Today’s Presentation Outline
 History
 Preparation
 Construction
 Safety and
Environment
 Design Evolution
 Rehabilitation
 Community
2
Leading Practice Drill Pad Methodology
History
 1900
3
Leading Practice Drill Pad Methodology
History
 1953
4
Leading Practice Drill Pad Methodology
History
 1990
5
Leading Practice Drill Pad Methodology
History
 Today
6
Leading Practice Drill Pad Methodology
History
 Stats
 How
many
drill
pads?
7
Leading Practice Drill Pad Methodology
Preparation
 Site selection and
layout
 Stakeholder
access negotiation
 Regulatory
documentation
 Contractor and
equipment
selection
8
Leading Practice Drill Pad Methodology
Site selection and layout
 Mt Carrington Drake
NSW gold-silver
 3000 historical holes
 Exploration and
resource targets
9
 Number of holes
 Angle and azimuth
 Ground check, peg
and photograph
 WRM – 2011
 60 pads,+10000m
Leading Practice Drill Pad Methodology
Site selection and layout
 Proactive
management of
impacts
 Initial ground
check
10
Leading Practice Drill Pad Methodology
Site selection and layout
11
 Potential for harm
• Tree overhang
• Buried assets
 Distance from
drainage
 Flora and fauna
 Slope of site
 Water supply
 Waste disposal
 Site specific
Leading Practice Drill Pad Methodology
Site selection and layout
 Flora and fauna
12
 Vulnerable bird
species
 Habitat trees –
Casuarina seed
cone count
 30 on ground is
critical
Leading Practice Drill Pad Methodology
Site selection and layout
 Flora and
fauna
Glossy Black
Cockatoo
Red Tailed
Cockatoo
13
Leading Practice Drill Pad Methodology
Stakeholder Access &
Negotiation
 Communication
 Regulatory
documentation
14
 Landowners
 Forests NSW
 Requirements
• Agreement
• S30
• SDN
• REF
• Mine Ops Plan
Leading Practice Drill Pad Methodology
Stakeholder Access &
Negotiation
15
 Administered
by Environment
division in
Resources and
Energy
 Liaising with
Forests NSW
establishes
requirements
for FMZ’s
Leading Practice Drill Pad Methodology
Contractors and Equipment
Selection – Drillers and Earthmovers
 Smallest footprint
possible
 Experience and
safety record
 Reliability and
communication
 Local knowledge
 Drill Management
Plan
16
Leading Practice Drill Pad Methodology
Construction
 Tree audit for
Forestry
 Payments for
larger trees
 Earthmoving
contractor shown
pad design
 15m x 10m plan
agreed
17
Leading Practice Drill Pad Methodology
Construction
 Track making that
minimises excavation
 Best chance for flora
regeneration
18
Leading Practice Drill Pad Methodology
Construction
 Storage of topsoil
and vegetative
matter
 Pad base set for
strata protection
 Sediment fencing
minimises
washaways in wet
weather
19
Leading Practice Drill Pad Methodology
Construction
 Plastic lining fitted
to capture
accidental fluid
spills
 Bunding around
perimeter to
contain potential
fluid spills
20
Leading Practice Drill Pad Methodology
Construction
 Coconut fibre
matting
provides good
working surface
 Minimises
hazards
 Absorbs
accidental spills
21
Leading Practice Drill Pad Methodology
Construction
 Barrier fencing
for visibility –
day and night
 Sign-off for
each pad
 Mobilise
equipment onto
site
22
Leading Practice Drill Pad Methodology
Safety & Environment
 Review all
aspects of setup
once all
equipment is
set up
 Confirm
prestart
checklist
23
Leading Practice Drill Pad Methodology
Safety & Environment
 Checklists
sign off
 Site Prep
 Size etc.
 Access
 Water
24
Leading Practice Drill Pad Methodology
Safety & Environment
 Site Prep
 Bunds
 Turnaround
 Sed fence
 Sketch
25
Leading Practice Drill Pad Methodology
Safety & Environment
 Rig setup
 PPE
 First aid
 Guards
 Documentation
26
Leading Practice Drill Pad Methodology
Safety & Environment
 Rig setup
 Comms.
 Fire ext.
 Containment
27
Leading Practice Drill Pad Methodology
Safety & Environment
 Rig Pack-up
 Removal
 Cap hole
 Pad and
access rehab
28
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
 REX Minerals
2008 – Hillside SA
 Wheat paddock
 Plastic and sand
 Adaptability of
method
 Tableland and
range forests
 Replace sand with
Coconut fibre
mats
29
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX Minerals
 REX Minerals
2008
 South Australia
 Hillside copper
 Wheat paddocks
 Flat terrain
 Cropping –
grazing land
30
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX Minerals
 Wheat paddock
 No surface
scrape
 Plastic cover
sheeting
 Sand on
plastic
31
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX Minerals
 Wheat paddock
 Bunding
 Barrier
fencing
32
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX Minerals
 Wheat paddock
 Whole set up
 Hay bales as
light and noise
barriers
33
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX / White Rock Minerals
 NE NSW 2009
 (State) Forest
and/or
undulating
terrain
 Excavation
 Plastic lining
 Sand on plastic
 Bunding
 Barrier fencing
 Sediment fencing
34
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
White Rock Minerals
 2010 program
issues
 Problems emerged
 Wet weather
 Sand washes away
in heavy rain
 Sand gets in
equipment
 Construction and
clean-up costs
escalated
35
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
White Rock Minerals
 2010-11 Solutions
discussed
 Needed to lessen
impact
 Smaller rig – smaller
pad
 Smaller excavator or
backhoe
 Replace sand with
coconut fibre matting
 Make Mats recyclable
36
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
White Rock Minerals
 2011 - Solutions
implemented
 Cost savings
 Use of mats up to 3
times
 No need to collect
sand and dispose
 Backhoe costs lower
per hour vs. excavator
 Speedier rehab
37
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
WRM / REX Minerals
 Solutions
successfully
implemented at
WRM
 Now used by
REX Minerals in
wheat
paddocks
38
Leading Practice Drill Pad Methodology
Evolution of Drill Pad Methodology
REX Minerals
 Solutions
implemented
 Easy and
speedy rehab
on pastures
and crop land
39
Leading Practice Drill Pad Methodology
Rehabilitation
 Discussions with
Forests NSW
 Landholders
 Re-use
disturbed
topsoil and
vegetative
matter
 Documentation
signoff
40
Leading Practice Drill Pad Methodology
Rehabilitation
 Example –
immediately
after
41
Leading Practice Drill Pad Methodology
Rehabilitation
 Example –
after 9
months
42
Leading Practice Drill Pad Methodology
Rehabilitation
 Example –
after 2
years
43
Leading Practice Drill Pad Methodology
Community
 Showcase
methods to
mines
inspectorate
 Community site
visit days
44
Leading Practice Drill Pad Methodology
Community
 Primary school
site visits
45
Leading Practice Drill Pad Methodology
In Summary
46
 Preparation
 Construction
 Safety and
Environment
 Design
continual
evolution
 Rehabilitation
 Community
Leading Practice Drill Pad Methodology
Thank You
47

