SlideShare a Scribd company logo
1 of 19
Haven Teen Center 
Project 
Elizabeth Davidson 
Ed Moran 
Tasfia Raisa
Start 
Mon 1/13/14 
Finish 
Mon 5/26/14 
Scope 
Mon 1/13/14 - Tue 
1/14/14 
Testing 
Tue 3/4/14 - Fri 
3/7/14 
Pilot 
Wed 
5/7/14 - 
Thu 
5/15/14 
Time Line 
Documentation 
Thu 4/3/14 - Wed 5/7/14 
Training 
Mon 3/10/14 - Wed 4/2/14 
Internet/Networ 
k Connections 
Wed 2/19/14 - 
Mon 3/3/14 
Computer 
Upgrade 
Wed 
1/29/14 - 
Thu 2/6/14 
Analysis/Soft 
ware 
Requirements 
Thu 1/16/14 - 
Mon 1/27/14 
Post 
Impl 
eme 
ntati 
on 
Revi 
ew 
Wed 
5/21 
/14 - 
Mon 
5/26 
/14 
Computer lab 
development 
complete 
Mon 5/26/14 
Deplo 
yment 
Thu 
5/15/1 
4 - 
Wed 
5/21/1 
4 
February March April May
Teen center 
 Furniture 
 Tables: face same direction. 
 Cable Management: All tables 
must have wire management to 
avoid cables being run across the 
floor. 
 Chairs: One per workstation. 
 Lockdowns: All computers must be 
locked down. 
 ADA Considerations: There must be 
ample space for a wheelchair to 
turn around between rows. 
 Computers 
 Software 
 Any additional software that is 
needed for the lab must be 
approved and purchased. 
 Standard software such as 
Microsoft Office and antivirus 
software is already included 
under the District’s master licenses
Teen Center Readiness Cont. 
 Accessories 
 Power Strips: Ensure adequate 
outlets and cable length. Note 
that power strips may not be 
daisy chained, per fire code. 
 Network “Patch” Cables: Two 
(2) per computer – one for the 
computer, and one for the 
patch panel, plus two (2) more 
for each printer or other 
network devices 
 Optional Items 
 Lab Printer: Networked 
printer 
 Data Projector: Ceiling-mounted 
with brackets and 
installation (preferred) or 
locked down to a cart.
Haven Teen Center Project 
 Electrical Supply: Verify 
the electrical supply is 
adequate for the 
anticipated load. 
 Electrical Outlets: Two (2) 
outlets per workstation 
(computer and monitor). 
Network 
 Network Infrastructure: Verify 
there are adequate switch ports 
in the IDF closet to accommodate 
the number of computers (one 
port per computer). 
 Network Cabling: Verify there are 
adequate network connections. If 
new cable is being run, install two 
(2) network cables per 
workstation. 
Electrical
Facilities 
 LAB FACILITIES 
 The building housing the lab should be internet ready using wireless technology. 
 Video conferencing facilities is desirable in the lab 
 Filters are to be install in the lab to monitor access by users 
 Network printer should be installed for use by users 
 Projector is desirable in the lab to facilitate delivery of lectures 
 Original software are to be installed on system to reduce the incidence of virus 
propagation in the lab 
 Lab should be well ventilated.
Hire Low voltage Electrician 
 POWER SOURCE TO THE LAB 
 Backup must be put in place. 
 Current entering the lab must be constantly gauged and rated so as to 
ensure that surges are avoided 
 The lab should be connected to the national grid
Name Finish 
Scope complete Thu 1/16/14 
Electric complete Mon 1/13/14 
Network complete Wed 1/15/14 
ADA Considerations Mon 2/3/14 
Analysis complete Tue 1/28/14 
Software Installs complete Tue 2/11/14 
Connetions complete Mon 3/3/14 
Unit testing complete Fri 3/28/14 
Integration testing complete Tue 4/15/14 
Training materials complete Wed 4/2/14 
Documentation complete Wed 5/7/14 
Pilot complete Thu 5/15/14
