkyl Area, Homogenization, Bagging, Palletizing and Warehouse,
Interconnecting & Pipe Racks, Effluent Basin, Purification, Propane Storage, Control
Room and Substation, Valve House, Flare Area, Underground.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
32
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: ENI Oil Co. Ltd, Libyan Branch
Year: 2005-2006
Project : Water Injection Plant & Power Generation System, El Feel Field, Libya
(FEED)
Description : The Water Injection Plant (275,000 BWPD) consists of:
Water Supply System, including Oil / Water separation by induced gas flotation,
Filtration and Chemicals Injection Systems.
Injection Water System, consisting of: Buffer Tank, Injection Water Booster Pumps,
Injection Water Pumps.
Gathering System, consisting of n. 5 Trunk-lines up to 24’’ x 38 km
The Power Generation Systems (50 MWe) consisting of: n. 3+1 Heavy Duty Gas
Turbines GE FR5-1 Dual Fuel fed with Crude Oil (chemically treated for V inhibition)
or Natural Gas.
New dedicated Control Room & Electrical Sub-Station.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
33
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Milazzo Refinery (RaM)
Year: 2005 – 2008
Contract Value (LSTK): Phase 1 – 2.7 M€, Phase 2 – 2.9 M€
Project : Revamping of Marine Loading Arms, Italy
Description :
The Project consisted of two Phases:
During Phase 1, 4 x 16” existing Crude Oil Loading Arms at Pier 2/Mooring 5 were
dismantled and replaced with 3 x 16’’ Loading Arms. During Phase 2, the same
operation, as per Phase 1, were carried out on Pier 2 / Mooring 6.
FMC Technologies were in charge for the supply of the Loading Arms. SIMECO
provided Engineering Services, Procurement of piping materials and Supervision
during Erection, Commissioning and Start-up.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
34
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Snamprogetti
Year: 2005
Project : ISOCRACKER at Sannazzaro de Burgondi Refinery, Italy (Detail Design)
Description:
Sannazzaro’s ISOCRACKER is a 25,000 BPSD Hydrocracking Plant based on Chevron
Lummus Global technology.
Scope of the Engineering Services executed by SIMECO and Partners included the
Main Process Units along with the following Auxiliary Units:
• Sour Water Stripper Unit
• Amine Regeneration Unit
• Interconnecting
• Off-sites
• Cooling Water Unit.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
35
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Snamprogetti Sud
Year: 2003-2004
Project : FCC GASOLINE HDS Unit at Eni’s Sannazzaro Refinery, Italy (Detail
Design)
Description:
Sannazzaro’s FCC Gasoline Hydrodesulphurization Unit is a 20,000 BPSD plant based
on CDHYDRO catalytic distillation technology by CDTECH.
Auxiliary Units were also included in the SOW.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
36
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: Snamprogetti Sud
Year: 2003
Project: Topping 2 Revamping Project at Eni’s Sannazzaro Refinery, Italy (Detail
Design)
Description:
Topping 2 was originally designed to process 715 t/h of Arabian Light Crude Oil.
A major de-bottlenecking to process up to 770 t/h of Djeno Melange Crude Oil was
required.
The revamping consisted of:
• Addition of a new Pre-flash Column upstream of the existing Topping Column
along with relevant Heaters and Pumps;
• Design of new steel structures Complete review/check of the existing Utilities and
Off-sites systems, i.e. BD, Utilities, Closed Drain.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
37
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: PRAOIL Oleodotti Italiani
Year: 2003-2004
Project : Genoa De-bottlenecking Project, Italy (Detail Design)
Description:
Underground interconnecting to upgrade and rationalize the 100 years old oil products
offloading marine terminal in Genoa.
“Trench-less” and “micro-tunnel” technologies have been deployed due to the very
populated and geologically critical areas.
4 x 30” + 2 x 12” pipelines have been laid down in a 2.6 m x 650 m micro tunnel
between Genoa Marine Oil Terminal and Praoil Petroleum Products Depot & Pumping
Booster Station.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
38
Simeco S.p.A.
REFERENCE – OIL & GAS SECTOR
Client: VISCOLUBE
Year: 2001-2003
Project : Spent Lube Oil Re-refining Plant and Offsites Revamping , Italy (FEED +
Detail Design + Procurement Services)
Description:
VISCOLUBE is the European leader in re-refining of spent lube oils, with over 60,000
MTPY of reclaimed oils.
The Spent Lube Oil Hydrotreating Unit is based on Axens technology.
The Plant includes a Hydrogen Generation Unit designed by CALORIC Anlagenbau
(Germany). CALORIC is a firm specialized in supply of gas generation plant package,
i.e.: syngas, carbon monoxide, hydrogen.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
39
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Eni, Venice Refinery
Year: 2014
Project: Revamping of S. Leonardo Oil Terminal – Feasibility Study
Description:
Venice Refinery scope was to convert San Leonardo Crude Oil receiving terminal to
finished product terminal for ship with DWT variable between 10.000 to 80.000 Tons.
The Feasibility Study included:
• the verification about the possibility to re-use the existing loading arms;
• the study of the modification of the existing lines in order to optimize discharge rates
and operability;
• the verification of the mooring systems, including:
• Jetty height above the average sea-level
• Jetty structural integrity
• Status of the existing mooring equipment
• Analysis of ship positioning
• Identification and sizing of new mooring points.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
40
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Eni, Livorno Refinery
Year: 2013
Project: Revamping of the existing LPG Terminal
Description:
The Scope of Work included the revamping of the existing LPG terminal in order to
unload LPG carrier up to 30,000 DWT with a discharge rate of 500 ton/h.
The Scope of Work included the verification of the mooring systems, including:
• Jetty height above average sea-level
• Status of the existing mooring equipment
• Mooring study, i.e. analysis of ship positioning, identification and sizing of new
mooring points.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
41
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Genoa Port Authority
Year: 2011
Project: Study of petroleum products transfer operations under steady state and
transient conditions
Description:
The main purpose of the study was to carry out the Conceptual Design of a system to
protect the lines and the loading arms from overpressures during operations
The activities carried included:
• Steady state analysis of loading/unloading operations to determine the
maximum allowe transfer rates.
• Transient state analsysis of the pressure peak over the lines and the loading in
case of emergency shut down (i.e. water hammer effect due to block valve closure)
• Conceptual Design of the High Integrity Pressure Protection System (HIPPS).
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
42
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Snamprogetti
Year: 2006 – 2007
Project: Trans Anatolian Pipeline, Turkey (Conceptual Design + FEED).
Description : The Project included the following facilities: A new unloading terminal
located east of Samsun, on the Black Sea, suitable for handling a wide range of tankers,
including VLCCs, through three (3) Single Point Moorings and relevant unloading
facilities; A new tank farm located east of Samsun, on the Black Sea, featuring 12
floating roof storage tanks (total net capacity of 1,500,000 m3), including all relevant
facilities and a new dedicated power plant; A 48”and 42” (for the last section), 550 km
long carbon steel pipeline provided with a Pressure Reducing Station (PRS), mainline
isolation block valves and pigging trap systems; One head pump station (PS1) located
at the unloading terminal on the Black Sea and three additional pump stations (PS2,
PS3, PS4) located along the route of the TAP pipeline at different elevations, provided
with power generation and all required facilities such as control rooms,
accommodation, security and maintenance buildings; A new tank farm located at
Ceyhan, featuring 12 floating roof storage tanks (total net capacity of 1,800,000 m3),
including all relevant facilities; A new jetty marine loading terminal, on the
Mediterranean Sea, located in front of the new Ceyhan tank farm, suitable for a wide
range of tankers, including VLCCs..
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
43
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Eni, Gaeta Oil Terminal
Year: 2003
Project: Feasibility Study of a New Multibuoy Mooring Terminal for carriers up to
40,000 DWT
Description:
The scope of the study was to investigate different alternatives for the expansion of the existing
Oil Terminal.
In particular, the Feasibility Study addressed:
• The new subsea Pipeline End Manifold (PLEM)
• n. 3 sealines for trasnfer of oil products
• The study of n. 5 Buoys + swamp mooring.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
44
Simeco S.p.A.
REFERENCE – MARINE OIL TERMINALS
Client: Compagnia Italpetroli Spa
Year: 1997
Project: Civitavecchia New Oil Terminal – Basic Design
Description:
The project included:
• n.1 single buoy mooring system (water depth 50 m)
• n.2 24’’ x 2.2 km sealines + n.2 24’’ x 1.15 km on-shore lines for transfer of fuel oil;
• n.2 22’’ x 2.2 km sealines + n.2 22’’ x 4.7 km on-shore lines for transfer of light
petroleum products (i.e. gasoline, kerosene, diesel).
SIMECO carried out the basic design for the single buoy mooring system and the
pipelines.
The type of foundations have been designed based on site geological data, while
metocean data (wind, waves, streams,….) have been used as a basis for the mooring
study in order to select the most suitable mooring equipment.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
45
Simeco S.p.A.
REFERENCE – ENERGY SECTOR
Client: Enipower
Year: 2010
Project : Combined Heat & Power Plant Revamping , Italy (FEED)
Description:
Project scope was the Front End Engineering Design for the revamping of Enipower
Combined Heat & Power Plant located in Bolgiano, San Donato Milanese, Italy.
The revamping consisted in dismantling the existing power generation units and their
replacement with a new gas turbine (aero derivative type), installation of n.2
endothermic engines with waste heat boilers for power generation and production of
hot water, n.3 auxiliary boilers, n.10 buffer tanks for hot water distribution to the
existing district heating network, n.1 new pumping station, new electrical room, new
technical room.
SIMECO Scope of Work included also +/- 15% cost estimate and preparation of the
EPC Tender Documents.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
46
Simeco S.p.A.
REFERENCE – ENERGY SECTOR
Client: Maire Engineering
Year: 2007
Project : Bocamina II - Power Plant, Chile (Basic + Detail Design)
Description: Bocamina II is a 370 MWe Coal Power Plant owned by Endesa located in
Puerto Coronel, 30 Km SE of Concepcion, Chile.
The Plant features a SES Boiler and a GE Steam Turbine model D5.
SIMECO and JV partners Scope of Work covered Basic Engineering and Detailed
Mechanical Design for Piping Engineering, including 3D modeling, of the following
systems:
Steam Generation, Auxiliary Steam System, Machinery Cooling, De-mineralized Water,
Instrument Air, Fire Fighting Water, Waste Water, Condensate Recovery, Vacuum
Condenser, Boiler Feed Water, Fuel Oil, Sampling, Chemical Injection.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
47
Simeco S.p.A.
REFERENCE – ENVIRONMENTAL SECTOR
Client: Eni R&M Division
Year: 2011-2012
Project: Waste Water Treatment System for Water Re-use at Eni’s Sannazzaro
Refinery, Italy (Detail Design)
Description:
Project scope is the installation of a new Waste Water Treatment Package to process 740
m3/h of water discharged from the existing Refinery Water Treatment System, to
obtain permeated desalted water (conductivity < 100 µS/cm, hardness < 5 mg/l as
CaCO3 ) suitable for steam generation.
The purpose of the new Unit is to recycle water previously discharged to the
environment in order to feed the existing demineralized water production system for
the requirements of the new Process Plants .
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
48
Simeco S.p.A.
REFERENCE – ENVIRONMENTAL SECTOR
Client: Polimeri Europa
Year: 2006 – 2007
Contract Value (LSTK): 6 M€
Project: TAS (Waste Water Treatment) Covering System at Sarroch Petrochemical
Complex, Italy (EPC)
Description:
The New Unit recovers as condensate the vapors produced at existing jetty on oil
tankers during loading operations and as well the vapors produced in the API
Separator basins.
A GRP fixed roofing system, pressurized with nitrogen, is provided on the API
Separator basins to recover and neutralize hazardous vapors.
The New Cryogenic Condensation Unit was designed to reduce emissions of VOC
(Volatile Organic Compounds) to the atmosphere, in compliance with the most recent
EU environmental standards.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
49
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Ministry of Local Government and Housing , ZAMBIA
Year: May 2014 - ongoing
Contract Value: 1mln USD
Project : Consulting Services For The Design And Supervision Of The Expansion
And Rehabilitation Of Water And Sewerage Infrastructure – Choma
Description : The Ministry of Local Government and Housing intended to provide
funds to Southern Water and Sewerage Company Limited, the Water Utility mandated
to provide water and sewerage services in Southern Province, to ensure that the water
supply and sanitation situation in the town of Choma is improved in order to support
the activities of the Provincial Capital. The activities proposed to be undertaken in the
improvement of water supply and sewerage systems have, wherever possible, been
linked to measurement indicators which will assist to evaluate progress towards
improvement of service quality and efficiency in Choma Town.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
50
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Ministry of Energy and Public Utilities, MAURITIUS and the outer island of
Rodrigues
Year: 2010 – 2012
Contract Value: 813. 282, 07 USD
Project : Hiring of Consultancy Service for Mauritius Wastewater Master Plan Study
Description : The Study for the Sewerage Master Plan of Mauritius is focused on the
attainment of three objectives: The first objective is the formulation of a phased
programme covering a period of 20 years (2014-2033) for implementing wastewater
system improvements to meet future demands in main islands of Mauritius and the
outer island of Rodrigues. The second objective is the delivery of wastewater sector
master plan report that will detail the investments needed for the twenty years period
and will recommend the actions to optimize the management of assets as well as
achieve financial efficiency and environmental compliance. The third objective is the
formulation of a feasibility study for urgent projects to be implemented in the first ten
years of the Plan
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
51
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: République du Niger, RIVER NIGER
Year: 2010 – 2011
Contract Value: 182.000 EU
Project : Preparation of a master plan for water supply targeting villages on the River
Niger
Description : The aim of the project is the preparation of master plan for water supply
in the River Niger territory, that will be part of the studies and researches necessary for
the Ministry of Hydraulic and for the other Stakeholders charged of planning the AEP
programme in the river valley. Specifically the project includes specific objectives:
• The definition of the program context and preliminary analysis of the area;
• The preparation of a general plan for the water supply, starting with surface water.
• The involvement of all the relevant actors concerned aiming at obtaining the
general approval on the plan
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
52
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Sierra Leone Water Company Ministry of Energy and Power Ministry of
Energy and Power
Year: 2006 – 2009
Contract Value: 681, 187.51 USD
Project : Water Supply & Sanitation Project ( in the towns of Makemi, Bo and
Kenema) Rural Water Supply and Sanitation
Description : To develop a full proposal of the rural water supply sanitation initiative
(RWSSI) of Sierra Leone that will facilitate both the mobilization of financial support
and detailed implementation requirements:
