SlideShare a Scribd company logo
1 of 42
Download to read offline
RISK ENGINEERING SOCIETY
Legal Obligations for OHS Risk
Minimisation by Designers and Suppliers of
Mining Machinery
19th February 2014
Engineers Australia – West Perth
© Copyright of all content owned by EUC Engineering Pty Ltd or others.
No content may be reproduced without prior written consent of EUC Engineering Pty Ltd.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

MIKE DEAN – ABOUT ME
• Electrical Engineer (UWA, 1984).
• Iron Ore industry 1981-87 and 1992-2000 (15 years).
• Insurance industry 2000-2003 – Energy & Mining Clients – Intro to
results when things go wrong.
• In 2004 completed Grad Dip Risk Management – UNSW Safety
Science
• Since 2004 minerals processing risk & safety involvement (mainly
alumina, iron ore)
• Since 2010 functional safety for machinery (iron ore industry) (to AS
62061/ISO 13849) and underground mine winder (2013, to AS
61508).
DISCLAIMERS
•
•
•
•

[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

I am not a lawyer and I don’t work for a government department.
I have simply read the legislation and some relevant legal commentary.
None of this presentation should be considered “legal advice”.
Only some key aspects of compliance relevant to “designers & suppliers of
mining machinery” are being highlighted in this presentation.

ACKNOWLEDGMENTS & SOURCES
• Richard Robinson’s paper “Near enough not safe enough” [(Jan 2014),
Engineers Australia Magazine] got me thinking about this subject and has
formed a basis for the content.
• “The Relationship Between ‘Reasonably Practicable’ and Risk
Management Regulation” (2004), Bluff & Johnstone
(http://alturl.com/5eksi).
• HSE UK website (ALARP suite of guidance).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

PRESENTATION OUTLINE
•
•
•
•

What Legislation Applies & Where To Find It.
What are the Legal Obligations for Designers & Suppliers.
What is “Reasonably Practicable”.
Observations on Why Conventional OHS “Risk Management”
Doesn’t Achieve Compliance.
• Model WHS Law – Possible Changes to Obligations?
• Summary.
• Question Time.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

SCOPE
• Western Australian “mines”.
• Other facilities have own legislation:
• Petroleum and Geothermal Energy Resources .
• Rail.
• “Other” business sectors.

• As a designer/supplier: You need to know which legislation
applies.
• Facility owners need to make this clear in contractual
documentation.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

RELEVANT LEGISLATION & WHERE TO FIND IT
• Two main pieces of applicable legislation:
• Mines Safety & Inspection Act (MSIA)(1994).
• Mines Safety & Inspection Regulations (MSIR)(1995).

• Compliance to both is required.
• Can easily obtain copies of this legislation for free at:
• http://www.slp.wa.gov.au/

• In addition there are approved Codes of Practice available at.
• http://www.dmp.wa.gov.au/6694.aspx#6884
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHO ADMINISTERS?
• Department Mines & Petroleum (DMP) – Resources Safety
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

ACT & REGULATIONS – WHAT’S THE DIFFERENCE?
• For the keen – but not hugely relevant to the presentation:
•
•
•
•
•

Acts become law by passage through both houses in the Parliament,
acceptance by the Governor and then proclamation in the Government
Gazette.
Regulations are a form of “subsidiary (or delegated) legislation”.
Subsidiary legislation can be enacted by the Governor, Ministers or other
bodies as allowed for under an Act.
The Act contains the “law”, whereas the Regulations are specific means
by which the law is to be observed.
For more info: http://www.department.dotag.wa.gov.au/_files/How_to_read_legislation.pdf

• The above is maybe of interest(?) – but compliance with both the
Act and Regulations is required (So you need a copy of both.)
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

MSIA (1994) – OBJECTIVES OF THE ACT
• Objects (Part 1 s3 (1))
• …
c) to protect employees against the risks associated with
mines, mining operations, work systems at mines, and plant
and hazardous substances at mines by eliminating those
risks, or imposing effective controls in order to minimize
them;
• …
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIA (1994) Part 2 s14 – These are “Duties” under the Act…

Remember: “…must, so far as is practicable - …”
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY
PENALTIES FOR BREACH OF MSIA (1994) S14

[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

•
•

From s15 and s4A.
Penalties below are for “First Offence” only. Penalties for subsequent offences are +25% on
fines for first offence.

•

Gross Negligence is defined in s8B (next slide).

Nature of Breach
Causing death or serious harm
(due to Gross Negligence)

Penalty
Level
4

Causing Death or Serious Harm
(but not Gross Negligence)

3

Not Causing Death or Serious
Harm & Not Gross Negligence

2

Individual

Corp

$250,000 and $500,000
2 years
imprisonment
$200,000
$400,000

$100,000

$200,000
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

GROSS NEGLIGENCE DEFINITION (S8B)
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

SOME FURTHER RELEVANT BITS (FOR OTHER PARTIES)
• MSIA (1994)
• For installers/constructors – See Part 2 s14 (2).
• For designers/constructors of buildings or structures – See Part 2 s14
(3).
• For manufacturers, importers and suppliers of “substances” for use at
a mine – See Part 2 s14 (4).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIR (1995)
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIR (1995)

• See also sub-reg (2)(b) and (c) – for “powered mobile plant”
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIR (1995)

See MSIR for list of items (a) to (f) that must be provided to the manufacturer by the
designer (See next slide).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