Risks Probability Impact Response 
1 Conflicts between users 
High 
High 
Resolve conflict 
immediately 
2 User with negative 
attitudes toward 
project 
low 
high 
Find reasons 
3 System requirement not 
adequately identified 
med 
med 
Review weekly 
4 High level of technical 
complexity 
med 
low 
Keep Technical advisor on 
staff 
5 Project not monitored 
closely enough 
low 
med 
Follow up 
6 Inadequate estimation 
of required resources 
low 
high 
Closely monitor all needed 
resources 
7 Inexperience team 
members 
med 
med 
Train 
8 Team members lack the 
specialized skills for 
project 
med 
high 
Review skills 
9 Lack of management 
commitment to the 
project 
high 
high 
Meet with manager weekly 
10 Misunderstanding of 
requirements 
med 
med 
Review requirements twice 
a week 
11 Failure to manage end-users 
expectations 
high 
high 
Meet with end users 
weekly and get opinions, 
change plans as needed 
12 Changing scope low low Scope can change 
13 Unclear scope objectives 
med 
high 
Weekly meetings 
14 Lack of adequate user 
involvement 
low 
high 
Weekly check ups 
15 Wrong time estimate 
Risk Factors
Title 
Computer Lab 
Development 
Hardware 
Installing 
Internet 
service 
Software 
Management 
Project Management 
Planning 
Cost/schedule 
Management 
Scope 
Task 
Project 
communications 
Technical Planning 
Technical 
supervision 
System 
requirements 
Name 
Title 
Name 
Title 
Software Install 
Securtity 
Debugging 
Name 
Title 
Hardware 
requirments 
Component 
selection 
Hardware testing 
Install Modem 
Deployment and 
service 
User support 
Documentation/ 
Manual 
User training 
Installion 
management 
coordination 
Installation testing 
and verification 
Human resources 
Space and 
facilities planning 
Risk management 
Quality 
management 
Unit Testing 
Software Design 
Software 
requirement 
specifications 
Rearch 
Purchase 
Unit test plan 
Unit test 
Performance 
monitoring 
Deliverables 
Management 
System Test 
Tracking 
System 
Integration 
testing 
Acceptance testing 
Tracking 
User acceptance 
Meeting signoff 
May 18, 2014 Page 1 
W 
B 
S
Estimate Vs Actual 
0 20 40 60 80 100 120 140 
24 
32 
48 
75 
24 
24 
7 
5 
7 
2 
4 
ACTUAL HRS
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 36.0 in. 
72.0 in. x 28 ft. 
Haven Teen Center Floor 
Plan
Progress Report 
Project Name: Haven Teen Center 
Reporting Period: January to May 
Work completed this reporting period: Project Scope, Electric, Network, Furniture, Room floor plan, 
Software requirement, Computer Upgrade, Accessories, Internet, Testing, Training, Documentation, Pilot, 
and Deployment. 
Work to complete next reporting period: Post Implementation, completion of project. 
What’s going well and why: Upgrade and install have gone very well. All station have gone as planned and 
extra help has been given due to community involvement to help the teen center succeed 
What’s not going well and why: There has been some cabling issues, due to old wiring within the building, 
but everyone was able to adjust and keep projects on track. 
Suggestions/Issues: There have been a large amount of volunteers coming forth, but some of the major 
issues have been with the internet contracts. The internet contract person was limited with time, and with the 
wiring issues, project task had to be moved. 
Project changes: The cabling specialist brought in to cable the computer had to take over some internet 
connections.
Completed Lab