More Related Content

Similar to WRM_JMarinelli_LeadPracDrillPadMeth_Final

2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design IntroductionTheodore Scott
 
Mining Practices With Objective Of Sustainability
Mining Practices With Objective Of SustainabilityMining Practices With Objective Of Sustainability
Mining Practices With Objective Of Sustainabilitypartha sharma
 
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTION
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTIONGREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTION
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTIONiQHub
 
Mine propcessdisposal
Mine propcessdisposalMine propcessdisposal
Mine propcessdisposalDC Graphics
 
Parking Forest Materials
Parking Forest MaterialsParking Forest Materials
Parking Forest MaterialsMaria Cahill
 
Performance of geosynthetic filters in treatment of urban storm water runoff
Performance of geosynthetic filters in treatment of urban storm water runoffPerformance of geosynthetic filters in treatment of urban storm water runoff
Performance of geosynthetic filters in treatment of urban storm water runoffAnchit Agrawal
 
Disc Seeders in Conservation Agriculture - An Australian survey
Disc Seeders in Conservation Agriculture - An Australian surveyDisc Seeders in Conservation Agriculture - An Australian survey
Disc Seeders in Conservation Agriculture - An Australian surveyJoanna Hicks
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionChris Bridges
 
Presentation for public information centres
Presentation for public information centresPresentation for public information centres
Presentation for public information centresknelischer
 
HSE-BMS-003 Environmental Management.ppt
HSE-BMS-003 Environmental Management.pptHSE-BMS-003 Environmental Management.ppt
HSE-BMS-003 Environmental Management.pptPokikoMikoto
 
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Sam Stribling
 
new technique of erosion control
new technique of erosion controlnew technique of erosion control
new technique of erosion controlsurbhi lokhande
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfKeat Wei, Gavin Chung
 
Urban Water Quality Issues - Green Design & Development
Urban Water Quality Issues - Green Design & DevelopmentUrban Water Quality Issues - Green Design & Development
Urban Water Quality Issues - Green Design & Developmentnacaa
 
Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Maccaferri World
 

Similar to WRM_JMarinelli_LeadPracDrillPadMeth_Final (20)

2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction
 
Mining Practices With Objective Of Sustainability
Mining Practices With Objective Of SustainabilityMining Practices With Objective Of Sustainability
Mining Practices With Objective Of Sustainability
 
