SlideShare a Scribd company logo
1 of 22
Download to read offline
The value of storage
Chris Elliott
Senior Hydropower Engineer
8th November 2016
Overview
1
• Stroud, Gloucestershire
• Hydro is largest part of the business
• High and Low head systems
• Design
• Install
• Maintain
• Screening systems
Aims of Presentation
• Outline of the type of schemes FiT has encouraged
• Aside from FiT, where does a scheme’s income come from?
• To what extent can water storage be added to a scheme to increase
• Energy capture
• Income per MWh generated
• Trends in prices leading from changes to generation mix and demand
responsivity
• TRIADs
• Wholesale prices
• New battery storage technology
What types of scheme have been built under FiT
under 15kW
schemes
•2MW
•194 schemes
15kW to 100kW
schemes
•25MW
• 362 schemes
100kW to 500kW
schemes
•54MW
•137 schemes
500kW to
2000kW schemes
•83MW
•70 schemes
2000kW to
5000kW schemes
•4MW
•1 scheme
Output<15kW
1%
15kW<Output<100kW
15%
100kW<Output<500kW
32%
500kW<Output<2000kW
50%
2000kW<Output<5000kW
2%
TOTAL INSTALLED CAPACITY BY PLANT SIZE
Mainly simple high head, no storage
What types of scheme have been built
focus on high head, no storage
Drivers
• Digression time pressures push developers to simple consents
• Lower impoundment heights
• Hard engineered intakes
• Fine screens
• Space constraints
• FiT income predominates – storage is peripheral to economics
Most FiT schemes don’t have storage
Scheme income examples –
FiT payment does not have any time sensitive element
Site pre accredited
before 2014, 99kW
size
• 75% FiT,
• 25% Other (Electricity, DUoS, TRIAD, REGO)
Site pre accredited
2015, 500kW+ size
• 59% FiT
• 41% Other (Electricity, DUoS, TRIAD, REGO)
Site pre accredited
late 2016, 500kW+
size
• 47% FiT
• 53% Other (Electricity, DUoS, TRIAD, REGO)
Non FiT income
typical PPA, example 500kW scheme
Electricity export
• c. 5p/kWh with time
sensitivity
• £88,000 p.a. for 500kW
scheme
TRIAD avoidance benefit
• £45/kW typically with
time and location
sensitivity
• £18,000 p.a. for a
500kW scheme hitting
90% TRIADs @ 90%
GTPS
GDUoS credits
• Var. p/kWh location
specific, but potentially
time sensitive
REGO
• neg.
If you have no storage:
• You are not able influence how well you hit TRIADs or maximise sale price intra
day on a STOD tariff
• You are unable to avoid spilling once at capacity
Therefore storage may increase both energy capture and £/MWh
Energy capture improvement with active upstream
storage
500kW plant, 150m head, 10000m3 storage
0
100
200
300
400
500
600
19/10/2014 00:00 19/11/2014 00:00 19/12/2014 00:00 19/01/2015 00:00 19/02/2015 00:0019/03/2015 00:00 19/04/2015 00:00 19/05/2015 00:00
Power with no storage /kW
Energy capture improvement with active upstream
storage
500kW plant, 150m head, 10000m3 storage
• Potentially look to introduce
separate storage at convenient
point upstream
• Topology
• Ownership
• Ecology
• No change to FiT accredited
scheme
• Relatively small impoundment,
modest volumes
• May avoid Reservoirs act
• Generally lower risk
structure
• Analogous to a mill pond rather
than large dam
Energy capture improvement with active upstream
storage
500kW plant, 150m head, 10000m3 storage
0
200
400
600
800
1000
1200
03/05/201507:12
03/05/201508:24
03/05/201509:36
03/05/201510:48
03/05/201512:00
03/05/201513:12
03/05/201514:24
03/05/201515:36
03/05/201516:48
03/05/201518:00
03/05/201519:12
Storage effect from summer storm
Power /kW Stored volume /m3 Total power /kW
Energy capture improvement with active upstream
storage
500kW plant, 150m head, 10000m3 storage
Extra capture – calculated to be 102MWh, value £17.1k p.a.*
*=2015 pre accreditation
Major pro – certainty that this benefit will remain for life of FiT
0
50
100
150
200
250
300
19/10/2014 00:00 19/11/2014 00:00 19/12/2014 00:00 19/01/2015 00:00 19/02/2015 00:00 19/03/2015 00:00 19/04/2015 00:00 19/05/2015 00:00
extra energy capture /kWh
Production time shifting with active upstream storage
500kW plant, 150m head, 10000m3 storage
Jan
Mar
May
Jul
Sep
Nov
0
1
2
3
4
5
6
7
8
9
