SlideShare a Scribd company logo
1 of 2
Download to read offline
199
W a t e r T r e a t m e n t & S u p p l y
C
hertsey Water Treatment Works (WTW) is located on the bend of the River Thames opposite Laleham Park in
Surrey. The existing works was originally constructed in 1900 and has since been extended and upgraded during the
1970s and 1990s and more recently with the installation of a new submerged membrane plant completed in 2003.
The WTW has a current total treatment capacity of 65Ml/d and treats water pumped from two sources of very differing
water quality characteristics; Abbeymeads, a gravel well water source and River Thames water fed from the Northern
Burway reservoir. To ensure that water produced from this works remains consistently of a high quality and free from
contamination such as cryptosporidium Three Valleys Water has invested in a 41Ml/d submerged membrane plant.
Chertsey Microfiltration Plant
first submerged membrane plant for Three Valleys Water
by Andrew Bailey MSc (Hons)
Chertsey WTW: Main membrane filtrate pumps & pipework courtesy: Black & Veatch Limited
The Chertsey project was awarded to Black & Veatch
after extensive on-site Pilot Trials carried out on both water sources
from which Memcor Ltd Continuous Microfiltration Submerged
(CMF-S) system proved to be the preferred membrane option. The
application of low pressure submerged membrane systems for
potable water supplies has seen significant growth over the last ten
years. The increased popularity in membrane systems has been due
to the technology having the ability to deliver potable water to a
high standard whilst maintaining a modular design, sophisticated
automation at a competitive cost.
The Chertsey project saw the successful development of a
partnership between Black & Veatch Ltd, Veolia Water Partnership
and Three Valleys Water with the sole aim of the successful
completion of their first potable submerged membrane plant. The
principal goal was to provide a barrier against Cryptosporidium to
a greater than 5 log removal rate. Black & Veatch was responsible
for the design and supply of all mechanical, electrical and
instrumentation for the treatment plant.
Membrane operation
The membrane plant is designed to achieve a maximum output of
41.2 MLD. through the operation of five duty CMF-S cells, operating
at a design flux of 140lh-1m-2 and one standby cell. Each CM F S cell
consists of 192 submerged membrane modules, the modules hold
approximately 14,000 hollow fibres constructed from PVDF material
with a nominal fibre size of 0.2 m. When in filtration the Filtrate
Pump creates suction on the inside of the hollow fibres, drawing
water through the membrane walls leaving solids on the surface of
the membrane. The membranes are submerged in feed water within
the cell and the water level is automatically maintained at a level
above the membranes by a modulating inlet valve.
The membrane modules are cleaned with a low pressure air assisted
backwash to maintain the filtrate flow rates. Filtered water is used as
the backwash water medium, flowing from the inside of the fibres,
through the membrane wall removing any accumulated suspended
solids from the membranes outer surface. The CMF-S units are
chemically cleaned in place (CIP), using either sulphuric acid or
sodium hypochlorite, to remove scaling and biological growth and
other forms of fouling which can not be removed by backwashing
alone.
The integrity of the membrane barrier is maintained on a daily basis
200
W a t e r T r e a t m e n t & S u p p l y
through the use of a Pressure Decay Test (PDT) to ensure a greater
than 5 log removal rate. A manual test may be initiated from the
SCADA. This test applies air pressure to the filtrate side of the
membranes and monitors the pressure drop over a time interval.
The results are logged and alarms may be raised if the results are
outside of pre-determined limits. If the pressure drop is excessive,
the unit will shutdown and may only be returned to service after
the integrity failure has been repaired.
Throughout the construction phase of the project Black & Veatch
maintained a strong site management presence with technical
support being provided by the design team at B & V Head Office.
The Civil construction and plant M & E was started in January
2002 and completed in September 2002. The civil subcontractor
used at Chertsey was JBS Construction with the piping contractor
being B-Meck. All purchased equipment and materials for
construction of the plant was done so using B & V’s approved
suppliers listing. Each supplier was selected and managed by B &
V to ensure that the end product fulfilled the client’s expectations
within budget and on time whilst still maintaining a high standard
of engineering.
Commissioning phase
The commissioning phase of Chertsey MF plant was completed
over a 12 week period from November 2002 to January 2003. B & V
provided project management along with on-site technical support
throughout this period with each contractor taking responsibility
for commissioning of equipment in their scope of supply. Memcor,
suppliers of the membranes modules, the process control and
SCADA system led the onsite process commissioning with B & V
on-site support.
Overall automation of the microfiltration plant is achieved with the
use of a centralised control and distributed flex input/output
architecture supported by a distributed high speed control network.
The membrane plant status and water quality parameters and
alarms are transmitted via telemetry to Three Valleys Water
Operations Centre at Clay Lane WTW close to Watford.
During this period B & V worked closely with the Three Valleys
Water managerial and operational staff to maximise the integration
of the new Crytosporidium barrier into the existing conventional
works. Together with Memcor, B & V provided continuous 24 hour
technical support and troubleshooting throughout the
commissioning period up to the point of plant Take-Over which
was achieved in early May 2003.
Design development, operational experience and lessons learned
from the Chertsey Project have allowed Black & Veatch Ltd to
complete design and build submerged membrane projects for other
valued clients such as Portsmouth Water at Farlington WTW
(84Ml/d) and Southern Water at Otterbourne (58Ml/d) and Arundel
WTW (4.5Ml/d) over the last three years. ■
Note: The author of this article, Andrew Bailey, is Senior Project
Engineer with Black & Veatch Limited.
courtesy: Black & Veatch Limited
courtesy: Black & Veatch Limited
External view of Chertsey Microfiltration Plant
View of top of CMF5 units showing the filtrate and air headers

