Primer On Application For Exploration Permit (EP)
(For application filed on August 26, 2005, or thereafter)
NOTE: This Primer is based on Republic Act No. 7942, i.e., “The Philippine Mining Act of 1995” and its
implementing rules and regulations.
What is an Exploration Permit?
An Exploration Permit (EP) is an initial mode of entry in mineral exploration allowing a
Qualified Person to undertake exploration activities for mineral resources in certain areas
open to mining in the country.
Who is a Qualified Person?
A Qualified Person is:
(a) any Filipino citizen of legal age and with capacity to contract;
(b) a Filipino-owned Corporation, Partnership, Association or Cooperative, at least sixty
percent (60%) of the capital is owned by Filipino citizens, organized or authorized for the
purpose of engaging in mining with technical and financial capability to undertake
mineral resources development and duly registered in accordance with the law; or
(c) a foreign-owned Corporation, Partnership, Association or Cooperative duly registered in
accordance with law and in which less than fifty percent (50%) of the capital is owned
by Filipino citizens.
How much area is granted for an Exploration Permit?
Each Qualified Person is limited to the following maximum size of area to apply for or
hold at any one time under an EP.
QUALIFIED
PERSON
ONSHORE
( in any one Province)
ONSHORE
(In the entire Philippines)
OFFSHORE
(In the entire Philippines,
beyond five hundred meters
[500 m] from the mean low
tide level)
Individual 20 meridional blocks
or 1,620 hectares
40 meridional blocks
or 3,240 hectares
100 meridional blocks or
8,100 hectares
Corporation/
Partnership/
Association/
Cooperative
200 meridional blocks
or 16,200 hectares
400 meridional blocks
or 32,400 hectares
1,000 meridional blocks
or 81,000 hectares
Note: One meridional block is equivalent to approximately 81 hectares.
What is the term of an Exploration Permit?
The term of an Exploration Permit is for a period of two (2) years from date of its
issuance, renewable for like periods but not to exceed a total term of four (4) years for
nonmetallic mineral exploration or six (6) years for metallic mineral exploration.
Renewal of the Permit is allowed if the Permittee has complied with all the terms and
conditions of the Permit and he/she/it has not been found guilty of violation of any provision of
Republic Act No. 7942 or the “The Philippine Mining Act of 1995” and its implementing rules
and regulations.
Likewise, the conduct of a feasibility study and filing of the declaration of mining project
feasibility are undertaken during the term of the Permit.
What are the mandatory requirements in the acceptance of an EP
application?
An EP application shall be filed in the Mines and Geosciences Bureau (MGB)
Regional Office (RO) concerned, for mineral and non-mineral reservation areas, using the
prescribed form (MGB Form No. 05-1) through payment of the filing fee and submission of
five (5) sets of the following mandatory requirements:
Location map/sketch plan of the proposed permit area showing its geographic
coordinates/ meridional block(s) and boundaries in relation to major environmental
features and other projects using a National Mapping and Resource Information
Authority (NAMRIA) topographic map in a scale of 1:50,000 duly prepared, signed and
sealed by a deputized Geodetic Engineer;
.
Two-year Exploration Work Program (MGB Form No. 5-4) duly prepared, signed
and sealed by a licensed Mining Engineer or Geologist;
Proof of technical competence, including, among others, curricula vitae and track
records in exploration and environmental management of the technical personnel who
shall undertake the activities in accordance with the submitted Exploration Work
Program;
Proof of financial capability to undertake the Exploration Work Program, such as the
following:
1. For an individual – Copy of income tax return for the preceding year and proof of
bank deposit or credit line in the amount of at least Two Million Five Hundred