• To prepare an economically and technically sound project for the water supplies of
Makeni, Bo and Kenema towns.
• To assess the rural water supply and sanitation of the country and prepare a rural
water supply sanitation Program.
• To Prepare an action plan to meet the needs of year 2015 that will be include the
identification and designing of a priority scheme on a pilot basis.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
53
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Water Management Authority –Mauritius, MAURITIUS
Year: 2003 – 2007
Contract Value: 976,378.32 USD
Project : Rehabilitation of Infrastructures on CHA Estates – Extension of Phase III
Description : Rehabilitation of sewerage infrastructure on Housing Estates in
Mauritius. Involves the construction of reticulation Networks to cater for 2, 777 houses
connections to the main sewer; two sewage pumping stations and construction of
outfall Sewer 3,67 km long as well as rising main 1315 km long
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
54
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Water Management Authority –Mauritius, MAURITIUS
Year: 2002 – 2003
Contract Value: 153,178 USD
Project : Rehabilitation and Improvement of Infrastructure on CHA Estates –
Extension of Phase II
Description : Over the period 1960 -1988 a total of 158 housing estates were built across
the Country to provide shelter. For families made homeless as a result of cyclones.
However the housing estates lacked adequate facilities such as roads, water supply,
sewerage, surface water drainage and waste collection. During the years 1990 to 1998
the Phase I the Rehabilitation of Infrastructure Program was launched for the provision
of sewerage facilities to some estates Phase II of this Programme has been extended
through a Project for the rehabilitation of a satisfactory collection and disposal of
sewage in seven housing estates serving a population of 24 000 in habitants.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
55
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Ministry of Water Dar es Salaam ,TANZANIA
Year: 1998 – 2002
Contract Value: 1.282. 907 USD
Project : Consultancy Services for the Institutional Strengthening for Urban Water
and Sewerage Improvements in Tanzania
Description : The project purpose is the strengthening of the capacity of the Urban
Water and Sewerage Authorities (UWSAs) in Mwanza, Iringa, Mbeya, and Mtwara, in
terms of management, personnel and equipment. The consulting services aim at
enhancing the Ministry Officers’ expertise and know how in order to ensure the local
government an autonomous management of the waste water system. The consultants
services are also intended to:
• Safeguard water resources;
• Identity adequate financial resources;
• Promote an industrial policy for the improvement of the existing control of water
resources and utilities
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
56
Sari Consulting Ltd.
REFERENCE – WATER SECTOR
Client: Ministry of Natural Resources and Energy Water Department, GUINEA
BISSAU
Year: January - November 2001
Contract Value: 301,073 USD
Project : Technical Assistance for the Institutional strengthening of the Water
Supply and Sewerage
Description : The project overall objective in enhancing the national water
management system by providing consulting services to the Ministry of Natural
Resources and Energy in Guinea Bissau. The Coverage of the water treatment and
distribution network is inadequate due to the inability to operate and maintain the
public facilities effectively. Therefore the projects aims at strengthening the
autonomous management of those facilities at regional and local levels.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
57
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: ANE , Mozambique
Year: February 2015 - 2019
Contract Value: USD 3.757.000 + MZN 9.430.000
Project : The multinational Nacala Road Corridor Project – Phase I:Consulting
Services for Design Review and Update and Supervision of Civil Works for Lot D:
Cuamba-Muita (138 km) and Technical Assistance to ANE
Description : The Government of Mozambique intends to upgrade the strategic Nacala
Corridor to provide a more economical, reliable, and seamless flow of goods and
services between the countries of the region and at the same time to stimulate the
regional economy in the northern part of Mozambique, where the lack of all weather
roads is a major constraint on development. Currently, the Nampulato Cuamba (348km
) stretchis under implementation on in three subsections.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
58
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Road Development Agency (RDA), ZAMBIA
Year: June 2015 - Ongoing
Contract Value: USD 1.000.000
Project : Consulting Services for the detailed engineering designs and supervision of
the construction of urban roads using segmented/concrete paving block and
cobblestone technology in Northern and Luapula Provinces (250 km)
Description : The principal, overall objective of the services is to perform the necessary
surveys, detailed engineering designs, preparation of Bill of Quantities to be used
during implementation by Contractors with a view of improving road infrastructure
and general aesthetics in urban areas through the use of segmented paving blocks and
cobblestones.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
59
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Road Development Agency (RDA), ZAMBIA
Year: April 2015 - Ongoing
Contract Value: USD 1.000.000
Project : Consulting Services for the detailed engineering designs and supervision of
the construction of urban roads using segmented/concrete paving block and
cobblestone technology in Central and Muchinga Provinces -350 km
Description : The urban roads in deplorable condition in Central and Muchinga
Provinces are part of the Pave Zambia 2000 project which is an initiative of the
Government of the Republic of Zambia aimed at constructing urban roads using
segmented Paving Blocks through labor intensive methods. The services shall include
feasibility study, skill-development, materials, equipment and labor force
identification, SME and local construction sector development, contract management
and sustainability and commercialization to support Pro-poor development through
Job creation.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
60
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of infrastructure Development, TANZANIA
Year: November 2011 – ongoing
Contract Value: USD 1.670.000
Project : Consulting services for design review and pre-contract services and
construction supervision of the upgrading of Namtumbo – Tunduru road (193 km) to
bitumen standard lot A: Namtumbo – Kalimesera section (60.7 km)
Description : The Namtumbo – Tunduru road is situated in Ruvuma Region, Southern
part of Tanzania bordering Malawi to the West and Mozambique to the South. The 193
km road starts from Namtumbo and runs through woodland, bush land thicket and
grasslands and crosses Selous-Niassa wildlife corridor over a 40 km stretch and ends in
the center of the Tunduru District. The final objective of the assignment is to undertake
consultancy services on behalf of TANROADS for the design review, pre-contract
services and supervision of construction works.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
61
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Uganda National Roads Authority (UNRA), UGANDA
Year: 2011 – 2015
Contract Value: USD 2.233.000
Project : Consulting services for design review and construction supervision of
HOIMA-KAISOTONYA (92 KM)
Description : The Hoima-Kaiso-Tonya Road (92 Km) is currently a gravel road located
in Hoima District on Western Uganda and is about 225 Km west of Kampala. The scope
of the Consultancy Services are two:
• Carry out the review and update of the existing engineering design and make all
amendments and additional studies for the soundness and sufficiency of the
detailed engineering design and bid documents
• Provide Construction Supervision during the pre-construction and the
construction periods and during the Defects Liability Period
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
62
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: TANROADS, TANZANIA
Year: 2011 – 2006
Contract Value: USD 1.593.000
Project : Supervision of Works for the upgrading of the road Isaka – Nzega
Description : The Nzega-Isaka road is part of the Dar Es Salaam-Mwanza road which
transverses the towns of Morogoro, Dodoma, Manyoni, Singida, Nzega and Mwanza
(towards the north). After starting off at Nzega, the road cuts across rich agricultural
areas and terminates at Isaka connecting towns, district headquarters and economic
growth center. The rehabilitation of his section is part of a wider project providing for
the upgrading of the entire section Mwanza Border-Nzega from gravel roads to a Class
I trunk road in bitumen pavement standard. The road influence area is about 20,000
km2.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
63
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of WorksMDI Road Kanifing , THE GAMBIA
Year: 2007 - 2009
Contract Value: USD 1.366.000
Project : Supervision of rehabilitation and upgrading works of trunks roads in The
Gambia and Senegal (Lot1)Road length: 19.9 Km.
Description : Lot1 : Barra to Amdellai section (19.9 km) of the Trans West African
Highway connecting Banjul the capital of Gambia with Senegal. Lot2: Soma to Basse
and Velingara the major section of the South bank truck linking the capital Banjul and
the provincial towns(215.5 km)
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
64
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of Finance, BENIN
Year: 2004 - 2008
Contract Value: USD 1.038.000
Project : Technical Assistance to the control and supervision works for the
settlement of bituminous roads NATITINGOU- PORGA
Description : The Natitingou – Porga road (102 km) represents one of the most
important parts of the Inter-state National Road n 3 which connects Benin and Burkina
Faso. The road is a two lane highway with 3 bridges (average length 25 meters). The
project focuses on supervising the works concerning bituminous settlement in the
NATITINGOUPORGA road
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
65
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: NAO (National Authorizing Office), SIERRA LEONE
Year: 2003 – 2006
Contract Value: USD 1.160.000
Project : Consultancy Services for the Management and Supervision of Works
Contract for the Construction of the Freetown-Conakry Highway Phase I
Description : Reconstruction of the Rogbere-Pamelap Road in the Republic of Sierra
Leone of approximately 77 km length based on the approved design and contact
documents; Reconstruction of the Pamelap-Farmoreah Road in the Republic of Guinea
Conakry of approximately 9 km length, based on the approved design and contract
documents.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
66
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of Transport and Public Works, MADAGASCAR
Year: 2003 - 2006
Contract Value: USD 3.594.000
Project : Detailed Design, procurement and supervision of the rehabilitation work of
the National Roads N. 44 and N 3. Study for the Periodic Maintenance of Road RN 2.
Description : The project includes the rehabilitation and maintenance national primary
and secondary road network corridors which connects the capital of Madagascar to the
very important economic regions of the country such as Lac Alaotra through the
national road RN 44 in bituminous concrete pavement and to the port of Toamasina
through the national Road n.2 .
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
67
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of Transport and Public Works, MADAGASCAR
Year: 2003 - 2005
Contract Value: USD 1.690.000
Project : Planning , Control and Supervision of Construction works of the RN5A
between Sambava and Antalaha and of Antalaha harbour’s resettlement works.
Description : The main objective of the project is to rebuild the Nat ional Road RN5A,
between the cities of Sambava and Antalaha, in the north-east of the island. This road is
180 km long, included 1.5 km of urban road inside the city of Antalaha, road in
bituminous concrete pavement. The construction and rehabilitation works on this road
aim at the economic development of the region the main tasks concern the construction
and reconstruction of different bridges and the building of riprap foundation of the
harbor infrastructures.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
68
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of Transport and Public Works, MADAGASCAR
Year: 2002 – 2004
Contract Value: USD 1.339.000
Project : Supervision for the works of Reinforcement of Structural Network of Lot
Projects from 4 to 7
Description : The project concerns the backing of several sections and the
reconstruction of the access to the Toamasina harbor. The roads leads in concrete
pavement from Brickaville to Toamasina (total Length 115 Km).
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
69
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Ministry of Road and Transport, GHANA
Year: 2001 – 2004
Contract Value: USD 1.280.000
Project : Technical Assistance Towards the Efficient, Effective and Sustainable
Management of Maintenance in the Road Sub-Sector Project No.8 ACP GH 009
Description : The project entails the review of all existing systems and implements
actions required to put the road maintenance management in the Ministry of Roads
and Transport’s road agencies Ghana Highway Authority (GHA), Department of
Feeder Roads ( DFR) and Department of Urban Roads (DUR) on an efficient, effective
and sustainable basis.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
70
Sari Consulting Ltd.
REFERENCE – ROAD SECTOR
Client: Cabinet of Vice prime minister in charge of Economic and Social
Reconstruction, GUINEA BISSAU
Year: 2000 – 2003
Contract Value: USD 301.000
Project : Short term technical assistance to the general direction of transport
infrastructures
Description : The project aims at assisting the Ministry of Social Reconstruction
(General Directorate of Transport Infrastructures – DGIT) in developing new policies
for the setting-up of a privatized management of the road sector in cement concrete
pavement. A permanent technical assistance is provided to the management of
different types of development projects with a major focus on those financed under the
EDF.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
71
Sari Consulting Ltd.
REFERENCE – BUILDING SECTOR
Client: Republic of Uganda through the Ministry of Public Service
Year: July 2012 - Ongoing
Contract Value: USD 500.000
Project : Consulting Services to Prepare Designs, Tender Documents and Supervise
the Refurbishment of the Proposed Civil Service College Uganda (CSCU).
Description : The consultancy services entails feasibility study, preparation of
topographical survey, socio/environmental study and geotechnical study including
preliminary and outline designs and cost estimates; preparation of detailed
architectural & engineering designs including tender documents and tender action and
construction supervision including the defects liability period.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
72
Sari Consulting Ltd (SARI) operating offices are at:
via Giacomo Peroni 452, Rome, Italy
SARI Consulting (Zambia) Limited, Company Registration N. 111853.
Plot N. 53, Central Street, Jesmondine, Lusaka, Zambia
SARI Consulting (Mozambique) Ltd, Av. Kwame Nkrumah, 1335,
Maputo , Mozambique
SARI Consulting (Uganda) Ltd , Plot 26 Flat B, Golf Course Road, Off
Wampewo Avenue, Kololo, P.O.Box 6960, Kampala, Uganda
SARI Consulting (Zimbabwe) Ltd, 40 Arcturus Road Highlands, Harare,
Zimbabwe
SARI Consulting (Kenia) Ltd, Upper Hill on Kiambere Road, Casia B2
next to former World Bank offices
SARI Consulting (South Africa) Ltd, 20 Weenen Road, Milnerton, Cape
Town 7441
Sari Consulting Ltd
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
73
SIMECO operating offices are at:
Via Arcivescovo Romilli 22, 20139 Milano, Italy
Petrodar Tower, Office Suite 32, Al Seef District, Kingdom of Bahrain
Simeco Systems d.o.o., Gradacacka 29B, 71000 Sarajevo, Bosnia and
Herzegovina
Simeco S.p.A.
SARI CONSULTING LTD and SIMECO SPA
JOINT VENTURE PRESENTATION
74
SARI Consulting Ltd.
Mr. Goffredo DE PASCALE
CEO
via Giacomo Peroni 452
Rome
ITALY
Phone : + 39 06 45563173
Fax : + 39 06 45563109
e-mail:
sari@sariltd. com
g.depascale@sariltd.com
Website: www.simeco-sari.com
CONTACT
THANK YOU FOR YOUR
KIND ATTENTION
We look forward to seeing you again.
Sari Consulting Ltd and Simeco Spa

