Risk Breakdown Structure
Risks are present in nearly every aspect of decision-making. The manner in which a
business handles risk can result with insignificant consequences, their ultimate failure, or
anywhere in between. Identifying risks and listing them in priority fails to provide insight into
the risk structure, especially given the volumes of data accompanying risks. “Traditional
qualitative assessment cannot indicate those areas of the project which require special attention,
or expose recurring themes, concentrations of risk, or ‘hot‐ spots’ of risk exposure. The best way
to deal with a large amount of data is to structure the information to aid comprehension”
(Hillson, 2003). Qualitative assessments assist in prioritization of risks individually and do not
account for exposure patterns of risk. The key to minimizing the negative impact, avoid a
particular risk, or maximize the opportunity of risk is learning to identify, understand, and then
categorize a risk into an organized, systematic framework. One such framework, risk breakdown
structure (RBS), was initially developed by The Software Engineering Institute’s Taxonomy-
Based Risk Identification in 1994 before refinement in 2002 by Dr. David Hillson. He
referenced the work breakdown structure (WBS) as a model for the RBS. His description of the
RBS is, “A source-oriented grouping of project risks that organizes and defines the total risk
exposure of the project. Each descending level represents an increasingly detailed definition of
sources of risk to the project” (Hillson, 2002). The remainder of this paper will provide more
depth and description of the RBS.
According to Pritchard, “The use of the RBS actually comprises two stages, first in
development and later in application.” Generic versions of RBS’s are frequently used as starting
points and evolve over the life of a project. Pritchard also points out that inputs for the
development stage include a list of risks sources and inputs for the application stage include the
list of project risks, the RBS itself, and an objective for the application. Outputs from the
development stage include a hierarchy of risk sources for a project or an organization. Outputs
for the application stage entail wide-ranging list of risk or list of risk categories. These inputs
and outputs are unique to each project and organization. Many types of RBSs are used by
companies and the type depends on their industry and the way they manage risks (organizational
framework). A common structure displays a two-level RBS containing a few categories at the
top. “Up to two dozen (sometimes more) categories could be used at the second level of RBS
grouped under the top categories. The level of RBS granularity should be explained in the project
risk management plan” (Raydugin, 2013). Raydugin includes operations as one level and
explains although operations are not part of a project, the project development and execution
activities are typically sources of risks in operations. An important point Raydugin mentions is
the risks brought about by change management and the way it is handled. Specifically, the
impacts of uncertain events incurred on the remainder of the project as a result of changes in the
project. To mitigate the uncertainty, reference to a RBS that is applicable across other relevant
projects proves useful. Other RBSs are project-specific and less likely to be helpful. Dr. Hillson
list the main uses and benefits of the RBS. They include risk identification aid, risk assessment,
comparison of projects or tenders, risk reporting, and lessons learned for future projects. Risk
identification can be accomplished through brainstorming and a list of identified risks can be
developed. Using this list to map to risk identified in other methods exposes gaps in risk
identification. It is critical to not forget the severity of risks when assessing them for
prioritization. In risk reporting, information on the risk is distributed to senior management by
detailing project team actions. A risk score or total number of risk is entailed within the report.
Surprisingly, lessons learned is one of the more challenging tasks usually because it is not
usually stored in an accessible location. Lessons learned is an important benefit that can
alleviate repeating the same mistakes. Below in Figure 1 is a simple example of a risk
breakdown structure.
Figure 1 Risk Breakdown Structure
Risk breakdown structures provide many benefits and drastically increase efficiency of
project completion. Similar to many other risk management tools, they prove to be a great asset
if they are accessible and void of uncommon jargon.
References
Hillson, D. (2003) "Using a Risk Breakdown Structure in project management", Journal
of Facilities Management, Vol. 2 Issue: 1, pp.85-97. Retrieved June 29, 2017
from http://www.emeraldinsight.com/doi/abs/10.1108/14725960410808131
Hillson, D. (2002). Use a Risk Breakdown Structure (RBS) to Understand Your Risk.
Retrieved June 29, 2017 from http://www.risk-doctor.com/pdf-files/rbs1002.pdf
Pritchard, C. (2014). Risk Management Concepts and Guidance, Fifth Edition. Hoboken:
CRC Press.
Raydugin, Y. (2013). Project risk management: essential methods for project teams and
decision makers. Hoboken, NJ: John Wiley & Sons.