More Related Content

What's hot

A Radio Frequency Identification (RFID)-based wireless sensor device for drug...
A Radio Frequency Identification (RFID)-based wireless sensor device for drug...A Radio Frequency Identification (RFID)-based wireless sensor device for drug...
A Radio Frequency Identification (RFID)-based wireless sensor device for drug...Health Informatics New Zealand
 
Lie detector
Lie detectorLie detector
Lie detectorankit jha
 
James-Benoit_Resume
James-Benoit_ResumeJames-Benoit_Resume
James-Benoit_ResumeJames Benoit
 
Poised For Change
Poised For ChangePoised For Change
Poised For Changerebeccajp42
 
When do software issues get reported in large open source software
When do software issues get reported in large open source softwareWhen do software issues get reported in large open source software
When do software issues get reported in large open source softwareRAKESH RANA
 
Software Testing in a Digital Transformation Journey
Software Testing in a Digital Transformation JourneySoftware Testing in a Digital Transformation Journey
Software Testing in a Digital Transformation JourneyAlan Cafruni Gularte
 
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...South Tyrol Free Software Conference
 
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...Eero Laukkanen
 
More Aim, Less Blame: How to use postmortems to turn failures into something ...
More Aim, Less Blame: How to use postmortems to turn failures into something ...More Aim, Less Blame: How to use postmortems to turn failures into something ...
More Aim, Less Blame: How to use postmortems to turn failures into something ...Daniel Kanchev
 
Using Wireless Technology to Create Simple Laboratory Tools
Using Wireless Technology to Create Simple Laboratory ToolsUsing Wireless Technology to Create Simple Laboratory Tools
Using Wireless Technology to Create Simple Laboratory ToolsShane Cox
 
Using Machine Learning to Optimize DevOps Practices
Using Machine Learning to Optimize DevOps PracticesUsing Machine Learning to Optimize DevOps Practices
Using Machine Learning to Optimize DevOps PracticesPeter Varhol
 
DevOps Productivity Report 2013 ignite talk
DevOps Productivity Report 2013 ignite talkDevOps Productivity Report 2013 ignite talk
DevOps Productivity Report 2013 ignite talkZeroTurnaround
 
01 software testing_introduction
01 software testing_introduction01 software testing_introduction
01 software testing_introductionManishJha237
 
Risk-Based Testing - Designing & managing the test process (2002)
Risk-Based Testing - Designing & managing the test process (2002)Risk-Based Testing - Designing & managing the test process (2002)
Risk-Based Testing - Designing & managing the test process (2002)Neil Thompson
 
What is penetration testing and career path
What is penetration testing and career pathWhat is penetration testing and career path
What is penetration testing and career pathVikram Khanna
 

What's hot (19)

A Radio Frequency Identification (RFID)-based wireless sensor device for drug...
A Radio Frequency Identification (RFID)-based wireless sensor device for drug...A Radio Frequency Identification (RFID)-based wireless sensor device for drug...
A Radio Frequency Identification (RFID)-based wireless sensor device for drug...
 
Lie detector
Lie detectorLie detector
Lie detector
 
James-Benoit_Resume
James-Benoit_ResumeJames-Benoit_Resume
James-Benoit_Resume
 
Pass2 play v2 final
Pass2 play v2 finalPass2 play v2 final
Pass2 play v2 final
 
Poised For Change
Poised For ChangePoised For Change
Poised For Change
 
When do software issues get reported in large open source software
When do software issues get reported in large open source softwareWhen do software issues get reported in large open source software
When do software issues get reported in large open source software
 
Software Testing in a Digital Transformation Journey
Software Testing in a Digital Transformation JourneySoftware Testing in a Digital Transformation Journey
Software Testing in a Digital Transformation Journey
 
Software testing methods
Software testing methodsSoftware testing methods
Software testing methods
 
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...
SFSCon19 - Kristian Schwienbacher - Custom error and event tracking for Ember...
 
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...
Bottom-up Adoption of Continuous Delivery in a Stage-gate Managed Software Or...
 
Testing introduction
Testing introductionTesting introduction
Testing introduction
 
More Aim, Less Blame: How to use postmortems to turn failures into something ...
More Aim, Less Blame: How to use postmortems to turn failures into something ...More Aim, Less Blame: How to use postmortems to turn failures into something ...
More Aim, Less Blame: How to use postmortems to turn failures into something ...
 