MSIR (1995) R6.5 CONTINUED
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIR (1995) – Other Regulations (Heading Only provided)
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY

• MSIR (1995) – Other Regulations (Heading Only provided)

BE AWARE!! These obligations for hazard ID, risk assessment and risk reduction under the MSIR
“ripple forward” and are inherited by the first party in the “supply chain” who is the legal entity
in Western Australia – this in addition to their own duties under the Act & Regs.
Inside WA

E.g. (Ref r6.9):
Designer

Manufacturer
Outside WA

Importer

Sale of Plant

Constructor

Importer inherits obligations of designer &
manufacturer under MSIR for hazard ID/risk
assessment and risk reduction

Client/Owner
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

PENALTIES FOR BREACH OF MSIR (1995) R6.4 TO R6.14
•
•
•

From r17.1 – Penalties below are for “First Offence” only.
Penalties for subsequent offences are +25% on fines for first offence.
Penalties apply to each regulation not complied with.

Employee

Individual

Corporation

$5,000

$25,000

$50,000
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

OTHER SPECIFIC REGULATIONS
• Note: There are likely to be other regulations requiring your
designs to include certain measures and features.
• These are not specifically identified here in this presentation.
• You need to read and understand any plant & machinery
specific requirements made in the MSIR – See for example:
• Part 4 (General Safety Requirements).
• Part 5 (Electricity in mines).
• r6.26 - 6.31 (Pressurised plant, moving parts, hot or cold parts,
electrical plant, industrial robots, lasers).
• r6.32 – 6.40 (Classified plant)….
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

OTHER RELEVANT DOCUMENTS - CODES OF PRACTICE
• Endorsed by MIAC and Approved by
the Minister (as provided under
MSIA).
• Provides practical guidance.
• This Code of Practice addresses
“Safeguarding of machinery &
plant”.
• Available for free at
http://www.dmp.wa.gov.au/6694.a
spx#6884.
• Compliance to code not mandatory,
but may be used by courts as
representing the standard.
• Non-compliance with code not
sufficient for prosecution.
• Get, read and deploy this
document.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

BACK TO THE KEY ISSUE – MSIA (1994) S14
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

GETTING TO THE BOTTOM OF “SO FAR AS IS PRACTICABLE” –
DEFINITION IN MSIA

• (MSIA (1994) s4) “Practicable - means reasonably practicable
having regard, where the context permits, to —
(a) the severity of any potential injury or harm to health that
may be involved and the degree of risk of such injury or
harm occurring; and

(b) the state of knowledge about —
(i) the injury or harm to health referred to in paragraph (a); and
(ii) the risk of that injury or harm to health occurring; and
(iii) means of removing or mitigating the potential injury or harm to
health; and
(c) the availability, suitability, and cost of the means
referred to in paragraph (b)(iii); “
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHAT DOES “REASONABLY PRACTICABLE” MEAN?
• “Complex” legal topic – with considerable case law/papers.
• Involves weighing up (judgement) between:
•
•

“Quantum of risk” on one hand
The “Cost” of the measure to avert the risk on the other.

• Only if the “cost” is grossly disproportionate to the risk reduction
achieved can the measure be called NOT “reasonably practicable”.
• The “balance” and decision has to be made BEFORE the incident
(not after).
• If the judiciary make a judgement (afterwards) it will involve what a
“reasonable” person should have done and should have known in
making or not making a decision.
•
•

Suggested reference for more info is “The Relationship Between ‘Reasonably Practicable’ and Risk
Management Regulation” (2004), Bluff & Johnstone (http://alturl.com/5eksi).
Also HSE UK has excellent guidance on this subject: http://www.hse.gov.uk/risk/theory/alarp.htm.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

GUIDANCE ON HOW TO DO IT (REASONABLY PRACTICABLE)

Governance Questions
(Tests of the results)

• Step One: Identifying the Circumstances, Hazards and Risks
•

(You need to do this under the MSIR anyway – Ref r6.3).

• Step Two – Determine What You Can Do (Ignoring Cost)
•
•
•
•

Use the hierarchy of controls (NB: Currently not a legislated requirement in
WA – but coming soon).
Look at options.
Don’t eliminate an option at this stage due to “cost”.
Record the process.

• Step Three – Determine What You are Reasonably Able to Do
•
•
•
•

Carefully – keeping in mind the severity/risk of harm – decide what can
reasonably be done.
Only eliminate risk reduction measures – which are clearly “unreasonable” to
do. Err on the side of caution.
Cost can be a valid reason for not proceeding with a risk reduction measure.
Record the process & decision making.

• Step Four – Periodically Review Decisions & Outcomes
•

Things change. You have to account for this in the design/delivery process.

What would a “reasonable”
person know or ought to know
about the hazards & risks?

What would a
“reasonable” person
know or ought to know
about the ways of
eliminating or
minimising the risk?

Is the process and
decision making
robust?
Have valid risk
reduction measures
been missed, glossed
over or discarded?

Review process in place?

