SlideShare a Scribd company logo
1 of 10
Download to read offline
JIIRP Workshop
Feb 26, 2007
Janos Toth, Ph.D., P. Eng.
British Columbia
Transmission Corporation
2
Topics
1. Acceptable Risk Tolerance Level
3
Topics
1. Acceptable Risk Tolerance Level
2. Recovery and Restoration Times
4
Acceptable Risk Tolerance Level
To prepare a risk response plan we need to know the
Acceptable Risk Tolerance Level from Natural
Events (Seismic, Ice Storm, Wind Storm etc.) for
infrastructure elements (utility, road system etc.) by
the company and the public (social acceptance of
loss levels)
5
Acceptable Risk Tolerance Level
From CAN/CSA-Q850-97 (Reaffirmed 2002) Risk Management: Guideline for Decision-Makers
6
Acceptable Risk Tolerance Level
•  Company and Public Risk Tolerance could be very
different !
7
Acceptable Risk Tolerance Level
•  Company and Public Risk Tolerance could be very
different !
•  Recent wind an snow storms in BC created extended
electrical outages for customers.
8
Recovery and Restoration Times
•  Acceptable recovery and restoration times for
infrastructure components (hours, weeks or
months?)
•  Company and public requirements could be quite
different.
•  Public usually requires quick response
•  Companies have limited resources to respond.
9
Answers Required
When we can get reasonable answers for these
questions we can plan for an event (potential
disaster) and mitigate its impact within our resource
and political constrains (cost of service delivered).
Currently there is no coordinated risk tolerance level
among utilities. NBCC 2005 has requirements for
new construction, mainly buildings, but many
existing system elements do not meet these
requirements and some items are outside the scope
of the code, for example transmission lines and
substations.
10
Answers Required
What can we do now? Upgrade to some technically
reasonable risk tolerance level, usually defined
within companies.
Is this acceptable by the public?

More Related Content

Similar to Janos_Toth_JIIRP_UBC_Workshop_070226

Site Selection for Mission Critical Facilities
Site Selection for Mission Critical FacilitiesSite Selection for Mission Critical Facilities
Site Selection for Mission Critical FacilitiesSchneider Electric
 
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013New Jersey Future
 
Sirr presentation
Sirr presentationSirr presentation
Sirr presentationecowatchers
 
Financing Energy Efficiency Projects Presentation
Financing Energy Efficiency Projects PresentationFinancing Energy Efficiency Projects Presentation
Financing Energy Efficiency Projects PresentationDermotDuncan
 
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTUREAN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTUREiQHub
 
Decommissioning presentations complete
Decommissioning presentations   completeDecommissioning presentations   complete
Decommissioning presentations completeNuclear Energy Insider
 
Restoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disasterRestoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disasterRick Case, PMP, P.E.
 
Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsOECD Governance
 
Economic Justification for Action Now in Rhode Island
Economic Justification for Action Now in Rhode IslandEconomic Justification for Action Now in Rhode Island
Economic Justification for Action Now in Rhode Islandriseagrant
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Snyder
 
Disaster Recovery Planning PowerPoint Presentation Slides
Disaster Recovery Planning PowerPoint Presentation SlidesDisaster Recovery Planning PowerPoint Presentation Slides
Disaster Recovery Planning PowerPoint Presentation SlidesSlideTeam
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 
Challengesindrpostinstallationpresentation
ChallengesindrpostinstallationpresentationChallengesindrpostinstallationpresentation
ChallengesindrpostinstallationpresentationZondits
 
TNC 2014 nren climate change preparedness
TNC 2014   nren climate change preparednessTNC 2014   nren climate change preparedness
TNC 2014 nren climate change preparednessBill St. Arnaud
 

Similar to Janos_Toth_JIIRP_UBC_Workshop_070226 (20)

Site Selection for Mission Critical Facilities
Site Selection for Mission Critical FacilitiesSite Selection for Mission Critical Facilities
Site Selection for Mission Critical Facilities
 
Mail shark case study
Mail shark case studyMail shark case study
Mail shark case study
 
