SlideShare a Scribd company logo
1 of 25
Dredging and Disposal Site Reclamation at
John Redmond Reservoir, Kansas
26th Annual Kansas Hydrology Seminar
November 17, 2017
2
WHY REDMOND?
SUPPLY vs DEMAND
6
• 33 U.S.C. Section 408
– RoD Authorized KWO to conduct project on federal property
– Programmatic Environmental Impact Statement (PEIS)
• Section 106 Programmatic Agreement
– USACE Tulsa District, KSHS & Osage Nation of Oklahoma
– Ensure any historic sites were identified/protected
• Section 404 Permit (USACE) & Stream Obstruction Permit (DWR)
– Slurry pipeline crossing of Neosho River
• Dam Safety Permits KDA-DWR
– Required for all CDFs (based on DWR dam criteria)
• Floodplain Fill Permits (DWR)
– CDFs B and F (SFHA Zone A)
• Water Term Permit (DWR)
– Authorized use of water from Redmond for dredging purposes (> 6 months)
• NOI for Stormwater Runoff from Construction Activities (KDHE)
• NPDES Permit (KDHE)
– Effluent Limits at point of discharge
PROJECT PERMITTING
PHASE I IMPLEMENTATION TIMELINE
• 2012 - Planning process begins with USACE
• May 2015 – Section 408 Request Final RoD and
FONSI on Programmatic EIS Issued.
• November 2015 – June 2016: Confined Disposal
Facility (CDF) construction takes place
• May 2016: Dredging operations begin
• October 2016: Dredging operations complete
• October 2016: CDF dewatering efforts begin
• 2017 to current: CDF reclamation
CDF CONSTRUCTION
PIPELINE WORK
NEOSHO RIVER
SLURRY PIPELINE CROSSING
DREDGING MOBILIZATION
DREDGE “LP”
22” ELECTRIC DREDGE “LP”
 CSD “LP”
 22” Discharge
 3,500 Total HP
 Booster Pump
 1,000 HP
 Crane Barge
 Tug Boats
 Survey Vessels
 Crew Vessels
 Skidder Barge
ONSHORE BOOSTER STATION
O/A Length: 40’
Width: 12’
Height: 16’
HP: 1,000HP Cat. 399
Discharge Diameter: 18”
21,000 Gallon Frack Tank with
4” Electric Pump (175 GPM)
10,000 Gallon Fuel Tank with
Secondary Containment
DREDGING KICKOFF CEREMONY
DREDGED MATERIAL ENTERING CDF E
GRAVITY TREATED WATER ENTERING
FINAL CLARIFICATION CELL (CDF B)
EFFLUENT DISCHARGE TO NEOSHO RIVER
CONFINED DISPOSAL FACILITIES
CDF DEWATERING AND RECLAMATION
Continue Work with Great Lakes Dredge & Dock on CDF
Reclamation
• CDF dewatering has progressed since October 2016
• June 2017, treated water no longer being released to Neosho
River
• CDF F first in line to be put back into cropland production
– All dredged material stays on site, CDF walls will be removed and dirt
work will be completed to establish surface drainage network as well as
re-slope perimeter to stabilize.
JUNE 2017
CDF E (Top) & F (Bottom)
CDF F: FEBRUARY & OCTOBER 2017
PROJECT SUMMARY
• 3,000,000 CY of sediment removed (~1,900 AF)
– Average: ~19,000 CY/day
– Max: ~32,000 CY/day
• $20 million ~ $6.67/CY
– Total cost includes permitting, engineering & design, construction,
dredging, lease payments and land reclamation
– Includes some funds for watershed practices above reservoir
• Project financed by 15-year Bond
– State Water Plan Funds
– Water Sales Revenue through Water Marketing Program
QUESTIONS & DISCUSSION
Matt Unruh
Chief of Planning
Kansas Water Office
785-296-3185
matt.unruh@kwo.ks.gov

More Related Content

What's hot

Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015law138
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Fairfax County
 
An algorithm for design of brick lining for irrigation channels
An algorithm for design of brick lining for irrigation channelsAn algorithm for design of brick lining for irrigation channels
An algorithm for design of brick lining for irrigation channelseSAT Journals
 
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van Megchelen
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van MegchelenDSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van Megchelen
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van MegchelenDeltares
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design designavirup naskar
 