This guidance is from: http://www.safeworkaustralia.gov.au/sites/SWA/about/Publications/Documents/774/Guide-ReasonablyPracticable.pdf
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN
FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14

It is important to note:
The conventional “risk management” approach according to many
company risk management guidelines – focussed at achieving a
company defined tolerable level of risk.
DOES NOT AUTOMATICALLY YIELD
Compliance with the (s14) MSIA/MSIR requirements for “so far as
is practicable” hazard/risk minimisation ….
• The process of the conventional “risk management” approach is not
usually targeted at determining/documenting “so far as is
practicable” decisions.
• This is an important reason why these MSIA/MSIR obligations can
be missed.
• Important issue for designers … and those involved in delivering risk
management/workshops etc to designers (and owners, operators).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN
FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14

• From AS/NZS ISO 31000:2009
AS/NZS ISO 31000:2009
doesn’t explicitly address
treating risks until there
are no further
“reasonably practicable”
risk reduction measures
available.
[CLIENT – EDIT IN MASTER SLIDE
WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]
FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14- CONTINUED

Typically company “risk management” processes involve:
1-Low

2-Minor

Severity
3-Moderate

4-Major

5-Critical

5-Almost
Certain

11

16

20

23

25

4-Likely

7

12

17

21

24

3-Possible

4

8

13

18

22

2-Unlikely

2

Likelihood

1.
2.

Hazard/scenario identification.
{Possibly – risk assess “inherent”
risk of scenario}
3. Identify existing risk controls.
4. Risk assess current level of risk.
5. Compare risk level to tolerable
levels (if “low” risk – go to Step 10,
otherwise go to Step 6).
6. Identify additional (new) risk
controls.
7. Risk assess future risk level.
8. Compare risk level to tolerable
levels (if “low” risk – go to Step 9,
otherwise go to Step 6).
9. Implement additional/new risk
controls.
10. Periodic review.

1-Rare

IMPORTANT!
9
14
19
The MSIA doesn’t require that
1
3
10
the risk is6 as low as a 15
company defined tolerable
risk level. It requires you
determine and implement
“ALL reasonably practicable”
measures to reduce exposure
to the hazard(s)– and to not
stop until you have.
5
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

PRACTICAL EXAMPLE – CONVENTIONAL HAZID & RISK ASSESSMENT
[CLIENT – EDIT
PRACTICAL EXAMPLE – CONVENTIONAL HAZID & RISK ASSESSMENT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

Hydraulic hoses near a large hydraulic cylinder near a walkway

• Hazard: Hydraulic hose containing high
pressure hydraulic fluid.
• Risk: Hose (or fitting) failure with person
in vicinity causing injury.
• Severity: LTI (Moderate).
• Risk Controls:
• Fit for purpose/AS compliant
equipment specified.
• Routine maintenance & inspection.
• Personnel wearing PPE.
• Assessed likelihood: Unlikely.
• Risk Level: “Green” “9” – Acceptable risk.
• Move on to next hazard….

2-Minor

Severity
3-Moderate

4-Major

5-Critical

5-Almost
Certain

11

16

20

23

25

4-Likely

7

12

17

21

24

3-Possible

4

8

13

18

22

2-Unlikely

2

5

9

14

19

1-Rare

Is this process familiar to anyone in the room….!!

1-Low

1

3

6

10

15

Likelihood
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

CONTRAST WITH S14 MSIA REQUIREMENTS
• Following slide is a hypothetical approach to meeting the s14
MSIA requirements of the machine designer addressing the
same hazard.
• Caution:
• This is a “discussion” starter to address a perceived deficiency in
current practice.
• Methodology has not been “endorsed” by risk fraternity nor is it
endorsed as achieving s14 compliance by DMP.
[CLIENT – EDIT
PRACTICAL EXAMPLE – S14 MSIA – POSSIBLE APPROACH IN MASTER SLIDE VIEW]
[PROJECT]

Hydraulic hoses near a large hydraulic cylinder near a walkway

• Hazard: Hydraulic hose containing high
pressure hydraulic fluid.
• Risk: Hose (or fitting) failure with person
in vicinity causing injury.
• Severity: Burns or pressurised liquid
injury (requires hospitalisation)
(=“Major”). Evidence presented of
hydraulic system hazards (see note
below).
• Likelihood: Assessed as Unlikely based on
hose/fitting failure data.
Level of Risk informs
degree of focus on
• Risk: High (14).
control measures
• Establish available risk reduction
measures according hierarchy of controls
(see next slide).
Note: See for eg: http://www.dennismac.co.uk/hands/hyd/index.html.

[SUBJECT/EVENT] – [DATE]

Gain knowledge of
“Severity”. Consider
reasonable worst case.

This operator was burned when a hydraulic hose,
neglected during maintenance, burst and spewed
hydraulic oil, at normal operating temperature,
over his entire body (from HandS – Dennis Mac).
This approach is the key
differentiator from conventional
risk assessment
Reasonably– EDIT IN MASTER SLIDE VIEW]
[CLIENT
Rationale
Practicable?
[PROJECT]

Hierarchy of
Controls

Available Measures

Elimination

None Identified.

N/A

Substitution

None Identified.

N/A

Isolation/
Separation

Hoses and fittings to relevant Australian
Standards.

Yes

Hoses run in web of beams

Yes

Guarding of walkway areas

Yes

Engineering
Controls

None Identified.