More Related Content

Similar to Simeco_Sari_JV_Business PresentationV1 8(10 11 2015)_FINALE

Capita Symonds Aviation capability
Capita Symonds Aviation capability Capita Symonds Aviation capability
Capita Symonds Aviation capability Capita Symonds
 
MCM Invest - Oil Compani̇es
MCM Invest - Oil Compani̇esMCM Invest - Oil Compani̇es
MCM Invest - Oil Compani̇esOğuzhan Ali
 
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange ProgrammeCaribbean Development Bank
 
Inpac Dev Co V011809 V2
Inpac Dev Co V011809 V2Inpac Dev Co V011809 V2
Inpac Dev Co V011809 V2Paul Allen
 
2016-09-Spans profile
2016-09-Spans profile2016-09-Spans profile
2016-09-Spans profileVicky Love
 
PT Habibillah Energi Adidaya Company Profile
PT Habibillah Energi Adidaya Company ProfilePT Habibillah Energi Adidaya Company Profile
PT Habibillah Energi Adidaya Company ProfileJaka Legawa
 
Rodecon-Engineering-business-Profile.pdf
Rodecon-Engineering-business-Profile.pdfRodecon-Engineering-business-Profile.pdf
Rodecon-Engineering-business-Profile.pdfLungisani Miya
 
Zindzi Mining & Engineering Company Profile
Zindzi Mining & Engineering Company ProfileZindzi Mining & Engineering Company Profile
Zindzi Mining & Engineering Company ProfileShamima Mulla
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN PanigrahiSN Panigrahi, PMP
 
Proventures corporate profile v2.1
Proventures corporate profile v2.1Proventures corporate profile v2.1
Proventures corporate profile v2.1ProventuresEducation
 
White paper-iodtech-1-1 (1)
White paper-iodtech-1-1 (1)White paper-iodtech-1-1 (1)
White paper-iodtech-1-1 (1)ali tajalli
 
ACCIONA Infrastructure
ACCIONA InfrastructureACCIONA Infrastructure
ACCIONA Infrastructureacciona
 
ESD Company Profile - 17-2-2016 Rev2
ESD Company Profile - 17-2-2016 Rev2ESD Company Profile - 17-2-2016 Rev2
ESD Company Profile - 17-2-2016 Rev2T. MADIBA
 
