Gantt chart and aon of Mykitten Company made by Nguyen Trong Tan
1.
2. Number Activities Start End Notes
1 Gathering time data from classmate 1-Apr 4-Apr Whole class
2 Planning & setting schedule 5-Apr 6-Apr Team task
3 Popularizing job duty 7-Apr 7-Apr Whole class
4 Selling in campus 8-Apr 13-Apr Whole class
5 Record 8-Apr 13-Apr Team task
6 Evaluating people efficiency 8-Apr 13-Apr Team task
7 Evaluating project efficiency 8-Apr 13-Apr Team task
8 Planning for project 2 14-Apr 18-Apr Work with CEO and other VPs
9 Set up for concert 19-Apr 3-May Whole class
10 Setting & popularizing schedule 3-May 5-May Team task
11 Evaluating 6-May 15-May Team task
12 Meeting 6-Apr 21-may Team task
3.
4. Activity Activity Description
Immediate
Predecessors
A Gathering information None
B
Define and manage
information
A
C Analyze information B
D Set up schedule of working C
E
Adjust suitable schedule for
members
C
F Plan backup plans D
G Predict problems E
H Run the project F,G
I Evaluate people’ s efficiency H