SlideShare a Scribd company logo
1 of 49
Copyright Projecting Success 2018
Martin Paver
CEO / Founder
www.projectingsuccess.co.uk
Lessons Learned Don’t Work:
Why a Data Centric Approach May Hold the Key
APM South Wales and West of England
Branch Event
22 Nov 2018
Copyright Projecting Success 2018
Why ‘Lessons Learned’?
Project Lead for $Bn
Nuclear New Build
Programme Manager
for £400m portfolio of
60 projects
PMO roles in multi
$Bn portfolios
I’ve always struggled to leverage the broad
experience that I know exists.
"Those that fail
to learn from
history are
doomed to
repeat it."
Copyright Projecting Success 2018
Leverage Experience – A Wicked Problem?
Small
Margins
Source:APM
Project Success Factors
https://commons.wikimedia.org/wiki/File:Tour_de_France_2016,_team_sky_(28595456475).jpghttps://upload.wikimedia.org/wikipedia/commons/7/76/Mclaren_racing_usgp_2004.jpg
Avoiding the
avoidable
Certainty in delivery
Reduced outliers
Strategic focus
Reputation
Reduce incidents
Increased profit
Cost avoidance
Sector 1
International A
Sector 2
ScheduleRiskLessons Cost
Project Delivery Experience
Company A
Copyright Projecting Success 2018
The failure of the FiReControl project
The Stark Reality of Not Learning Lessons
Common Agricultural Policy Futures
programme
We do not expect the programme to deliver value for money. The cost of
£178 million is 74 per cent more than the original business case, and the
programme will not fully deliver the anticipated benefits. Farmers reported
they have been adversely affected by the programme delays, highlighting cash
flow problems that have knock-on effects for the wider rural economy.
http://www.audit-scotland.gov.uk/uploads/docs/report/2016/nr_160519_cap_futures.pdf
‘911 Upgrade’
(Emergency Communications
Transformation Program)
The project started in 2004 with an estimated cost of $1.3 billion and a three
year time frame.
According to an audit from City Comptroller, released 21 March 2012, the
project is now $1 billion over budget and seven years behind schedule.
The Comptroller blamed the cost overruns on inadequate project
management within the city.
http://sa.acs.org.au/gallery/leaders_lunch/20120516_Common_causes_of_failure_in_major_ICT-enabled_projects.pdf
NHS 24
The total cost of the Future Programme had risen by 55 per cent to £117.4
million, compared to a business case cost of £75.8 million covering the ten-
year contract period. The increase was due to changes in the contract
specification and costs associated with the delay in implementing the IT
system. [2016]
http://www.audit-scotland.gov.uk/uploads/docs/report/2016/s22_161006_nhs_24.pdf
Disclosure Scotland
The whole programme was estimated to cost £31 million and included a
£29 million project to design and build a new ICT system to support the new
arrangements and replace the existing system, along with other information
management projects, training and guidance.
The programme experienced a number of significant problems when it went
live in February 2011. Disclosure Scotland and the supplier continue to work
on these problems and core functionality is now expected to be established by
autumn 2012.
Crown Office and Procurator Fiscal
Service (COPFS)
The Phoenix programme was initiated in early 2009, at an estimated cost
of £10 million, because a number of software elements of the existing case
management system used to help prepare criminal cases for prosecution were
outdated and lacked readily available technical support.
Management of the programme exhibited a number of weaknesses but it was
cancelled in November 2010 before construction started due to increased
costs and a significantly reduced capital budget.
National Polar-orbiting Operational
Environmental Satellite System
Department of Veterans Affairs’ Scheduling Replacement Project was
terminated in September 2009 after spending an estimated $127 million over
9 years.
http://www.gao.gov/assets/690/681420.pdf
Secure Border Initiative Network program
The Department of Homeland Security’s Secure Border Initiative Network program
was ended in January 2011, after the department obligated more than $1 billion to
the program, because it did not meet cost-effectiveness and viability standards.
http://www.gao.gov/assets/690/681420.pdf
Financial and Logistics Integrated Technology
Enterprise program
The Department of Veterans Affairs’ Financial and Logistics Integrated Technology Enterprise program
was intended to be delivered by 2014 at a total estimated cost of $609 million, but was terminated in
October 2011 due to challenges in managing the program
http://www.gao.gov/assets/690/681420.pdf
eCare
eCare programme was supposed to solve all our data communication
problems in the health and social care service, but it was abandoned
completely after seven or eight years at—we are told—a cost of £56 million,
although I suspect that the cost was substantially more.
http://www.parliament.scot/S4_PublicAuditCommittee/20_January_2016.pdf
Registers of Scotland (RoS)
Responsible for compiling and maintaining registers relating to
property and other legal documents. Its annual operating costs were
£78 million in 2010/11. While both RoS and BT consider the ongoing
ICT service provision has largely been successful, RoS now considers
that the partnership outsourcing of all ICT was inappropriate and it
has terminated the SPA.
Two individual projects within the programme now cancelled, with
costs of £6.7 million written off in March 2011.
Expeditionary Combat Support System
The Department of Defense’s Expeditionary Combat Support System was
canceled in December 2012 after spending more than a billion dollars and
failing to deploy within 5 years of initially obligating funds.
http://www.gao.gov/assets/690/681420.pdf
Retirement Systems Modernization program
The Office of Personnel Management’s Retirement Systems Modernization program was canceled in
February 2011, after spending approximately $231 million on the agency’s third attempt to automate
the processing of federal employee retirement claims.
http://www.gao.gov/assets/690/681420.pdf
>£20,000,000,000
Copyright Projecting Success 2018
Stagnating Productivity
Copyright Projecting Success 2018
But does it really matter?
Within the next 10 years….
How much could be saved?
The analysis of National Infrastructure and
Construction Pipeline contains projections of £600
billion of public and private investment in
infrastructure over the next 10 years.
McKinsey analysis estimates that global
capital spending will total $77 trillion between
2018 and 2023, which places the annual value
of that spending at more than $10 trillion.
…. >$100 trillion over 10 years
Copyright Projecting Success 2018