Thousand Pesos (PhP 2,500,000.00) and
2. For a corporation, partnership, association or cooperative - Latest audited
financial statement and, where applicable, Annual Report for the preceding
year, credit line(s), bank guarantee(s) and/or similar negotiable instruments;
Photocopy of Articles of Incorporation/Partnership/Association, By-Laws and
Certificate of Registration, duly certified by the Securities and Exchange Commission
or authorized Government agency(ies) concerned, for a corporation, partnership,
association or cooperative, or Certification from the Bureau/Regional Office concerned
that said documents are duly registered in that Office; and
Affidavit of Undertaking for corporation, partnership, association or cooperatives
(Annex A of DENR Memorandum Order No. 99-10) declaring:
1. The list of applications filed and the Mining Permit(s)/Contract(s) granted to the
applicants, including the corresponding hectarage and location of the areas,
disaggregated on a per province basis; and
2. The list of other Applicant(s)/Contractor(s)/Permittee(s) in which more than
seventy percent (70%) of the authorized capital stock is held by stockholders of
the applicant, including the corresponding hectarage, disaggregated on a per
province basis.
Please note that any application with incomplete mandatory requirements shall not be
accepted.
What are the other additional requirements after an EP application
is filed?
The following additional requirements shall be required from the applicant submitted after
the acceptance of the application but prior to the issuance of the Exploration Permit:
Certificate of Environmental Management and Community Relations Record
(CEMCRR)/Certificate of Exemption;
Environmental Work Program (MGB Form No. 16-1 or MGB Form No. 16-1A). If
the applicant is a member of the Chamber of Mines of the Philippines, Inc. (COMP),
he/she/it must submit Certificate of Good Membership Standing, which is a necessary
requirement before the EWP can be evaluated.
Certification Precondition from the National Commission on Indigenous Peoples
attesting that –
a. The proposed permit area does not overlap any ancestral land/domain claim in case
of non-Indigenous People (IP) area; or
b. The Free and Prior Informed Consent (FPIC) has been issued by the Indigenous
Cultural Community (ICC)/IP concerned.
For OFFSHORE applications, the following additional requirements shall be submitted:
Name, port of registry, tonnage, type and class of survey vessel(s) or platform(s). If a
foreign vessel is to be used, the expected date of first entry or appearance and final
departure of the survey vessel shall be provided and the necessary clearances obtained
A certification from the Coast and Geodetic Survey Department of NAMRIA that the
proposed Exploration Work Program was duly registered to provide update in the
publication of “Notice to Mariners” together with a list of safety measures to be
regularly undertaken to ensure the safety of navigation at sea and prevent accident
An agreement to:
1. Properly identify all installations, vessels and other crafts involved in exploration
recognizable to all vessels within reasonable distance;
2. Notify the Bureau 30 calendar days prior to the intention to remove all scientific
installations or equipment and apparatus; and
3. Allow the Bureau’s authorized personnel, the Philippine Coast Guard and other
authorized persons during reasonable hours to board the vessel(s) while within
the Exclusive Economic Zone.
Other supporting documents that may required by the Mines and Geosciences
Bureau.
EP PROCESS FLOWCHART
PRELIMINARY EVALUATION
PLOTTING DOCUMENT EVALUATION
AREA STATUS AND
CLEARANCE
NCIP
CERTIFICATION
PUBLICATION,
POSTING,
RADIO ANNOUNCEMENT AND
SECURING OF CERTIFICATIONS
INITIAL EVALUATION
ENDORSEMENT TO MGB CENTRAL OFFICE
FINAL EVALUATION AND APPROVAL
FILING IN MGB REGIONAL OFFICE
(Submission of MGB Form No. 05-1 and 5 sets of
mandatory requirements and payment of filing
NUMBERING, REGISTRATION AND
RELEASING BY MGB REGIONAL
OFFICE