More Related Content

What's hot

Why Your Organization Should Leverage Data Science for Risk Intelligence and ...
Why Your Organization Should Leverage Data Science for Risk Intelligence and ...Why Your Organization Should Leverage Data Science for Risk Intelligence and ...
Why Your Organization Should Leverage Data Science for Risk Intelligence and ...Resolver Inc.
 
Project risk management notes bagamoyo 12.10.2017 final v1
Project risk management  notes bagamoyo 12.10.2017 final v1Project risk management  notes bagamoyo 12.10.2017 final v1
Project risk management notes bagamoyo 12.10.2017 final v1EMAC Consulting Group
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk ManagementResolver Inc.
 
How to Prove the Value of Security Investments
How to Prove the Value of Security InvestmentsHow to Prove the Value of Security Investments
How to Prove the Value of Security InvestmentsResolver Inc.
 
Aligning Risk Management with ITIL
Aligning Risk Management with ITILAligning Risk Management with ITIL
Aligning Risk Management with ITILAustin Songer
 
Risk Based Security Management
Risk Based Security ManagementRisk Based Security Management
Risk Based Security ManagementLuis Martins
 
Risk Management Case Study - Applied Concepts
Risk Management Case Study - Applied ConceptsRisk Management Case Study - Applied Concepts
Risk Management Case Study - Applied ConceptsResolver Inc.
 
Information Security - Implementation Effectiveness
Information Security -  Implementation EffectivenessInformation Security -  Implementation Effectiveness
Information Security - Implementation EffectivenessVenkidesan Narayanan
 
Risk management and IT technologies
Risk management and IT technologiesRisk management and IT technologies
Risk management and IT technologiesHadi Fadlallah
 
IIA Facilitated Risk Workshop
IIA Facilitated Risk Workshop IIA Facilitated Risk Workshop
IIA Facilitated Risk Workshop Ersoy AKSOY
 
The Journey to Integrated Risk Management: Lessons from the Field
The Journey to Integrated Risk Management: Lessons from the Field The Journey to Integrated Risk Management: Lessons from the Field
The Journey to Integrated Risk Management: Lessons from the Field Resolver Inc.
 
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...WolfPAC - Integrated Risk Management
 
Elements of an Effective Enterprise Risk Management System
Elements of an Effective Enterprise Risk Management SystemElements of an Effective Enterprise Risk Management System
Elements of an Effective Enterprise Risk Management SystemRao Chalasani
 
Enterprise Risk Management for the Digital Transformation Age
Enterprise Risk Management for the Digital Transformation AgeEnterprise Risk Management for the Digital Transformation Age
Enterprise Risk Management for the Digital Transformation AgeCareer Communications Group
 
Ken Kurdziel: Enterprise Risk Management
Ken Kurdziel: Enterprise Risk ManagementKen Kurdziel: Enterprise Risk Management
Ken Kurdziel: Enterprise Risk ManagementJamesMooreCo
 

What's hot (20)

Revista PM Network
Revista PM NetworkRevista PM Network
Revista PM Network
 
Why Your Organization Should Leverage Data Science for Risk Intelligence and ...
Why Your Organization Should Leverage Data Science for Risk Intelligence and ...Why Your Organization Should Leverage Data Science for Risk Intelligence and ...
Why Your Organization Should Leverage Data Science for Risk Intelligence and ...
 