N/A

Administrative
Controls

Maintenance requirements in O&M Manual

Yes

Hydraulic System hazards in O&M Manual

Yes

Standard site PPE

Yes

High temperature oil resistant suit over Kevlar
body armour

No

PPE

[SUBJECT/EVENT] – [DATE]

This new/additional
control was revealed
through the MSIA
compliance mindset

This measure was
deemed to be Not
Reasonably Practicable –
with rationale given

User discomfort/health
impacts at high ambient
temperatures.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

PRACTICAL EXAMPLE – S14 MSIA – POSSIBLE APPROACH
• Something like the previous slides isn’t often done.
• Focus shifts from conventional “is risk low enough” to identifying
available & reasonably practicable hazard/risk control measures.
• Would add cost/time to the HAZID & Risk Assessments already
being undertaken (in the conventional model).
• Cost impacts on plant & machinery for WA minesites to implement
all reasonably practicable hazard/risk control measures?
• Suggested work is to:
•
•
•

Discuss issues outlined here – is it a “real” issue needing addressing?
Obtain DMP view on how best to demonstrate MSIA s14 compliance.
Expedite and improve the process so it isn’t overly onerous in time &
expense.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

OTHER REASONS WHY COMPLIANCE NOT ACHIEVED
• Companies use “Project Risk” mindset when doing risk
assessment (concerned with project delivery, missing OHS
risks).
• Observation: You don’t run the risk of jail time if you fail to identify a
project delivery risk.

• Designers rely on client “risk assessment” process instead of
their own.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

THE IMPENDING “MODEL WHS” CHANGES
• From DMP website:
• “New work health and safety (WHS) legislation for the Western
Australian resources sector is expected to be introduced in early 2015.
• This will be based on model laws developed under the harmonisation
process driven by Safe Work Australia and the National Mine Safety
Framework.
• It is expected that this will be a single piece of safety legislation for the
resources sector in Western Australia, effectively combining mining,
petroleum and major hazard facilities into one act – the Work Health
and Safety (Resources) Act.”
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

NEW MODEL WHS ACT/REGS - IMPACTS
• By review of Model WHS Act/Regs – there will be minor impacts on
subject being discussed here.
• Slightly different wording for equivalent of MSIA s14 (see s22):

• Get used to hearing abbreviation “SFAIRP”.

• Hierarchy of Controls embedded in Regs (see r36).
• Summary is that Model WHS Act/Regs if implemented in WA will
not undermine / change the current MSIA requirements (will
strengthen them).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

OTHER RELATED TOPICS OF INTEREST
• The “Safety Lifecycle” approach of AS 61508.1 offers a sound
framework for treatment of all machinery & plant.
• This is supported by the recent (2013) update of AS 3007 which
requires a full “lifecycle” approach to risks and risk management.
• Please consider.

• MSIA (1995) s14 and similar clauses – need to be achieved
even where Australian Standards/Codes etc require an explicit
tolerable risk target (ie AS 61508 for Functional Safety).
• Issue of reconciling SFAIRP and quantitative risk targets. NB: An issue
for risk engineers to ponder.
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

SUMMARY
• All designs for plant & machinery need to be subjected to OHS
focussed hazard ID & risk assessment.
• Conventional risk assessment isn’t sufficient for MSIA (1994)
s14 compliance.
• MSIA (1994) s14 compliance requires that every “reasonably
practicable” measure to reduce exposure of personnel to
hazards – has been taken.
• Demonstrating this will require additional efforts than applied
in most conventional HAZID/risk assessments.
• Devising a way to cost effectively do this is required.
• Model WHA Act/Regs coming to WA wont change/undermine
the current obligations of designers (only strengthen them).
[CLIENT – EDIT IN MASTER SLIDE VIEW]
[PROJECT]
[SUBJECT/EVENT] – [DATE]

THANK-YOU
Questions?

Mike Dean
0448 103 028
mike.dean@euceng.com.au

More Related Content

Similar to Res desgnr obligmsir_20140219_b

Steel Forging Manufacturing Plant Project Report.pptx
Steel Forging Manufacturing Plant Project Report.pptxSteel Forging Manufacturing Plant Project Report.pptx
Steel Forging Manufacturing Plant Project Report.pptxbhuvneshimarc
 
COMPANY PRESENTATION
COMPANY PRESENTATIONCOMPANY PRESENTATION
COMPANY PRESENTATIONSilvia Iovu
 
Diversified Power Point Slide Show 2016
Diversified Power Point Slide Show 2016Diversified Power Point Slide Show 2016
Diversified Power Point Slide Show 2016Raymond Harris
 
EHS Regulatory Compliance in 2018 and the Changes That Lie Ahead
EHS Regulatory Compliance in 2018 and the Changes That Lie AheadEHS Regulatory Compliance in 2018 and the Changes That Lie Ahead
EHS Regulatory Compliance in 2018 and the Changes That Lie AheadTriumvirate Environmental
 
TALAT Lecture 2204: Design Philosophy
TALAT Lecture 2204: Design PhilosophyTALAT Lecture 2204: Design Philosophy
TALAT Lecture 2204: Design PhilosophyCORE-Materials
 
C.V_Suhail_Ahmad_ Mechanical Engr.
C.V_Suhail_Ahmad_ Mechanical Engr.C.V_Suhail_Ahmad_ Mechanical Engr.
C.V_Suhail_Ahmad_ Mechanical Engr.Suhail Khan
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Denis Senin
 
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...Versli Lietuva (Enterprise Lithuania)
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Versli Lietuva (Enterprise Lithuania)
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Denis Senin
 
Landmark Industrial Services Brochures
Landmark Industrial Services BrochuresLandmark Industrial Services Brochures
Landmark Industrial Services BrochuresFrank McNeill
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide ToolsFlank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide ToolsIRJET Journal
 
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Versli Lietuva (Enterprise Lithuania)
 
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Denis Senin
 

Similar to Res desgnr obligmsir_20140219_b (20)

