SlideShare a Scribd company logo
1 of 17
1
PETRUCCO GROUP
Italy Spain U.S.A.
1
www.petrucco.com
PETRUCCOPETRUCCO
GROUP
2
La Dittta fu fondata
nel 1911 da Alvise Petrucco.
Ha sede in
Cividale del Friuli
nel Nord Est dell’Italia.
STORIA DEL GRUPPO
2
COMPANY HISTORY
The company was set
in 1911, by Alvise Petrucco.
Based in Cividale del Friuli,
The Nord East, Italy
www.petrucco.com
PETRUCCO GROUP
3
DALLA FONDAZIONE AD OGGI
LA COMPAGNIA HA OPERATO
NEI SEGUENTI SETTORI:
Costruzione di:
• Strade e Ferrovie
• Ponti e Viadotti
• Fondazioni Speciali
• Impiandi Idroelettrici e Chimici
3
FROM ITS ORIGIN TO PRESENT
DATE THE COMPANY HAS BEEN
ACTIVE IN THE FOLLOWING AREAS:
Construction of :
. Roads and Railways
. Bridges and Viaducts
. Special Foundations
. Hydroelectric and Chemical
Plant
www.petrucco.com
PETRUCCO GROUP
4
Fin dal 1978 la Petrucco si è
specializzata nella realizzazione di
sottopassaggi con il sistema della
spinta oleodinamica, eseguendo
con successo ad oggi oltre 1.200
opere in Italia ed in Spagna, con
una media annuale di oltre 70
opere.
PARAMETER
PARAMETRI
FROM
DA
TO
A
WIDTH m
LARGHEZZA m
3 50
LENGTH m
LUNGHEZZA m
10 140
HEIGHT m
ALTEZZA m
2 20
WEIGHT ton
PESO ton
100 20000
4
Since 1978 Petrucco Group
specialized in the Incremental
Box Jacking System, and to date
has successfully completed over
1.200 projects in Italy and Spain
varying in size / width / length /
height /weight
www.petrucco.com
PETRUCCO GROUP
5
Installing concrete temporary base, including rear jacking wall.
Finished surface of temporary baseFinished surface of temporary base
Soletta di varo terminataSoletta di varo terminata
5
Costruzione della soletta di varo e del muro reggi spinta
6
roof of the box complete with waterproofing course applied
soletta superiore completata e impermeabilizzazione
6
7
7
PETRUCCO
SISTEMA “VERONA”
VILLAFRANCA DI VERONA (VR) – SINGOLO BINARIO
8
8
PETRUCCO
SISTEMA “VERONA”
PATENT PENDING
9
launching beams positioned under
rail support system , supported
from the top of the box
9
Travi di manovra poste sotto i
binari che scorrono sopra la
soletta superiore del monolito
10
On a project where there is a
high water table . The water
table must be lowered 50cm
below the foundation.
Normally this is a simple
procedure , by placing two or
more pumps in sump holes at
the appropriate locations.
10
Nei lavori ove vi sia
presenza d’acqua,
bisogna tenere il livello
di falda più basso di 50
cm. rispetto al piano di
scorrimento del
monolito.
11
Jacks in operation with spacers
fittet , jacks are normally fitted
in craddles.
11
Jacks stroke : 500 mm
Capacity : 300 ton force each
Martinetti e distanziatori in funzione,
I martinetti sono collocati in selle.
12
Large Box Tunnels
Villaseca - Spain , this project
was completed on time.
42.2 meter wide Box, with a height of 9.4m, 39m jacking movement
and weighing 12000 tons
12
Monolito di geande dimensione a Villaseca
13
ADJACENT BOXES
MONOLITI ADIACENTI
The Advantage on
this project was To
Build And Jacked
two boxes
at Same Time .
The Madrid M50 Project , Two Side By Side
Boxes 45 Mt Wide each.