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...Texas Alliance of Groundwater Districts
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Carl Greenstreet
 
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Niraj Lamichhane
 
2011ppt dev hydrologydecisionsupporttool_final
2011ppt dev hydrologydecisionsupporttool_final2011ppt dev hydrologydecisionsupporttool_final
2011ppt dev hydrologydecisionsupporttool_finalbcogcommission
 
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...inventionjournals
 
Professional Geologist Work Experience
Professional Geologist Work ExperienceProfessional Geologist Work Experience
Professional Geologist Work ExperienceWilliamOlsenPG
 
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Stephen Flood
 
Exploring the Outer Limits of the Grand Banks- 2001 AAPG Denver
Exploring the Outer Limits of the Grand Banks- 2001 AAPG DenverExploring the Outer Limits of the Grand Banks- 2001 AAPG Denver
Exploring the Outer Limits of the Grand Banks- 2001 AAPG DenverJock McCracken
 
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - Becker
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - BeckerDSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - Becker
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - BeckerDeltares
 

What's hot (20)

Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015
 
Southmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy AdamsSouthmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy Adams
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
 
February 2022 Texas Railroad Commission Updates
February 2022 Texas Railroad Commission UpdatesFebruary 2022 Texas Railroad Commission Updates
February 2022 Texas Railroad Commission Updates
 
Ellis Sess14 102009
Ellis Sess14 102009Ellis Sess14 102009
Ellis Sess14 102009
 
An algorithm for design of brick lining for irrigation channels
An algorithm for design of brick lining for irrigation channelsAn algorithm for design of brick lining for irrigation channels
An algorithm for design of brick lining for irrigation channels
 
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van Megchelen
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van MegchelenDSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van Megchelen
DSD-INT 2020 Lake Turnover Assessments using Delft3D and SOBEK - van Megchelen
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design design
 
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...
Brackish Groundwater Characterization, John Meyer and Sanjeev Kalaswad, Texas...
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
 
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
Investigating Flooding Pattern Using Hydrologic Engineering Center-River Anal...
 
2011ppt dev hydrologydecisionsupporttool_final
2011ppt dev hydrologydecisionsupporttool_final2011ppt dev hydrologydecisionsupporttool_final
2011ppt dev hydrologydecisionsupporttool_final
 
Kansas rivermodel
Kansas rivermodelKansas rivermodel
Kansas rivermodel
 
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...
Simulation of Sediment Transport in the Canal Using the Hec-Ras (Hydrologic E...
 
Presentation on high dam
Presentation on high damPresentation on high dam
Presentation on high dam
 
Professional Geologist Work Experience
Professional Geologist Work ExperienceProfessional Geologist Work Experience
Professional Geologist Work Experience
 
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
 
Exploring the Outer Limits of the Grand Banks- 2001 AAPG Denver
Exploring the Outer Limits of the Grand Banks- 2001 AAPG DenverExploring the Outer Limits of the Grand Banks- 2001 AAPG Denver
Exploring the Outer Limits of the Grand Banks- 2001 AAPG Denver
 
Presentation_Niraj_Final
Presentation_Niraj_Final Presentation_Niraj_Final
Presentation_Niraj_Final
 
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - Becker
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - BeckerDSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - Becker
DSD-INT 2017 Morphological river modelling in Ecuador, using Delft3D FM - Becker
 

Similar to Dredging and Disposal Site Reclamation at John Redmond Reservoir

LIDDLE - Project-Related Work Experience
LIDDLE - Project-Related Work ExperienceLIDDLE - Project-Related Work Experience
LIDDLE - Project-Related Work ExperienceGeorge Liddle
 
LCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyLCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyTWCA
 
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...TWCA
 
Rabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectRabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectFairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationFairfax County
 
Sneen & Rochotte SFS Poster 2015 FINAL VERSION
Sneen & Rochotte SFS Poster 2015 FINAL VERSIONSneen & Rochotte SFS Poster 2015 FINAL VERSION
Sneen & Rochotte SFS Poster 2015 FINAL VERSIONMarty Sneen
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
 
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelCitizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelR Ray Saikus
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2leann_mays
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
 
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bayArmy Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bayecowatchers
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715Max Kroschel
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfecowatchers
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 

Similar to Dredging and Disposal Site Reclamation at John Redmond Reservoir (20)

LIDDLE - Project-Related Work Experience
LIDDLE - Project-Related Work ExperienceLIDDLE - Project-Related Work Experience
LIDDLE - Project-Related Work Experience
 
LCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen BondyLCRA Lane City Reservoir Project, Karen Bondy
LCRA Lane City Reservoir Project, Karen Bondy
 
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...
Luce Bayou Interbasin Project: Updates on a Key Regional Water Supply Project...
 
Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
 
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
 
Rabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectRabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration Project
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Indiana Harbor Illinois
Indiana Harbor IllinoisIndiana Harbor Illinois
Indiana Harbor Illinois
 
Sneen & Rochotte SFS Poster 2015 FINAL VERSION
Sneen & Rochotte SFS Poster 2015 FINAL VERSIONSneen & Rochotte SFS Poster 2015 FINAL VERSION
Sneen & Rochotte SFS Poster 2015 FINAL VERSION
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River JewelCitizens Vision - Cleveland OH Scranton Peninsula River Jewel
Citizens Vision - Cleveland OH Scranton Peninsula River Jewel
 
September 1 - 0130 - Donald D. Etler
September 1 - 0130 - Donald D. EtlerSeptember 1 - 0130 - Donald D. Etler
September 1 - 0130 - Donald D. Etler
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bayArmy Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
 
Planning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil StichertPlanning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil Stichert
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 

Recently uploaded

Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Christina Parmionova
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersCongressional Budget Office
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolSERUDS INDIA
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...ankitnayak356677
 

Recently uploaded (20)

Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists Lawmakers
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnool
 
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
Model Town (Delhi)  9953330565 Escorts, Call Girls ServicesModel Town (Delhi)  9953330565 Escorts, Call Girls Services
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...
Vip Vaishali Escorts Service Call -> 9999965857 Available 24x7 ^ Call Girls G...
 

Dredging and Disposal Site Reclamation at John Redmond Reservoir

  • 1. Dredging and Disposal Site Reclamation at John Redmond Reservoir, Kansas 26th Annual Kansas Hydrology Seminar November 17, 2017
  • 3.
  • 5.
  • 6. 6
  • 7. • 33 U.S.C. Section 408 – RoD Authorized KWO to conduct project on federal property – Programmatic Environmental Impact Statement (PEIS) • Section 106 Programmatic Agreement – USACE Tulsa District, KSHS & Osage Nation of Oklahoma – Ensure any historic sites were identified/protected • Section 404 Permit (USACE) & Stream Obstruction Permit (DWR) – Slurry pipeline crossing of Neosho River • Dam Safety Permits KDA-DWR – Required for all CDFs (based on DWR dam criteria) • Floodplain Fill Permits (DWR) – CDFs B and F (SFHA Zone A) • Water Term Permit (DWR) – Authorized use of water from Redmond for dredging purposes (> 6 months) • NOI for Stormwater Runoff from Construction Activities (KDHE) • NPDES Permit (KDHE) – Effluent Limits at point of discharge PROJECT PERMITTING
  • 8. PHASE I IMPLEMENTATION TIMELINE • 2012 - Planning process begins with USACE • May 2015 – Section 408 Request Final RoD and FONSI on Programmatic EIS Issued. • November 2015 – June 2016: Confined Disposal Facility (CDF) construction takes place • May 2016: Dredging operations begin • October 2016: Dredging operations complete • October 2016: CDF dewatering efforts begin • 2017 to current: CDF reclamation
  • 14. 22” ELECTRIC DREDGE “LP”  CSD “LP”  22” Discharge  3,500 Total HP  Booster Pump  1,000 HP  Crane Barge  Tug Boats  Survey Vessels  Crew Vessels  Skidder Barge
  • 15. ONSHORE BOOSTER STATION O/A Length: 40’ Width: 12’ Height: 16’ HP: 1,000HP Cat. 399 Discharge Diameter: 18” 21,000 Gallon Frack Tank with 4” Electric Pump (175 GPM) 10,000 Gallon Fuel Tank with Secondary Containment
  • 18. GRAVITY TREATED WATER ENTERING FINAL CLARIFICATION CELL (CDF B)
  • 19. EFFLUENT DISCHARGE TO NEOSHO RIVER
  • 21. CDF DEWATERING AND RECLAMATION Continue Work with Great Lakes Dredge & Dock on CDF Reclamation • CDF dewatering has progressed since October 2016 • June 2017, treated water no longer being released to Neosho River • CDF F first in line to be put back into cropland production – All dredged material stays on site, CDF walls will be removed and dirt work will be completed to establish surface drainage network as well as re-slope perimeter to stabilize.
  • 22. JUNE 2017 CDF E (Top) & F (Bottom)
  • 23. CDF F: FEBRUARY & OCTOBER 2017
  • 24. PROJECT SUMMARY • 3,000,000 CY of sediment removed (~1,900 AF) – Average: ~19,000 CY/day – Max: ~32,000 CY/day • $20 million ~ $6.67/CY – Total cost includes permitting, engineering & design, construction, dredging, lease payments and land reclamation – Includes some funds for watershed practices above reservoir • Project financed by 15-year Bond – State Water Plan Funds – Water Sales Revenue through Water Marketing Program
  • 25. QUESTIONS & DISCUSSION Matt Unruh Chief of Planning Kansas Water Office 785-296-3185 matt.unruh@kwo.ks.gov