Typical STOD tariff structure (weekday)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
Production time shifting with active upstream storage
500kW plant, 150m head, 5000m3 storage
0
1
2
3
4
5
6
7
8
9
10
0
1000
2000
3000
4000
5000
6000
0 10 20 30 40 50 60 70 80 90 100
April flow duration and production from stored water
Stored volume /m3 Movable production /kWh River Flow /m3s-1
Production time shifting with active upstream storage
500kW plant, 150m head, 5000m3 storage
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 2 4 6 8 10 12
Peak time capacity factor
Monthly capacity factors 1600h to 1900h No storage Monthly capacity factors 1600h to 1900h With storage
Production time shifting with active upstream storage
500kW plant, 150m head, 10000m3 storage
Value of shifting production
£1300 p.a
Derived from aiming at
maximising production
1600h – 1900h on an all
export STOD tariff
Electricity
value
£1300 p.a.
Derived from increasing
likely TRIAD capacity
factor from 91% to 99%
TRIAD
value
£variable –c. £6300 p.a.
in 22 area
The presence of storage
allows access to a
banded DUoS tariff and
optimisation of capacity
factor in the red band.
GDUoS
value
Significantly higher where
there is on-site demand
Total current value of storage
500kW plant, 150m head, 10000m3 storage
Constraints
• If you have a FiT accredited site designed to have Qdesign ≈ Qmean you
cannot scale up the plant because you lose FiT accreditation
• Reservoirs act volumes
Capacity
factor
increase
£17.1k
Minimise wasted
flow
Marginal
opportunity to
eliminate start up
volume as
turbine can run
efficiently
intermittantly
Generate
at peak
time
£1.3k
Generate at peak
times
Optimise
hitting
TRIADs and
GDUoS
£7.6k
£26.0k Total benefit
Minimise
production
loss from
plant
maintenance
Other situations where storage is significantly more
valuable
Existing storage
• If there is existing storage which can be adapted with relatively little additional regulatory and
operational burden the benefit of storage can be enhanced
On site usage
• Larger differentials between off peak export and import prices, and more time at this differential make
this more attractive than working simply on export price differentials
Flashy catchment
• Flashier catchments would usually lead to more than average spill and can benefit disproportionately
from attenuating this
Large design flow
•
Grid services
• Potentially STOR market via aggregator
Batteries
• How come batteries are the in thing if we show that the business case for
water storage is largely driven by gathering more FiTs
• Current storage capacity dominated by Hydro, but lots of hype around
batteries and other storage technology
Storage – revenue streams
Response
• Enhanced
Frequency
Response
• Firm Frequency
Response
Reserve
• Fast reserve
• Short Term
Operating
Reserve
• Capacity
Market
Price / Time shift
• Transmission or
Distribution
cost avoidance
/ payment
• Own use
• Curtailment
Avoidance
• Price arbitrage
TRIAD changes
• OFGEM open letter
• TRIADs – the three max demand HH / year – result in apportionment of
TNUoS charges
• TRIADs encourage demand reduction, but prediction “getting too good”,
high users perceived to avoid fair share
• TRIAD avoidance via embedded diesel Distributed Generation (DG) at
high users, and incentive not to just reduce on site demand, but export
as much as possible
• Government would like to encourage new CCGT via capacity Market
which is currently outcompeted by diesel DG
• But TRIADs are established and do lead to peak reduction, DNOs not
clear on what latent demand there is
• Conclusion –
• probably difficult to change
• probably hydro would not be badly hit by a broader base to
transmission network charging
Overall conclusion on storage
• A combination of improved energy capture, plus
better value for units generated makes storage on
100m head + sites worth considering
• Water storage based storage can be cost effective
especially with
– High head, flashy watercourse
– On site demand
• If you are considering a project Renewables First
are a capable partner for assessment, design,
delivery
20
8th November 2016
Thanks for your attention

