Steady progress on our Parsippany II data center expansion. Once completed it will give us 70,000 gross sq. ft. of additional building space, with the capacity for 1,500 new cabinets. Look for our Grand Opening in Q1 2015!
Net Access Data Center Expansion Update - Parsippany NJ
1. PARSIPANY II EXPANSION PROJECT UPDATES
Steady progress on the Net Access Parsippany II data center expansion.
Once completed it will give us 70,000 gross sq. ft. of additional building
space, with the capacity for 1,500 new cabinets. Look for our Grand
Opening in Q1 2015!
11. Parsippany II, Phase II (WBR2)
• 70,000 gross sq. ft. of additional building space (120,000 total sq. ft.)
• Capacity for 1,500 new Cabinets
• Powered by two additional Power Systems with over 5MG of usable UPS power
• Onsite JCP&L Power Substation
• Available for occupancy in Q1 2015
11
12. Parsippany II Data Center – Overview (WBR)
• Owned, purpose-built, state-of-the-art
facility
– 2 mirrored UPS rooms supported by 2
mirrored generator rooms
– 4 independent N+1 electrical systems
– N+1 cooling redundancy
– 4.9 megawatts of useable UPS at capacity
• Advanced, ultra efficient N+1 cooling
• Hot air discharged via cabinet chimneys
– hot/cold air don’t mix
• Hot air exchanged with cooler outside air
• Full portfolio of Onsite FLEXServices for
hybrid IT solution implementations
12