Steel Forging Manufacturing Plant Project Report.pptx
Steel Forging Manufacturing Plant Project Report.pptxSteel Forging Manufacturing Plant Project Report.pptx
Steel Forging Manufacturing Plant Project Report.pptx
 
COMPANY PRESENTATION
COMPANY PRESENTATIONCOMPANY PRESENTATION
COMPANY PRESENTATION
 
Diversified Power Point Slide Show 2016
Diversified Power Point Slide Show 2016Diversified Power Point Slide Show 2016
Diversified Power Point Slide Show 2016
 
EHS Regulatory Compliance in 2018 and the Changes That Lie Ahead
EHS Regulatory Compliance in 2018 and the Changes That Lie AheadEHS Regulatory Compliance in 2018 and the Changes That Lie Ahead
EHS Regulatory Compliance in 2018 and the Changes That Lie Ahead
 
1 3 amec
1 3 amec1 3 amec
1 3 amec
 
Doing Business in Myanmar
Doing Business in MyanmarDoing Business in Myanmar
Doing Business in Myanmar
 
SABER CV
SABER CVSABER CV
SABER CV
 
3rd generation modularization by flour
3rd generation modularization   by flour3rd generation modularization   by flour
3rd generation modularization by flour
 
TALAT Lecture 2204: Design Philosophy
TALAT Lecture 2204: Design PhilosophyTALAT Lecture 2204: Design Philosophy
TALAT Lecture 2204: Design Philosophy
 
C.V_Suhail_Ahmad_ Mechanical Engr.
C.V_Suhail_Ahmad_ Mechanical Engr.C.V_Suhail_Ahmad_ Mechanical Engr.
C.V_Suhail_Ahmad_ Mechanical Engr.
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
 
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...
Jens Gunnars, „Inspecta Technology“ technikos vadovas, Mikael Kuokkanen, „Ins...
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
 
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
Purje Juha, Inspecta Tarkastus (Suomija), „Visagino VAE projektas. Techniniai...
 
FORGING HAMMER
FORGING HAMMERFORGING HAMMER
FORGING HAMMER
 
Landmark Industrial Services Brochures
Landmark Industrial Services BrochuresLandmark Industrial Services Brochures
Landmark Industrial Services Brochures
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide ToolsFlank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
 
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
 
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
Mikael Kuokkkanen, Inspecta Nuclear (Švedija), „Visagino VAE projektas. Techn...
 