Sincrono solutions Traffic and Transportation
Sincrono solutions Traffic and TransportationSincrono solutions Traffic and Transportation
Sincrono solutions Traffic and Transportationjitendra mane
 

Similar to Simeco_Sari_JV_Business PresentationV1 8(10 11 2015)_FINALE (20)

Ppi Profile October 2008
Ppi Profile October 2008Ppi Profile October 2008
Ppi Profile October 2008
 
Capita Symonds Aviation capability
Capita Symonds Aviation capability Capita Symonds Aviation capability
Capita Symonds Aviation capability
 
MCM Invest - Oil Compani̇es
MCM Invest - Oil Compani̇esMCM Invest - Oil Compani̇es
MCM Invest - Oil Compani̇es
 
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
 
EoI Nigeria-BRT
EoI Nigeria-BRTEoI Nigeria-BRT
EoI Nigeria-BRT
 
Inpac Dev Co V011809 V2
Inpac Dev Co V011809 V2Inpac Dev Co V011809 V2
Inpac Dev Co V011809 V2
 
2016-09-Spans profile
2016-09-Spans profile2016-09-Spans profile
2016-09-Spans profile
 
CPC_PROFILE_COMPLETE
CPC_PROFILE_COMPLETECPC_PROFILE_COMPLETE
CPC_PROFILE_COMPLETE
 
PT Habibillah Energi Adidaya Company Profile
PT Habibillah Energi Adidaya Company ProfilePT Habibillah Energi Adidaya Company Profile
PT Habibillah Energi Adidaya Company Profile
 
Rodecon-Engineering-business-Profile.pdf
Rodecon-Engineering-business-Profile.pdfRodecon-Engineering-business-Profile.pdf
Rodecon-Engineering-business-Profile.pdf
 
Zindzi Mining & Engineering Company Profile
Zindzi Mining & Engineering Company ProfileZindzi Mining & Engineering Company Profile
Zindzi Mining & Engineering Company Profile
 
corporate_catalog2016
corporate_catalog2016corporate_catalog2016
corporate_catalog2016
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 
Proventures corporate profile v2.1
Proventures corporate profile v2.1Proventures corporate profile v2.1
Proventures corporate profile v2.1
 
White paper-iodtech-1-1 (1)
White paper-iodtech-1-1 (1)White paper-iodtech-1-1 (1)
White paper-iodtech-1-1 (1)
 
ACCIONA Infrastructure
ACCIONA InfrastructureACCIONA Infrastructure
ACCIONA Infrastructure
 
Corporate Presentation 2013 english
Corporate Presentation 2013 englishCorporate Presentation 2013 english
Corporate Presentation 2013 english
 
Automotive UK M+E_Jan 2016_Screen
Automotive UK M+E_Jan 2016_ScreenAutomotive UK M+E_Jan 2016_Screen
Automotive UK M+E_Jan 2016_Screen
 
ESD Company Profile - 17-2-2016 Rev2
ESD Company Profile - 17-2-2016 Rev2ESD Company Profile - 17-2-2016 Rev2
ESD Company Profile - 17-2-2016 Rev2
 
Sincrono solutions Traffic and Transportation
Sincrono solutions Traffic and TransportationSincrono solutions Traffic and Transportation
Sincrono solutions Traffic and Transportation
 