Project risk management notes bagamoyo 12.10.2017 final v1
Project risk management  notes bagamoyo 12.10.2017 final v1Project risk management  notes bagamoyo 12.10.2017 final v1
Project risk management notes bagamoyo 12.10.2017 final v1
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk Management
 
How to Prove the Value of Security Investments
How to Prove the Value of Security InvestmentsHow to Prove the Value of Security Investments
How to Prove the Value of Security Investments
 
Risk Management Frameworks
Risk Management FrameworksRisk Management Frameworks
Risk Management Frameworks
 
Aligning Risk Management with ITIL
Aligning Risk Management with ITILAligning Risk Management with ITIL
Aligning Risk Management with ITIL
 
Risk Based Security Management
Risk Based Security ManagementRisk Based Security Management
Risk Based Security Management
 
Risk indicators
Risk indicatorsRisk indicators
Risk indicators
 
Risk Management Case Study - Applied Concepts
Risk Management Case Study - Applied ConceptsRisk Management Case Study - Applied Concepts
Risk Management Case Study - Applied Concepts
 
Information Security - Implementation Effectiveness
Information Security -  Implementation EffectivenessInformation Security -  Implementation Effectiveness
Information Security - Implementation Effectiveness
 
Risk management
Risk managementRisk management
Risk management
 
Risk management and IT technologies
Risk management and IT technologiesRisk management and IT technologies
Risk management and IT technologies
 
IIA Facilitated Risk Workshop
IIA Facilitated Risk Workshop IIA Facilitated Risk Workshop
IIA Facilitated Risk Workshop
 
51_operational_risk
51_operational_risk51_operational_risk
51_operational_risk
 
The Journey to Integrated Risk Management: Lessons from the Field
The Journey to Integrated Risk Management: Lessons from the Field The Journey to Integrated Risk Management: Lessons from the Field
The Journey to Integrated Risk Management: Lessons from the Field
 
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...
Why Community-based Financial Institutions Should Practice Enterprise Risk Ma...
 
Elements of an Effective Enterprise Risk Management System
Elements of an Effective Enterprise Risk Management SystemElements of an Effective Enterprise Risk Management System
Elements of an Effective Enterprise Risk Management System
 
Enterprise Risk Management for the Digital Transformation Age
Enterprise Risk Management for the Digital Transformation AgeEnterprise Risk Management for the Digital Transformation Age
Enterprise Risk Management for the Digital Transformation Age
 
Ken Kurdziel: Enterprise Risk Management
Ken Kurdziel: Enterprise Risk ManagementKen Kurdziel: Enterprise Risk Management
Ken Kurdziel: Enterprise Risk Management
 

Similar to Risk Breakdown Structure by David Bustin

Reflect on the assigned readings for the week.1) Identify wh.docx
Reflect on the assigned readings for the week.1) Identify wh.docxReflect on the assigned readings for the week.1) Identify wh.docx
Reflect on the assigned readings for the week.1) Identify wh.docxringrid1
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship AliAbbas390458
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as OpportunityGlen Alleman
 
as response to this post 75 words if in text cite use reference 
as response to this post 75 words if in text cite use reference as response to this post 75 words if in text cite use reference 
as response to this post 75 words if in text cite use reference mallisonshavon
 
Risk Analysis Checklist and Templates for Managers
Risk Analysis  Checklist and Templates for ManagersRisk Analysis  Checklist and Templates for Managers
Risk Analysis Checklist and Templates for ManagersTahir Abbas
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxGeorgeKabongah2
 
Transforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty managementTransforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty managementHani Saad
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxjoellemurphey
 
Risk governance by David Bustin
Risk governance by David BustinRisk governance by David Bustin
Risk governance by David BustinDavid Bustin
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - PaperDaniel Ackermann
 