Res desgnr obligmsir_20140219_b

  • 1. RISK ENGINEERING SOCIETY Legal Obligations for OHS Risk Minimisation by Designers and Suppliers of Mining Machinery 19th February 2014 Engineers Australia – West Perth © Copyright of all content owned by EUC Engineering Pty Ltd or others. No content may be reproduced without prior written consent of EUC Engineering Pty Ltd.
  • 2. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] MIKE DEAN – ABOUT ME • Electrical Engineer (UWA, 1984). • Iron Ore industry 1981-87 and 1992-2000 (15 years). • Insurance industry 2000-2003 – Energy & Mining Clients – Intro to results when things go wrong. • In 2004 completed Grad Dip Risk Management – UNSW Safety Science • Since 2004 minerals processing risk & safety involvement (mainly alumina, iron ore) • Since 2010 functional safety for machinery (iron ore industry) (to AS 62061/ISO 13849) and underground mine winder (2013, to AS 61508).
  • 3. DISCLAIMERS • • • • [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] I am not a lawyer and I don’t work for a government department. I have simply read the legislation and some relevant legal commentary. None of this presentation should be considered “legal advice”. Only some key aspects of compliance relevant to “designers & suppliers of mining machinery” are being highlighted in this presentation. ACKNOWLEDGMENTS & SOURCES • Richard Robinson’s paper “Near enough not safe enough” [(Jan 2014), Engineers Australia Magazine] got me thinking about this subject and has formed a basis for the content. • “The Relationship Between ‘Reasonably Practicable’ and Risk Management Regulation” (2004), Bluff & Johnstone (http://alturl.com/5eksi). • HSE UK website (ALARP suite of guidance).
  • 4. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] PRESENTATION OUTLINE • • • • What Legislation Applies & Where To Find It. What are the Legal Obligations for Designers & Suppliers. What is “Reasonably Practicable”. Observations on Why Conventional OHS “Risk Management” Doesn’t Achieve Compliance. • Model WHS Law – Possible Changes to Obligations? • Summary. • Question Time.
  • 5. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] SCOPE • Western Australian “mines”. • Other facilities have own legislation: • Petroleum and Geothermal Energy Resources . • Rail. • “Other” business sectors. • As a designer/supplier: You need to know which legislation applies. • Facility owners need to make this clear in contractual documentation.
  • 6. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] RELEVANT LEGISLATION & WHERE TO FIND IT • Two main pieces of applicable legislation: • Mines Safety & Inspection Act (MSIA)(1994). • Mines Safety & Inspection Regulations (MSIR)(1995). • Compliance to both is required. • Can easily obtain copies of this legislation for free at: • http://www.slp.wa.gov.au/ • In addition there are approved Codes of Practice available at. • http://www.dmp.wa.gov.au/6694.aspx#6884
  • 7. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHO ADMINISTERS? • Department Mines & Petroleum (DMP) – Resources Safety
  • 8. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] ACT & REGULATIONS – WHAT’S THE DIFFERENCE? • For the keen – but not hugely relevant to the presentation: • • • • • Acts become law by passage through both houses in the Parliament, acceptance by the Governor and then proclamation in the Government Gazette. Regulations are a form of “subsidiary (or delegated) legislation”. Subsidiary legislation can be enacted by the Governor, Ministers or other bodies as allowed for under an Act. The Act contains the “law”, whereas the Regulations are specific means by which the law is to be observed. For more info: http://www.department.dotag.wa.gov.au/_files/How_to_read_legislation.pdf • The above is maybe of interest(?) – but compliance with both the Act and Regulations is required (So you need a copy of both.)
  • 9. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] MSIA (1994) – OBJECTIVES OF THE ACT • Objects (Part 1 s3 (1)) • … c) to protect employees against the risks associated with mines, mining operations, work systems at mines, and plant and hazardous substances at mines by eliminating those risks, or imposing effective controls in order to minimize them; • …
  • 10. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIA (1994) Part 2 s14 – These are “Duties” under the Act… Remember: “…must, so far as is practicable - …”
  • 11. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY
  • 12. PENALTIES FOR BREACH OF MSIA (1994) S14 [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] • • From s15 and s4A. Penalties below are for “First Offence” only. Penalties for subsequent offences are +25% on fines for first offence. • Gross Negligence is defined in s8B (next slide). Nature of Breach Causing death or serious harm (due to Gross Negligence) Penalty Level 4 Causing Death or Serious Harm (but not Gross Negligence) 3 Not Causing Death or Serious Harm & Not Gross Negligence 2 Individual Corp $250,000 and $500,000 2 years imprisonment $200,000 $400,000 $100,000 $200,000
  • 13. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] GROSS NEGLIGENCE DEFINITION (S8B)
  • 14. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] SOME FURTHER RELEVANT BITS (FOR OTHER PARTIES) • MSIA (1994) • For installers/constructors – See Part 2 s14 (2). • For designers/constructors of buildings or structures – See Part 2 s14 (3). • For manufacturers, importers and suppliers of “substances” for use at a mine – See Part 2 s14 (4).
  • 15. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIR (1995)
  • 16. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIR (1995) • See also sub-reg (2)(b) and (c) – for “powered mobile plant”
  • 17. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIR (1995) See MSIR for list of items (a) to (f) that must be provided to the manufacturer by the designer (See next slide).
  • 18. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] MSIR (1995) R6.5 CONTINUED
  • 19. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIR (1995) – Other Regulations (Heading Only provided)
  • 20. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT’S RELEVANT FOR DESIGNERS & SUPPLIERS OF MINING MACHINERY • MSIR (1995) – Other Regulations (Heading Only provided) BE AWARE!! These obligations for hazard ID, risk assessment and risk reduction under the MSIR “ripple forward” and are inherited by the first party in the “supply chain” who is the legal entity in Western Australia – this in addition to their own duties under the Act & Regs. Inside WA E.g. (Ref r6.9): Designer Manufacturer Outside WA Importer Sale of Plant Constructor Importer inherits obligations of designer & manufacturer under MSIR for hazard ID/risk assessment and risk reduction Client/Owner