Simeco_Sari_JV_Business PresentationV1 8(10 11 2015)_FINALE

  • 1. JOINT VENTURE PRESENTATION Together we build something better WELCOME TO OUR
  • 2. WHO WE ARE? SARI Consulting Ltd is a quality-driven, leading engineering company with over 18 years experience in the provision of independent professional management, strategic advice, design of infrastructures and environmental engineering. SARI is a company participating in FG Tecnopolo Alliance. FG Tecnopolo Alliance is an initiative of FG Tecnopolo Holding, a structured network of partner companies specialized in consulting services in the fields of architecture, engineering, and information technology, delivering fully integrated design services for large scale projects. The FG Tecnopolo Alliance business model is based on the integration of skills of the individual Companies participating in the coalition, which while preserving their independence, contribute to the definition of integrated and harmonized design proposals. The scope is to provide integrated consultancy services characterized by the Maximum Specialization in the disciplines, thanks to the excellent standard of all Partners, through the interface of the Structured Organization of FG Tecnopolo Alliance. SIMECO Spa is a leading mid-size engineering and contracting company, established in 1984, providing: • qualified and competitive services from basic design & FEED to detail engineering and site services, for Oil & Gas plants (On-shore/Off-shore Upstream Facilities, Refining), Pipelines, Petrochemical & Chemical Plants, Power Plants (including renewable energies), Plant Off-sites & Utility Generation Units; • contracting for the execution of projects on turn key lump sum basis; • design and supply of skid mounted plants.
  • 3. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 3 Sari Consulting Ltd (SARI) activity cover: • Economic and financial analysis, feasibility studies, and concessions of infrastructure projects; • Institutional strengthening and capacity- building, assistance to program management, as well as programming for operation and maintenance of infrastructure and equipment; • Irrigation/Agricultural planning, including design and/or modernization of infrastructure; • Technical assistance, planning, studies, design and/or construction supervision of all types of transport infrastructure, building technology, water and environment, in projects ranging from major infrastructure to small local projects. SARI Clients include: Developing Aid Agencies, Government Ministries Municipal Authorities, Private Sector Companies. SARI is registered with the majority of funding agencies such as the European Union (EDF), and International Financial Institutions such as the World Bank Group (IBRD/IDA), the African Development Bank (AfDB), and the Asian Development Bank. Sari Consulting Ltd.
  • 4. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 4 Sari Consulting Ltd (SARI) has carried out projects in the following countries: Africa: Tanzania, Uganda, Zambia, Mozambico, Gambia, Guinea Bissau, Benin, Sierra Leone, Madagascar, Ghana , Mauritius, Niger, Lesotho, Angola, Morocco, Djibouti, Rwanda, Botswana, Angola, Seychelles , Nigeria, Burkina Faso, Republic of Congo (Brazaville), Malawi, Somalia, Togo, Algeria, Comore Islands , Egypt, Tunisia, Libya, Ivory Coast, Guinea (Conakry), Liberia, Senegal Central & South America: Saint Lucie(West Indies), Haiti, Honduras, Ecuador, Nicaragua, Venezuela, El Salvador, Guatemala Asia Pakistan, India, Philippines, Thailand, Indonesia, Myanmar, Mongolia Oceania Vanuatu Europe Italy, Albania Sari Consulting Ltd.
  • 5. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 5 Simeco S.p.A. possess the organization and the skilled experienced staff to provide the following services to the Oil & Gas, Petrochemical and Chemical Industry: • Feasibility Studies and Cost Estimates • Conceptual Design • Basic Engineering Design • Front End Engineering and Design (FEED) • Project Management • Project Management Consultancy • Owner’s Engineering Services • Risk Analysis and HSE Reports • Detail Engineering • Procurement Services • Expediting and Inspections • Construction Management & Site Supervision • Commissioning • Assistance to Plant Start-up and Operation • Operative Maintenance & Training • Supply of equipment and skid mounted units on EP/EPC basis Simeco S.p.A.
  • 6. SARI CONSULTING LTD and SIMECO SPA PARTNERSHIP PRESENTATION 6 Our mission is to operate in different fields of engineering and architecture on behalf of private and public customers, expressing their freedom of action and choice in identifying the best solutions for each project, in order to ensure the highest satisfaction of our customers and the achievement of their targets. Commitment, consistency and accountability are the fundamental values through which we build the confidence of our customers during the execution of each project. VISION AND MISSION
  • 7. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 7 Oil & Gas FIELD OF ACTIVITIES Water Infrastructures Environmental Architecture, Civil Engineeering Environmental Engineering Hydraulic & Coastal Engineering Geology & Geotechnical Engineering Town & Regional Planning Roads & Highways Railroads Bridges & Structures Water, Drainage & Sewerage Systems Sari Consulting Ltd. Oil & Gas Plants Refineries Petrochemical Plants Chemical Plants Power Plants Tank Farms Pipelines Renewable Energies Simeco S.p.A.
  • 8. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 8 YEARLY TURNOVER $15M 2015 $7M 2014 $5M 2013 $15M 2015 $17M 2014 $19M 2013 Sari Consulting Ltd. Simeco S.p.A.
  • 9. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 9 JOINT VENTURE OFFICES WORLDWIDE Milano, Italy Rome, Italy Sarajevo, Bosnia and Herzegovina Kingdom of Bahrain Lusaka, ZambiaKampala, Uganda Maputo, MozambiqueCape Town, South Africa Harare, ZimbabweNairobi, Kenya
  • 10. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 10 50+ CLIENTS 500+ ITEMS DELIVERED 500+ PROJECTS JOINT VENTURE WORKFORCE More than 250 engineers and technicians to develop your ideas and support your business
  • 11. BUSINESS PRESENTATION 11 MEET OUR TEAM Pierfranco FORLANI President Goffredo DEPASCALE CEO Antonio GNISCI COO * Lorenzo TAGLIABUE New Business Development Mirella REGGIANI CFO Alfonso PANTALENA Relations with Oil Companies Giuseppe PEDATA Communication & Relations with Middle East countries Pietro FONTANA Oil & Gas Technical Director Gianluca GASPERINI O&G Process Technologies Director Marco FORLANI O&G Operations Director Francesco GALLI ** Transportation & Water Technical Director Francis BYARUHANGA Executive Director Uganda Jacob SIKAZWE Executive Director Zambia Nico BEZUIDENHOUT Executive Director S.A • Managing Director of FG Tecnopolo Holding Srl ** Africa Director of SGI – Studio Galli Ingegneria Srl
  • 12. BUSINESS PRESENTATION 12 Our Quality Management System is certified by D.N.V. (Det Norske Veritas) for conformity to the Requirements of ISO 9001:2008 for: Multidisciplinary basic and detailed design of chemical, petrochemical, refinery, power generation and of gas and oil pipelines. Equipment and material procurement. QUALITY MANAGEMENT SYSTEM
  • 13. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 13 WRc Group Stoat 4.01 Modelling of Waste Water Treatment Plants LEDA FLOW Flow Assurance, Dynamic Multiphase Flow HTRI / MICROTECH / PV ELITE Design of heat exchangers, aircoolers, pressure vessels PDS / SMART PLAN / PDMS CAD 3D of industrial plants CAESAR II Piping stress analysis SPI (former INTOOLS), AVEVA Instrumentation Instrumentation Database PLC 2005 Software to design and plan PLC inputs-outputs NEPLAN / AMPERE / ETAP Design, optimization and simulation of electrical systems MS PROJECT /PRIMAVERA P6 Project management (planning and control) ASPEN ONE ENGINEERING DESKTOP / HYSYS / PRO II Process simulators BIOWIN 3 Analysis, testing and design of wastewater treatment plants ANOVA Swater Modelling of suspended-biomass wastewater treatment plant AFT Arrow / Fathom / Impulse Steady state & dynamic simulation of pipeline networks DHI Mike Integrated modelling of the entire water cycle (storm and waste waters, open channels, urban water networks,…). CSdU Urbis Pro Hydraulic simulation of flood waves in water basins SANEX 2.0 Design and planning of septic tanks and sewers EMS-I SMS (RMA2-RMA4) 2D hydro-dynamic modelling of waste waters SOFTWARE TOOLS Plant Design
  • 14. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 14 ESRI Arc View Geographic Information System (GIS) MAT 3D / FOUNDATION 3D Design of foundations STAAD PRO / SAP 2000 Structural Design TEKLA 3D Modelling of steel structures DIGICORP CIVIL DESIGN AUTOCAD add-on for civil works, topography, road and railways design MX Road Design / AutoTURN/ Civil 3D Road Design HDM-4 Economic analysis for roads and highways ESRI Arc View Geographic information system (GIS) Sierrasoft ProST Planning and accounting of civil works SOFTWARE TOOLS Civil Works & Infrastructures:
  • 15. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 15 2 Hanna Instruments photometers for analysis of free and total chlorine 2 two-channel Spectralog with incorporated 10 bar pressure transducer 9 one-channel Spectralog with incorporated 10 bar pressure transducer 2 Spectrascan bi-directional quadrina to gauge flow 2 Spectrascan gauge poles (for quadrina) 1 Palmer MC5 model micro-correlator 1 stetophon Sewerin listening poles with extensions EQUIPMENT FOR ANALYSIS AND MONITORING OF WATER AND DRAINAGE SYSTEMS 1 Sewerin AQUAPHON model geophone 1 Sewerin manhole cover detector 4 Casella Rain Gauges 1 MONTEC DETECT 3013 portable level-speedometer to gauge water speed 1 ISCO sampler 1 SIGMA sampler
  • 16. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 16 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Pacific Future Energy (Canada) Year: 2014 Project : British Columbia Greenfield Refinery, Canada (Feasibility Study) Description: Pacific Future Energy Co. is committed to build and operate the world’s greenest refinery on British Columbia’s north coast. PFEC believes it is in Canada’s national strategic interest to gain access to international markets for Alberta’s oil, especially the fast growing Asian market. The company believes it should not be done at the sacrifice of BC’s coast or broader environment and must be done in full partnership with First Nations. The $10 Billion refinery will be built in modules (each phase having a process capacity of 200,000 BPSD).
  • 17. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 17 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Milazzo Refinery (RaM) Year: 2014-2015 Project : New Naphtha Hydrotreating Unit, Italy (Basic Design) Description: The scope of the Basic Design Package is a new naphtha hydrotreating unit named HDT-3. HDT-3 will produce 450,000 tons per year of hydrotreated Naphtha containing less than 0.5 ppmw of sulphur and 24,000 tons per year of olefin saturated LPG with target specification Pro Isomerization. The plant will include a refurbished hydrotreating reactor and new pumps, heat exchangers in the preheating trains, fired heater, three-phase separators, reboiled stripper distillation tower, associated utilities, LPG and off-gas amine gas treating packages, recycle / make-up gas compressor package and control systems.
  • 18. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 18 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Milazzo Refinery (RaM) Year: 2014-in progress Contract Value (LSTK): 15M€ Project : Revamping of Kerosene Desulphurization Unit, Italy (EPC) Description : Project scope is a major revamping of the existing Kerosene Hydrodesulphurization Unit (HDS-1) to expand the capacity from 2,400 to 4,000 t/d. Improvement of product quality to target specification Pro Clear and Bright and maximum S content of 10 ppm are also foreseen. New feed pumps, stripper, kero dryer and heat exchange train are being installed.
  • 19. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 19 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Eni R&M Division (Italy) Year: 2011-2013 Contract Value (LSTK): 14M€ Project : Vacuum Column & Filtration System for FCC Slurry Oil (EPC) Description : Project scope is the installation of a new Vacuum Column & Automatic Filtration System on the Slurry Oil stream produced by the existing FCC Plant of the Refinery. The purpose of the new Unit is: 1) to recover additional LVGO as feed for the Hydrocracking Unit 2) to increase Slurry Oil flash point 3) to remove the catalyst fines in order to feed the Clarified Oil (CLO) stream to the existing Gasification Plant or to recycle it to the FCC riser .
  • 20. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 20 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Danieli Far East Year: 2011-2012 Project : Carbon Dioxide Removal Unit (FEED + Detail Design + Procurement Services) Description: Project scope was the Detail Design, the Equipment & Bulk Material Procurement and the Home Office Project Management Services for the 10,000 Nm3/h Carbon Dioxide Removal Unit at an iron ore reduction plant. The Unit, based on Giammarco-Vetrocoke hot carbonate process, was extensively modularized in order to facilitate the construction utilizing local labour.
  • 21. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 21 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Eni E&P Division Year: 2010-2011 Project: Fauzia, Elettra & Benedetta Platforms, Adriatic Sea (FEED) Description : The project was carried out providing our Client with the EPC Tender Documents for n.3 new gas platforms located offshore Adriatic Sea and the relevant ± 15% Cost Estimate. SIMECO developed the Front End Engineering Design according to the following main specifications: • FAUZIA PLATFORM: 12” export sealine; n° 2 wellheads double completion; 3-legs jacket. • ELETTRA PLATFORM: 8” export sealine; n° 1 wellhead double completion; 3-legs jacket. • BENEDETTA PLATFORM: 8” export sealine; n° 1 wellhead single completion; monopode.