Using Wireless Technology to Create Simple Laboratory Tools
Using Wireless Technology to Create Simple Laboratory ToolsUsing Wireless Technology to Create Simple Laboratory Tools
Using Wireless Technology to Create Simple Laboratory Tools
 
Using Machine Learning to Optimize DevOps Practices
Using Machine Learning to Optimize DevOps PracticesUsing Machine Learning to Optimize DevOps Practices
Using Machine Learning to Optimize DevOps Practices
 
DevOps Productivity Report 2013 ignite talk
DevOps Productivity Report 2013 ignite talkDevOps Productivity Report 2013 ignite talk
DevOps Productivity Report 2013 ignite talk
 
01 software testing_introduction
01 software testing_introduction01 software testing_introduction
01 software testing_introduction
 
Risk-Based Testing - Designing & managing the test process (2002)
Risk-Based Testing - Designing & managing the test process (2002)Risk-Based Testing - Designing & managing the test process (2002)
Risk-Based Testing - Designing & managing the test process (2002)
 
[Paul Holland] Bad Metrics and What You Can Do About It
[Paul Holland] Bad Metrics and What You Can Do About It[Paul Holland] Bad Metrics and What You Can Do About It
[Paul Holland] Bad Metrics and What You Can Do About It
 
What is penetration testing and career path
What is penetration testing and career pathWhat is penetration testing and career path
What is penetration testing and career path
 

Similar to Haven Teen Center Project

NSA Capstone Project III final pp
NSA Capstone Project III final ppNSA Capstone Project III final pp
NSA Capstone Project III final ppAlfonso Zamorano
 
IT331 Final Presentation
IT331 Final PresentationIT331 Final Presentation
IT331 Final PresentationQuanda Moore
 
Woodside Technology
Woodside TechnologyWoodside Technology
Woodside Technologybpemer
 
RonMalleryCurrentITResume
RonMalleryCurrentITResumeRonMalleryCurrentITResume
RonMalleryCurrentITResumeRon Mallery
 
Maha Mahmoud Fawzy Resume
Maha Mahmoud Fawzy ResumeMaha Mahmoud Fawzy Resume
Maha Mahmoud Fawzy Resumemaha fawzy
 
What I learned at Energizer
What I learned at EnergizerWhat I learned at Energizer
What I learned at EnergizerDavid Epperson
 
Cuong Duy Ngu's Resume
Cuong Duy Ngu's ResumeCuong Duy Ngu's Resume
Cuong Duy Ngu's ResumeCuong Ngu
 
Network Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping QuarterNetwork Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping Quarterrichlan421
 
Case study on Pamplona National High School Local Area Network
Case study on Pamplona National High School Local Area NetworkCase study on Pamplona National High School Local Area Network
Case study on Pamplona National High School Local Area NetworkJude Rainer
 
Mutassem Shalab CV
Mutassem Shalab CVMutassem Shalab CV
Mutassem Shalab CVpaldosar
 
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...NetworkCollaborators
 
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdf
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdfCSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdf
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdfAlNioTarusan
 
Network & computer systems administrator
Network & computer systems administratorNetwork & computer systems administrator
Network & computer systems administratorJLAUTSBAUGH
 
Ctc presentation tablet-based-data-collection20141027
Ctc presentation tablet-based-data-collection20141027Ctc presentation tablet-based-data-collection20141027
Ctc presentation tablet-based-data-collection20141027Jonathan Pletzke
 
Mpho Allen Maluleke
Mpho Allen MalulekeMpho Allen Maluleke
Mpho Allen Malulekempho allen
 
Johaysa Pereira Electronic Engineer Resume
Johaysa Pereira Electronic Engineer ResumeJohaysa Pereira Electronic Engineer Resume
Johaysa Pereira Electronic Engineer ResumeJohaysa Pereira
 

Similar to Haven Teen Center Project (20)

NSA Capstone Project III final pp
NSA Capstone Project III final ppNSA Capstone Project III final pp
NSA Capstone Project III final pp
 
IT331 Final Presentation
IT331 Final PresentationIT331 Final Presentation
IT331 Final Presentation
 
Robbie Greig CV
Robbie Greig CVRobbie Greig CV
Robbie Greig CV
 
Woodside Technology
Woodside TechnologyWoodside Technology
Woodside Technology
 
RonMalleryCurrentITResume
RonMalleryCurrentITResumeRonMalleryCurrentITResume
RonMalleryCurrentITResume
 
