2. Background
30-45 minutes to take out tanks, take out 4-5 tanks
Difficulty to find tanks
Affects processing and packaging
Overflow
Inaccessible, different tank sizes Highly accessible, but effective space use?
3. Issues
Limited Space
Accessibility
Safety
Number of tanks , assume 17 tanks in use
Tank Size # of Tanks Foot Print
2000 33 72’’ x 72’’
1600 6 54’’ x 58’’
1200 7 48’’ x 48‘’
1000 30 56’’ x 56’’
550 12 46’’ x 46’’
250 19 32’’ x 34’’
Total 107
10. Costs
Category Cost Description
Labor XXXX Move barriers and netting.
Materials XXXX Anchors, extension posts, sealant,
labeling, tape/paint, etc
Labor and materials to move
rack outside of pre-weigh to
expand isle
XXXX If necessary
TOTAL XXXX
Time Required to implement ~12-24 hrs Dependent on number of people
11. Action Plan
Action Item Responsible
Days
Needed Date Status
Railings Mike G./Elaine M. 4 10/23/2009 Ready to put in order
Communication of
finish goods staging Joshua Miller/Elaine M. 1
10/23/2009
Powerpoint presentation made
Flexnet Locations
An Tran/Kevin Stewart/ Elaine
M. 2
10/30/2009
Determined cannot use put-away
function, Meeting with Kevin to
finalize zones
Tags Brian Wagner/ Elaine M. 1 11/06/2009 Testing needed for hanging tags
Grinding and
Coating Tom Zollo/ Elaine M. 5/Area
11/13/2009
Three areas: Rails, 2000's, 1000's
Tape Walter Rhodes/ Elaine M. 1/Area 11/13/2009 No tape trial necessary
Training Mike G./Elaine M. 2 TBD
12. Gains
Four to five tanks
Check through whole
tank farm
Up to 40 minutes a
tank
At most two
Find by location (lane
or rack space)
Up to an estimated 10
minutes to find a tank
Current Proposed