  • 22. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 22 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Saipem SES Year: 2008-2010 Project : OLT Livorno FSRU, Italy (Detail Design) Description: The world’s first offshore Floating Storage and Regassification Unit (FSRU) was constructed by converting the LNG Carrier Golar Frost. The FSRU is permanently moored offshore Livorno, Italy, about 12 miles from the coast in a water depth of about 120 meters and connected to shore through a gas export pipeline. Storage capacity is 137,000 cubic meters of LNG in four spheres. Production capacity is 3,75 billion standard cubic meters year (bscmpa).
  • 23. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 23 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Saipem (Iraq) Year: 2010-2011 Project : Zubair Degassing Station, Iraq (FEED) Description : Project scope was the development of the Front End Engineering Design for a new Oil Degassing Station (DGS) and rehabilitation of an existing one at Zubair field, Iraq. The Zubair field - being developed by Eni with Occidental Oil Co., Korean Gas and Missan Oil Company - with an estimated production capacity of 1,200,000 BOPD is one of the few super giant oil field presently developed worldwide. Zubair is a “brown field” project involving the realization of new plants as well as the revamping of existing unit.
  • 24. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 24 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: ENI R&M Div. Year: 2010-2011 Contract Value (LSTK) : 1.1 M€ Project : Electrically Traced Transfer Line for Liquid Sulfur at Eni’s Taranto Refinery, Italy (EPC) Description: Project scope was the installation of a new 4’’ x 1 km Liquid Sulfur transfer line from the Sulfur storage tanks to the flaker unit producing solid sulfur flakes. The un-flanged transfer line is electrically heated by a skin effect tracing system capable to re-melt the sulfur in case of in line solidification.
  • 25. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 25 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Saipem Year: 2009-2012 Project : EST Project at Eni’s Sannazzaro Refinery, Italy (Detail Design) Description: EST (Eni Slurry Technology) is a new deep hydrocracking technology developed by Eni for the valorization of heavy and extra heavy oils, tar sands and refinery residues. Sannazzaro Plant, with a capacity of 20,000 BPSD, will be the first industrial application of the EST technology, which has been extensively tested in a Commercial Demonstration Unit in Italy. EST plant features n.2 x 2,000 t hydro-cracking reactors made of CrMoV + SS 347 Weld Overlay, supplied by GE-Nuovo Pignone, the largest built ever. SIMECO has been in charge for the Technical Bid Evaluation and the follow-up of the hydro-cracking reactors, hydro-treating reactors (400 t) and large HP Gas/Liquid Separators (300 t) made of CrMoV (supplied by ATB).
  • 26. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 26 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Eni SpA Year: 2008-2009 Contract Value (LSTK): 8.5 M€ Project : C4 Dryers Package at Eni’s Sannazzaro Refinery, Italy (EPC) Description: The new C4 Dryer Package was designed to remove impurities (water, acetone, acetonitryle) from a C4 Olefinic Stream , feeding the existing Isomerization Unit. The purification is obtained throughout adsorbents continuously regenerated. The regeneration unit includes a hydrogenation reactor to remove to reduce olefins content from the adsorbent regeneration stream. The Unit is entirely installed on a steel structure “straddling” an existing pipe-way in a very congested area of the Refinery.
  • 27. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 27 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Saipem Energy Services Year: 2009 Project : GOSP at Burun Oil Field, Turkmenistan (BDP review and assessment) Description: The Gas Oil Separation Plant (GOSP) at Burun Oil Field had some trouble operations, i.e. sand carry over, clogging of filters by paraffines contained in the crude oil and HSE issues. The Scope of Work was to carry out, on a very tight schedule, a review of the existing BDP developed by the previous Owner of the Oil Field in order to solve the operating problems. Each document of the BDP was reviewed and several inconsistencies were identified. For each document a Comment Sheet was produced. Eventually, recommendations have been provided to Company regarding the possibility to use the BDP as a basis for an EPC bid to de-bottleneck the Plant.
  • 28. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 28 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Bonatti Year: 2008-2009 Project : Underground Gas Storage, Italy (Detail Design) Description: Bordolano is a depleted gas field, 50 km from Milan (Italy), owned by SNAM Rete Gas/STOGIT (Stoccaggi Gas Italia). STOGIT intended to convert the existing reservoir into an Underground Gas Storage. The Plant consisted of a temporary gas compression and Injection station, called Early Injection Station, withdrawing natural gas from the national pipeline network owned by Snam Rete Gas. Natural Gas was collected and delivered to the reservoir through 2 new pipelines. The Early Injection Station was dismantled once completed the injection phase of the cushion gas in the reservoir.
  • 29. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 29 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Saipem Year: 2008-2009 Project : QAFCO V Ammonia Plant, Qatar (Detail Design) Description: The Project include N. 2 complete Ammonia Plants (Licensor Haldor Topsoe A/S - design capacity 2 x 2,200 t/d) based on Steam Reforming of Natural Gas consisting of the following process systems: Natural gas desulphurization; Process Air Compression; Steam Reforming of Natural Gas and Waste Heat Recovery; HT & LT Shift Converters; CO2 removal by MDEA; Methanation; Syngas Compression; Ammonia Synthesis Loop; Ammonia Refrigeration; Purge Gas Scrubbing & Hydrogen Recovery; Process Condensate Stripper; Deaerator & BFW pumps.
  • 30. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 30 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Snamprogetti Year: 2007-2008 Project : ENVEN 1.3 Project - Ammonia / Urea Plant, Pakistan (Detail Design) Description : N.1 complete Ammonia Plant (Licensor Haldor Topsoe A/S; 2184 MTPD) based on Steam Reforming of Natural Gas consisting of the following process systems: Natural gas desulphurization; Process Air Compression; Steam Reforming of Natural Gas and Waste Heat Recovery; HT & LT Shift Converters; CO2 removal by MDEA; Methanation; Syngas Compression; Ammonia Synthesis Loop; Ammonia Refrigeration; Purge Gas Scrubbing & Hydrogen Recovery; Process Condensate Stripper; Deaerator & BFW pumps. Urea Plant (Licensor Snamprogetti; 3835 MTPD) Process units have been connected to existing Facilities as: Instrument Air, Plant Air, Steam Generation, Power Generation, Raw Water, Potable Water, Natural Gas Treatment.
  • 31. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 31 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Tecnimont Year: 2006-2007 Project: NKNK LLDPE/HDPE Plant, Russia (Detail Design) Description: NKNK (Nizhnekamsk Neftekhim) LLDPE/HDPE is a Polyethylene Plant based on the Spherilene Process Technology from Basell Italia. The plant annual capacity is 230,000 MTPY of polyethylene in pallets, HDPE, MDPE and LLDPR type. The units included in the engineering activities were: Polymerization Area, Extrusion Area, Alkyl Area, Homogenization, Bagging, Palletizing and Warehouse, Interconnecting & Pipe Racks, Effluent Basin, Purification, Propane Storage, Control Room and Substation, Valve House, Flare Area, Underground.
  • 32. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 32 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: ENI Oil Co. Ltd, Libyan Branch Year: 2005-2006 Project : Water Injection Plant & Power Generation System, El Feel Field, Libya (FEED) Description : The Water Injection Plant (275,000 BWPD) consists of: Water Supply System, including Oil / Water separation by induced gas flotation, Filtration and Chemicals Injection Systems. Injection Water System, consisting of: Buffer Tank, Injection Water Booster Pumps, Injection Water Pumps. Gathering System, consisting of n. 5 Trunk-lines up to 24’’ x 38 km The Power Generation Systems (50 MWe) consisting of: n. 3+1 Heavy Duty Gas Turbines GE FR5-1 Dual Fuel fed with Crude Oil (chemically treated for V inhibition) or Natural Gas. New dedicated Control Room & Electrical Sub-Station.
  • 33. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 33 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Milazzo Refinery (RaM) Year: 2005 – 2008 Contract Value (LSTK): Phase 1 – 2.7 M€, Phase 2 – 2.9 M€ Project : Revamping of Marine Loading Arms, Italy Description : The Project consisted of two Phases: During Phase 1, 4 x 16” existing Crude Oil Loading Arms at Pier 2/Mooring 5 were dismantled and replaced with 3 x 16’’ Loading Arms. During Phase 2, the same operation, as per Phase 1, were carried out on Pier 2 / Mooring 6. FMC Technologies were in charge for the supply of the Loading Arms. SIMECO provided Engineering Services, Procurement of piping materials and Supervision during Erection, Commissioning and Start-up.
  • 34. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 34 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Snamprogetti Year: 2005 Project : ISOCRACKER at Sannazzaro de Burgondi Refinery, Italy (Detail Design) Description: Sannazzaro’s ISOCRACKER is a 25,000 BPSD Hydrocracking Plant based on Chevron Lummus Global technology. Scope of the Engineering Services executed by SIMECO and Partners included the Main Process Units along with the following Auxiliary Units: • Sour Water Stripper Unit • Amine Regeneration Unit • Interconnecting • Off-sites • Cooling Water Unit.
  • 35. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 35 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Snamprogetti Sud Year: 2003-2004 Project : FCC GASOLINE HDS Unit at Eni’s Sannazzaro Refinery, Italy (Detail Design) Description: Sannazzaro’s FCC Gasoline Hydrodesulphurization Unit is a 20,000 BPSD plant based on CDHYDRO catalytic distillation technology by CDTECH. Auxiliary Units were also included in the SOW.
  • 36. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 36 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: Snamprogetti Sud Year: 2003 Project: Topping 2 Revamping Project at Eni’s Sannazzaro Refinery, Italy (Detail Design) Description: Topping 2 was originally designed to process 715 t/h of Arabian Light Crude Oil. A major de-bottlenecking to process up to 770 t/h of Djeno Melange Crude Oil was required. The revamping consisted of: • Addition of a new Pre-flash Column upstream of the existing Topping Column along with relevant Heaters and Pumps; • Design of new steel structures Complete review/check of the existing Utilities and Off-sites systems, i.e. BD, Utilities, Closed Drain.
  • 37. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 37 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: PRAOIL Oleodotti Italiani Year: 2003-2004 Project : Genoa De-bottlenecking Project, Italy (Detail Design) Description: Underground interconnecting to upgrade and rationalize the 100 years old oil products offloading marine terminal in Genoa. “Trench-less” and “micro-tunnel” technologies have been deployed due to the very populated and geologically critical areas. 4 x 30” + 2 x 12” pipelines have been laid down in a 2.6 m x 650 m micro tunnel between Genoa Marine Oil Terminal and Praoil Petroleum Products Depot & Pumping Booster Station.
  • 38. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 38 Simeco S.p.A. REFERENCE – OIL & GAS SECTOR Client: VISCOLUBE Year: 2001-2003 Project : Spent Lube Oil Re-refining Plant and Offsites Revamping , Italy (FEED + Detail Design + Procurement Services) Description: VISCOLUBE is the European leader in re-refining of spent lube oils, with over 60,000 MTPY of reclaimed oils. The Spent Lube Oil Hydrotreating Unit is based on Axens technology. The Plant includes a Hydrogen Generation Unit designed by CALORIC Anlagenbau (Germany). CALORIC is a firm specialized in supply of gas generation plant package, i.e.: syngas, carbon monoxide, hydrogen.
  • 39. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 39 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Eni, Venice Refinery Year: 2014 Project: Revamping of S. Leonardo Oil Terminal – Feasibility Study Description: Venice Refinery scope was to convert San Leonardo Crude Oil receiving terminal to finished product terminal for ship with DWT variable between 10.000 to 80.000 Tons. The Feasibility Study included: • the verification about the possibility to re-use the existing loading arms; • the study of the modification of the existing lines in order to optimize discharge rates and operability; • the verification of the mooring systems, including: • Jetty height above the average sea-level • Jetty structural integrity • Status of the existing mooring equipment • Analysis of ship positioning • Identification and sizing of new mooring points.
  • 40. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 40 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Eni, Livorno Refinery Year: 2013 Project: Revamping of the existing LPG Terminal Description: The Scope of Work included the revamping of the existing LPG terminal in order to unload LPG carrier up to 30,000 DWT with a discharge rate of 500 ton/h. The Scope of Work included the verification of the mooring systems, including: • Jetty height above average sea-level • Status of the existing mooring equipment • Mooring study, i.e. analysis of ship positioning, identification and sizing of new mooring points.