Project Management - Risk management
Project Management - Risk managementProject Management - Risk management
Project Management - Risk managementMaria Gomez
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
16Risk Management Methods of Risk Identific
16Risk Management  Methods of Risk Identific16Risk Management  Methods of Risk Identific
16Risk Management Methods of Risk IdentificEttaBenton28
 

Similar to Risk Breakdown Structure by David Bustin (20)

Reflect on the assigned readings for the week.1) Identify wh.docx
Reflect on the assigned readings for the week.1) Identify wh.docxReflect on the assigned readings for the week.1) Identify wh.docx
Reflect on the assigned readings for the week.1) Identify wh.docx
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Essentials of Risk Management
Essentials of Risk ManagementEssentials of Risk Management
Essentials of Risk Management
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
as response to this post 75 words if in text cite use reference 
as response to this post 75 words if in text cite use reference as response to this post 75 words if in text cite use reference 
as response to this post 75 words if in text cite use reference 
 
Risk Analysis Checklist and Templates for Managers
Risk Analysis  Checklist and Templates for ManagersRisk Analysis  Checklist and Templates for Managers
Risk Analysis Checklist and Templates for Managers
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Transforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty managementTransforming project risk management into project uncertainty management
Transforming project risk management into project uncertainty management
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
 
RM Maturity Level Development 2002
RM Maturity Level Development 2002RM Maturity Level Development 2002
RM Maturity Level Development 2002
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
Risk governance by David Bustin
Risk governance by David BustinRisk governance by David Bustin
Risk governance by David Bustin
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Risk management
Risk managementRisk management
Risk management
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
Project Management - Risk management
Project Management - Risk managementProject Management - Risk management
Project Management - Risk management
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
16Risk Management Methods of Risk Identific
16Risk Management  Methods of Risk Identific16Risk Management  Methods of Risk Identific
16Risk Management Methods of Risk Identific
 

More from David Bustin

Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...David Bustin
 
Project Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinProject Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinDavid Bustin
 
Managing IT projects by David Bustin
Managing IT projects by David BustinManaging IT projects by David Bustin
Managing IT projects by David BustinDavid Bustin
 
Risk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareRisk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareDavid Bustin
 
Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...David Bustin
 
Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.David Bustin
 
My Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinMy Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinDavid Bustin
 

More from David Bustin (7)

Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...Security Analysis Findings and Recommendations for the Department of Veterans...
Security Analysis Findings and Recommendations for the Department of Veterans...
 
Project Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David BustinProject Management: Integrating a PMO Case Study by David Bustin
Project Management: Integrating a PMO Case Study by David Bustin
 
Managing IT projects by David Bustin
Managing IT projects by David BustinManaging IT projects by David Bustin
Managing IT projects by David Bustin
 
Risk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareRisk management plan for Human Resource Software
Risk management plan for Human Resource Software
 
Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...Business it and labor strategy infrastructure enhancements to achieve corpora...
Business it and labor strategy infrastructure enhancements to achieve corpora...
 
Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.Case Problem for Global Finance, Inc.
Case Problem for Global Finance, Inc.
 
My Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David BustinMy Risk Assessment and Mitigation Strategy by David Bustin
My Risk Assessment and Mitigation Strategy by David Bustin
 

Recently uploaded

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...Khaled Al Awadi
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxgeorgebrinton95
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 

Recently uploaded (20)

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...NewBase  22 April  2024  Energy News issue - 1718 by Khaled Al Awadi  (AutoRe...
NewBase 22 April 2024 Energy News issue - 1718 by Khaled Al Awadi (AutoRe...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 