More Related Content

What's hot

Geophysical prospecting
Geophysical prospecting Geophysical prospecting
Geophysical prospecting Spondan Bora
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining systemSrimontorumpa
 
Mining and Resources Law Review 2020
Mining and Resources Law Review 2020Mining and Resources Law Review 2020
Mining and Resources Law Review 2020Fernando Penarroyo
 
Excursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal MinesExcursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal MinesAnurag Jha
 
Mining Situation in the Philippines
Mining Situation in the Philippines Mining Situation in the Philippines
Mining Situation in the Philippines Kalikasan Partylist
 
MINE MANAGEMENT LEGISLATION-II_short notes.pdf
MINE MANAGEMENT LEGISLATION-II_short notes.pdfMINE MANAGEMENT LEGISLATION-II_short notes.pdf
MINE MANAGEMENT LEGISLATION-II_short notes.pdfKopparthiJanardhan1
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELAIndrajeetKumar110
 
Surface mining methods
Surface mining methodsSurface mining methods
Surface mining methodsSafdar Ali
 
Mining and environmental impact
Mining and environmental impactMining and environmental impact
Mining and environmental impactGhassan Hadi
 
stages of exploration
stages of explorationstages of exploration
stages of explorationNgatcha Bryan
 

What's hot (20)

Geophysical prospecting
Geophysical prospecting Geophysical prospecting
Geophysical prospecting
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining system
 
Stages in life of mine
Stages in life of mineStages in life of mine
Stages in life of mine
 
Square set stoping
Square set stopingSquare set stoping
Square set stoping
 
Lecture 4: Underground Mining
Lecture 4: Underground MiningLecture 4: Underground Mining
Lecture 4: Underground Mining
 
Mining and Resources Law Review 2020
Mining and Resources Law Review 2020Mining and Resources Law Review 2020
Mining and Resources Law Review 2020
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Excursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal MinesExcursion Report of Jhanjhra Coal Mines
Excursion Report of Jhanjhra Coal Mines
 
Topic 2 the mining cycle
Topic 2  the mining cycleTopic 2  the mining cycle
Topic 2 the mining cycle
 
Mining Situation in the Philippines
Mining Situation in the Philippines Mining Situation in the Philippines
Mining Situation in the Philippines
 
Lecture 2: Prospecting to Proving
Lecture 2: Prospecting to ProvingLecture 2: Prospecting to Proving
Lecture 2: Prospecting to Proving
 
MINE MANAGEMENT LEGISLATION-II_short notes.pdf
MINE MANAGEMENT LEGISLATION-II_short notes.pdfMINE MANAGEMENT LEGISLATION-II_short notes.pdf
MINE MANAGEMENT LEGISLATION-II_short notes.pdf
 
Cut and Fill Stoping
Cut and Fill StopingCut and Fill Stoping
Cut and Fill Stoping
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
 
Stages of mining Development and Exploitation
Stages of mining Development and ExploitationStages of mining Development and Exploitation
Stages of mining Development and Exploitation
 
What is-geophysics
What is-geophysicsWhat is-geophysics
What is-geophysics
 
Surface mining methods
Surface mining methodsSurface mining methods
Surface mining methods
 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
 
Mining and environmental impact
Mining and environmental impactMining and environmental impact
Mining and environmental impact
 
stages of exploration
stages of explorationstages of exploration
stages of exploration
 

Similar to Guide Exploration Permit Application

DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptx
DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptxDAO 2004-24 - FORESHORE LEASE AGREEMENT.pptx
DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptxPhillisYvonMarshBagu
 
293895881-Petroleum-Act REPORT REPORT.pptx
293895881-Petroleum-Act REPORT REPORT.pptx293895881-Petroleum-Act REPORT REPORT.pptx
293895881-Petroleum-Act REPORT REPORT.pptxabegailbalbero1
 
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...Kevin Perry
 
Manual mineriaingles
Manual mineriainglesManual mineriaingles
Manual mineriainglesNilton Huaita
 
Colombian environmental regime
Colombian environmental regimeColombian environmental regime
Colombian environmental regimeProColombia
 
2010_06_24_Prospectus.pdf
2010_06_24_Prospectus.pdf2010_06_24_Prospectus.pdf
2010_06_24_Prospectus.pdfJESUS SALAMANCA
 
FAO 197-1 s. 2012.Administratives order
FAO 197-1  s. 2012.Administratives orderFAO 197-1  s. 2012.Administratives order
FAO 197-1 s. 2012.Administratives orderfishpondleasingbfar9
 
Mines and GeoScience Bureau - Region 7 Philippines
Mines and GeoScience Bureau - Region 7 PhilippinesMines and GeoScience Bureau - Region 7 Philippines
Mines and GeoScience Bureau - Region 7 PhilippinesPhilippine Press Institute
 
Colombian Environmental Regime
Colombian Environmental RegimeColombian Environmental Regime
Colombian Environmental RegimeProColombia
 
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...Proposed Mining Engineering Profession Bill and its Implications to Geotherma...
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...Fernando Penarroyo
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectVR M
 
FAO 197-1 - FOR REVIEW.administrative re
FAO 197-1 - FOR REVIEW.administrative reFAO 197-1 - FOR REVIEW.administrative re
FAO 197-1 - FOR REVIEW.administrative refishpondleasingbfar9
 
