Monday Tuesday Wednesday Thursday Friday Saturday Sunday
w/b 04.02.13 Task 1 - FMP Launch
Meeting
w/b 11.02.13 Half-Term
w/b 18.02.13 Book meeting slot Research into cell Research into popular Continue Research Continue Research Finish up all Research Review Schedule and
with project manager. animations kid’s shows tasks Production Log
w/b 25.02.13 Start Story planning Tweak Story planning Do storyboard Continue Storyboard Continue Storyboard Review Schedule and
Production Log
w/b 04.03.13 Finish Storyboard (Do Research popular Continue research Continue research Review Schedule and
Pitch) shows from survey from survey from survey Production Log
w/b 11.03.13 Finish research Do Risk Assessment Do preproduction Prepare for Review Schedule and
production Production Log
w/b 18.03.13 Think about what to Finish pre-production Review Schedule and
use to produce FMP Production Log
25.03.13 Easter Review Schedule and
Production Log
01.04.13 Easter Review Schedule and
Production Log
w/b 08.04.13 Start work on Flash Continue Work on Continue Work on Continue Work on Review Schedule and
Flash Flash Flash Production Log
w/b 15.04.13 Continue Work on Continue Work on Continue Work on Continue Work on Review Schedule and
Flash Flash Flash Flash Production Log
w/b 22.04.13 Continue Work on Continue Work on Finish Flash, Convert Do Evaluation Review Schedule and
Flash Flash both movies into one. Production Log
w/b 29.04.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 06.05.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 13.05.13 Spare Day Spare Day Spare Day Spare Day Review Schedule and
Production Log
w/b 20.05.13 Task 8: Evaluation DEADLINE