Risk Breakdown Structure by David Bustin

  • 1. Risk Breakdown Structure Risks are present in nearly every aspect of decision-making. The manner in which a business handles risk can result with insignificant consequences, their ultimate failure, or anywhere in between. Identifying risks and listing them in priority fails to provide insight into the risk structure, especially given the volumes of data accompanying risks. “Traditional qualitative assessment cannot indicate those areas of the project which require special attention, or expose recurring themes, concentrations of risk, or ‘hot‐ spots’ of risk exposure. The best way to deal with a large amount of data is to structure the information to aid comprehension” (Hillson, 2003). Qualitative assessments assist in prioritization of risks individually and do not account for exposure patterns of risk. The key to minimizing the negative impact, avoid a particular risk, or maximize the opportunity of risk is learning to identify, understand, and then categorize a risk into an organized, systematic framework. One such framework, risk breakdown structure (RBS), was initially developed by The Software Engineering Institute’s Taxonomy- Based Risk Identification in 1994 before refinement in 2002 by Dr. David Hillson. He referenced the work breakdown structure (WBS) as a model for the RBS. His description of the RBS is, “A source-oriented grouping of project risks that organizes and defines the total risk exposure of the project. Each descending level represents an increasingly detailed definition of sources of risk to the project” (Hillson, 2002). The remainder of this paper will provide more depth and description of the RBS. According to Pritchard, “The use of the RBS actually comprises two stages, first in development and later in application.” Generic versions of RBS’s are frequently used as starting points and evolve over the life of a project. Pritchard also points out that inputs for the development stage include a list of risks sources and inputs for the application stage include the
  • 2. list of project risks, the RBS itself, and an objective for the application. Outputs from the development stage include a hierarchy of risk sources for a project or an organization. Outputs for the application stage entail wide-ranging list of risk or list of risk categories. These inputs and outputs are unique to each project and organization. Many types of RBSs are used by companies and the type depends on their industry and the way they manage risks (organizational framework). A common structure displays a two-level RBS containing a few categories at the top. “Up to two dozen (sometimes more) categories could be used at the second level of RBS grouped under the top categories. The level of RBS granularity should be explained in the project risk management plan” (Raydugin, 2013). Raydugin includes operations as one level and explains although operations are not part of a project, the project development and execution activities are typically sources of risks in operations. An important point Raydugin mentions is the risks brought about by change management and the way it is handled. Specifically, the impacts of uncertain events incurred on the remainder of the project as a result of changes in the project. To mitigate the uncertainty, reference to a RBS that is applicable across other relevant projects proves useful. Other RBSs are project-specific and less likely to be helpful. Dr. Hillson list the main uses and benefits of the RBS. They include risk identification aid, risk assessment, comparison of projects or tenders, risk reporting, and lessons learned for future projects. Risk identification can be accomplished through brainstorming and a list of identified risks can be developed. Using this list to map to risk identified in other methods exposes gaps in risk identification. It is critical to not forget the severity of risks when assessing them for prioritization. In risk reporting, information on the risk is distributed to senior management by detailing project team actions. A risk score or total number of risk is entailed within the report. Surprisingly, lessons learned is one of the more challenging tasks usually because it is not
  • 3. usually stored in an accessible location. Lessons learned is an important benefit that can alleviate repeating the same mistakes. Below in Figure 1 is a simple example of a risk breakdown structure. Figure 1 Risk Breakdown Structure Risk breakdown structures provide many benefits and drastically increase efficiency of project completion. Similar to many other risk management tools, they prove to be a great asset if they are accessible and void of uncommon jargon.
  • 4. References Hillson, D. (2003) "Using a Risk Breakdown Structure in project management", Journal of Facilities Management, Vol. 2 Issue: 1, pp.85-97. Retrieved June 29, 2017 from http://www.emeraldinsight.com/doi/abs/10.1108/14725960410808131 Hillson, D. (2002). Use a Risk Breakdown Structure (RBS) to Understand Your Risk. Retrieved June 29, 2017 from http://www.risk-doctor.com/pdf-files/rbs1002.pdf Pritchard, C. (2014). Risk Management Concepts and Guidance, Fifth Edition. Hoboken: CRC Press. Raydugin, Y. (2013). Project risk management: essential methods for project teams and decision makers. Hoboken, NJ: John Wiley & Sons.