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
 
Sirr presentation
Sirr presentationSirr presentation
Sirr presentation
 
Financing Energy Efficiency Projects Presentation
Financing Energy Efficiency Projects PresentationFinancing Energy Efficiency Projects Presentation
Financing Energy Efficiency Projects Presentation
 
Scotsem-Economic Resilience_F.PDF
Scotsem-Economic Resilience_F.PDFScotsem-Economic Resilience_F.PDF
Scotsem-Economic Resilience_F.PDF
 
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTUREAN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
AN INVESTOR VIEW OF POST-COMBUSTION CO₂ CAPTURE
 
Draft EIS - Kemper County IGCC Project
Draft EIS - Kemper County IGCC ProjectDraft EIS - Kemper County IGCC Project
Draft EIS - Kemper County IGCC Project
 
Decommissioning presentations complete
Decommissioning presentations   completeDecommissioning presentations   complete
Decommissioning presentations complete
 
Restoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disasterRestoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disaster
 
Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR Projects
 
Economic Justification for Action Now in Rhode Island
Economic Justification for Action Now in Rhode IslandEconomic Justification for Action Now in Rhode Island
Economic Justification for Action Now in Rhode Island
 
Final EIS Summary - Kemper County IGCC Project
Final EIS Summary - Kemper County IGCC Project Final EIS Summary - Kemper County IGCC Project
Final EIS Summary - Kemper County IGCC Project
 
Current IssuesDOE's Nuclear Energy Programs
Current IssuesDOE's Nuclear Energy ProgramsCurrent IssuesDOE's Nuclear Energy Programs
Current IssuesDOE's Nuclear Energy Programs
 
Dermarkar
DermarkarDermarkar
Dermarkar
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resume
 
Disaster Recovery Planning PowerPoint Presentation Slides
Disaster Recovery Planning PowerPoint Presentation SlidesDisaster Recovery Planning PowerPoint Presentation Slides
Disaster Recovery Planning PowerPoint Presentation Slides
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 
Challengesindrpostinstallationpresentation
ChallengesindrpostinstallationpresentationChallengesindrpostinstallationpresentation
Challengesindrpostinstallationpresentation
 
TNC 2014 nren climate change preparedness
TNC 2014   nren climate change preparednessTNC 2014   nren climate change preparedness
TNC 2014 nren climate change preparedness
 

Janos_Toth_JIIRP_UBC_Workshop_070226

  • 1. JIIRP Workshop Feb 26, 2007 Janos Toth, Ph.D., P. Eng. British Columbia Transmission Corporation
  • 2. 2 Topics 1. Acceptable Risk Tolerance Level
  • 3. 3 Topics 1. Acceptable Risk Tolerance Level 2. Recovery and Restoration Times
  • 4. 4 Acceptable Risk Tolerance Level To prepare a risk response plan we need to know the Acceptable Risk Tolerance Level from Natural Events (Seismic, Ice Storm, Wind Storm etc.) for infrastructure elements (utility, road system etc.) by the company and the public (social acceptance of loss levels)
  • 5. 5 Acceptable Risk Tolerance Level From CAN/CSA-Q850-97 (Reaffirmed 2002) Risk Management: Guideline for Decision-Makers
  • 6. 6 Acceptable Risk Tolerance Level •  Company and Public Risk Tolerance could be very different !
  • 7. 7 Acceptable Risk Tolerance Level •  Company and Public Risk Tolerance could be very different ! •  Recent wind an snow storms in BC created extended electrical outages for customers.
  • 8. 8 Recovery and Restoration Times •  Acceptable recovery and restoration times for infrastructure components (hours, weeks or months?) •  Company and public requirements could be quite different. •  Public usually requires quick response •  Companies have limited resources to respond.
  • 9. 9 Answers Required When we can get reasonable answers for these questions we can plan for an event (potential disaster) and mitigate its impact within our resource and political constrains (cost of service delivered). Currently there is no coordinated risk tolerance level among utilities. NBCC 2005 has requirements for new construction, mainly buildings, but many existing system elements do not meet these requirements and some items are outside the scope of the code, for example transmission lines and substations.
  • 10. 10 Answers Required What can we do now? Upgrade to some technically reasonable risk tolerance level, usually defined within companies. Is this acceptable by the public?