Pursuing the Case for Change: PMI
Copyright Projecting Success 2018
Programme Manager for
£400m portfolio of 60
projects
Sept 2018 Blog
Pursuing the Case for Change: APM
Copyright Projecting Success 2018
Papers and ArticlesPapers and Articles
Copyright Projecting Success 2018
The Journey
Lessons learned
systems do not work Instinctively, we
should be able to
leverage experience Why don’t the
methods work?
What can we do to fix
it?
What have others
done?
Is it fixable?
• NAO Reports
• GAO Reports
• Public hearings
• Public Accounts Committees
• Lessons learned data (Aus, Sco, NI)
• Audit Reports (Can, Aus, NZ, Holland)
• FOI requests
• Commercially sensitive data
Copyright Projecting Success 2018
Capacity to Learn Lessons
Home Office Government Major Projects Portfolio 2016
Ministry of Justice Government Major Projects Portfolio 2016
With so many projects not delivering to plan there should be a rich opportunity for
leveraging experience for the collective benefit of UK PLC….
…..but there is limited evidence of this happening.
Dept of Health Government Major Projects Portfolio 2016
Ministry of Defence Government Major Projects Portfolio 2016
Copyright Projecting Success 2018
Digging a Little Deeper
Year RAG Forecast End Forecast Whole Life
Costs £m
2012 31/12/2014 138
2013 01/04/2016 1375
2014 01/09/2016 1205
2015 30/11/2017 1706
2016 30/11/2017 2879
Source: GMPP Reports
Copyright Projecting Success 2018
projectdataanalytics.uk
Copyright Projecting Success 2018
Reasons for Not Recording Lessons?
Capitalizing from past projects the value of lessons learned. PMI CONFERENCE
PAPER 2008
By Trevino, Stephanie A. | Anantatmula, Vittal S.
Its a matter of priorities for:
• Senior Management
• Project Leadership
Priority not given because:
• Benefits are not measurable
• Lessons recorded aren’t used
• Process driven approach
Therefore, effort is prioritised on
delivery.
With exceptions for:
• Projects in heavily regulated
industries
• Public sector projects with learning
legacy as a key factor
• Projects in consultancies where
learning provides clear competitive
advantage.
Copyright Projecting Success 2018
Lessons Learned Processes
DH does not have any policies or processes on lessons learned.
Lesson learned methodology is standard Programme and Project
Management practice which programmes and projects deploy as
they see fit.
Copyright Projecting Success 2018
But aren’t the NAO fixing the problem?
https://www.nao.org.uk/naoblog/a-systematic-look-at-major-programmes/
It is the role of Departments to leverage the experience, not the NAO
Copyright Projecting Success 2018
Nearly 20,000 Lessons….. Overview
>50 Organisations
>1,000 Projects
>2 Years of effort to collate
Covering 3Continents
Estimated Portfolio ~$30 bn
From ….
”Benefits clearer”
to …”There was insufficient clarity about
accountability for each budget line, reflecting
a centralised approach to budget
management. Poor links between the Finance
Team and key programmes compounded this
lack of accountability, which meant that
forecasting, monitoring and budget
discussions, as well as early planning of
procurement strategies, did not take place in a
sufficiently timely manner to identify and
address the key risks”.
Copyright Projecting Success 2018
Existing Lessons Learned Analysis
http://www.treasury.govt.nz
Copyright Projecting Success 2018
Is This A Knowledge Management Problem?
Project, Programme, Portfolio Management
Technical Delivery
I don’t
know
I do
know
Knowable
Unknowable
Copyright Projecting Success 2018
Every Lesson has An Action… Or does it?
Lessons learned…..
You experienced XYZ and if you do ABC in the future then the lesson
won’t be repeated.
Observation 1: We should be getting better at this… but the list of
lessons has been similar for the last 30 years.
Observation 2: An effective project manager needs to know every
lesson, in every context about every sort of project.
Observation 3: There are organisational factors that inhibit learning
Copyright Projecting Success 2018
Findings From the Lessons
• Lack of forensic insight
• ‘The number of technical reviews increased during this time
and were discussed at the project board but there is limited
evidence that the risks highlighted in the reviews were
acted upon or resolved’.
• ‘Lack of robust business requirements at the outset, leading
to unrealistic IT project budgets and timescales’.
• Lots of lessons on reporting, but few define the problem or what to do about it.
• Very variable.
• Process rather than outcome focus.
• Repetition. Some lessons repeated up to x10.
• Often lack context.
• Lack consequence. Difficult to understand what was a big problem.
• Lacks root cause analysis.
• Difficult to identify correlations between lessons.
The best lessons address the above.
Copyright Projecting Success 2018
Nature & Quality of the Lessons
The SRO and Project Team should develop a
robust and comprehensive Stakeholder
Management and Communication Plan.
The project should consider a workshop to
capture all Lessons Learned to date and
ensure that the learning is embedded within
all future development
Review and implement project
governance arrangements.
Project reporting format should be
reviewed.
Observation?
Something to consider in the next phase?
Missing the basics and don’t know better
Should know better
Fundamental shortfall with minor impact
Fundamental shortfall with major impact
Copyright Projecting Success 2018
‘Avoidability’ of lessons
•Act of God, environmental factors
•Unknown/unknowable external event
•Unknown/knowable external event
•Known external event
•Internal decision or organisational constraint
•Lesson identified or known but deemed irrelevant
•Lesson identified or known but ignored due to other priorities/resourcing
Unavoidable lesson
But may be aware of
emerging environmental
conditions
Avoidable lesson
Priority, resourcing, SQEP or
judgment call
Strategic lesson
Organisation proceeded
knowing that strategic
decisions may/will likely
impact the project. Lesson
learned was foreseeable
and wasn’t mitigated.
Copyright Projecting Success 2018
The Link Between Risk and Lessons
Risk
IssueLesson
If the lesson is not acted
upon it becomes a risk
for the next project
How many organisations link lessons learned and risk management?
What is the correlation between
risk drawdown and lessons
learned?
Tolerate
Treat
Transfer
Terminate
Copyright Projecting Success 2018
Projects: An Enabler or Primary Purpose?
Project Duration
Similarity
Short Long
SimilarDissimilar
Major IT upgrades
Business
transformation
Enabling Activity
Office Move
New office
Call Centre
Project Duration
Similarity
Short Long
SimilarDissimilar
Event management
Major IT upgrades