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTION
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTIONGREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTION
GREEN DEEP SEA MINING – MOVING AHEAD WITH PRECAUTION
 
Mine propcessdisposal
Mine propcessdisposalMine propcessdisposal
Mine propcessdisposal
 
Parking Forest Materials
Parking Forest MaterialsParking Forest Materials
Parking Forest Materials
 
On-farm measures for sediment control: options, impacts and challenges
On-farm measures for sediment control: options, impacts and challengesOn-farm measures for sediment control: options, impacts and challenges
On-farm measures for sediment control: options, impacts and challenges
 
Performance of geosynthetic filters in treatment of urban storm water runoff
Performance of geosynthetic filters in treatment of urban storm water runoffPerformance of geosynthetic filters in treatment of urban storm water runoff
Performance of geosynthetic filters in treatment of urban storm water runoff
 
Disc Seeders in Conservation Agriculture - An Australian survey
Disc Seeders in Conservation Agriculture - An Australian surveyDisc Seeders in Conservation Agriculture - An Australian survey
Disc Seeders in Conservation Agriculture - An Australian survey
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway construction
 
Valgma losses
Valgma lossesValgma losses
Valgma losses
 
Valgma losses
Valgma lossesValgma losses
Valgma losses
 
Presentation for public information centres
Presentation for public information centresPresentation for public information centres
Presentation for public information centres
 
Green Infrastructure Maintenance Workshop
Green Infrastructure Maintenance WorkshopGreen Infrastructure Maintenance Workshop
Green Infrastructure Maintenance Workshop
 
HSE-BMS-003 Environmental Management.ppt
HSE-BMS-003 Environmental Management.pptHSE-BMS-003 Environmental Management.ppt
HSE-BMS-003 Environmental Management.ppt
 
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages...
 
new technique of erosion control
new technique of erosion controlnew technique of erosion control
new technique of erosion control
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdf
 
Urban Water Quality Issues - Green Design & Development
Urban Water Quality Issues - Green Design & DevelopmentUrban Water Quality Issues - Green Design & Development
Urban Water Quality Issues - Green Design & Development
 