Ohio ODNR Forced Pooling ("Unitization") Guidelines
Ohio ODNR Forced Pooling ("Unitization") GuidelinesOhio ODNR Forced Pooling ("Unitization") Guidelines
Ohio ODNR Forced Pooling ("Unitization") GuidelinesMarcellus Drilling News
 
Mexico_Round_One_Fourth_Public_Bid
Mexico_Round_One_Fourth_Public_BidMexico_Round_One_Fourth_Public_Bid
Mexico_Round_One_Fourth_Public_BidThomas Heather
 
New microsoft word document (2)
New microsoft word document (2)New microsoft word document (2)
New microsoft word document (2)BABLI1973
 
Colombian environmental regime 2018
Colombian environmental regime 2018Colombian environmental regime 2018
Colombian environmental regime 2018ProColombia
 
Training Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of FormsTraining Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of FormsBananaIP Counsels
 
IVMP Procedures - revised
IVMP Procedures - revisedIVMP Procedures - revised
IVMP Procedures - revisedRenee Forque
 
Ancestral lands and icc areas
Ancestral lands and icc areasAncestral lands and icc areas
Ancestral lands and icc areasAbdel Dimapunong
 

Similar to Guide Exploration Permit Application (20)

DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptx
DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptxDAO 2004-24 - FORESHORE LEASE AGREEMENT.pptx
DAO 2004-24 - FORESHORE LEASE AGREEMENT.pptx
 
293895881-Petroleum-Act REPORT REPORT.pptx
293895881-Petroleum-Act REPORT REPORT.pptx293895881-Petroleum-Act REPORT REPORT.pptx
293895881-Petroleum-Act REPORT REPORT.pptx
 
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...
Beeching, Thomas, Conestoga-Rovers & Associates, Illinois Hydraulic Fracturin...
 
Manual mineriaingles
Manual mineriainglesManual mineriaingles
Manual mineriaingles
 
Colombian environmental regime
Colombian environmental regimeColombian environmental regime
Colombian environmental regime
 
2010_06_24_Prospectus.pdf
2010_06_24_Prospectus.pdf2010_06_24_Prospectus.pdf
2010_06_24_Prospectus.pdf
 
FAO 197-1 s. 2012.Administratives order
FAO 197-1  s. 2012.Administratives orderFAO 197-1  s. 2012.Administratives order
FAO 197-1 s. 2012.Administratives order
 
Mines and GeoScience Bureau - Region 7 Philippines
Mines and GeoScience Bureau - Region 7 PhilippinesMines and GeoScience Bureau - Region 7 Philippines
Mines and GeoScience Bureau - Region 7 Philippines
 
Colombian Environmental Regime
Colombian Environmental RegimeColombian Environmental Regime
Colombian Environmental Regime
 
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...Proposed Mining Engineering Profession Bill and its Implications to Geotherma...
Proposed Mining Engineering Profession Bill and its Implications to Geotherma...
 
Dao 2015 07
Dao 2015 07Dao 2015 07
Dao 2015 07
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
 
FAO 197-1 - FOR REVIEW.administrative re
FAO 197-1 - FOR REVIEW.administrative reFAO 197-1 - FOR REVIEW.administrative re
FAO 197-1 - FOR REVIEW.administrative re
 
Ohio ODNR Forced Pooling ("Unitization") Guidelines
Ohio ODNR Forced Pooling ("Unitization") GuidelinesOhio ODNR Forced Pooling ("Unitization") Guidelines
Ohio ODNR Forced Pooling ("Unitization") Guidelines
 
Mexico_Round_One_Fourth_Public_Bid
Mexico_Round_One_Fourth_Public_BidMexico_Round_One_Fourth_Public_Bid
Mexico_Round_One_Fourth_Public_Bid
 
New microsoft word document (2)
New microsoft word document (2)New microsoft word document (2)
New microsoft word document (2)
 
Colombian environmental regime 2018
Colombian environmental regime 2018Colombian environmental regime 2018
Colombian environmental regime 2018
 
Training Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of FormsTraining Session: 1 Indian Patent Process: Study of Forms
Training Session: 1 Indian Patent Process: Study of Forms
 
IVMP Procedures - revised
IVMP Procedures - revisedIVMP Procedures - revised
IVMP Procedures - revised
 
Ancestral lands and icc areas
Ancestral lands and icc areasAncestral lands and icc areas
Ancestral lands and icc areas
 