Business
transformation
Office Move
Crossrail
New office
Primary Activity
HS2
Call Centre
Station refit
Station build 1, 2, 3
Copyright Projecting Success 2018
Leveraging Experience: Events Scotland
Security
Transport
Ticketing
Funding
Marketing
Infrastructure
…….
Opportunity to recycle experience:
• Capturing schedules, assumptions, risks and budgets.
• Identifying areas of stability and uncertainty and which
are likely to change. Management effort is then focused
on areas of instability.
• Understanding the effectiveness of management action
associated with risks, assumptions and delivery.
• Embedding members of a team into an existing project so
that the learning can be recycled into the next project.
“A 6-7year journey”
Immovable deadlines
• Context is critical in understanding application of experience
• Cost over-runs tend to be associated with infrastructure
• Organisational Capacity to leverage experience
• International sharing of experience
Copyright Projecting Success 2018
One Dataset. Different Perspectives
Assurance
reviewer
Governance
Supply chain
Project
team
Next project
Other organisations
Process of personal
promotion, personal
reflection & learning
for the next phase
Holding to
account
Preparation for key
gateway reviews
Enabling the supply
chain and improving
efficiency
Leveraging experience
for aligned projects
Leveraging experience
for other
organisations or other
parts of ‘the group’
Copyright Projecting Success 2018
A Tailored Approach
Any approach to improving project delivery productivity must be tailored to the organisation:
Stable workforce & suppliers
Experience is ‘recycled’
Transient workforce. Churn in supply base
Experience is fragmented
Multiple and parallel implementations of
similar projects
Bespoke, unique projects delivered
infrequently
Experience is primary guide Process is primary guide
Highly competitive where productivity is a
major differentiator
Public sector or monopoly, incremental
improvement
Cross fertilisation between departments Experience is typically siloed within the
organisation
Internal governance External regulation/governance
Workflows, Wikis, Processes, Assurance
Key considerations
Knowledge sharing, project controls, lean
Spectrum of approaches
Copyright Projecting Success 2018
An Example: Crossrail
Copyright Projecting Success 2018
Exhaust plume
from project
delivery
An Example: Crossrail
Copyright Projecting Success 2018
What Happens to the Data?
Copyright Projecting Success 2018
An Realisable Vision
Copyright Projecting Success 2018
Instinctive Behaviours
System 1
System 1 is an automatic, fast and often
unconscious way of thinking.
•It is autonomous and efficient, requiring little
energy or attention,
•Is susceptical to biases and systematic errors.
System 2 is an effortful, slow and
controlled way of thinking. It requires
energy and can’t work without
attention but, once engaged, has the
ability to filter the instincts of System 1
System 2
Nudge Theory
We adjust
our driving
to the
conditions
of the road
We adjust our
speed if we
know that
others have
experienced
costly
accidents
VS
System 1 and 2 thinking
Copyright Projecting Success 2018
Leveraging the Connected Data
Projects LessonsRisks$
Graph
Data Stored in Silos
Lesson X
Draw
down
Cost
impact
Time
impact
Mitigate
Cost
Mitigate
effective
-ness
Project 1
Project 2
Taxon-
omy
TechnicalSafetySecurity
Technical
issue
Security
Issue
Safety
Issue
Copyright Projecting Success 2018
Exploitation of Data
Actors
Views
User Stories Degree of fit
‘Perfect Data’ ‘Typical Data’
For most organisations, the ‘lessons learned’ process is only solving 25% of the requirement, at best.
“As a Project Manager I want to be able to drill
into lessons that I am interested in so that I can
gain a better understanding of context, relevance
and how the lesson may impact my own project”
Copyright Projecting Success 2018
EVM data
Resourcing
Weather
Supplier performance
Dependencies
Risks etc
Real time
update of
assigned tasks
WBS Elements
Scheduling Corpus and
Context Extract Triples
Benchmarking
Adaptive SchedulingRecommendations
Scheduling
Copyright Projecting Success 2018
A once through process
Risk lifecycle
Leveraging Risk Experience
Connected risks Risks-Issues-Lessons
Informed risk
registers
Risk
trends
Risk mitigations
Risk
budget
Systemic Risk
Risks
Copyright Projecting Success 2018
Benefits
Copyright Projecting Success 2018
So... What is Advanced Data Analytics
Copyright Projecting Success 2018
Icons made by Freepik from www.flaticon.com
Machine Learning: Bid Data – a worked example
Copyright Projecting Success 2018
Bent Flyvbjerg’s work on Major Projects
Copyright Projecting Success 2018
Bent Flyvbjerg’s work on Major Projects
Copyright Projecting Success 2018
Bent Flyvbjerg’s work on Major Projects
Copyright Projecting Success 2018
Counteracting Bias
• Consistency/desirability bias
• Recency effects
• Human memory bias
• Optimism bias
• ‘Strategic Deception’
Data
Copyright Projecting Success 2018
Fundamentally:
• What is the predisposition of the work to variance?
• Can we predict it?
• How do we test for it?
• How do we treat it and change the future?
Evidence based, tempering against bias.
Project DNA
Copyright Projecting Success 2018
Barriers to Adoption
Its not on the corporate ‘to do’ list
• Lack of a shared vision
• Lack of evidence to support the vision
• Lack of skilled horsepower
• Lack of data
• Siloed
• Poor quality
• Understanding the investment case
Copyright Projecting Success 2018
Summary
• The majority of organisations in the sample are not leveraging experience
• The opportunity to leverage experience is significant
• Potential impact on project delivery productivity is huge (up to 30%)
• The approaches do not differentiate between P3M and technical lessons. They are different!
• Does your organisation believe there is value in leveraging past investments?
• STOP box ticking processes and START to link value to your particular challenge
• Pivot towards a data driven insights approach where evidence shapes future decisions
• Deliver information and insights when required, in the right form, which are consumable
• Supported by wikis, peer assists, communities of practice etc.
• Machine learning is marching towards us which will be transformational.
• We need to develop an approach to support it.
"Those that
fail to learn
from history
are doomed
to repeat it."
Copyright Projecting Success 2018
• Free to join
• Free to attend
• Crosses professional boundaries
• Developing a community
• Developing into a force for good
Developing a Community
Copyright Projecting Success 2018
Any questions, comments….
…. Or could you share your own experience?