More Related Content

Similar to Renewables First - storage - Chris Elliott final version

GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyInvest Northern Ireland
 
June 2015 ITM Power Company Presentation
June 2015 ITM Power Company PresentationJune 2015 ITM Power Company Presentation
June 2015 ITM Power Company PresentationRebecca Markillie
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)Suresh Sunny
 
Solving Nigeria's Power Problems
Solving Nigeria's Power ProblemsSolving Nigeria's Power Problems
Solving Nigeria's Power ProblemsOlumuyiwa Abiodun
 
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick Keatley
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick KeatleyEnterprise Europe Network | Coleraine District Energy Scheme | Patrick Keatley
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick KeatleyInvest Northern Ireland
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and TechnologyBushveld Energy
 
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...Invest Northern Ireland
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Parker Hannifin Corporation
 
Powergen off grid power supply
Powergen off grid power supplyPowergen off grid power supply
Powergen off grid power supplyHoward Wright
 
Hug Teeth
Hug TeethHug Teeth
Hug Teethroaudet
 
ITM Power Results Presentation
ITM Power Results PresentationITM Power Results Presentation
ITM Power Results PresentationITM Power
 
Closing the Deal - Selling Solar to Commercial Customers
Closing the Deal - Selling Solar to Commercial CustomersClosing the Deal - Selling Solar to Commercial Customers
Closing the Deal - Selling Solar to Commercial CustomersAlternergy
 
ITM Power Company Presentation
ITM Power Company PresentationITM Power Company Presentation
ITM Power Company PresentationRebecca Markillie
 
Company Update February 2017
Company Update February 2017Company Update February 2017
Company Update February 2017Rebecca Markillie
 
Power-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas gridPower-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas gridRebecca Markillie
 
Power-to-Gas Storing Renewable Energy in the Gas Grid
Power-to-Gas Storing Renewable Energy in the Gas GridPower-to-Gas Storing Renewable Energy in the Gas Grid
Power-to-Gas Storing Renewable Energy in the Gas GridITM Power
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements Iceland Geothermal
 

Similar to Renewables First - storage - Chris Elliott final version (20)

GB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny GowdyGB Energy storage market update and supply chain opportunities Johnny Gowdy
GB Energy storage market update and supply chain opportunities Johnny Gowdy
 
June 2015 ITM Power Company Presentation
June 2015 ITM Power Company PresentationJune 2015 ITM Power Company Presentation
June 2015 ITM Power Company Presentation
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)
 
Solving Nigeria's Power Problems
Solving Nigeria's Power ProblemsSolving Nigeria's Power Problems
Solving Nigeria's Power Problems
 
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick Keatley
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick KeatleyEnterprise Europe Network | Coleraine District Energy Scheme | Patrick Keatley
Enterprise Europe Network | Coleraine District Energy Scheme | Patrick Keatley
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and Technology
 
AllEnergy2016
AllEnergy2016AllEnergy2016
AllEnergy2016
 
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...
Energy Storage Solutions for an Intelligent Future, Dr John Harrison, Regener...
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
 
Powergen off grid power supply
Powergen off grid power supplyPowergen off grid power supply
Powergen off grid power supply
 
Hug Teeth
Hug TeethHug Teeth
Hug Teeth
 
Ntpc business strategy
Ntpc business strategyNtpc business strategy
Ntpc business strategy
 
ITM Power Results Presentation
ITM Power Results PresentationITM Power Results Presentation
ITM Power Results Presentation
 
Closing the Deal - Selling Solar to Commercial Customers
Closing the Deal - Selling Solar to Commercial CustomersClosing the Deal - Selling Solar to Commercial Customers
Closing the Deal - Selling Solar to Commercial Customers
 
ITM Power Company Presentation
ITM Power Company PresentationITM Power Company Presentation
ITM Power Company Presentation
 
Sgcp13lloyd
Sgcp13lloydSgcp13lloyd
Sgcp13lloyd
 
Company Update February 2017
Company Update February 2017Company Update February 2017
Company Update February 2017
 
Power-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas gridPower-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas grid
 
Power-to-Gas Storing Renewable Energy in the Gas Grid
Power-to-Gas Storing Renewable Energy in the Gas GridPower-to-Gas Storing Renewable Energy in the Gas Grid
Power-to-Gas Storing Renewable Energy in the Gas Grid
 
A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements A3 - Financing geothermal development: Decreasing equity requirements
A3 - Financing geothermal development: Decreasing equity requirements
 