Recently uploaded

如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书Fir L
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一jr6r07mb
 
如何办理美国波士顿大学(BU)毕业证学位证书
如何办理美国波士顿大学(BU)毕业证学位证书如何办理美国波士顿大学(BU)毕业证学位证书
如何办理美国波士顿大学(BU)毕业证学位证书Fir L
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书1k98h0e1
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书Fs Las
 
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书SD DS
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxKUHANARASARATNAM1
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书srst S
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书Fir sss
 
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfMilind Agarwal
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书Fir sss
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 
Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesHome Tax Saver
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书Fir sss
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书SD DS
 

Recently uploaded (20)

如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
 
如何办理美国波士顿大学(BU)毕业证学位证书
如何办理美国波士顿大学(BU)毕业证学位证书如何办理美国波士顿大学(BU)毕业证学位证书
如何办理美国波士顿大学(BU)毕业证学位证书
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
 
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
如何办理(CQU毕业证书)中央昆士兰大学毕业证学位证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书
 
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书
 
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 
young Call Girls in Pusa Road🔝 9953330565 🔝 escort Service
young Call Girls in  Pusa Road🔝 9953330565 🔝 escort Serviceyoung Call Girls in  Pusa Road🔝 9953330565 🔝 escort Service
young Call Girls in Pusa Road🔝 9953330565 🔝 escort Service
 
Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax Rates
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
 