More Related Content

Similar to Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key

Project Data Analytics - How do we leverage experience of project delivery? w...
Project Data Analytics - How do we leverage experience of project delivery? w...Project Data Analytics - How do we leverage experience of project delivery? w...
Project Data Analytics - How do we leverage experience of project delivery? w...Association for Project Management
 
Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...Association for Project Management
 
Does your Board exhibit good governance of project/change management?
Does your Board exhibit good governance of project/change management?Does your Board exhibit good governance of project/change management?
Does your Board exhibit good governance of project/change management?Association for Project Management
 
Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Association for Project Management
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation MasterclassCaribbean Development Bank
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAssociation for Project Management
 
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010UNSW Canberra
 
Presentation slides for investor meetings in Hong Kong
Presentation slides for investor meetings in Hong KongPresentation slides for investor meetings in Hong Kong
Presentation slides for investor meetings in Hong KongKeppelCorporation
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015FBE Manchester
 
Surviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits ManagementSurviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits Managementcombera
 
Best Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit CrunchBest Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit Crunchrmoret
 
Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019KeppelCorporation
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand FinaleLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand FinaleAnupreet Choudhary
 
Spottitt - NOAH18 London
Spottitt - NOAH18 LondonSpottitt - NOAH18 London
Spottitt - NOAH18 LondonNOAH Advisors
 
It Skills At The Frontiers V2.1
It Skills At The Frontiers V2.1It Skills At The Frontiers V2.1
It Skills At The Frontiers V2.1Ben Grinnell
 
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...KTN
 
Keppel Corporation Presentation to Investors in Bangkok- September 2019
Keppel Corporation Presentation to Investors in Bangkok- September 2019Keppel Corporation Presentation to Investors in Bangkok- September 2019
Keppel Corporation Presentation to Investors in Bangkok- September 2019KeppelCorporation
 
Egf Mgt Strengthening Program
Egf Mgt Strengthening ProgramEgf Mgt Strengthening Program
Egf Mgt Strengthening ProgramRoy Consulta
 

Similar to Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key (20)

Project Data Analytics - How do we leverage experience of project delivery? w...
Project Data Analytics - How do we leverage experience of project delivery? w...Project Data Analytics - How do we leverage experience of project delivery? w...
Project Data Analytics - How do we leverage experience of project delivery? w...
 
Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...
 
Does your Board exhibit good governance of project/change management?
Does your Board exhibit good governance of project/change management?Does your Board exhibit good governance of project/change management?
Does your Board exhibit good governance of project/change management?
 
Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation Masterclass
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
 
Graphical CV
Graphical CVGraphical CV
Graphical CV
 
Presentation slides for investor meetings in Hong Kong
Presentation slides for investor meetings in Hong KongPresentation slides for investor meetings in Hong Kong
Presentation slides for investor meetings in Hong Kong
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015
 
Surviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits ManagementSurviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits Management
 
Best Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit CrunchBest Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit Crunch
 
Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019
 
RoshanKanyady
RoshanKanyadyRoshanKanyady
RoshanKanyady
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand FinaleLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
 
Spottitt - NOAH18 London
Spottitt - NOAH18 LondonSpottitt - NOAH18 London
Spottitt - NOAH18 London
 
It Skills At The Frontiers V2.1
It Skills At The Frontiers V2.1It Skills At The Frontiers V2.1
It Skills At The Frontiers V2.1
 
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
 
Keppel Corporation Presentation to Investors in Bangkok- September 2019
Keppel Corporation Presentation to Investors in Bangkok- September 2019Keppel Corporation Presentation to Investors in Bangkok- September 2019
Keppel Corporation Presentation to Investors in Bangkok- September 2019
 
