Year Project Name Project # Start Date End Date Contract Amt
2014 Repair Runway 111409 05/21/14 08/04/14 $ 450,398.00
Minot, North Dakota
2015 APS Four Corners Plant 161575 11/30/15 In Progress $ 720,416.00
Okland Construction/Geneva Rock Products, Inc.
Year Project Name Project# Start Date End Date Contract Amt
2014 CAFB Repave Overruns 0026 07/07/14 11/18/14 $ 198,215.30
Cannon Air Force Base
Granite Construction
Year Project Name Project # Start Date End Date Contract Amt
2014 APS – Ash Pond 6 Closure 468539 09/22/14 11/02/15 $ 668,633.00
FNF Construction, Inc.
Year Project Name Project# Start Date End Date Contract Amt
2014 US 54, Lincoln CN 2100250 05/05/14 05/15/15 $ 750,720.00
2014 I-40, McKinley County CN 6100715 07/16/14 11/15/14 $ 318,480.00
2015 I-40, McKinley County CN 6100421 04/01/15 05/30/15 $ 215,200.00
2015 I-40, McKinley County CN 6100650 08/19/15 10/30/15 $ 400,017.00
2015 I-25, Santa Fe County CN S100140 06/24/15 In Progress $ 197,480.00
Mesa Verde Enterprises
Year Project Name Project # Start Date End Date Contract Amt
2014 White Sands Missile Range 14-136 12/22/14 03/31/15 $ 30,000.00
Ramsite
2015 Alamogordo, Airport 000000 01/20/15 03/17/15 $ 125,345.00
Acme Concrete Paving
Year Project Name Project # Start Date End Date Contract Amt
2014 Williston, North Dakota 000000 08/11/2014 10/14/14 $ 311,420.00
2015 Sea Tac International Airport MC-0318131 06/18/2015 11/06/15 $ 300,000.00
PCI Roads
Year Project Name Project # Start Date End Date Contract Amt
2014 Watford City, North Dakota 000000 09/02/2014 09/19/14 $ 7,935.00
Mountain States Constructors, Inc.
Year Project Name Project # Start Date End Date Contract Amt
2016 US 64, San Juan CN F100110 01/12/2016 In Progress
Constructors, Inc.
Year Project Name Project # Start Date End Date Contract Amt
2016 Artesia Airport Runway 152105 02/03/2016 In Progress $ 220,718.50

More Related Content

Similar to Past Performance

Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Crosstown TO
 
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Fairfax County
 
South Van Dorn Street Walkway
South Van Dorn Street WalkwaySouth Van Dorn Street Walkway
South Van Dorn Street WalkwayFairfax County
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Crosstown TO
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanOsvaldo Zumba
 
Presentation
PresentationPresentation
PresentationKrm Chari
 
Silverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsSilverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Crosstown TO
 

Similar to Past Performance (12)

San Bernardino County Transportation Funding Update
San Bernardino County Transportation Funding UpdateSan Bernardino County Transportation Funding Update
San Bernardino County Transportation Funding Update
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019
 
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
 
South Van Dorn Street Walkway
South Van Dorn Street WalkwaySouth Van Dorn Street Walkway
South Van Dorn Street Walkway
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning Plan
 
Presentation
PresentationPresentation
Presentation
 
Silverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsSilverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection Improvements
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
FDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
FDOT SR-997/Krome Avenue Safety Improvement Projects Status UpdateFDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
FDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
 
Sears
SearsSears
Sears
 

Past Performance

  • 1. Past Performance Sundt Construction Year Project Name Project # Start Date End Date Contract Amt 2014 Repair Runway 111409 05/21/14 08/04/14 $ 450,398.00 Minot, North Dakota 2015 APS Four Corners Plant 161575 11/30/15 In Progress $ 720,416.00 Okland Construction/Geneva Rock Products, Inc. Year Project Name Project# Start Date End Date Contract Amt 2014 CAFB Repave Overruns 0026 07/07/14 11/18/14 $ 198,215.30 Cannon Air Force Base Granite Construction Year Project Name Project # Start Date End Date Contract Amt 2014 APS – Ash Pond 6 Closure 468539 09/22/14 11/02/15 $ 668,633.00 FNF Construction, Inc. Year Project Name Project# Start Date End Date Contract Amt 2014 US 54, Lincoln CN 2100250 05/05/14 05/15/15 $ 750,720.00 2014 I-40, McKinley County CN 6100715 07/16/14 11/15/14 $ 318,480.00 2015 I-40, McKinley County CN 6100421 04/01/15 05/30/15 $ 215,200.00 2015 I-40, McKinley County CN 6100650 08/19/15 10/30/15 $ 400,017.00 2015 I-25, Santa Fe County CN S100140 06/24/15 In Progress $ 197,480.00
  • 2. Mesa Verde Enterprises Year Project Name Project # Start Date End Date Contract Amt 2014 White Sands Missile Range 14-136 12/22/14 03/31/15 $ 30,000.00 Ramsite 2015 Alamogordo, Airport 000000 01/20/15 03/17/15 $ 125,345.00 Acme Concrete Paving Year Project Name Project # Start Date End Date Contract Amt 2014 Williston, North Dakota 000000 08/11/2014 10/14/14 $ 311,420.00 2015 Sea Tac International Airport MC-0318131 06/18/2015 11/06/15 $ 300,000.00 PCI Roads Year Project Name Project # Start Date End Date Contract Amt 2014 Watford City, North Dakota 000000 09/02/2014 09/19/14 $ 7,935.00 Mountain States Constructors, Inc. Year Project Name Project # Start Date End Date Contract Amt 2016 US 64, San Juan CN F100110 01/12/2016 In Progress Constructors, Inc. Year Project Name Project # Start Date End Date Contract Amt 2016 Artesia Airport Runway 152105 02/03/2016 In Progress $ 220,718.50