This document discusses a project to improve governance and access to drinking water and sanitation in the rural Nirnova sub-basin of Moldova. It involves cooperation between France and Moldova. The project aims to create a local inter-municipal structure covering the Nirnova sub-basin to manage drinking water and sanitation projects. This structure would develop a multi-year program and serve as a contact point for implementing measures from the river basin management plan. The document also describes an assessment that was conducted and the creation of a "platform of mayors" to discuss establishing the inter-municipal structure and selecting initial demonstration projects.
Improving Rural Water Access in Moldova's Nirnova Sub-Basin
1. Improvement of governance and
access to drinking water and
sanitation in the rural sub-basin of
Nirnova (Moldova)
1
2. Decentralized cooperation in the field of drinking water and sanitation
FRANCE
MOLDOVA
Solidarity Water Europe
SEE/SWE
Artois Picardie Water Agency (AEAP)
Rhin Meuse Water Agency (AERM)
The National School of Water and Environment Engineering of
Strasbourg (ENGEES)
Grand Est Solidarity and Cooperations for Development (GESCOD)
Alsace-Moselle Water and Sanitation Inter-municipal Structure
(SDEA)
Rayon of Nisporeni
Rayon of Hincesti
Water Agency : Apele Moldovei
Agency of Central Regional Development
French Embassy
Convention between And
2
3. Project identification and localization : 30 municipalities concerned
Moldova two hydrographic basins Nirnova sub-basin 3
16 villages in Nisporeni
14 villages in Hincesti
2 Rayons
4. Actual context of the project
4
43 858 inhabitants
23 %
urban areas
77 %
rural areas
30 % connected to WS system
15 % without Nisporeni
Other part use wells and sources
4 municipalities have a sewer system
1 treatment plant in Nisporeni
15 % have a septic tank
VT1
5. Slide 4
VT1 Groundwater has high level of mineral not suitable for drinking/non compliant with water drinking normes
Vrabie Tudor; 07.06.2018
6. Building up a local inter-municipal structure covering the Nirnova sub-basin
5
Gathering the means and skills to reach the critical size and think at a proper scale
Become a credible project owner to design, implement and ensure the
decentralized management of drinking water and sanitation projects
Establish a feasible multi-year programme for the development of municipal water
and sanitation services, taking into account the considerable needs and constraints
Be a focal point for the local implementation, on the sub-basin of the NIRNOVA, of
concrete actions envisaged by the basin management plan of the river PRUT
7. 6
Link between inter-municipal structure and river basin Management Plan
Overall political vision of Management Plans
Local implementation of concrete measures and actions
The inter-municipal structure could be:
• consulted and give its opinion for the elaboration of the
Programme of measures (pressure on the resource, advice
on the provisions to be retained in the PoM)
• Support local implementation of selected measures
8. Project Implementation
7
A technical and institutional diagnosis of the sub-basin was carried out (Moldovan regulatory
framework, water and sanitation situation in the villages, detection of first priority projects that
can be financed)
Creation in Strasbourg in March 2018 of a Moldovan and Alsatian "platform of mayors",
resulting in:
• a consensus on the creation of an inter-municipal structure model of the Inter-
municipal Development Association (IDA) type, with a technical operator
• selection of a first series of demonstration projects (protection of catchment areas,
construction of a wetland treatment plant, improvement of access to drinking water
with pricing) for experience sharing at district scale with EUWI+ support
VT3
VT4
9. Slide 7
VT3 ...as demostrative projects
Vrabie Tudor; 07.06.2018
VT4 I would take off the technical operator. put another point saying a consensus about having a single technical/regional operator
for the region
Vrabie Tudor; 07.06.2018
10. Setting up of two task groups :
- Inter-municipal structure development
- Technical operator management
Presentation of the first solutions to the steering committee in early October
Proposal to contribute to better connect the measure implementation model developed at
Nirnova sub-basin scale with the RBMPlanning process at Danube Prut and Black sea River Basin
District scale including consistency of stakeholders involvement mechanisms
Project Implementation
8
Necessary skills
Choice
Organizing mode
Legal form
Missions
Operating mode
11. An example of intermunicipal structure for
improving water-sanitation governance in Moldova
More competent and credible project owner who could better
carry out its mission on WSS development, financing project,
attract and guide international aid
This model could constitute a standard strategic “meta-measure"
that can be integrated to the programme of measure of the
Moldavan 2 RBMP
9