  • 21. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] PENALTIES FOR BREACH OF MSIR (1995) R6.4 TO R6.14 • • • From r17.1 – Penalties below are for “First Offence” only. Penalties for subsequent offences are +25% on fines for first offence. Penalties apply to each regulation not complied with. Employee Individual Corporation $5,000 $25,000 $50,000
  • 22. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] OTHER SPECIFIC REGULATIONS • Note: There are likely to be other regulations requiring your designs to include certain measures and features. • These are not specifically identified here in this presentation. • You need to read and understand any plant & machinery specific requirements made in the MSIR – See for example: • Part 4 (General Safety Requirements). • Part 5 (Electricity in mines). • r6.26 - 6.31 (Pressurised plant, moving parts, hot or cold parts, electrical plant, industrial robots, lasers). • r6.32 – 6.40 (Classified plant)….
  • 23. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] OTHER RELEVANT DOCUMENTS - CODES OF PRACTICE • Endorsed by MIAC and Approved by the Minister (as provided under MSIA). • Provides practical guidance. • This Code of Practice addresses “Safeguarding of machinery & plant”. • Available for free at http://www.dmp.wa.gov.au/6694.a spx#6884. • Compliance to code not mandatory, but may be used by courts as representing the standard. • Non-compliance with code not sufficient for prosecution. • Get, read and deploy this document.
  • 24. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] BACK TO THE KEY ISSUE – MSIA (1994) S14
  • 25. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] GETTING TO THE BOTTOM OF “SO FAR AS IS PRACTICABLE” – DEFINITION IN MSIA • (MSIA (1994) s4) “Practicable - means reasonably practicable having regard, where the context permits, to — (a) the severity of any potential injury or harm to health that may be involved and the degree of risk of such injury or harm occurring; and (b) the state of knowledge about — (i) the injury or harm to health referred to in paragraph (a); and (ii) the risk of that injury or harm to health occurring; and (iii) means of removing or mitigating the potential injury or harm to health; and (c) the availability, suitability, and cost of the means referred to in paragraph (b)(iii); “
  • 26. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHAT DOES “REASONABLY PRACTICABLE” MEAN? • “Complex” legal topic – with considerable case law/papers. • Involves weighing up (judgement) between: • • “Quantum of risk” on one hand The “Cost” of the measure to avert the risk on the other. • Only if the “cost” is grossly disproportionate to the risk reduction achieved can the measure be called NOT “reasonably practicable”. • The “balance” and decision has to be made BEFORE the incident (not after). • If the judiciary make a judgement (afterwards) it will involve what a “reasonable” person should have done and should have known in making or not making a decision. • • Suggested reference for more info is “The Relationship Between ‘Reasonably Practicable’ and Risk Management Regulation” (2004), Bluff & Johnstone (http://alturl.com/5eksi). Also HSE UK has excellent guidance on this subject: http://www.hse.gov.uk/risk/theory/alarp.htm.
  • 27. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] GUIDANCE ON HOW TO DO IT (REASONABLY PRACTICABLE) Governance Questions (Tests of the results) • Step One: Identifying the Circumstances, Hazards and Risks • (You need to do this under the MSIR anyway – Ref r6.3). • Step Two – Determine What You Can Do (Ignoring Cost) • • • • Use the hierarchy of controls (NB: Currently not a legislated requirement in WA – but coming soon). Look at options. Don’t eliminate an option at this stage due to “cost”. Record the process. • Step Three – Determine What You are Reasonably Able to Do • • • • Carefully – keeping in mind the severity/risk of harm – decide what can reasonably be done. Only eliminate risk reduction measures – which are clearly “unreasonable” to do. Err on the side of caution. Cost can be a valid reason for not proceeding with a risk reduction measure. Record the process & decision making. • Step Four – Periodically Review Decisions & Outcomes • Things change. You have to account for this in the design/delivery process. What would a “reasonable” person know or ought to know about the hazards & risks? What would a “reasonable” person know or ought to know about the ways of eliminating or minimising the risk? Is the process and decision making robust? Have valid risk reduction measures been missed, glossed over or discarded? Review process in place? This guidance is from: http://www.safeworkaustralia.gov.au/sites/SWA/about/Publications/Documents/774/Guide-ReasonablyPracticable.pdf
  • 28. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14 It is important to note: The conventional “risk management” approach according to many company risk management guidelines – focussed at achieving a company defined tolerable level of risk. DOES NOT AUTOMATICALLY YIELD Compliance with the (s14) MSIA/MSIR requirements for “so far as is practicable” hazard/risk minimisation …. • The process of the conventional “risk management” approach is not usually targeted at determining/documenting “so far as is practicable” decisions. • This is an important reason why these MSIA/MSIR obligations can be missed. • Important issue for designers … and those involved in delivering risk management/workshops etc to designers (and owners, operators).
  • 29. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14 • From AS/NZS ISO 31000:2009 AS/NZS ISO 31000:2009 doesn’t explicitly address treating risks until there are no further “reasonably practicable” risk reduction measures available.
  • 30. [CLIENT – EDIT IN MASTER SLIDE WHY CONVENTIONAL “RISK MANAGEMENT” PROCESSES CAN VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] FAIL TO ACHIEVE COMPLIANCE TO MSIA (1994) S14- CONTINUED Typically company “risk management” processes involve: 1-Low 2-Minor Severity 3-Moderate 4-Major 5-Critical 5-Almost Certain 11 16 20 23 25 4-Likely 7 12 17 21 24 3-Possible 4 8 13 18 22 2-Unlikely 2 Likelihood 1. 2. Hazard/scenario identification. {Possibly – risk assess “inherent” risk of scenario} 3. Identify existing risk controls. 4. Risk assess current level of risk. 5. Compare risk level to tolerable levels (if “low” risk – go to Step 10, otherwise go to Step 6). 6. Identify additional (new) risk controls. 7. Risk assess future risk level. 8. Compare risk level to tolerable levels (if “low” risk – go to Step 9, otherwise go to Step 6). 9. Implement additional/new risk controls. 10. Periodic review. 1-Rare IMPORTANT! 9 14 19 The MSIA doesn’t require that 1 3 10 the risk is6 as low as a 15 company defined tolerable risk level. It requires you determine and implement “ALL reasonably practicable” measures to reduce exposure to the hazard(s)– and to not stop until you have. 5
  • 31. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] PRACTICAL EXAMPLE – CONVENTIONAL HAZID & RISK ASSESSMENT