Editor's Notes

  1. To get the presentation going let’s first look at the question of Why Dredge Redmond? That’s a question we get asked frequently, so I’d like to give some background as to what the situation was with John Redmond Reservoir that made it a candidate for a large-scale dredging project.
  2. As many of you know, our reservoirs are in a battle with nature. While artificial, constructed lakes or reservoirs are efficient at trapping and holding water, they are also efficient at trapping sediment. This chart shows some of the federal reservoirs within Kansas and the estimated percent of capacity lost to sedimentation. As you can see from this graphic, reservoirs such as John Redmond, Tuttle Creek and Toronto have lost around 40 percent or more of their conservation pool capacity. The fact that we are losing storage to sedimentation is not surprising. Sedimentation rates are part of the engineering design plans for these reservoirs. What is surprising is that many of these reservoirs are silting in at a higher rate than anticipated. In the case of John Redmond, the current estimated sedimentation rate is over 1.5 times that of the design sedimentation rate.
  3. Losing reservoir storage capacity impacts the ability to deliver raw water to meet downstream water use needs. This graph shows supply and demand projections for the Neosho River Basin served by John Redmond Reservoir. The red line shows available supply if no action were to be taken and Redmond continued to silt in at it’s current sedimentation rate, the blue line represents current customer demand within the Neosho River Basin from Redmond on downstream, and the green line shows supply factoring in a 2’ pool rise, Phase I dredging operations at Redmond, as well as streambank stabilization projects above Redmond to help reduce the amount of sediment entering the lake. For those of you not aware of this, a reallocation request was initiated by the Kansas Water Office in 1996 and was authorized by the Corps of Engineers in 2013 which allowed for 2’ of flood storage to be converted into water supply storage. This reallocation increased the state’s water supply storage capacity within Redmond by a little more than 17,000 acre-feet. As you can see, the green line still dips below the current customer demand for the basin as we approach the 2030’s and before the year 2045. This 2045 date is significant in that Wolf Creek Nuclear power plant, which draws water from releases made from Redmond and pumps this water to their cooling lake, has an operating license which goes through 2045. This illustrates the need to do additional sediment removal work within Redmond to increase available water supply storage, helping to ensure available supply meets current customer demand, including the demand of Wolf Creek Nuclear power plant, through at least the year 2045. 2012 – extended dry period; full in May, at 30% capacity in Nov. of that same year
  4. Looking closer at Redmond, bathymetric surveys can be used to view and quantify the amount of sediment across the entire lake bottom to determine the amount of water supply storage lost to sedimentation. Comparison of lake bottom elevation data from 1957 to the bathymetric survey conducted in 2007 shows a good portion of the lake experiencing over 1’ of sediment deposition, with areas closest to the dam near the outlet and along the Neosho River channel through the reservoir seeing 10-25’ of deposition.
  5. The dredging project itself is on both federal and private property. The Kansas Water Office has real estate agreements in place for the dredging zone on Redmond, the pipeline route across federal property, the staging area which shows up in orange at Damsite Park, as well as use of land in association with CDF B. All other disposal sites are on private property, and the Kansas Water Office entered into lease agreements for use of this property. From the dredge zone on Redmond, dredged material was pumped around the north side of the dam embankment, then south across the Neosho River towards the disposal sites downstream of the dam. Dredged material placed within the CDFs then was routed back through the CDFs, with gravity-treated effluent water being discharged back to the Neosho River out of CDF B. This discharge is permitted with an NPDES permit obtained by the Kansas Water Office through the Kansas Department of Health and Environment.