Maha Mahmoud Fawzy Resume
Maha Mahmoud Fawzy ResumeMaha Mahmoud Fawzy Resume
Maha Mahmoud Fawzy Resume
 
What I learned at Energizer
What I learned at EnergizerWhat I learned at Energizer
What I learned at Energizer
 
Cuong Duy Ngu's Resume
Cuong Duy Ngu's ResumeCuong Duy Ngu's Resume
Cuong Duy Ngu's Resume
 
Network Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping QuarterNetwork Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping Quarter
 
Pres_O
Pres_OPres_O
Pres_O
 
Case study on Pamplona National High School Local Area Network
Case study on Pamplona National High School Local Area NetworkCase study on Pamplona National High School Local Area Network
Case study on Pamplona National High School Local Area Network
 
Mutassem Shalab CV
Mutassem Shalab CVMutassem Shalab CV
Mutassem Shalab CV
 
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...
Cisco Connect 2018 Thailand - Introducing cisco dna assurance the future of n...
 
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdf
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdfCSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdf
CSS_G 10_Quarter 2_LAS 2 - Allan Montenegro_edited.pdf
 
Network & computer systems administrator
Network & computer systems administratorNetwork & computer systems administrator
Network & computer systems administrator
 
Ctc presentation tablet-based-data-collection20141027
Ctc presentation tablet-based-data-collection20141027Ctc presentation tablet-based-data-collection20141027
Ctc presentation tablet-based-data-collection20141027
 
Mpho Allen Maluleke
Mpho Allen MalulekeMpho Allen Maluleke
Mpho Allen Maluleke
 
Resume
ResumeResume
Resume
 
Elmer_Santos_CV
Elmer_Santos_CVElmer_Santos_CV
Elmer_Santos_CV
 
Johaysa Pereira Electronic Engineer Resume
Johaysa Pereira Electronic Engineer ResumeJohaysa Pereira Electronic Engineer Resume
Johaysa Pereira Electronic Engineer Resume
 