  • 32. [CLIENT – EDIT PRACTICAL EXAMPLE – CONVENTIONAL HAZID & RISK ASSESSMENT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] Hydraulic hoses near a large hydraulic cylinder near a walkway • Hazard: Hydraulic hose containing high pressure hydraulic fluid. • Risk: Hose (or fitting) failure with person in vicinity causing injury. • Severity: LTI (Moderate). • Risk Controls: • Fit for purpose/AS compliant equipment specified. • Routine maintenance & inspection. • Personnel wearing PPE. • Assessed likelihood: Unlikely. • Risk Level: “Green” “9” – Acceptable risk. • Move on to next hazard…. 2-Minor Severity 3-Moderate 4-Major 5-Critical 5-Almost Certain 11 16 20 23 25 4-Likely 7 12 17 21 24 3-Possible 4 8 13 18 22 2-Unlikely 2 5 9 14 19 1-Rare Is this process familiar to anyone in the room….!! 1-Low 1 3 6 10 15 Likelihood
  • 33. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] CONTRAST WITH S14 MSIA REQUIREMENTS • Following slide is a hypothetical approach to meeting the s14 MSIA requirements of the machine designer addressing the same hazard. • Caution: • This is a “discussion” starter to address a perceived deficiency in current practice. • Methodology has not been “endorsed” by risk fraternity nor is it endorsed as achieving s14 compliance by DMP.
  • 34. [CLIENT – EDIT PRACTICAL EXAMPLE – S14 MSIA – POSSIBLE APPROACH IN MASTER SLIDE VIEW] [PROJECT] Hydraulic hoses near a large hydraulic cylinder near a walkway • Hazard: Hydraulic hose containing high pressure hydraulic fluid. • Risk: Hose (or fitting) failure with person in vicinity causing injury. • Severity: Burns or pressurised liquid injury (requires hospitalisation) (=“Major”). Evidence presented of hydraulic system hazards (see note below). • Likelihood: Assessed as Unlikely based on hose/fitting failure data. Level of Risk informs degree of focus on • Risk: High (14). control measures • Establish available risk reduction measures according hierarchy of controls (see next slide). Note: See for eg: http://www.dennismac.co.uk/hands/hyd/index.html. [SUBJECT/EVENT] – [DATE] Gain knowledge of “Severity”. Consider reasonable worst case. This operator was burned when a hydraulic hose, neglected during maintenance, burst and spewed hydraulic oil, at normal operating temperature, over his entire body (from HandS – Dennis Mac). This approach is the key differentiator from conventional risk assessment
  • 35. Reasonably– EDIT IN MASTER SLIDE VIEW] [CLIENT Rationale Practicable? [PROJECT] Hierarchy of Controls Available Measures Elimination None Identified. N/A Substitution None Identified. N/A Isolation/ Separation Hoses and fittings to relevant Australian Standards. Yes Hoses run in web of beams Yes Guarding of walkway areas Yes Engineering Controls None Identified. N/A Administrative Controls Maintenance requirements in O&M Manual Yes Hydraulic System hazards in O&M Manual Yes Standard site PPE Yes High temperature oil resistant suit over Kevlar body armour No PPE [SUBJECT/EVENT] – [DATE] This new/additional control was revealed through the MSIA compliance mindset This measure was deemed to be Not Reasonably Practicable – with rationale given User discomfort/health impacts at high ambient temperatures.
  • 36. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] PRACTICAL EXAMPLE – S14 MSIA – POSSIBLE APPROACH • Something like the previous slides isn’t often done. • Focus shifts from conventional “is risk low enough” to identifying available & reasonably practicable hazard/risk control measures. • Would add cost/time to the HAZID & Risk Assessments already being undertaken (in the conventional model). • Cost impacts on plant & machinery for WA minesites to implement all reasonably practicable hazard/risk control measures? • Suggested work is to: • • • Discuss issues outlined here – is it a “real” issue needing addressing? Obtain DMP view on how best to demonstrate MSIA s14 compliance. Expedite and improve the process so it isn’t overly onerous in time & expense.
  • 37. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] OTHER REASONS WHY COMPLIANCE NOT ACHIEVED • Companies use “Project Risk” mindset when doing risk assessment (concerned with project delivery, missing OHS risks). • Observation: You don’t run the risk of jail time if you fail to identify a project delivery risk. • Designers rely on client “risk assessment” process instead of their own.
  • 38. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] THE IMPENDING “MODEL WHS” CHANGES • From DMP website: • “New work health and safety (WHS) legislation for the Western Australian resources sector is expected to be introduced in early 2015. • This will be based on model laws developed under the harmonisation process driven by Safe Work Australia and the National Mine Safety Framework. • It is expected that this will be a single piece of safety legislation for the resources sector in Western Australia, effectively combining mining, petroleum and major hazard facilities into one act – the Work Health and Safety (Resources) Act.”
  • 39. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] NEW MODEL WHS ACT/REGS - IMPACTS • By review of Model WHS Act/Regs – there will be minor impacts on subject being discussed here. • Slightly different wording for equivalent of MSIA s14 (see s22): • Get used to hearing abbreviation “SFAIRP”. • Hierarchy of Controls embedded in Regs (see r36). • Summary is that Model WHS Act/Regs if implemented in WA will not undermine / change the current MSIA requirements (will strengthen them).
  • 40. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] OTHER RELATED TOPICS OF INTEREST • The “Safety Lifecycle” approach of AS 61508.1 offers a sound framework for treatment of all machinery & plant. • This is supported by the recent (2013) update of AS 3007 which requires a full “lifecycle” approach to risks and risk management. • Please consider. • MSIA (1995) s14 and similar clauses – need to be achieved even where Australian Standards/Codes etc require an explicit tolerable risk target (ie AS 61508 for Functional Safety). • Issue of reconciling SFAIRP and quantitative risk targets. NB: An issue for risk engineers to ponder.
  • 41. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] SUMMARY • All designs for plant & machinery need to be subjected to OHS focussed hazard ID & risk assessment. • Conventional risk assessment isn’t sufficient for MSIA (1994) s14 compliance. • MSIA (1994) s14 compliance requires that every “reasonably practicable” measure to reduce exposure of personnel to hazards – has been taken. • Demonstrating this will require additional efforts than applied in most conventional HAZID/risk assessments. • Devising a way to cost effectively do this is required. • Model WHA Act/Regs coming to WA wont change/undermine the current obligations of designers (only strengthen them).
  • 42. [CLIENT – EDIT IN MASTER SLIDE VIEW] [PROJECT] [SUBJECT/EVENT] – [DATE] THANK-YOU Questions? Mike Dean 0448 103 028 mike.dean@euceng.com.au