  6. Here’s a look at the timeline for Phase I dredging operations at Redmond, including the start of the planning process. From 2012 through 2015, the Kansas Water Office worked with the Corps of Engineers to determine the feasibility of a dredging project at Redmond, then initiated the process of developing a Section 408 request and Programmatic Environmental Impact Statement. Earth work started on construction of the CDFs in November 2015 and enough capacity was built to be able to start dredging operations in May 2016. By October 2016, 3,000,000 cubic yards of sediment had been removed from Redmond and Phase I dredging operations were complete. With the removal of this sediment, almost 1,900 acre-feet of water supply storage capacity was restored within John Redmond Reservoir. From the completion of Phase I dredging operations through today, CDF dewatering activities have been taking place which will ultimately allow for reclamation of the disposal sites.
  7. Now we’ll briefly look at some pictures of the project, beginning with some of the construction activity associated with CDF construction. Overall, this phase of the project which built enough capacity to treat 3,000,000 cubic yards of dredged material lasted approximately 7 months.
  8. Over 5 miles of pipeline was assembled to route dredged material from Redmond to the downstream disposal sites.
  9. A slurry pipeline crossing of the Neosho River was built to route the dredged material to the disposal sites south of the Neosho. For this crossing we did acquire a Section 404 Permit from the Corps of Engineers.
  10. The dredge itself was trucked in on a series of roughly 20 semis and put together onsite. This picture shows the dredge as it’s nearing completion and getting close to being pushed into the water in advance of dredging operations.
  11. Great Lakes Dredge & Dock Company out of Oak Brook, Illinois was the company which won the design-build contract for dredging operations at Redmond. The dredge utilized at Redmond was the Dredge “LP”. On the right picture you can see a portion of the cutter head on the dredge.
  12. The LP is an electric powered dredge which had power supplied to it via a line which was attached to the floating slurry pipeline. A fleet of support vessels was also in place including a crane barge, tug boats, a survey vessel, crew boats, and a skidder barge to provide sufficient workforce for dredging operations.
  13. One booster pump was necessary to help push the dredged material to the downstream disposal sites. This booster pump was placed on the north side of Damsite Park just to the west of the northern extent of the Redmond dam embankment. With this booster pump in line, there was enough power in place to push the dredged material out to CDF I-South, the furthest disposal site away from the dredge.
  14. On May 17, 2016, a kickoff ceremony took place at Redmond to commemorate the start of dredging operations. Dredging at Redmond is a significant event in that this project represents a first of its kind in the nation with a non-federal agency sponsor conducting a large-scale inland dredging project on a U.S. Army Corps of Engineers reservoir. This project will serve as a model both in Kansas as well as nationwide for water supply restoration efforts within federal reservoirs. With dredging starting on a notable project such as this we wanted to celebrate and recognize the significance of this event.
  15. This video shows dredged material being placed into CDF E, the largest of the 5 disposal sites utilized for the project. As you can see the material is very dark and muddy in appearance and approximately 80% and 20% dredged material. This ratio can be modified to increase the amount of solids contained within the slurry mix depending on dredging rate as well as material composition.
  16. From the previous video, those solids within CDF E settled out and then were routed to CDF B, the final clarification cell of the disposal system. Notice how much cleaner the water is in comparison to the previous video. No flocculants were utilized to help with settling out of solids within the CDFs.
  17. With the additional settling time in CDF B, the effluent water was ready for discharge into the Neosho River. This is the point of discharge into the river and note the clarity of the water.
  18. Here is a view of John Redmond in the background with 3 of the disposal sites in the foreground, CDFs I-South, I-North and E. The small area between I-South and I-North was not utilized for sediment disposal to avoid impacts to jurisdictional Waters of the U.S.
  19. CDF dewatering activities have been taking place which will ultimately allow for reclamation of the disposal sites.
  20. CDF F (no water) CDF E (with water)
  21. Breakdown on major project cost components as follows: CDF Construction = 23%, Sediment Removal = 44%, Land Reclamation = 11%, Land Lease Payments = 3%, Electrical Infrastructure Upgrades = <1%