SlideShare a Scribd company logo
1 of 2
Download to read offline
www.armgroupltd.co.uk 	t. +44 (0) 1889 583811
naturalwastewatertreatment
Need
The Wildlife Trust Visitor Centre at Wolseley Bridge is the headquarters of the
Staffordshire Wildlife Trust. It is set in 26 acres of landscaped gardens which are
managed for wildlife and provide a visitor attraction for thousands of visitors each
year. As well as toilet facilities there is a small sandwich cafe which generates
wastewater for treatment. The centre has seen increasing numbers of visitors over
the years and has added conference facilities. This has resulted in the need for the
wastewater treatment system to evolve with demand to achieve adequate treatment
for discharge into Stafford Brook which lies alongside the Visitor Centre.
Staffordshire Wildlife trust established the centre in 2002 and initially a horizontal
flow reed bed was used to treat discharge from a septic tank installed on site.
In 2005 the bed was converted to vertical downflow to treat the higher loads
associated with increased visitor numbers and the introduction of an ammonia
consent. For the same reason the reed bed was converted to an aerated vertical
downflow system using Forced Bed Aeration™ (FBA™) technology in 2012. Details
of the loads passing forward to the beds are given below.
The varying flow rates, and consequently loads passing forwards, are characteristic
of an event driven system common with visitor attractions which requires a solution
which can offer adaption to changing treatment requirements.
www.armgroupltd.co.uk 	t. +44 (0) 1889 583811
Wolseley Bridge
Aerated saturated vertical flow reed bed
Project
Wolseley Bridge,
Wildlife Trust, Visitor Centre
Location
Wolseley Bridge, Staffordshire
Project type
Refurbishment
Wastewater type
Primary treated,
municipal waste water
Completion date
June 2012
Treatment
Aerated saturated vertical
downflow
CASE
STUDY
Average Flow
rate (m3
/d)
BOD (mg/l) BOD (Kg/d)
Ammonia
(mg/l)
Ammonia
(kg/d)
Suspended
Solids (mg/l)
Load 0.54 – 7 426 3 63 3.7 511
Consent – 20 – 12 – 30
www.armgroupltd.co.uk 	t. +44 (0) 1889 583811
naturalwastewatertreatment
Solution
In 2011 as a result of fluctuating and increasing loads from the Visitor centre the
bed was converted to a FBA™ system. Yellow flag irises were planted to make the
bed more of a feature as it is positioned directly adjacent to the
Visitor Centre. Through its development the bed has not required
enlargement maintaining an area of 77m2
. The system provides
3-37 days retention depending on loads and uses a 1.6 kW blower.
The blower was initially set to run for 10 hrs per day.
Benefits
The graph below indicates the benefit of the last conversion
to FBA™ technology indicating an immediate improvement in
ammonia reduction from 40% to 95%. The application of air can
be controlled which suits the seasonal variation in load associated
with visitor numbers. The increase in variability seen in the graph
caused by upstream loading changes was quickly corrected, and the potential for
recurrence eliminated, through increasing the aeration to 14 hours per day.
The aerated reed bed system at Wolseley Bridge provides the increased level of
treatment required by the site to discharge into the Staffordshire Brook within
consent. It also has the flexibility to adapt to varying loads seen throughout the year.
The use of Flag Irises as the primary plant stock provides an aesthetically attractive
water treatment solution position directly adjacent to the visitor centre.
CASE
STUDY
continued
Wolseley Bridge
Wolseley Bridge: Ammonia inlet and outlet
160
140
120
100
80
60
40
20
0
2 3 4 6 12 16 21 29 30 31 32 33 34 35 36 37 41 43 44 45 46 47 48 49 50 51 52 53 55
mgNH4-N/L
Week No.
Inlet Outlet
aerationswitchedon
optimisedaeration

More Related Content

Similar to Visitor Centre Wastewater Treatment Upgrade

UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016Charlie Bell
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Iain McGregor
 
Thames_Beckton_Crossness_THPs_2014
Thames_Beckton_Crossness_THPs_2014Thames_Beckton_Crossness_THPs_2014
Thames_Beckton_Crossness_THPs_2014Jason Adams
 
Suez Victorian Desalination Project
Suez Victorian Desalination ProjectSuez Victorian Desalination Project
Suez Victorian Desalination ProjectRick Nabett
 
Middle East Construction Trends - GineersNow Engineering Magazine
Middle East Construction Trends - GineersNow Engineering MagazineMiddle East Construction Trends - GineersNow Engineering Magazine
Middle East Construction Trends - GineersNow Engineering MagazineGineersNow
 
Compressed Air Energy Storage
Compressed Air Energy StorageCompressed Air Energy Storage
Compressed Air Energy StorageSharathKumar528
 
Evac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureEvac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureJustin Shuler
 
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTCOMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTWALEBUBLÉ
 
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...Neil McCarthy
 
2751,Brochure_Actina_VWS_ENG_LR_Draft_v0
2751,Brochure_Actina_VWS_ENG_LR_Draft_v02751,Brochure_Actina_VWS_ENG_LR_Draft_v0
2751,Brochure_Actina_VWS_ENG_LR_Draft_v0Ludovic Renoux
 
Environmental presentation from malthouse engineering
Environmental presentation from malthouse engineeringEnvironmental presentation from malthouse engineering
Environmental presentation from malthouse engineeringMalthouse Engineering Ltd.
 