Egf Mgt Strengthening Program
Egf Mgt Strengthening ProgramEgf Mgt Strengthening Program
Egf Mgt Strengthening Program
 

Recently uploaded

RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhi
RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝DelhiRS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhi
RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhijennyeacort
 
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一F La
 
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort servicejennyeacort
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfLars Albertsson
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfJohn Sterrett
 
Call Girls In Dwarka 9654467111 Escorts Service
Call Girls In Dwarka 9654467111 Escorts ServiceCall Girls In Dwarka 9654467111 Escorts Service
Call Girls In Dwarka 9654467111 Escorts ServiceSapana Sha
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxStephen266013
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...Florian Roscheck
 
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一F sss
 
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...Jack DiGiovanna
 
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
20240419 - Measurecamp Amsterdam - SAM.pdf
20240419 - Measurecamp Amsterdam - SAM.pdf20240419 - Measurecamp Amsterdam - SAM.pdf
20240419 - Measurecamp Amsterdam - SAM.pdfHuman37
 
Generative AI for Social Good at Open Data Science East 2024
Generative AI for Social Good at Open Data Science East 2024Generative AI for Social Good at Open Data Science East 2024
Generative AI for Social Good at Open Data Science East 2024Colleen Farrelly
 
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptx
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptxAmazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptx
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptxAbdelrhman abooda
 
Top 5 Best Data Analytics Courses In Queens
Top 5 Best Data Analytics Courses In QueensTop 5 Best Data Analytics Courses In Queens
Top 5 Best Data Analytics Courses In Queensdataanalyticsqueen03
 
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...limedy534
 
How we prevented account sharing with MFA
How we prevented account sharing with MFAHow we prevented account sharing with MFA
How we prevented account sharing with MFAAndrei Kaleshka
 
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理科罗拉多大学波尔得分校毕业证学位证成绩单-可办理
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理e4aez8ss
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsappssapnasaifi408
 

Recently uploaded (20)

RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhi
RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝DelhiRS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhi
RS 9000 Call In girls Dwarka Mor (DELHI)⇛9711147426🔝Delhi
 
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一
办理(UWIC毕业证书)英国卡迪夫城市大学毕业证成绩单原版一比一
 
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service
9711147426✨Call In girls Gurgaon Sector 31. SCO 25 escort service
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdf
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdf
 
Call Girls In Dwarka 9654467111 Escorts Service
Call Girls In Dwarka 9654467111 Escorts ServiceCall Girls In Dwarka 9654467111 Escorts Service
Call Girls In Dwarka 9654467111 Escorts Service
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docx
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
 
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
 
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...
Building on a FAIRly Strong Foundation to Connect Academic Research to Transl...
 
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制南十字星大学毕业证(SCU毕业证)#文凭成绩单#真实留信学历认证永久存档
 
Call Girls in Saket 99530🔝 56974 Escort Service
Call Girls in Saket 99530🔝 56974 Escort ServiceCall Girls in Saket 99530🔝 56974 Escort Service
Call Girls in Saket 99530🔝 56974 Escort Service
 
20240419 - Measurecamp Amsterdam - SAM.pdf
20240419 - Measurecamp Amsterdam - SAM.pdf20240419 - Measurecamp Amsterdam - SAM.pdf
20240419 - Measurecamp Amsterdam - SAM.pdf
 
Generative AI for Social Good at Open Data Science East 2024
Generative AI for Social Good at Open Data Science East 2024Generative AI for Social Good at Open Data Science East 2024
Generative AI for Social Good at Open Data Science East 2024
 
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptx
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptxAmazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptx
Amazon TQM (2) Amazon TQM (2)Amazon TQM (2).pptx
 
Top 5 Best Data Analytics Courses In Queens
Top 5 Best Data Analytics Courses In QueensTop 5 Best Data Analytics Courses In Queens
Top 5 Best Data Analytics Courses In Queens
 
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...
Effects of Smartphone Addiction on the Academic Performances of Grades 9 to 1...
 
How we prevented account sharing with MFA
How we prevented account sharing with MFAHow we prevented account sharing with MFA
How we prevented account sharing with MFA
 
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理科罗拉多大学波尔得分校毕业证学位证成绩单-可办理
科罗拉多大学波尔得分校毕业证学位证成绩单-可办理
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
 

Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key

  • 1. Copyright Projecting Success 2018 Martin Paver CEO / Founder www.projectingsuccess.co.uk Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key APM South Wales and West of England Branch Event 22 Nov 2018
  • 2. Copyright Projecting Success 2018 Why ‘Lessons Learned’? Project Lead for $Bn Nuclear New Build Programme Manager for £400m portfolio of 60 projects PMO roles in multi $Bn portfolios I’ve always struggled to leverage the broad experience that I know exists. "Those that fail to learn from history are doomed to repeat it."
  • 3. Copyright Projecting Success 2018 Leverage Experience – A Wicked Problem? Small Margins Source:APM Project Success Factors https://commons.wikimedia.org/wiki/File:Tour_de_France_2016,_team_sky_(28595456475).jpghttps://upload.wikimedia.org/wikipedia/commons/7/76/Mclaren_racing_usgp_2004.jpg Avoiding the avoidable Certainty in delivery Reduced outliers Strategic focus Reputation Reduce incidents Increased profit Cost avoidance Sector 1 International A Sector 2 ScheduleRiskLessons Cost Project Delivery Experience Company A
  • 4. Copyright Projecting Success 2018 The failure of the FiReControl project The Stark Reality of Not Learning Lessons Common Agricultural Policy Futures programme We do not expect the programme to deliver value for money. The cost of £178 million is 74 per cent more than the original business case, and the programme will not fully deliver the anticipated benefits. Farmers reported they have been adversely affected by the programme delays, highlighting cash flow problems that have knock-on effects for the wider rural economy. http://www.audit-scotland.gov.uk/uploads/docs/report/2016/nr_160519_cap_futures.pdf ‘911 Upgrade’ (Emergency Communications Transformation Program) The project started in 2004 with an estimated cost of $1.3 billion and a three year time frame. According to an audit from City Comptroller, released 21 March 2012, the project is now $1 billion over budget and seven years behind schedule. The Comptroller blamed the cost overruns on inadequate project management within the city. http://sa.acs.org.au/gallery/leaders_lunch/20120516_Common_causes_of_failure_in_major_ICT-enabled_projects.pdf NHS 24 The total cost of the Future Programme had risen by 55 per cent to £117.4 million, compared to a business case cost of £75.8 million covering the ten- year contract period. The increase was due to changes in the contract specification and costs associated with the delay in implementing the IT system. [2016] http://www.audit-scotland.gov.uk/uploads/docs/report/2016/s22_161006_nhs_24.pdf Disclosure Scotland The whole programme was estimated to cost £31 million and included a £29 million project to design and build a new ICT system to support the new arrangements and replace the existing system, along with other information management projects, training and guidance. The programme experienced a number of significant problems when it went live in February 2011. Disclosure Scotland and the supplier continue to work on these problems and core functionality is now expected to be established by autumn 2012. Crown Office and Procurator Fiscal Service (COPFS) The Phoenix programme was initiated in early 2009, at an estimated cost of £10 million, because a number of software elements of the existing case management system used to help prepare criminal cases for prosecution were outdated and lacked readily available technical support. Management of the programme exhibited a number of weaknesses but it was cancelled in November 2010 before construction started due to increased costs and a significantly reduced capital budget. National Polar-orbiting Operational Environmental Satellite System Department of Veterans Affairs’ Scheduling Replacement Project was terminated in September 2009 after spending an estimated $127 million over 9 years. http://www.gao.gov/assets/690/681420.pdf Secure Border Initiative Network program The Department of Homeland Security’s Secure Border Initiative Network program was ended in January 2011, after the department obligated more than $1 billion to the program, because it did not meet cost-effectiveness and viability standards. http://www.gao.gov/assets/690/681420.pdf Financial and Logistics Integrated Technology Enterprise program The Department of Veterans Affairs’ Financial and Logistics Integrated Technology Enterprise program was intended to be delivered by 2014 at a total estimated cost of $609 million, but was terminated in October 2011 due to challenges in managing the program http://www.gao.gov/assets/690/681420.pdf eCare eCare programme was supposed to solve all our data communication problems in the health and social care service, but it was abandoned completely after seven or eight years at—we are told—a cost of £56 million, although I suspect that the cost was substantially more. http://www.parliament.scot/S4_PublicAuditCommittee/20_January_2016.pdf Registers of Scotland (RoS) Responsible for compiling and maintaining registers relating to property and other legal documents. Its annual operating costs were £78 million in 2010/11. While both RoS and BT consider the ongoing ICT service provision has largely been successful, RoS now considers that the partnership outsourcing of all ICT was inappropriate and it has terminated the SPA. Two individual projects within the programme now cancelled, with costs of £6.7 million written off in March 2011. Expeditionary Combat Support System The Department of Defense’s Expeditionary Combat Support System was canceled in December 2012 after spending more than a billion dollars and failing to deploy within 5 years of initially obligating funds. http://www.gao.gov/assets/690/681420.pdf Retirement Systems Modernization program The Office of Personnel Management’s Retirement Systems Modernization program was canceled in February 2011, after spending approximately $231 million on the agency’s third attempt to automate the processing of federal employee retirement claims. http://www.gao.gov/assets/690/681420.pdf >£20,000,000,000
  • 5. Copyright Projecting Success 2018 Stagnating Productivity
  • 6. Copyright Projecting Success 2018 But does it really matter? Within the next 10 years…. How much could be saved? The analysis of National Infrastructure and Construction Pipeline contains projections of £600 billion of public and private investment in infrastructure over the next 10 years. McKinsey analysis estimates that global capital spending will total $77 trillion between 2018 and 2023, which places the annual value of that spending at more than $10 trillion. …. >$100 trillion over 10 years
  • 7. Copyright Projecting Success 2018 Pursuing the Case for Change: PMI