More Related Content

Similar to Three Valleys Chertsey WTW 2005

NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Roxtec UK & Ireland
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-finalJohn Grover
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Iain McGregor
 
Thames Perry Oaks-Iver South 2005
Thames Perry Oaks-Iver South 2005Thames Perry Oaks-Iver South 2005
Thames Perry Oaks-Iver South 2005Robert Sharpe
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyAndrew White
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
Desalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeDesalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeRick Nabett
 
Desalination the sustainable alternative
Desalination the sustainable alternativeDesalination the sustainable alternative
Desalination the sustainable alternativeRick Nabett
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
doc - Interdisciplinary Capstone Design
doc - Interdisciplinary Capstone Designdoc - Interdisciplinary Capstone Design
doc - Interdisciplinary Capstone Designbutest
 
Melbourne Pipeline Protection
Melbourne Pipeline ProtectionMelbourne Pipeline Protection
Melbourne Pipeline ProtectionSikko Krol
 
Southern_Peacehaven_2014
Southern_Peacehaven_2014Southern_Peacehaven_2014
Southern_Peacehaven_2014Iain McGregor
 
Pipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & CatchpitsPipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & Catchpitseddiebradbrook
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control systemAmit Nitharwal
 
WorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownWorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownMorgan Swanlund
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01juwes
 

Similar to Three Valleys Chertsey WTW 2005 (20)

NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
Thames Perry Oaks-Iver South 2005
Thames Perry Oaks-Iver South 2005Thames Perry Oaks-Iver South 2005
Thames Perry Oaks-Iver South 2005
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case Study
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
Desalination, The Sustainable Alternative
Desalination, The Sustainable AlternativeDesalination, The Sustainable Alternative
Desalination, The Sustainable Alternative
 
Desalination the sustainable alternative
Desalination the sustainable alternativeDesalination the sustainable alternative
Desalination the sustainable alternative
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Siw Issue 3
Siw Issue 3Siw Issue 3
Siw Issue 3
 
doc - Interdisciplinary Capstone Design
doc - Interdisciplinary Capstone Designdoc - Interdisciplinary Capstone Design
doc - Interdisciplinary Capstone Design
 
Melbourne Pipeline Protection
Melbourne Pipeline ProtectionMelbourne Pipeline Protection
Melbourne Pipeline Protection
 
Southern_Peacehaven_2014
Southern_Peacehaven_2014Southern_Peacehaven_2014
Southern_Peacehaven_2014
 
Pipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & CatchpitsPipex Pumping Stations, Chambers & Catchpits
Pipex Pumping Stations, Chambers & Catchpits
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
WorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownWorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdown
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01
 