  • 41. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 41 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Genoa Port Authority Year: 2011 Project: Study of petroleum products transfer operations under steady state and transient conditions Description: The main purpose of the study was to carry out the Conceptual Design of a system to protect the lines and the loading arms from overpressures during operations The activities carried included: • Steady state analysis of loading/unloading operations to determine the maximum allowe transfer rates. • Transient state analsysis of the pressure peak over the lines and the loading in case of emergency shut down (i.e. water hammer effect due to block valve closure) • Conceptual Design of the High Integrity Pressure Protection System (HIPPS).
  • 42. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 42 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Snamprogetti Year: 2006 – 2007 Project: Trans Anatolian Pipeline, Turkey (Conceptual Design + FEED). Description : The Project included the following facilities: A new unloading terminal located east of Samsun, on the Black Sea, suitable for handling a wide range of tankers, including VLCCs, through three (3) Single Point Moorings and relevant unloading facilities; A new tank farm located east of Samsun, on the Black Sea, featuring 12 floating roof storage tanks (total net capacity of 1,500,000 m3), including all relevant facilities and a new dedicated power plant; A 48”and 42” (for the last section), 550 km long carbon steel pipeline provided with a Pressure Reducing Station (PRS), mainline isolation block valves and pigging trap systems; One head pump station (PS1) located at the unloading terminal on the Black Sea and three additional pump stations (PS2, PS3, PS4) located along the route of the TAP pipeline at different elevations, provided with power generation and all required facilities such as control rooms, accommodation, security and maintenance buildings; A new tank farm located at Ceyhan, featuring 12 floating roof storage tanks (total net capacity of 1,800,000 m3), including all relevant facilities; A new jetty marine loading terminal, on the Mediterranean Sea, located in front of the new Ceyhan tank farm, suitable for a wide range of tankers, including VLCCs..
  • 43. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 43 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Eni, Gaeta Oil Terminal Year: 2003 Project: Feasibility Study of a New Multibuoy Mooring Terminal for carriers up to 40,000 DWT Description: The scope of the study was to investigate different alternatives for the expansion of the existing Oil Terminal. In particular, the Feasibility Study addressed: • The new subsea Pipeline End Manifold (PLEM) • n. 3 sealines for trasnfer of oil products • The study of n. 5 Buoys + swamp mooring.
  • 44. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 44 Simeco S.p.A. REFERENCE – MARINE OIL TERMINALS Client: Compagnia Italpetroli Spa Year: 1997 Project: Civitavecchia New Oil Terminal – Basic Design Description: The project included: • n.1 single buoy mooring system (water depth 50 m) • n.2 24’’ x 2.2 km sealines + n.2 24’’ x 1.15 km on-shore lines for transfer of fuel oil; • n.2 22’’ x 2.2 km sealines + n.2 22’’ x 4.7 km on-shore lines for transfer of light petroleum products (i.e. gasoline, kerosene, diesel). SIMECO carried out the basic design for the single buoy mooring system and the pipelines. The type of foundations have been designed based on site geological data, while metocean data (wind, waves, streams,….) have been used as a basis for the mooring study in order to select the most suitable mooring equipment.
  • 45. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 45 Simeco S.p.A. REFERENCE – ENERGY SECTOR Client: Enipower Year: 2010 Project : Combined Heat & Power Plant Revamping , Italy (FEED) Description: Project scope was the Front End Engineering Design for the revamping of Enipower Combined Heat & Power Plant located in Bolgiano, San Donato Milanese, Italy. The revamping consisted in dismantling the existing power generation units and their replacement with a new gas turbine (aero derivative type), installation of n.2 endothermic engines with waste heat boilers for power generation and production of hot water, n.3 auxiliary boilers, n.10 buffer tanks for hot water distribution to the existing district heating network, n.1 new pumping station, new electrical room, new technical room. SIMECO Scope of Work included also +/- 15% cost estimate and preparation of the EPC Tender Documents.
  • 46. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 46 Simeco S.p.A. REFERENCE – ENERGY SECTOR Client: Maire Engineering Year: 2007 Project : Bocamina II - Power Plant, Chile (Basic + Detail Design) Description: Bocamina II is a 370 MWe Coal Power Plant owned by Endesa located in Puerto Coronel, 30 Km SE of Concepcion, Chile. The Plant features a SES Boiler and a GE Steam Turbine model D5. SIMECO and JV partners Scope of Work covered Basic Engineering and Detailed Mechanical Design for Piping Engineering, including 3D modeling, of the following systems: Steam Generation, Auxiliary Steam System, Machinery Cooling, De-mineralized Water, Instrument Air, Fire Fighting Water, Waste Water, Condensate Recovery, Vacuum Condenser, Boiler Feed Water, Fuel Oil, Sampling, Chemical Injection.
  • 47. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 47 Simeco S.p.A. REFERENCE – ENVIRONMENTAL SECTOR Client: Eni R&M Division Year: 2011-2012 Project: Waste Water Treatment System for Water Re-use at Eni’s Sannazzaro Refinery, Italy (Detail Design) Description: Project scope is the installation of a new Waste Water Treatment Package to process 740 m3/h of water discharged from the existing Refinery Water Treatment System, to obtain permeated desalted water (conductivity < 100 µS/cm, hardness < 5 mg/l as CaCO3 ) suitable for steam generation. The purpose of the new Unit is to recycle water previously discharged to the environment in order to feed the existing demineralized water production system for the requirements of the new Process Plants .
  • 48. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 48 Simeco S.p.A. REFERENCE – ENVIRONMENTAL SECTOR Client: Polimeri Europa Year: 2006 – 2007 Contract Value (LSTK): 6 M€ Project: TAS (Waste Water Treatment) Covering System at Sarroch Petrochemical Complex, Italy (EPC) Description: The New Unit recovers as condensate the vapors produced at existing jetty on oil tankers during loading operations and as well the vapors produced in the API Separator basins. A GRP fixed roofing system, pressurized with nitrogen, is provided on the API Separator basins to recover and neutralize hazardous vapors. The New Cryogenic Condensation Unit was designed to reduce emissions of VOC (Volatile Organic Compounds) to the atmosphere, in compliance with the most recent EU environmental standards.
  • 49. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 49 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Ministry of Local Government and Housing , ZAMBIA Year: May 2014 - ongoing Contract Value: 1mln USD Project : Consulting Services For The Design And Supervision Of The Expansion And Rehabilitation Of Water And Sewerage Infrastructure – Choma Description : The Ministry of Local Government and Housing intended to provide funds to Southern Water and Sewerage Company Limited, the Water Utility mandated to provide water and sewerage services in Southern Province, to ensure that the water supply and sanitation situation in the town of Choma is improved in order to support the activities of the Provincial Capital. The activities proposed to be undertaken in the improvement of water supply and sewerage systems have, wherever possible, been linked to measurement indicators which will assist to evaluate progress towards improvement of service quality and efficiency in Choma Town.
  • 50. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 50 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Ministry of Energy and Public Utilities, MAURITIUS and the outer island of Rodrigues Year: 2010 – 2012 Contract Value: 813. 282, 07 USD Project : Hiring of Consultancy Service for Mauritius Wastewater Master Plan Study Description : The Study for the Sewerage Master Plan of Mauritius is focused on the attainment of three objectives: The first objective is the formulation of a phased programme covering a period of 20 years (2014-2033) for implementing wastewater system improvements to meet future demands in main islands of Mauritius and the outer island of Rodrigues. The second objective is the delivery of wastewater sector master plan report that will detail the investments needed for the twenty years period and will recommend the actions to optimize the management of assets as well as achieve financial efficiency and environmental compliance. The third objective is the formulation of a feasibility study for urgent projects to be implemented in the first ten years of the Plan
  • 51. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 51 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: République du Niger, RIVER NIGER Year: 2010 – 2011 Contract Value: 182.000 EU Project : Preparation of a master plan for water supply targeting villages on the River Niger Description : The aim of the project is the preparation of master plan for water supply in the River Niger territory, that will be part of the studies and researches necessary for the Ministry of Hydraulic and for the other Stakeholders charged of planning the AEP programme in the river valley. Specifically the project includes specific objectives: • The definition of the program context and preliminary analysis of the area; • The preparation of a general plan for the water supply, starting with surface water. • The involvement of all the relevant actors concerned aiming at obtaining the general approval on the plan
  • 52. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 52 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Sierra Leone Water Company Ministry of Energy and Power Ministry of Energy and Power Year: 2006 – 2009 Contract Value: 681, 187.51 USD Project : Water Supply & Sanitation Project ( in the towns of Makemi, Bo and Kenema) Rural Water Supply and Sanitation Description : To develop a full proposal of the rural water supply sanitation initiative (RWSSI) of Sierra Leone that will facilitate both the mobilization of financial support and detailed implementation requirements: • To prepare an economically and technically sound project for the water supplies of Makeni, Bo and Kenema towns. • To assess the rural water supply and sanitation of the country and prepare a rural water supply sanitation Program. • To Prepare an action plan to meet the needs of year 2015 that will be include the identification and designing of a priority scheme on a pilot basis.
  • 53. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 53 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Water Management Authority –Mauritius, MAURITIUS Year: 2003 – 2007 Contract Value: 976,378.32 USD Project : Rehabilitation of Infrastructures on CHA Estates – Extension of Phase III Description : Rehabilitation of sewerage infrastructure on Housing Estates in Mauritius. Involves the construction of reticulation Networks to cater for 2, 777 houses connections to the main sewer; two sewage pumping stations and construction of outfall Sewer 3,67 km long as well as rising main 1315 km long
  • 54. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 54 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Water Management Authority –Mauritius, MAURITIUS Year: 2002 – 2003 Contract Value: 153,178 USD Project : Rehabilitation and Improvement of Infrastructure on CHA Estates – Extension of Phase II Description : Over the period 1960 -1988 a total of 158 housing estates were built across the Country to provide shelter. For families made homeless as a result of cyclones. However the housing estates lacked adequate facilities such as roads, water supply, sewerage, surface water drainage and waste collection. During the years 1990 to 1998 the Phase I the Rehabilitation of Infrastructure Program was launched for the provision of sewerage facilities to some estates Phase II of this Programme has been extended through a Project for the rehabilitation of a satisfactory collection and disposal of sewage in seven housing estates serving a population of 24 000 in habitants.
  • 55. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 55 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Ministry of Water Dar es Salaam ,TANZANIA Year: 1998 – 2002 Contract Value: 1.282. 907 USD Project : Consultancy Services for the Institutional Strengthening for Urban Water and Sewerage Improvements in Tanzania Description : The project purpose is the strengthening of the capacity of the Urban Water and Sewerage Authorities (UWSAs) in Mwanza, Iringa, Mbeya, and Mtwara, in terms of management, personnel and equipment. The consulting services aim at enhancing the Ministry Officers’ expertise and know how in order to ensure the local government an autonomous management of the waste water system. The consultants services are also intended to: • Safeguard water resources; • Identity adequate financial resources; • Promote an industrial policy for the improvement of the existing control of water resources and utilities