Ocean thermal energy conversion
Ocean thermal energy conversionOcean thermal energy conversion
Ocean thermal energy conversionPankaj Kumar
 
ARM Heathrow case study-LR
ARM Heathrow case study-LRARM Heathrow case study-LR
ARM Heathrow case study-LRNeil McCarthy
 
Blackburn Bowls Club Lessons for water storage
Blackburn Bowls Club Lessons for water storageBlackburn Bowls Club Lessons for water storage
Blackburn Bowls Club Lessons for water storageNEXTDC
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Roy Robinson
 
Aspirating Aerator's
Aspirating Aerator'sAspirating Aerator's
Aspirating Aerator'sAquasol
 
DKDDPC932A102_Fayard_Shipyard_LR (2)
DKDDPC932A102_Fayard_Shipyard_LR (2)DKDDPC932A102_Fayard_Shipyard_LR (2)
DKDDPC932A102_Fayard_Shipyard_LR (2)Jesper Gravesen
 

Similar to Visitor Centre Wastewater Treatment Upgrade (20)

UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
Thames_Beckton_Crossness_THPs_2014
Thames_Beckton_Crossness_THPs_2014Thames_Beckton_Crossness_THPs_2014
Thames_Beckton_Crossness_THPs_2014
 
Suez Victorian Desalination Project
Suez Victorian Desalination ProjectSuez Victorian Desalination Project
Suez Victorian Desalination Project
 
Middle East Construction Trends - GineersNow Engineering Magazine
Middle East Construction Trends - GineersNow Engineering MagazineMiddle East Construction Trends - GineersNow Engineering Magazine
Middle East Construction Trends - GineersNow Engineering Magazine
 
Compressed Air Energy Storage
Compressed Air Energy StorageCompressed Air Energy Storage
Compressed Air Energy Storage
 
Small fully biologial wastewater treatment plants
Small fully biologial wastewater treatment plantsSmall fully biologial wastewater treatment plants
Small fully biologial wastewater treatment plants
 
Evac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureEvac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage Brochure
 
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANTCOMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
COMMISSIONING OF A MEMBRANE BIOREACTOR WASTEWATER PLANT
 
16_IntegrationHPPwithinExistingWeir
16_IntegrationHPPwithinExistingWeir16_IntegrationHPPwithinExistingWeir
16_IntegrationHPPwithinExistingWeir
 
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...
British Airportss Authority BAA Mayfield Aerated Subsurface Horizontal Airpor...
 
2751,Brochure_Actina_VWS_ENG_LR_Draft_v0
2751,Brochure_Actina_VWS_ENG_LR_Draft_v02751,Brochure_Actina_VWS_ENG_LR_Draft_v0
2751,Brochure_Actina_VWS_ENG_LR_Draft_v0
 
Local Manufacture and Installation of Hydraulic Ram Pumps for Village Water S...
Local Manufacture and Installation of Hydraulic Ram Pumps for Village Water S...Local Manufacture and Installation of Hydraulic Ram Pumps for Village Water S...
Local Manufacture and Installation of Hydraulic Ram Pumps for Village Water S...
 
Environmental presentation from malthouse engineering
Environmental presentation from malthouse engineeringEnvironmental presentation from malthouse engineering
Environmental presentation from malthouse engineering
 
Ocean thermal energy conversion
Ocean thermal energy conversionOcean thermal energy conversion
Ocean thermal energy conversion
 
ARM Heathrow case study-LR
ARM Heathrow case study-LRARM Heathrow case study-LR
ARM Heathrow case study-LR
 
Blackburn Bowls Club Lessons for water storage
Blackburn Bowls Club Lessons for water storageBlackburn Bowls Club Lessons for water storage
Blackburn Bowls Club Lessons for water storage
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016
 
Aspirating Aerator's
Aspirating Aerator'sAspirating Aerator's
Aspirating Aerator's
 
DKDDPC932A102_Fayard_Shipyard_LR (2)
DKDDPC932A102_Fayard_Shipyard_LR (2)DKDDPC932A102_Fayard_Shipyard_LR (2)
DKDDPC932A102_Fayard_Shipyard_LR (2)
 

More from Neil McCarthy

Wetland Treatment Systems and Cold Weather
Wetland Treatment Systems and Cold WeatherWetland Treatment Systems and Cold Weather
Wetland Treatment Systems and Cold WeatherNeil McCarthy
 
Buffalo Airport De-Icing
Buffalo Airport De-IcingBuffalo Airport De-Icing
Buffalo Airport De-IcingNeil McCarthy
 