Three Valleys Chertsey WTW 2005

  • 1. 199 W a t e r T r e a t m e n t & S u p p l y C hertsey Water Treatment Works (WTW) is located on the bend of the River Thames opposite Laleham Park in Surrey. The existing works was originally constructed in 1900 and has since been extended and upgraded during the 1970s and 1990s and more recently with the installation of a new submerged membrane plant completed in 2003. The WTW has a current total treatment capacity of 65Ml/d and treats water pumped from two sources of very differing water quality characteristics; Abbeymeads, a gravel well water source and River Thames water fed from the Northern Burway reservoir. To ensure that water produced from this works remains consistently of a high quality and free from contamination such as cryptosporidium Three Valleys Water has invested in a 41Ml/d submerged membrane plant. Chertsey Microfiltration Plant first submerged membrane plant for Three Valleys Water by Andrew Bailey MSc (Hons) Chertsey WTW: Main membrane filtrate pumps & pipework courtesy: Black & Veatch Limited The Chertsey project was awarded to Black & Veatch after extensive on-site Pilot Trials carried out on both water sources from which Memcor Ltd Continuous Microfiltration Submerged (CMF-S) system proved to be the preferred membrane option. The application of low pressure submerged membrane systems for potable water supplies has seen significant growth over the last ten years. The increased popularity in membrane systems has been due to the technology having the ability to deliver potable water to a high standard whilst maintaining a modular design, sophisticated automation at a competitive cost. The Chertsey project saw the successful development of a partnership between Black & Veatch Ltd, Veolia Water Partnership and Three Valleys Water with the sole aim of the successful completion of their first potable submerged membrane plant. The principal goal was to provide a barrier against Cryptosporidium to a greater than 5 log removal rate. Black & Veatch was responsible for the design and supply of all mechanical, electrical and instrumentation for the treatment plant. Membrane operation The membrane plant is designed to achieve a maximum output of 41.2 MLD. through the operation of five duty CMF-S cells, operating at a design flux of 140lh-1m-2 and one standby cell. Each CM F S cell consists of 192 submerged membrane modules, the modules hold approximately 14,000 hollow fibres constructed from PVDF material with a nominal fibre size of 0.2 m. When in filtration the Filtrate Pump creates suction on the inside of the hollow fibres, drawing water through the membrane walls leaving solids on the surface of the membrane. The membranes are submerged in feed water within the cell and the water level is automatically maintained at a level above the membranes by a modulating inlet valve. The membrane modules are cleaned with a low pressure air assisted backwash to maintain the filtrate flow rates. Filtered water is used as the backwash water medium, flowing from the inside of the fibres, through the membrane wall removing any accumulated suspended solids from the membranes outer surface. The CMF-S units are chemically cleaned in place (CIP), using either sulphuric acid or sodium hypochlorite, to remove scaling and biological growth and other forms of fouling which can not be removed by backwashing alone. The integrity of the membrane barrier is maintained on a daily basis
  • 2. 200 W a t e r T r e a t m e n t & S u p p l y through the use of a Pressure Decay Test (PDT) to ensure a greater than 5 log removal rate. A manual test may be initiated from the SCADA. This test applies air pressure to the filtrate side of the membranes and monitors the pressure drop over a time interval. The results are logged and alarms may be raised if the results are outside of pre-determined limits. If the pressure drop is excessive, the unit will shutdown and may only be returned to service after the integrity failure has been repaired. Throughout the construction phase of the project Black & Veatch maintained a strong site management presence with technical support being provided by the design team at B & V Head Office. The Civil construction and plant M & E was started in January 2002 and completed in September 2002. The civil subcontractor used at Chertsey was JBS Construction with the piping contractor being B-Meck. All purchased equipment and materials for construction of the plant was done so using B & V’s approved suppliers listing. Each supplier was selected and managed by B & V to ensure that the end product fulfilled the client’s expectations within budget and on time whilst still maintaining a high standard of engineering. Commissioning phase The commissioning phase of Chertsey MF plant was completed over a 12 week period from November 2002 to January 2003. B & V provided project management along with on-site technical support throughout this period with each contractor taking responsibility for commissioning of equipment in their scope of supply. Memcor, suppliers of the membranes modules, the process control and SCADA system led the onsite process commissioning with B & V on-site support. Overall automation of the microfiltration plant is achieved with the use of a centralised control and distributed flex input/output architecture supported by a distributed high speed control network. The membrane plant status and water quality parameters and alarms are transmitted via telemetry to Three Valleys Water Operations Centre at Clay Lane WTW close to Watford. During this period B & V worked closely with the Three Valleys Water managerial and operational staff to maximise the integration of the new Crytosporidium barrier into the existing conventional works. Together with Memcor, B & V provided continuous 24 hour technical support and troubleshooting throughout the commissioning period up to the point of plant Take-Over which was achieved in early May 2003. Design development, operational experience and lessons learned from the Chertsey Project have allowed Black & Veatch Ltd to complete design and build submerged membrane projects for other valued clients such as Portsmouth Water at Farlington WTW (84Ml/d) and Southern Water at Otterbourne (58Ml/d) and Arundel WTW (4.5Ml/d) over the last three years. ■ Note: The author of this article, Andrew Bailey, is Senior Project Engineer with Black & Veatch Limited. courtesy: Black & Veatch Limited courtesy: Black & Veatch Limited External view of Chertsey Microfiltration Plant View of top of CMF5 units showing the filtrate and air headers