Haven Teen Center Project

  • 1. Haven Teen Center Project Elizabeth Davidson Ed Moran Tasfia Raisa
  • 2. Start Mon 1/13/14 Finish Mon 5/26/14 Scope Mon 1/13/14 - Tue 1/14/14 Testing Tue 3/4/14 - Fri 3/7/14 Pilot Wed 5/7/14 - Thu 5/15/14 Time Line Documentation Thu 4/3/14 - Wed 5/7/14 Training Mon 3/10/14 - Wed 4/2/14 Internet/Networ k Connections Wed 2/19/14 - Mon 3/3/14 Computer Upgrade Wed 1/29/14 - Thu 2/6/14 Analysis/Soft ware Requirements Thu 1/16/14 - Mon 1/27/14 Post Impl eme ntati on Revi ew Wed 5/21 /14 - Mon 5/26 /14 Computer lab development complete Mon 5/26/14 Deplo yment Thu 5/15/1 4 - Wed 5/21/1 4 February March April May
  • 3. Teen center  Furniture  Tables: face same direction.  Cable Management: All tables must have wire management to avoid cables being run across the floor.  Chairs: One per workstation.  Lockdowns: All computers must be locked down.  ADA Considerations: There must be ample space for a wheelchair to turn around between rows.  Computers  Software  Any additional software that is needed for the lab must be approved and purchased.  Standard software such as Microsoft Office and antivirus software is already included under the District’s master licenses
  • 4. Teen Center Readiness Cont.  Accessories  Power Strips: Ensure adequate outlets and cable length. Note that power strips may not be daisy chained, per fire code.  Network “Patch” Cables: Two (2) per computer – one for the computer, and one for the patch panel, plus two (2) more for each printer or other network devices  Optional Items  Lab Printer: Networked printer  Data Projector: Ceiling-mounted with brackets and installation (preferred) or locked down to a cart.
  • 5. Haven Teen Center Project  Electrical Supply: Verify the electrical supply is adequate for the anticipated load.  Electrical Outlets: Two (2) outlets per workstation (computer and monitor). Network  Network Infrastructure: Verify there are adequate switch ports in the IDF closet to accommodate the number of computers (one port per computer).  Network Cabling: Verify there are adequate network connections. If new cable is being run, install two (2) network cables per workstation. Electrical
  • 6. Facilities  LAB FACILITIES  The building housing the lab should be internet ready using wireless technology.  Video conferencing facilities is desirable in the lab  Filters are to be install in the lab to monitor access by users  Network printer should be installed for use by users  Projector is desirable in the lab to facilitate delivery of lectures  Original software are to be installed on system to reduce the incidence of virus propagation in the lab  Lab should be well ventilated.
  • 7. Hire Low voltage Electrician  POWER SOURCE TO THE LAB  Backup must be put in place.  Current entering the lab must be constantly gauged and rated so as to ensure that surges are avoided  The lab should be connected to the national grid
  • 8.
  • 9. Name Finish Scope complete Thu 1/16/14 Electric complete Mon 1/13/14 Network complete Wed 1/15/14 ADA Considerations Mon 2/3/14 Analysis complete Tue 1/28/14 Software Installs complete Tue 2/11/14 Connetions complete Mon 3/3/14 Unit testing complete Fri 3/28/14 Integration testing complete Tue 4/15/14 Training materials complete Wed 4/2/14 Documentation complete Wed 5/7/14 Pilot complete Thu 5/15/14
  • 10.
  • 11. Risks Probability Impact Response 1 Conflicts between users High High Resolve conflict immediately 2 User with negative attitudes toward project low high Find reasons 3 System requirement not adequately identified med med Review weekly 4 High level of technical complexity med low Keep Technical advisor on staff 5 Project not monitored closely enough low med Follow up 6 Inadequate estimation of required resources low high Closely monitor all needed resources 7 Inexperience team members med med Train 8 Team members lack the specialized skills for project med high Review skills 9 Lack of management commitment to the project high high Meet with manager weekly 10 Misunderstanding of requirements med med Review requirements twice a week 11 Failure to manage end-users expectations high high Meet with end users weekly and get opinions, change plans as needed 12 Changing scope low low Scope can change 13 Unclear scope objectives med high Weekly meetings 14 Lack of adequate user involvement low high Weekly check ups 15 Wrong time estimate Risk Factors
  • 12. Title Computer Lab Development Hardware Installing Internet service Software Management Project Management Planning Cost/schedule Management Scope Task Project communications Technical Planning Technical supervision System requirements Name Title Name Title Software Install Securtity Debugging Name Title Hardware requirments Component selection Hardware testing Install Modem Deployment and service User support Documentation/ Manual User training Installion management coordination Installation testing and verification Human resources Space and facilities planning Risk management Quality management Unit Testing Software Design Software requirement specifications Rearch Purchase Unit test plan Unit test Performance monitoring Deliverables Management System Test Tracking System Integration testing Acceptance testing Tracking User acceptance Meeting signoff May 18, 2014 Page 1 W B S
  • 13. Estimate Vs Actual 0 20 40 60 80 100 120 140 24 32 48 75 24 24 7 5 7 2 4 ACTUAL HRS
  • 14.
  • 15.
  • 16. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 36.0 in. 72.0 in. x 28 ft. Haven Teen Center Floor Plan
  • 17. Progress Report Project Name: Haven Teen Center Reporting Period: January to May Work completed this reporting period: Project Scope, Electric, Network, Furniture, Room floor plan, Software requirement, Computer Upgrade, Accessories, Internet, Testing, Training, Documentation, Pilot, and Deployment. Work to complete next reporting period: Post Implementation, completion of project. What’s going well and why: Upgrade and install have gone very well. All station have gone as planned and extra help has been given due to community involvement to help the teen center succeed What’s not going well and why: There has been some cabling issues, due to old wiring within the building, but everyone was able to adjust and keep projects on track. Suggestions/Issues: There have been a large amount of volunteers coming forth, but some of the major issues have been with the internet contracts. The internet contract person was limited with time, and with the wiring issues, project task had to be moved. Project changes: The cabling specialist brought in to cable the computer had to take over some internet connections.
  • 18.