  • 56. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 56 Sari Consulting Ltd. REFERENCE – WATER SECTOR Client: Ministry of Natural Resources and Energy Water Department, GUINEA BISSAU Year: January - November 2001 Contract Value: 301,073 USD Project : Technical Assistance for the Institutional strengthening of the Water Supply and Sewerage Description : The project overall objective in enhancing the national water management system by providing consulting services to the Ministry of Natural Resources and Energy in Guinea Bissau. The Coverage of the water treatment and distribution network is inadequate due to the inability to operate and maintain the public facilities effectively. Therefore the projects aims at strengthening the autonomous management of those facilities at regional and local levels.
  • 57. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 57 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: ANE , Mozambique Year: February 2015 - 2019 Contract Value: USD 3.757.000 + MZN 9.430.000 Project : The multinational Nacala Road Corridor Project – Phase I:Consulting Services for Design Review and Update and Supervision of Civil Works for Lot D: Cuamba-Muita (138 km) and Technical Assistance to ANE Description : The Government of Mozambique intends to upgrade the strategic Nacala Corridor to provide a more economical, reliable, and seamless flow of goods and services between the countries of the region and at the same time to stimulate the regional economy in the northern part of Mozambique, where the lack of all weather roads is a major constraint on development. Currently, the Nampulato Cuamba (348km ) stretchis under implementation on in three subsections.
  • 58. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 58 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Road Development Agency (RDA), ZAMBIA Year: June 2015 - Ongoing Contract Value: USD 1.000.000 Project : Consulting Services for the detailed engineering designs and supervision of the construction of urban roads using segmented/concrete paving block and cobblestone technology in Northern and Luapula Provinces (250 km) Description : The principal, overall objective of the services is to perform the necessary surveys, detailed engineering designs, preparation of Bill of Quantities to be used during implementation by Contractors with a view of improving road infrastructure and general aesthetics in urban areas through the use of segmented paving blocks and cobblestones.
  • 59. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 59 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Road Development Agency (RDA), ZAMBIA Year: April 2015 - Ongoing Contract Value: USD 1.000.000 Project : Consulting Services for the detailed engineering designs and supervision of the construction of urban roads using segmented/concrete paving block and cobblestone technology in Central and Muchinga Provinces -350 km Description : The urban roads in deplorable condition in Central and Muchinga Provinces are part of the Pave Zambia 2000 project which is an initiative of the Government of the Republic of Zambia aimed at constructing urban roads using segmented Paving Blocks through labor intensive methods. The services shall include feasibility study, skill-development, materials, equipment and labor force identification, SME and local construction sector development, contract management and sustainability and commercialization to support Pro-poor development through Job creation.
  • 60. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 60 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of infrastructure Development, TANZANIA Year: November 2011 – ongoing Contract Value: USD 1.670.000 Project : Consulting services for design review and pre-contract services and construction supervision of the upgrading of Namtumbo – Tunduru road (193 km) to bitumen standard lot A: Namtumbo – Kalimesera section (60.7 km) Description : The Namtumbo – Tunduru road is situated in Ruvuma Region, Southern part of Tanzania bordering Malawi to the West and Mozambique to the South. The 193 km road starts from Namtumbo and runs through woodland, bush land thicket and grasslands and crosses Selous-Niassa wildlife corridor over a 40 km stretch and ends in the center of the Tunduru District. The final objective of the assignment is to undertake consultancy services on behalf of TANROADS for the design review, pre-contract services and supervision of construction works.
  • 61. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 61 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Uganda National Roads Authority (UNRA), UGANDA Year: 2011 – 2015 Contract Value: USD 2.233.000 Project : Consulting services for design review and construction supervision of HOIMA-KAISOTONYA (92 KM) Description : The Hoima-Kaiso-Tonya Road (92 Km) is currently a gravel road located in Hoima District on Western Uganda and is about 225 Km west of Kampala. The scope of the Consultancy Services are two: • Carry out the review and update of the existing engineering design and make all amendments and additional studies for the soundness and sufficiency of the detailed engineering design and bid documents • Provide Construction Supervision during the pre-construction and the construction periods and during the Defects Liability Period
  • 62. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 62 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: TANROADS, TANZANIA Year: 2011 – 2006 Contract Value: USD 1.593.000 Project : Supervision of Works for the upgrading of the road Isaka – Nzega Description : The Nzega-Isaka road is part of the Dar Es Salaam-Mwanza road which transverses the towns of Morogoro, Dodoma, Manyoni, Singida, Nzega and Mwanza (towards the north). After starting off at Nzega, the road cuts across rich agricultural areas and terminates at Isaka connecting towns, district headquarters and economic growth center. The rehabilitation of his section is part of a wider project providing for the upgrading of the entire section Mwanza Border-Nzega from gravel roads to a Class I trunk road in bitumen pavement standard. The road influence area is about 20,000 km2.
  • 63. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 63 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of WorksMDI Road Kanifing , THE GAMBIA Year: 2007 - 2009 Contract Value: USD 1.366.000 Project : Supervision of rehabilitation and upgrading works of trunks roads in The Gambia and Senegal (Lot1)Road length: 19.9 Km. Description : Lot1 : Barra to Amdellai section (19.9 km) of the Trans West African Highway connecting Banjul the capital of Gambia with Senegal. Lot2: Soma to Basse and Velingara the major section of the South bank truck linking the capital Banjul and the provincial towns(215.5 km)
  • 64. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 64 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of Finance, BENIN Year: 2004 - 2008 Contract Value: USD 1.038.000 Project : Technical Assistance to the control and supervision works for the settlement of bituminous roads NATITINGOU- PORGA Description : The Natitingou – Porga road (102 km) represents one of the most important parts of the Inter-state National Road n 3 which connects Benin and Burkina Faso. The road is a two lane highway with 3 bridges (average length 25 meters). The project focuses on supervising the works concerning bituminous settlement in the NATITINGOUPORGA road
  • 65. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 65 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: NAO (National Authorizing Office), SIERRA LEONE Year: 2003 – 2006 Contract Value: USD 1.160.000 Project : Consultancy Services for the Management and Supervision of Works Contract for the Construction of the Freetown-Conakry Highway Phase I Description : Reconstruction of the Rogbere-Pamelap Road in the Republic of Sierra Leone of approximately 77 km length based on the approved design and contact documents; Reconstruction of the Pamelap-Farmoreah Road in the Republic of Guinea Conakry of approximately 9 km length, based on the approved design and contract documents.
  • 66. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 66 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of Transport and Public Works, MADAGASCAR Year: 2003 - 2006 Contract Value: USD 3.594.000 Project : Detailed Design, procurement and supervision of the rehabilitation work of the National Roads N. 44 and N 3. Study for the Periodic Maintenance of Road RN 2. Description : The project includes the rehabilitation and maintenance national primary and secondary road network corridors which connects the capital of Madagascar to the very important economic regions of the country such as Lac Alaotra through the national road RN 44 in bituminous concrete pavement and to the port of Toamasina through the national Road n.2 .
  • 67. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 67 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of Transport and Public Works, MADAGASCAR Year: 2003 - 2005 Contract Value: USD 1.690.000 Project : Planning , Control and Supervision of Construction works of the RN5A between Sambava and Antalaha and of Antalaha harbour’s resettlement works. Description : The main objective of the project is to rebuild the Nat ional Road RN5A, between the cities of Sambava and Antalaha, in the north-east of the island. This road is 180 km long, included 1.5 km of urban road inside the city of Antalaha, road in bituminous concrete pavement. The construction and rehabilitation works on this road aim at the economic development of the region the main tasks concern the construction and reconstruction of different bridges and the building of riprap foundation of the harbor infrastructures.
  • 68. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 68 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of Transport and Public Works, MADAGASCAR Year: 2002 – 2004 Contract Value: USD 1.339.000 Project : Supervision for the works of Reinforcement of Structural Network of Lot Projects from 4 to 7 Description : The project concerns the backing of several sections and the reconstruction of the access to the Toamasina harbor. The roads leads in concrete pavement from Brickaville to Toamasina (total Length 115 Km).
  • 69. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 69 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Ministry of Road and Transport, GHANA Year: 2001 – 2004 Contract Value: USD 1.280.000 Project : Technical Assistance Towards the Efficient, Effective and Sustainable Management of Maintenance in the Road Sub-Sector Project No.8 ACP GH 009 Description : The project entails the review of all existing systems and implements actions required to put the road maintenance management in the Ministry of Roads and Transport’s road agencies Ghana Highway Authority (GHA), Department of Feeder Roads ( DFR) and Department of Urban Roads (DUR) on an efficient, effective and sustainable basis.
  • 70. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 70 Sari Consulting Ltd. REFERENCE – ROAD SECTOR Client: Cabinet of Vice prime minister in charge of Economic and Social Reconstruction, GUINEA BISSAU Year: 2000 – 2003 Contract Value: USD 301.000 Project : Short term technical assistance to the general direction of transport infrastructures Description : The project aims at assisting the Ministry of Social Reconstruction (General Directorate of Transport Infrastructures – DGIT) in developing new policies for the setting-up of a privatized management of the road sector in cement concrete pavement. A permanent technical assistance is provided to the management of different types of development projects with a major focus on those financed under the EDF.
  • 71. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 71 Sari Consulting Ltd. REFERENCE – BUILDING SECTOR Client: Republic of Uganda through the Ministry of Public Service Year: July 2012 - Ongoing Contract Value: USD 500.000 Project : Consulting Services to Prepare Designs, Tender Documents and Supervise the Refurbishment of the Proposed Civil Service College Uganda (CSCU). Description : The consultancy services entails feasibility study, preparation of topographical survey, socio/environmental study and geotechnical study including preliminary and outline designs and cost estimates; preparation of detailed architectural & engineering designs including tender documents and tender action and construction supervision including the defects liability period.
  • 72. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 72 Sari Consulting Ltd (SARI) operating offices are at: via Giacomo Peroni 452, Rome, Italy SARI Consulting (Zambia) Limited, Company Registration N. 111853. Plot N. 53, Central Street, Jesmondine, Lusaka, Zambia SARI Consulting (Mozambique) Ltd, Av. Kwame Nkrumah, 1335, Maputo , Mozambique SARI Consulting (Uganda) Ltd , Plot 26 Flat B, Golf Course Road, Off Wampewo Avenue, Kololo, P.O.Box 6960, Kampala, Uganda SARI Consulting (Zimbabwe) Ltd, 40 Arcturus Road Highlands, Harare, Zimbabwe SARI Consulting (Kenia) Ltd, Upper Hill on Kiambere Road, Casia B2 next to former World Bank offices SARI Consulting (South Africa) Ltd, 20 Weenen Road, Milnerton, Cape Town 7441 Sari Consulting Ltd
  • 73. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 73 SIMECO operating offices are at: Via Arcivescovo Romilli 22, 20139 Milano, Italy Petrodar Tower, Office Suite 32, Al Seef District, Kingdom of Bahrain Simeco Systems d.o.o., Gradacacka 29B, 71000 Sarajevo, Bosnia and Herzegovina Simeco S.p.A.
  • 74. SARI CONSULTING LTD and SIMECO SPA JOINT VENTURE PRESENTATION 74 SARI Consulting Ltd. Mr. Goffredo DE PASCALE CEO via Giacomo Peroni 452 Rome ITALY Phone : + 39 06 45563173 Fax : + 39 06 45563109 e-mail: sari@sariltd. com g.depascale@sariltd.com Website: www.simeco-sari.com CONTACT
  • 75. THANK YOU FOR YOUR KIND ATTENTION We look forward to seeing you again. Sari Consulting Ltd and Simeco Spa