Il progetto di Madrid M 50, largh. 45 ml. cad
13
Udine Project, Italy
14
VERONA PROJECT 1990
Large Tunnel, Doubled Box , With Mid-span
Wall, 39 Mt Long, 36 Mt Wide, 9.7 Mt Height .
Two Smaller Boxes , Each 60 Mt Long , 14.3 Mt
Wide , 7.4 Mt Height.
The Total Movement Was 150 Mt . A
intermediate Jacking Station Was Necessary to
lower the forces.
14
Monolito a doppia canna: largh. 36ml.,
lungh. 39ml., h. 9,7 ml., L. spinta 43 ml.
Monoliti piccoli: largh. 14,3 ml.,
lungh. 60 ml., h. 7,4 ml.,
L. Spinta 150 ml. Cadauno (con stazione
Intermedia di spinta)
15
PADOVA, ITALY LERIDA, SPAIN
TWO BOXES BUILT AND
JACKED INTO POSITION
NEARBY EXISTING ARCHES
15
DUE MONOLITI COSTRUITI E
SPINTI I ADIACENZA DI
VECCHIE STRUTTURE AD ARCO
16
PETRUCCO S.A. ACCREDITATIONS
16
www.petrucco.com
PETRUCCO GROUP
17
PETRUCCO U.S.A. LLC
Railroad box Jacking Systems
1576 Daytonia Rd.
Miami Beach, Fl 33141
Tel. 305 206 1133
17
PETRUCCO S.A.
ROTONDA DE PITAGORAS Nº1
NAVE 508
PARQUE EMPRESARIAL EL PILAR
28806 ALCALÁ DE HENARES
(MADRID) ESPAÑA
Tel: +34 91 8870563
Fax: +34 91 8807026
E-mail: petrucco@petrucco.com
PETRUCCO ITALIA S.R.L.
VIA FORAMITTI nº 69
33043 CIVIDALE DEL FRIULI
(UDINE)ITALIA
Tel: +39 0432 733313
Fax: +39 0432 733912
E-mail: info@petruccosrl.it
PETRUCCO
GROUP

More Related Content

Featured

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Z depliant petrucco_ridotto_inglese__italiano_versione_usa 150 ppi

  • 1. 1 PETRUCCO GROUP Italy Spain U.S.A. 1 www.petrucco.com PETRUCCOPETRUCCO GROUP
  • 2. 2 La Dittta fu fondata nel 1911 da Alvise Petrucco. Ha sede in Cividale del Friuli nel Nord Est dell’Italia. STORIA DEL GRUPPO 2 COMPANY HISTORY The company was set in 1911, by Alvise Petrucco. Based in Cividale del Friuli, The Nord East, Italy www.petrucco.com PETRUCCO GROUP
  • 3. 3 DALLA FONDAZIONE AD OGGI LA COMPAGNIA HA OPERATO NEI SEGUENTI SETTORI: Costruzione di: • Strade e Ferrovie • Ponti e Viadotti • Fondazioni Speciali • Impiandi Idroelettrici e Chimici 3 FROM ITS ORIGIN TO PRESENT DATE THE COMPANY HAS BEEN ACTIVE IN THE FOLLOWING AREAS: Construction of : . Roads and Railways . Bridges and Viaducts . Special Foundations . Hydroelectric and Chemical Plant www.petrucco.com PETRUCCO GROUP
  • 4. 4 Fin dal 1978 la Petrucco si è specializzata nella realizzazione di sottopassaggi con il sistema della spinta oleodinamica, eseguendo con successo ad oggi oltre 1.200 opere in Italia ed in Spagna, con una media annuale di oltre 70 opere. PARAMETER PARAMETRI FROM DA TO A WIDTH m LARGHEZZA m 3 50 LENGTH m LUNGHEZZA m 10 140 HEIGHT m ALTEZZA m 2 20 WEIGHT ton PESO ton 100 20000 4 Since 1978 Petrucco Group specialized in the Incremental Box Jacking System, and to date has successfully completed over 1.200 projects in Italy and Spain varying in size / width / length / height /weight www.petrucco.com PETRUCCO GROUP