  • 8. Copyright Projecting Success 2018 Programme Manager for £400m portfolio of 60 projects Sept 2018 Blog Pursuing the Case for Change: APM
  • 9. Copyright Projecting Success 2018 Papers and ArticlesPapers and Articles
  • 10. Copyright Projecting Success 2018 The Journey Lessons learned systems do not work Instinctively, we should be able to leverage experience Why don’t the methods work? What can we do to fix it? What have others done? Is it fixable? • NAO Reports • GAO Reports • Public hearings • Public Accounts Committees • Lessons learned data (Aus, Sco, NI) • Audit Reports (Can, Aus, NZ, Holland) • FOI requests • Commercially sensitive data
  • 11. Copyright Projecting Success 2018 Capacity to Learn Lessons Home Office Government Major Projects Portfolio 2016 Ministry of Justice Government Major Projects Portfolio 2016 With so many projects not delivering to plan there should be a rich opportunity for leveraging experience for the collective benefit of UK PLC…. …..but there is limited evidence of this happening. Dept of Health Government Major Projects Portfolio 2016 Ministry of Defence Government Major Projects Portfolio 2016
  • 12. Copyright Projecting Success 2018 Digging a Little Deeper Year RAG Forecast End Forecast Whole Life Costs £m 2012 31/12/2014 138 2013 01/04/2016 1375 2014 01/09/2016 1205 2015 30/11/2017 1706 2016 30/11/2017 2879 Source: GMPP Reports
  • 13. Copyright Projecting Success 2018 projectdataanalytics.uk
  • 14. Copyright Projecting Success 2018 Reasons for Not Recording Lessons? Capitalizing from past projects the value of lessons learned. PMI CONFERENCE PAPER 2008 By Trevino, Stephanie A. | Anantatmula, Vittal S. Its a matter of priorities for: • Senior Management • Project Leadership Priority not given because: • Benefits are not measurable • Lessons recorded aren’t used • Process driven approach Therefore, effort is prioritised on delivery. With exceptions for: • Projects in heavily regulated industries • Public sector projects with learning legacy as a key factor • Projects in consultancies where learning provides clear competitive advantage.
  • 15. Copyright Projecting Success 2018 Lessons Learned Processes DH does not have any policies or processes on lessons learned. Lesson learned methodology is standard Programme and Project Management practice which programmes and projects deploy as they see fit.
  • 16. Copyright Projecting Success 2018 But aren’t the NAO fixing the problem? https://www.nao.org.uk/naoblog/a-systematic-look-at-major-programmes/ It is the role of Departments to leverage the experience, not the NAO
  • 17. Copyright Projecting Success 2018 Nearly 20,000 Lessons….. Overview >50 Organisations >1,000 Projects >2 Years of effort to collate Covering 3Continents Estimated Portfolio ~$30 bn From …. ”Benefits clearer” to …”There was insufficient clarity about accountability for each budget line, reflecting a centralised approach to budget management. Poor links between the Finance Team and key programmes compounded this lack of accountability, which meant that forecasting, monitoring and budget discussions, as well as early planning of procurement strategies, did not take place in a sufficiently timely manner to identify and address the key risks”.
  • 18. Copyright Projecting Success 2018 Existing Lessons Learned Analysis http://www.treasury.govt.nz
  • 19. Copyright Projecting Success 2018 Is This A Knowledge Management Problem? Project, Programme, Portfolio Management Technical Delivery I don’t know I do know Knowable Unknowable
  • 20. Copyright Projecting Success 2018 Every Lesson has An Action… Or does it? Lessons learned….. You experienced XYZ and if you do ABC in the future then the lesson won’t be repeated. Observation 1: We should be getting better at this… but the list of lessons has been similar for the last 30 years. Observation 2: An effective project manager needs to know every lesson, in every context about every sort of project. Observation 3: There are organisational factors that inhibit learning
  • 21. Copyright Projecting Success 2018 Findings From the Lessons • Lack of forensic insight • ‘The number of technical reviews increased during this time and were discussed at the project board but there is limited evidence that the risks highlighted in the reviews were acted upon or resolved’. • ‘Lack of robust business requirements at the outset, leading to unrealistic IT project budgets and timescales’. • Lots of lessons on reporting, but few define the problem or what to do about it. • Very variable. • Process rather than outcome focus. • Repetition. Some lessons repeated up to x10. • Often lack context. • Lack consequence. Difficult to understand what was a big problem. • Lacks root cause analysis. • Difficult to identify correlations between lessons. The best lessons address the above.
  • 22. Copyright Projecting Success 2018 Nature & Quality of the Lessons The SRO and Project Team should develop a robust and comprehensive Stakeholder Management and Communication Plan. The project should consider a workshop to capture all Lessons Learned to date and ensure that the learning is embedded within all future development Review and implement project governance arrangements. Project reporting format should be reviewed. Observation? Something to consider in the next phase? Missing the basics and don’t know better Should know better Fundamental shortfall with minor impact Fundamental shortfall with major impact
  • 23. Copyright Projecting Success 2018 ‘Avoidability’ of lessons •Act of God, environmental factors •Unknown/unknowable external event •Unknown/knowable external event •Known external event •Internal decision or organisational constraint •Lesson identified or known but deemed irrelevant •Lesson identified or known but ignored due to other priorities/resourcing Unavoidable lesson But may be aware of emerging environmental conditions Avoidable lesson Priority, resourcing, SQEP or judgment call Strategic lesson Organisation proceeded knowing that strategic decisions may/will likely impact the project. Lesson learned was foreseeable and wasn’t mitigated.
  • 24. Copyright Projecting Success 2018 The Link Between Risk and Lessons Risk IssueLesson If the lesson is not acted upon it becomes a risk for the next project How many organisations link lessons learned and risk management? What is the correlation between risk drawdown and lessons learned? Tolerate Treat Transfer Terminate
  • 25. Copyright Projecting Success 2018 Projects: An Enabler or Primary Purpose? Project Duration Similarity Short Long SimilarDissimilar Major IT upgrades Business transformation Enabling Activity Office Move New office Call Centre Project Duration Similarity Short Long SimilarDissimilar Event management Major IT upgrades Business transformation Office Move Crossrail New office Primary Activity HS2 Call Centre Station refit Station build 1, 2, 3