ARM Casper case study-LR
ARM Casper case study-LRARM Casper case study-LR
ARM Casper case study-LRNeil McCarthy
 
FBA Technology specific-LR
FBA Technology specific-LRFBA Technology specific-LR
FBA Technology specific-LRNeil McCarthy
 
ARM AASP brochure-LR
ARM AASP brochure-LRARM AASP brochure-LR
ARM AASP brochure-LRNeil McCarthy
 

More from Neil McCarthy (6)

Wetland Treatment Systems and Cold Weather
Wetland Treatment Systems and Cold WeatherWetland Treatment Systems and Cold Weather
Wetland Treatment Systems and Cold Weather
 
Buffalo Airport De-Icing
Buffalo Airport De-IcingBuffalo Airport De-Icing
Buffalo Airport De-Icing
 
ARM Casper case study-LR
ARM Casper case study-LRARM Casper case study-LR
ARM Casper case study-LR
 
FBA Technology specific-LR
FBA Technology specific-LRFBA Technology specific-LR
FBA Technology specific-LR
 
ARM AASP brochure-LR
ARM AASP brochure-LRARM AASP brochure-LR
ARM AASP brochure-LR
 
ARM about NEW LR
ARM about NEW LRARM about NEW LR
ARM about NEW LR
 

Visitor Centre Wastewater Treatment Upgrade

  • 1. www.armgroupltd.co.uk t. +44 (0) 1889 583811 naturalwastewatertreatment Need The Wildlife Trust Visitor Centre at Wolseley Bridge is the headquarters of the Staffordshire Wildlife Trust. It is set in 26 acres of landscaped gardens which are managed for wildlife and provide a visitor attraction for thousands of visitors each year. As well as toilet facilities there is a small sandwich cafe which generates wastewater for treatment. The centre has seen increasing numbers of visitors over the years and has added conference facilities. This has resulted in the need for the wastewater treatment system to evolve with demand to achieve adequate treatment for discharge into Stafford Brook which lies alongside the Visitor Centre. Staffordshire Wildlife trust established the centre in 2002 and initially a horizontal flow reed bed was used to treat discharge from a septic tank installed on site. In 2005 the bed was converted to vertical downflow to treat the higher loads associated with increased visitor numbers and the introduction of an ammonia consent. For the same reason the reed bed was converted to an aerated vertical downflow system using Forced Bed Aeration™ (FBA™) technology in 2012. Details of the loads passing forward to the beds are given below. The varying flow rates, and consequently loads passing forwards, are characteristic of an event driven system common with visitor attractions which requires a solution which can offer adaption to changing treatment requirements. www.armgroupltd.co.uk t. +44 (0) 1889 583811 Wolseley Bridge Aerated saturated vertical flow reed bed Project Wolseley Bridge, Wildlife Trust, Visitor Centre Location Wolseley Bridge, Staffordshire Project type Refurbishment Wastewater type Primary treated, municipal waste water Completion date June 2012 Treatment Aerated saturated vertical downflow CASE STUDY Average Flow rate (m3 /d) BOD (mg/l) BOD (Kg/d) Ammonia (mg/l) Ammonia (kg/d) Suspended Solids (mg/l) Load 0.54 – 7 426 3 63 3.7 511 Consent – 20 – 12 – 30
  • 2. www.armgroupltd.co.uk t. +44 (0) 1889 583811 naturalwastewatertreatment Solution In 2011 as a result of fluctuating and increasing loads from the Visitor centre the bed was converted to a FBA™ system. Yellow flag irises were planted to make the bed more of a feature as it is positioned directly adjacent to the Visitor Centre. Through its development the bed has not required enlargement maintaining an area of 77m2 . The system provides 3-37 days retention depending on loads and uses a 1.6 kW blower. The blower was initially set to run for 10 hrs per day. Benefits The graph below indicates the benefit of the last conversion to FBA™ technology indicating an immediate improvement in ammonia reduction from 40% to 95%. The application of air can be controlled which suits the seasonal variation in load associated with visitor numbers. The increase in variability seen in the graph caused by upstream loading changes was quickly corrected, and the potential for recurrence eliminated, through increasing the aeration to 14 hours per day. The aerated reed bed system at Wolseley Bridge provides the increased level of treatment required by the site to discharge into the Staffordshire Brook within consent. It also has the flexibility to adapt to varying loads seen throughout the year. The use of Flag Irises as the primary plant stock provides an aesthetically attractive water treatment solution position directly adjacent to the visitor centre. CASE STUDY continued Wolseley Bridge Wolseley Bridge: Ammonia inlet and outlet 160 140 120 100 80 60 40 20 0 2 3 4 6 12 16 21 29 30 31 32 33 34 35 36 37 41 43 44 45 46 47 48 49 50 51 52 53 55 mgNH4-N/L Week No. Inlet Outlet aerationswitchedon optimisedaeration