Guide Exploration Permit Application

  • 1. Primer On Application For Exploration Permit (EP) (For application filed on August 26, 2005, or thereafter) NOTE: This Primer is based on Republic Act No. 7942, i.e., “The Philippine Mining Act of 1995” and its implementing rules and regulations. What is an Exploration Permit? An Exploration Permit (EP) is an initial mode of entry in mineral exploration allowing a Qualified Person to undertake exploration activities for mineral resources in certain areas open to mining in the country. Who is a Qualified Person? A Qualified Person is: (a) any Filipino citizen of legal age and with capacity to contract; (b) a Filipino-owned Corporation, Partnership, Association or Cooperative, at least sixty percent (60%) of the capital is owned by Filipino citizens, organized or authorized for the purpose of engaging in mining with technical and financial capability to undertake mineral resources development and duly registered in accordance with the law; or (c) a foreign-owned Corporation, Partnership, Association or Cooperative duly registered in accordance with law and in which less than fifty percent (50%) of the capital is owned by Filipino citizens. How much area is granted for an Exploration Permit? Each Qualified Person is limited to the following maximum size of area to apply for or hold at any one time under an EP. QUALIFIED PERSON ONSHORE ( in any one Province) ONSHORE (In the entire Philippines) OFFSHORE (In the entire Philippines, beyond five hundred meters [500 m] from the mean low tide level) Individual 20 meridional blocks or 1,620 hectares 40 meridional blocks or 3,240 hectares 100 meridional blocks or 8,100 hectares Corporation/ Partnership/ Association/ Cooperative 200 meridional blocks or 16,200 hectares 400 meridional blocks or 32,400 hectares 1,000 meridional blocks or 81,000 hectares Note: One meridional block is equivalent to approximately 81 hectares.
  • 2. What is the term of an Exploration Permit? The term of an Exploration Permit is for a period of two (2) years from date of its issuance, renewable for like periods but not to exceed a total term of four (4) years for nonmetallic mineral exploration or six (6) years for metallic mineral exploration. Renewal of the Permit is allowed if the Permittee has complied with all the terms and conditions of the Permit and he/she/it has not been found guilty of violation of any provision of Republic Act No. 7942 or the “The Philippine Mining Act of 1995” and its implementing rules and regulations. Likewise, the conduct of a feasibility study and filing of the declaration of mining project feasibility are undertaken during the term of the Permit. What are the mandatory requirements in the acceptance of an EP application? An EP application shall be filed in the Mines and Geosciences Bureau (MGB) Regional Office (RO) concerned, for mineral and non-mineral reservation areas, using the prescribed form (MGB Form No. 05-1) through payment of the filing fee and submission of five (5) sets of the following mandatory requirements: Location map/sketch plan of the proposed permit area showing its geographic coordinates/ meridional block(s) and boundaries in relation to major environmental features and other projects using a National Mapping and Resource Information Authority (NAMRIA) topographic map in a scale of 1:50,000 duly prepared, signed and sealed by a deputized Geodetic Engineer; . Two-year Exploration Work Program (MGB Form No. 5-4) duly prepared, signed and sealed by a licensed Mining Engineer or Geologist; Proof of technical competence, including, among others, curricula vitae and track records in exploration and environmental management of the technical personnel who shall undertake the activities in accordance with the submitted Exploration Work Program; Proof of financial capability to undertake the Exploration Work Program, such as the following: 1. For an individual – Copy of income tax return for the preceding year and proof of bank deposit or credit line in the amount of at least Two Million Five Hundred Thousand Pesos (PhP 2,500,000.00) and 2. For a corporation, partnership, association or cooperative - Latest audited financial statement and, where applicable, Annual Report for the preceding year, credit line(s), bank guarantee(s) and/or similar negotiable instruments;
  • 3. Photocopy of Articles of Incorporation/Partnership/Association, By-Laws and Certificate of Registration, duly certified by the Securities and Exchange Commission or authorized Government agency(ies) concerned, for a corporation, partnership, association or cooperative, or Certification from the Bureau/Regional Office concerned that said documents are duly registered in that Office; and Affidavit of Undertaking for corporation, partnership, association or cooperatives (Annex A of DENR Memorandum Order No. 99-10) declaring: 1. The list of applications filed and the Mining Permit(s)/Contract(s) granted to the applicants, including the corresponding hectarage and location of the areas, disaggregated on a per province basis; and 2. The list of other Applicant(s)/Contractor(s)/Permittee(s) in which more than seventy percent (70%) of the authorized capital stock is held by stockholders of the applicant, including the corresponding hectarage, disaggregated on a per province basis. Please note that any application with incomplete mandatory requirements shall not be accepted. What are the other additional requirements after an EP application is filed? The following additional requirements shall be required from the applicant submitted after the acceptance of the application but prior to the issuance of the Exploration Permit: Certificate of Environmental Management and Community Relations Record (CEMCRR)/Certificate of Exemption; Environmental Work Program (MGB Form No. 16-1 or MGB Form No. 16-1A). If the applicant is a member of the Chamber of Mines of the Philippines, Inc. (COMP), he/she/it must submit Certificate of Good Membership Standing, which is a necessary requirement before the EWP can be evaluated. Certification Precondition from the National Commission on Indigenous Peoples attesting that – a. The proposed permit area does not overlap any ancestral land/domain claim in case of non-Indigenous People (IP) area; or b. The Free and Prior Informed Consent (FPIC) has been issued by the Indigenous Cultural Community (ICC)/IP concerned. For OFFSHORE applications, the following additional requirements shall be submitted: Name, port of registry, tonnage, type and class of survey vessel(s) or platform(s). If a foreign vessel is to be used, the expected date of first entry or appearance and final departure of the survey vessel shall be provided and the necessary clearances obtained
  • 4. A certification from the Coast and Geodetic Survey Department of NAMRIA that the proposed Exploration Work Program was duly registered to provide update in the publication of “Notice to Mariners” together with a list of safety measures to be regularly undertaken to ensure the safety of navigation at sea and prevent accident An agreement to: 1. Properly identify all installations, vessels and other crafts involved in exploration recognizable to all vessels within reasonable distance; 2. Notify the Bureau 30 calendar days prior to the intention to remove all scientific installations or equipment and apparatus; and 3. Allow the Bureau’s authorized personnel, the Philippine Coast Guard and other authorized persons during reasonable hours to board the vessel(s) while within the Exclusive Economic Zone. Other supporting documents that may required by the Mines and Geosciences Bureau.
  • 5. EP PROCESS FLOWCHART PRELIMINARY EVALUATION PLOTTING DOCUMENT EVALUATION AREA STATUS AND CLEARANCE NCIP CERTIFICATION PUBLICATION, POSTING, RADIO ANNOUNCEMENT AND SECURING OF CERTIFICATIONS INITIAL EVALUATION ENDORSEMENT TO MGB CENTRAL OFFICE FINAL EVALUATION AND APPROVAL FILING IN MGB REGIONAL OFFICE (Submission of MGB Form No. 05-1 and 5 sets of mandatory requirements and payment of filing NUMBERING, REGISTRATION AND RELEASING BY MGB REGIONAL OFFICE