  • 26. Copyright Projecting Success 2018 Leveraging Experience: Events Scotland Security Transport Ticketing Funding Marketing Infrastructure ……. Opportunity to recycle experience: • Capturing schedules, assumptions, risks and budgets. • Identifying areas of stability and uncertainty and which are likely to change. Management effort is then focused on areas of instability. • Understanding the effectiveness of management action associated with risks, assumptions and delivery. • Embedding members of a team into an existing project so that the learning can be recycled into the next project. “A 6-7year journey” Immovable deadlines • Context is critical in understanding application of experience • Cost over-runs tend to be associated with infrastructure • Organisational Capacity to leverage experience • International sharing of experience
  • 27. Copyright Projecting Success 2018 One Dataset. Different Perspectives Assurance reviewer Governance Supply chain Project team Next project Other organisations Process of personal promotion, personal reflection & learning for the next phase Holding to account Preparation for key gateway reviews Enabling the supply chain and improving efficiency Leveraging experience for aligned projects Leveraging experience for other organisations or other parts of ‘the group’
  • 28. Copyright Projecting Success 2018 A Tailored Approach Any approach to improving project delivery productivity must be tailored to the organisation: Stable workforce & suppliers Experience is ‘recycled’ Transient workforce. Churn in supply base Experience is fragmented Multiple and parallel implementations of similar projects Bespoke, unique projects delivered infrequently Experience is primary guide Process is primary guide Highly competitive where productivity is a major differentiator Public sector or monopoly, incremental improvement Cross fertilisation between departments Experience is typically siloed within the organisation Internal governance External regulation/governance Workflows, Wikis, Processes, Assurance Key considerations Knowledge sharing, project controls, lean Spectrum of approaches
  • 29. Copyright Projecting Success 2018 An Example: Crossrail
  • 30. Copyright Projecting Success 2018 Exhaust plume from project delivery An Example: Crossrail
  • 31. Copyright Projecting Success 2018 What Happens to the Data?
  • 32. Copyright Projecting Success 2018 An Realisable Vision
  • 33. Copyright Projecting Success 2018 Instinctive Behaviours System 1 System 1 is an automatic, fast and often unconscious way of thinking. •It is autonomous and efficient, requiring little energy or attention, •Is susceptical to biases and systematic errors. System 2 is an effortful, slow and controlled way of thinking. It requires energy and can’t work without attention but, once engaged, has the ability to filter the instincts of System 1 System 2 Nudge Theory We adjust our driving to the conditions of the road We adjust our speed if we know that others have experienced costly accidents VS System 1 and 2 thinking
  • 34. Copyright Projecting Success 2018 Leveraging the Connected Data Projects LessonsRisks$ Graph Data Stored in Silos Lesson X Draw down Cost impact Time impact Mitigate Cost Mitigate effective -ness Project 1 Project 2 Taxon- omy TechnicalSafetySecurity Technical issue Security Issue Safety Issue
  • 35. Copyright Projecting Success 2018 Exploitation of Data Actors Views User Stories Degree of fit ‘Perfect Data’ ‘Typical Data’ For most organisations, the ‘lessons learned’ process is only solving 25% of the requirement, at best. “As a Project Manager I want to be able to drill into lessons that I am interested in so that I can gain a better understanding of context, relevance and how the lesson may impact my own project”
  • 36. Copyright Projecting Success 2018 EVM data Resourcing Weather Supplier performance Dependencies Risks etc Real time update of assigned tasks WBS Elements Scheduling Corpus and Context Extract Triples Benchmarking Adaptive SchedulingRecommendations Scheduling
  • 37. Copyright Projecting Success 2018 A once through process Risk lifecycle Leveraging Risk Experience Connected risks Risks-Issues-Lessons Informed risk registers Risk trends Risk mitigations Risk budget Systemic Risk Risks
  • 39. Copyright Projecting Success 2018 So... What is Advanced Data Analytics
  • 40. Copyright Projecting Success 2018 Icons made by Freepik from www.flaticon.com Machine Learning: Bid Data – a worked example
  • 41. Copyright Projecting Success 2018 Bent Flyvbjerg’s work on Major Projects
  • 42. Copyright Projecting Success 2018 Bent Flyvbjerg’s work on Major Projects
  • 43. Copyright Projecting Success 2018 Bent Flyvbjerg’s work on Major Projects
  • 44. Copyright Projecting Success 2018 Counteracting Bias • Consistency/desirability bias • Recency effects • Human memory bias • Optimism bias • ‘Strategic Deception’ Data
  • 45. Copyright Projecting Success 2018 Fundamentally: • What is the predisposition of the work to variance? • Can we predict it? • How do we test for it? • How do we treat it and change the future? Evidence based, tempering against bias. Project DNA
  • 46. Copyright Projecting Success 2018 Barriers to Adoption Its not on the corporate ‘to do’ list • Lack of a shared vision • Lack of evidence to support the vision • Lack of skilled horsepower • Lack of data • Siloed • Poor quality • Understanding the investment case
  • 47. Copyright Projecting Success 2018 Summary • The majority of organisations in the sample are not leveraging experience • The opportunity to leverage experience is significant • Potential impact on project delivery productivity is huge (up to 30%) • The approaches do not differentiate between P3M and technical lessons. They are different! • Does your organisation believe there is value in leveraging past investments? • STOP box ticking processes and START to link value to your particular challenge • Pivot towards a data driven insights approach where evidence shapes future decisions • Deliver information and insights when required, in the right form, which are consumable • Supported by wikis, peer assists, communities of practice etc. • Machine learning is marching towards us which will be transformational. • We need to develop an approach to support it. "Those that fail to learn from history are doomed to repeat it."
  • 48. Copyright Projecting Success 2018 • Free to join • Free to attend • Crosses professional boundaries • Developing a community • Developing into a force for good Developing a Community
  • 49. Copyright Projecting Success 2018 Any questions, comments…. …. Or could you share your own experience?