Open-Deck Railroad Bridges
• Bridge ties rest directly atop
superstructure
• Affixed via notches, or Daps
• Regular tie replacement (5-10 year
cycle)
• Each tie is unique, re: daps required
& size
• Curved bridges more complex
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Examples of Open-Deck Bridges
Tangent Curved
(Usually with superelevation)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Background:
Traditional method:
• Survey structure: general line, grade, dimensions
• Superstructure details gathered
• Data provided to Bridge Office
• Ties calculated and configured, “typically”
• Information relayed back to field, corrected,
• Returned to Bridge, adjusted (repeat as needed…)
• Tie table generated & sent to manufacturer
• Ties shipped and installed
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
A & A approached by NS to find a ‘better’/more automated
way to calculate bridge-tie daps:
• More efficient (automated, accurate, effective)
• Universal: tangent or curved
• Also, provide depth of experience as experts retire from the
railroad.
A Better Way
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
Cross Sections
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
Cross Sections
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
• Review existing/available
shop drawings
• Acquire details of repairs
• Determine what needs to
be located, and
• What can be drawn from
plans
Survey Strategy:
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
• Coordinate with railroad
• Dates/times
• Track time is gold!
• Survey structure:
• Tie/superstructure interface
• Centerline, grade,
• Backwall-to-backwall
• Height/weight of rail
• Any detail re: tie daps
• Extend survey 500’ past
bridge abutments
Collect Field Measurements
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Another Important Tool
TIE DECK SURVEY CHECKLIST
Bridge No. ________________________ Mile Post __________________________
No. of Spans _________________________________________________________
Val Map No. _________________________ Track ___________________________
Bridge Over:
Creek: ____________________
Road: ____________________
Other: ____________________
Bench Mark Elevation _________________ Assumed ________________________
Description __________________________________________________________
Alignment:
Tangent: Yes or No _____________
Curve: Yes or No ________________ Direction: ______________________________
Spiral: Yes or No _________________
Girders per Span:
1) __________________________ Top Flange Width ________________________
2) __________________________ Top Flange Width ________________________
3) __________________________ Top Flange Width ________________________
4) __________________________ Top Flange Width ________________________
5) __________________________ Top Flange Width ________________________
6) __________________________ Top Flange Width ________________________
7) __________________________ Top Flange Width ________________________
8) __________________________ Top Flange Width ________________________
Size of Rail _________________________________________________________
Size of Existing Ties _________________________________________________
Check for daps and odd dimensions
Size of Tie Plates ____________________________________
No. of Ties per Span _________________________________________________
Average Tie Spacing _________________________________________________
Size of Back Wall Ties ________________________________________________
No. of Back Wall Ties ________________________________________________
Tie Spacer to CL Track _______________________________________________
* Does Hook Bolt Go Through Spacer: Yes or No
Raising Blocks: Yes or No Size: ______________________________
Location: __________________________
Any Long Ties: Yes or No Location: __________________________
Walkway: Yes or No Size: ______________________________
Location: __________________________
Safety Bays: Yes or No Size: ______________________________
Location: __________________________
SE in stringers or girders: Yes or No
Are the stringers or girders titled? Yes or No
Are the stringers or girders stepped? Yes or No
Is Bridge on a Skew? Yes or No
Locate face of back wall
Locate end of Girder to end of Girder each span
Locate TOR elevations 500’ min. from each end of bridge. Locate top of rail at
each end of each span
Locate top of Girders on each side of cover plates
Check for cover plate overhang
Is there a clearance issue? Yes or No ______________________________________
Locate any road crossings- switches, etc., in profile. Locate anything that might
affect proposed track raise
Locate gusset plates.
Locate all cross braces that would interfere with bottom of ties. Take plenty of
pictures and describe
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
• Gusset plate/connections
• Lateral bracing passages
Critical Features (typical)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
Cross Sections
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Rail Alignment
& Tie Placement
Rail alignment (Green line)
used to place ties evenly
across each bridge span.
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of BridgeCheck Plan & Profile of Bridge
Tie Size & Placement
Cross Sections
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Track C/L Profile
Track C/L located 500’ east and west of bridge abutments. Green lines
show bridge back wall locations. No dips or bumps in the profile.
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
• Girders, gusset
plates and lateral
steel applied to
each tie cross
section
• ¼” Tolerance built
into each edge of
girder
Tie Cross Section
With Survey Data Points (from CAD)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
CAD Derived Tie Cross Section
Tie cross section showing the stringers and plates that
interfere with this tie. Stringers have ¼” tolerance on each
edge shown above.
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
(Cross Sections)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
(Cross Sections)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Tie Cross Section Legend
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Dimensioned Tie
• Green outline shows the 10” tie shape after daps are cut
• Data can be sent to CNC machine for tie framing
• Dimensions are placed in Excel™ for tie manufactures
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
(Cross Sections)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Bridge-tie Table
Completed spreadsheet of ties & cuts
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Data Collection
Process/Draw Bridge
Out of Tolerance?
Advise Owner for
Plan of Action
Dimension Ties And Create Dimension Chart
Tie Size Adjusted
To Meet Current
Bridge Status
Create Tie Plan And CNC Drawings
Check Plan & Profile of Bridge
Tie Size & Placement
(Cross Sections)
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Finished Tie Plan
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
CNC Process
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Acknowledgements
• James N. Carter, Jr. – Norfolk Southern
• Jackson Owens – Norfolk Southern
• Alvin D. Young – CSXT
• Bill Bushman – Anderson & Associates
• Neil Martin – Anderson & Associates
• Joey Conrad – Anderson & Associates
• Steve Spillane – Anderson & Associates
• Mike Mascari – Anderson & Associates
• Chris Coffey - L & R Precision Tooling
A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E
Minneapolis, MN | October 4-7, 2015
Contact Information
Jason Williams, P.E.
Senior Project Manager
540.391.0277
williams@andassoc.com
Neil Martin, L.S.
Vice President of Survey
540.557.7171
martin@andassoc.com