  • 5. 5 Installing concrete temporary base, including rear jacking wall. Finished surface of temporary baseFinished surface of temporary base Soletta di varo terminataSoletta di varo terminata 5 Costruzione della soletta di varo e del muro reggi spinta
  • 6. 6 roof of the box complete with waterproofing course applied soletta superiore completata e impermeabilizzazione 6
  • 7. 7 7 PETRUCCO SISTEMA “VERONA” VILLAFRANCA DI VERONA (VR) – SINGOLO BINARIO
  • 9. 9 launching beams positioned under rail support system , supported from the top of the box 9 Travi di manovra poste sotto i binari che scorrono sopra la soletta superiore del monolito
  • 10. 10 On a project where there is a high water table . The water table must be lowered 50cm below the foundation. Normally this is a simple procedure , by placing two or more pumps in sump holes at the appropriate locations. 10 Nei lavori ove vi sia presenza d’acqua, bisogna tenere il livello di falda più basso di 50 cm. rispetto al piano di scorrimento del monolito.
  • 11. 11 Jacks in operation with spacers fittet , jacks are normally fitted in craddles. 11 Jacks stroke : 500 mm Capacity : 300 ton force each Martinetti e distanziatori in funzione, I martinetti sono collocati in selle.
  • 12. 12 Large Box Tunnels Villaseca - Spain , this project was completed on time. 42.2 meter wide Box, with a height of 9.4m, 39m jacking movement and weighing 12000 tons 12 Monolito di geande dimensione a Villaseca
  • 13. 13 ADJACENT BOXES MONOLITI ADIACENTI The Advantage on this project was To Build And Jacked two boxes at Same Time . The Madrid M50 Project , Two Side By Side Boxes 45 Mt Wide each. Il progetto di Madrid M 50, largh. 45 ml. cad 13 Udine Project, Italy
  • 14. 14 VERONA PROJECT 1990 Large Tunnel, Doubled Box , With Mid-span Wall, 39 Mt Long, 36 Mt Wide, 9.7 Mt Height . Two Smaller Boxes , Each 60 Mt Long , 14.3 Mt Wide , 7.4 Mt Height. The Total Movement Was 150 Mt . A intermediate Jacking Station Was Necessary to lower the forces. 14 Monolito a doppia canna: largh. 36ml., lungh. 39ml., h. 9,7 ml., L. spinta 43 ml. Monoliti piccoli: largh. 14,3 ml., lungh. 60 ml., h. 7,4 ml., L. Spinta 150 ml. Cadauno (con stazione Intermedia di spinta)
  • 15. 15 PADOVA, ITALY LERIDA, SPAIN TWO BOXES BUILT AND JACKED INTO POSITION NEARBY EXISTING ARCHES 15 DUE MONOLITI COSTRUITI E SPINTI I ADIACENZA DI VECCHIE STRUTTURE AD ARCO
  • 17. 17 PETRUCCO U.S.A. LLC Railroad box Jacking Systems 1576 Daytonia Rd. Miami Beach, Fl 33141 Tel. 305 206 1133 17 PETRUCCO S.A. ROTONDA DE PITAGORAS Nº1 NAVE 508 PARQUE EMPRESARIAL EL PILAR 28806 ALCALÁ DE HENARES (MADRID) ESPAÑA Tel: +34 91 8870563 Fax: +34 91 8807026 E-mail: petrucco@petrucco.com PETRUCCO ITALIA S.R.L. VIA FORAMITTI nº 69 33043 CIVIDALE DEL FRIULI (UDINE)ITALIA Tel: +39 0432 733313 Fax: +39 0432 733912 E-mail: info@petruccosrl.it PETRUCCO GROUP