Hank Rawlins
Hank RawlinsHank Rawlins
Hank Rawlins
 
Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017
 

WRM_JMarinelli_LeadPracDrillPadMeth_Final

  • 1. Leading Practice Drill Pad Methodology Julius Marinelli Consultant Exploration Geologist 1 Leading Practice Drill Pad Methodology
  • 2. Leading Practice Drill Pad Methodology Today’s Presentation Outline  History  Preparation  Construction  Safety and Environment  Design Evolution  Rehabilitation  Community 2
  • 3. Leading Practice Drill Pad Methodology History  1900 3
  • 4. Leading Practice Drill Pad Methodology History  1953 4
  • 5. Leading Practice Drill Pad Methodology History  1990 5
  • 6. Leading Practice Drill Pad Methodology History  Today 6
  • 7. Leading Practice Drill Pad Methodology History  Stats  How many drill pads? 7
  • 8. Leading Practice Drill Pad Methodology Preparation  Site selection and layout  Stakeholder access negotiation  Regulatory documentation  Contractor and equipment selection 8
  • 9. Leading Practice Drill Pad Methodology Site selection and layout  Mt Carrington Drake NSW gold-silver  3000 historical holes  Exploration and resource targets 9  Number of holes  Angle and azimuth  Ground check, peg and photograph  WRM – 2011  60 pads,+10000m
  • 10. Leading Practice Drill Pad Methodology Site selection and layout  Proactive management of impacts  Initial ground check 10
  • 11. Leading Practice Drill Pad Methodology Site selection and layout 11  Potential for harm • Tree overhang • Buried assets  Distance from drainage  Flora and fauna  Slope of site  Water supply  Waste disposal  Site specific
  • 12. Leading Practice Drill Pad Methodology Site selection and layout  Flora and fauna 12  Vulnerable bird species  Habitat trees – Casuarina seed cone count  30 on ground is critical
  • 13. Leading Practice Drill Pad Methodology Site selection and layout  Flora and fauna Glossy Black Cockatoo Red Tailed Cockatoo 13
  • 14. Leading Practice Drill Pad Methodology Stakeholder Access & Negotiation  Communication  Regulatory documentation 14  Landowners  Forests NSW  Requirements • Agreement • S30 • SDN • REF • Mine Ops Plan
  • 15. Leading Practice Drill Pad Methodology Stakeholder Access & Negotiation 15  Administered by Environment division in Resources and Energy  Liaising with Forests NSW establishes requirements for FMZ’s
  • 16. Leading Practice Drill Pad Methodology Contractors and Equipment Selection – Drillers and Earthmovers  Smallest footprint possible  Experience and safety record  Reliability and communication  Local knowledge  Drill Management Plan 16
  • 17. Leading Practice Drill Pad Methodology Construction  Tree audit for Forestry  Payments for larger trees  Earthmoving contractor shown pad design  15m x 10m plan agreed 17
  • 18. Leading Practice Drill Pad Methodology Construction  Track making that minimises excavation  Best chance for flora regeneration 18
  • 19. Leading Practice Drill Pad Methodology Construction  Storage of topsoil and vegetative matter  Pad base set for strata protection  Sediment fencing minimises washaways in wet weather 19
  • 20. Leading Practice Drill Pad Methodology Construction  Plastic lining fitted to capture accidental fluid spills  Bunding around perimeter to contain potential fluid spills 20
  • 21. Leading Practice Drill Pad Methodology Construction  Coconut fibre matting provides good working surface  Minimises hazards  Absorbs accidental spills 21
  • 22. Leading Practice Drill Pad Methodology Construction  Barrier fencing for visibility – day and night  Sign-off for each pad  Mobilise equipment onto site 22
  • 23. Leading Practice Drill Pad Methodology Safety & Environment  Review all aspects of setup once all equipment is set up  Confirm prestart checklist 23
  • 24. Leading Practice Drill Pad Methodology Safety & Environment  Checklists sign off  Site Prep  Size etc.  Access  Water 24
  • 25. Leading Practice Drill Pad Methodology Safety & Environment  Site Prep  Bunds  Turnaround  Sed fence  Sketch 25
  • 26. Leading Practice Drill Pad Methodology Safety & Environment  Rig setup  PPE  First aid  Guards  Documentation 26
  • 27. Leading Practice Drill Pad Methodology Safety & Environment  Rig setup  Comms.  Fire ext.  Containment 27
  • 28. Leading Practice Drill Pad Methodology Safety & Environment  Rig Pack-up  Removal  Cap hole  Pad and access rehab 28
  • 29. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology  REX Minerals 2008 – Hillside SA  Wheat paddock  Plastic and sand  Adaptability of method  Tableland and range forests  Replace sand with Coconut fibre mats 29
  • 30. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX Minerals  REX Minerals 2008  South Australia  Hillside copper  Wheat paddocks  Flat terrain  Cropping – grazing land 30
  • 31. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX Minerals  Wheat paddock  No surface scrape  Plastic cover sheeting  Sand on plastic 31
  • 32. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX Minerals  Wheat paddock  Bunding  Barrier fencing 32
  • 33. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX Minerals  Wheat paddock  Whole set up  Hay bales as light and noise barriers 33
  • 34. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX / White Rock Minerals  NE NSW 2009  (State) Forest and/or undulating terrain  Excavation  Plastic lining  Sand on plastic  Bunding  Barrier fencing  Sediment fencing 34
  • 35. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology White Rock Minerals  2010 program issues  Problems emerged  Wet weather  Sand washes away in heavy rain  Sand gets in equipment  Construction and clean-up costs escalated 35
  • 36. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology White Rock Minerals  2010-11 Solutions discussed  Needed to lessen impact  Smaller rig – smaller pad  Smaller excavator or backhoe  Replace sand with coconut fibre matting  Make Mats recyclable 36
  • 37. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology White Rock Minerals  2011 - Solutions implemented  Cost savings  Use of mats up to 3 times  No need to collect sand and dispose  Backhoe costs lower per hour vs. excavator  Speedier rehab 37
  • 38. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology WRM / REX Minerals  Solutions successfully implemented at WRM  Now used by REX Minerals in wheat paddocks 38
  • 39. Leading Practice Drill Pad Methodology Evolution of Drill Pad Methodology REX Minerals  Solutions implemented  Easy and speedy rehab on pastures and crop land 39
  • 40. Leading Practice Drill Pad Methodology Rehabilitation  Discussions with Forests NSW  Landholders  Re-use disturbed topsoil and vegetative matter  Documentation signoff 40
  • 41. Leading Practice Drill Pad Methodology Rehabilitation  Example – immediately after 41
  • 42. Leading Practice Drill Pad Methodology Rehabilitation  Example – after 9 months 42
  • 43. Leading Practice Drill Pad Methodology Rehabilitation  Example – after 2 years 43
  • 44. Leading Practice Drill Pad Methodology Community  Showcase methods to mines inspectorate  Community site visit days 44
  • 45. Leading Practice Drill Pad Methodology Community  Primary school site visits 45
  • 46. Leading Practice Drill Pad Methodology In Summary 46  Preparation  Construction  Safety and Environment  Design continual evolution  Rehabilitation  Community
  • 47. Leading Practice Drill Pad Methodology Thank You 47