More Related Content

Similar to AREMA_Developing an Expedited Bridge-Tie Replacement Methodology

Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_planE'ville Eye
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_planE'ville Eye
 
Phillip L French resume.V5.1
Phillip L French resume.V5.1Phillip L French resume.V5.1
Phillip L French resume.V5.1Phillip French
 
20150404-Scabbling and Levelling shims
20150404-Scabbling and Levelling shims20150404-Scabbling and Levelling shims
20150404-Scabbling and Levelling shimsAllan Phillips
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015Paul Schumann
 

Similar to AREMA_Developing an Expedited Bridge-Tie Replacement Methodology (8)

Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan
 
Phillip L French resume.V5.1
Phillip L French resume.V5.1Phillip L French resume.V5.1
Phillip L French resume.V5.1
 
20150404-Scabbling and Levelling shims
20150404-Scabbling and Levelling shims20150404-Scabbling and Levelling shims
20150404-Scabbling and Levelling shims
 
Mitchells resume
Mitchells resumeMitchells resume
Mitchells resume
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015
 

AREMA_Developing an Expedited Bridge-Tie Replacement Methodology

  • 1. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Developing an Expedited Bridge Tie Replacement Methodology Anderson & Associates, Inc. Blacksburg, Virginia
  • 2. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Open-Deck Railroad Bridges • Bridge ties rest directly atop superstructure • Affixed via notches, or Daps • Regular tie replacement (5-10 year cycle) • Each tie is unique, re: daps required & size • Curved bridges more complex
  • 3. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Examples of Open-Deck Bridges Tangent Curved (Usually with superelevation)
  • 4. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Background: Traditional method: • Survey structure: general line, grade, dimensions • Superstructure details gathered • Data provided to Bridge Office • Ties calculated and configured, “typically” • Information relayed back to field, corrected, • Returned to Bridge, adjusted (repeat as needed…) • Tie table generated & sent to manufacturer • Ties shipped and installed
  • 5. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 A & A approached by NS to find a ‘better’/more automated way to calculate bridge-tie daps: • More efficient (automated, accurate, effective) • Universal: tangent or curved • Also, provide depth of experience as experts retire from the railroad. A Better Way
  • 6. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement Cross Sections
  • 7. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement Cross Sections
  • 8. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 • Review existing/available shop drawings • Acquire details of repairs • Determine what needs to be located, and • What can be drawn from plans Survey Strategy:
  • 9. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 • Coordinate with railroad • Dates/times • Track time is gold! • Survey structure: • Tie/superstructure interface • Centerline, grade, • Backwall-to-backwall • Height/weight of rail • Any detail re: tie daps • Extend survey 500’ past bridge abutments Collect Field Measurements
  • 10. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Another Important Tool TIE DECK SURVEY CHECKLIST Bridge No. ________________________ Mile Post __________________________ No. of Spans _________________________________________________________ Val Map No. _________________________ Track ___________________________ Bridge Over: Creek: ____________________ Road: ____________________ Other: ____________________ Bench Mark Elevation _________________ Assumed ________________________ Description __________________________________________________________ Alignment: Tangent: Yes or No _____________ Curve: Yes or No ________________ Direction: ______________________________ Spiral: Yes or No _________________ Girders per Span: 1) __________________________ Top Flange Width ________________________ 2) __________________________ Top Flange Width ________________________ 3) __________________________ Top Flange Width ________________________ 4) __________________________ Top Flange Width ________________________ 5) __________________________ Top Flange Width ________________________ 6) __________________________ Top Flange Width ________________________ 7) __________________________ Top Flange Width ________________________ 8) __________________________ Top Flange Width ________________________ Size of Rail _________________________________________________________ Size of Existing Ties _________________________________________________ Check for daps and odd dimensions Size of Tie Plates ____________________________________ No. of Ties per Span _________________________________________________ Average Tie Spacing _________________________________________________ Size of Back Wall Ties ________________________________________________ No. of Back Wall Ties ________________________________________________ Tie Spacer to CL Track _______________________________________________ * Does Hook Bolt Go Through Spacer: Yes or No Raising Blocks: Yes or No Size: ______________________________ Location: __________________________ Any Long Ties: Yes or No Location: __________________________ Walkway: Yes or No Size: ______________________________ Location: __________________________ Safety Bays: Yes or No Size: ______________________________ Location: __________________________ SE in stringers or girders: Yes or No Are the stringers or girders titled? Yes or No Are the stringers or girders stepped? Yes or No Is Bridge on a Skew? Yes or No Locate face of back wall Locate end of Girder to end of Girder each span Locate TOR elevations 500’ min. from each end of bridge. Locate top of rail at each end of each span Locate top of Girders on each side of cover plates Check for cover plate overhang Is there a clearance issue? Yes or No ______________________________________ Locate any road crossings- switches, etc., in profile. Locate anything that might affect proposed track raise Locate gusset plates. Locate all cross braces that would interfere with bottom of ties. Take plenty of pictures and describe
  • 11. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 • Gusset plate/connections • Lateral bracing passages Critical Features (typical)
  • 12. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement Cross Sections
  • 13. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Rail Alignment & Tie Placement Rail alignment (Green line) used to place ties evenly across each bridge span.
  • 14. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of BridgeCheck Plan & Profile of Bridge Tie Size & Placement Cross Sections
  • 15. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Track C/L Profile Track C/L located 500’ east and west of bridge abutments. Green lines show bridge back wall locations. No dips or bumps in the profile.
  • 16. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 • Girders, gusset plates and lateral steel applied to each tie cross section • ¼” Tolerance built into each edge of girder Tie Cross Section With Survey Data Points (from CAD)
  • 17. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 CAD Derived Tie Cross Section Tie cross section showing the stringers and plates that interfere with this tie. Stringers have ¼” tolerance on each edge shown above.
  • 18. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement (Cross Sections)
  • 19. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement (Cross Sections)
  • 20. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Tie Cross Section Legend
  • 21. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Dimensioned Tie • Green outline shows the 10” tie shape after daps are cut • Data can be sent to CNC machine for tie framing • Dimensions are placed in Excel™ for tie manufactures
  • 22. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement (Cross Sections)
  • 23. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Bridge-tie Table Completed spreadsheet of ties & cuts
  • 24. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Data Collection Process/Draw Bridge Out of Tolerance? Advise Owner for Plan of Action Dimension Ties And Create Dimension Chart Tie Size Adjusted To Meet Current Bridge Status Create Tie Plan And CNC Drawings Check Plan & Profile of Bridge Tie Size & Placement (Cross Sections)
  • 25. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Finished Tie Plan
  • 26. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 CNC Process
  • 27. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Acknowledgements • James N. Carter, Jr. – Norfolk Southern • Jackson Owens – Norfolk Southern • Alvin D. Young – CSXT • Bill Bushman – Anderson & Associates • Neil Martin – Anderson & Associates • Joey Conrad – Anderson & Associates • Steve Spillane – Anderson & Associates • Mike Mascari – Anderson & Associates • Chris Coffey - L & R Precision Tooling
  • 28. A R E M A 2 0 1 5 A N N U A L C O N F E R E N C E Minneapolis, MN | October 4-7, 2015 Contact Information Jason Williams, P.E. Senior Project Manager 540.391.0277 williams@andassoc.com Neil Martin, L.S. Vice President of Survey 540.557.7171 martin@andassoc.com