Renewables First - storage - Chris Elliott final version

  • 1. The value of storage Chris Elliott Senior Hydropower Engineer 8th November 2016
  • 2. Overview 1 • Stroud, Gloucestershire • Hydro is largest part of the business • High and Low head systems • Design • Install • Maintain • Screening systems
  • 3. Aims of Presentation • Outline of the type of schemes FiT has encouraged • Aside from FiT, where does a scheme’s income come from? • To what extent can water storage be added to a scheme to increase • Energy capture • Income per MWh generated • Trends in prices leading from changes to generation mix and demand responsivity • TRIADs • Wholesale prices • New battery storage technology
  • 4. What types of scheme have been built under FiT under 15kW schemes •2MW •194 schemes 15kW to 100kW schemes •25MW • 362 schemes 100kW to 500kW schemes •54MW •137 schemes 500kW to 2000kW schemes •83MW •70 schemes 2000kW to 5000kW schemes •4MW •1 scheme Output<15kW 1% 15kW<Output<100kW 15% 100kW<Output<500kW 32% 500kW<Output<2000kW 50% 2000kW<Output<5000kW 2% TOTAL INSTALLED CAPACITY BY PLANT SIZE Mainly simple high head, no storage
  • 5. What types of scheme have been built focus on high head, no storage Drivers • Digression time pressures push developers to simple consents • Lower impoundment heights • Hard engineered intakes • Fine screens • Space constraints • FiT income predominates – storage is peripheral to economics Most FiT schemes don’t have storage
  • 6. Scheme income examples – FiT payment does not have any time sensitive element Site pre accredited before 2014, 99kW size • 75% FiT, • 25% Other (Electricity, DUoS, TRIAD, REGO) Site pre accredited 2015, 500kW+ size • 59% FiT • 41% Other (Electricity, DUoS, TRIAD, REGO) Site pre accredited late 2016, 500kW+ size • 47% FiT • 53% Other (Electricity, DUoS, TRIAD, REGO)
  • 7. Non FiT income typical PPA, example 500kW scheme Electricity export • c. 5p/kWh with time sensitivity • £88,000 p.a. for 500kW scheme TRIAD avoidance benefit • £45/kW typically with time and location sensitivity • £18,000 p.a. for a 500kW scheme hitting 90% TRIADs @ 90% GTPS GDUoS credits • Var. p/kWh location specific, but potentially time sensitive REGO • neg. If you have no storage: • You are not able influence how well you hit TRIADs or maximise sale price intra day on a STOD tariff • You are unable to avoid spilling once at capacity Therefore storage may increase both energy capture and £/MWh
  • 8. Energy capture improvement with active upstream storage 500kW plant, 150m head, 10000m3 storage 0 100 200 300 400 500 600 19/10/2014 00:00 19/11/2014 00:00 19/12/2014 00:00 19/01/2015 00:00 19/02/2015 00:0019/03/2015 00:00 19/04/2015 00:00 19/05/2015 00:00 Power with no storage /kW
  • 9. Energy capture improvement with active upstream storage 500kW plant, 150m head, 10000m3 storage • Potentially look to introduce separate storage at convenient point upstream • Topology • Ownership • Ecology • No change to FiT accredited scheme • Relatively small impoundment, modest volumes • May avoid Reservoirs act • Generally lower risk structure • Analogous to a mill pond rather than large dam
  • 10. Energy capture improvement with active upstream storage 500kW plant, 150m head, 10000m3 storage 0 200 400 600 800 1000 1200 03/05/201507:12 03/05/201508:24 03/05/201509:36 03/05/201510:48 03/05/201512:00 03/05/201513:12 03/05/201514:24 03/05/201515:36 03/05/201516:48 03/05/201518:00 03/05/201519:12 Storage effect from summer storm Power /kW Stored volume /m3 Total power /kW
  • 11. Energy capture improvement with active upstream storage 500kW plant, 150m head, 10000m3 storage Extra capture – calculated to be 102MWh, value £17.1k p.a.* *=2015 pre accreditation Major pro – certainty that this benefit will remain for life of FiT 0 50 100 150 200 250 300 19/10/2014 00:00 19/11/2014 00:00 19/12/2014 00:00 19/01/2015 00:00 19/02/2015 00:00 19/03/2015 00:00 19/04/2015 00:00 19/05/2015 00:00 extra energy capture /kWh
  • 12. Production time shifting with active upstream storage 500kW plant, 150m head, 10000m3 storage Jan Mar May Jul Sep Nov 0 1 2 3 4 5 6 7 8 9 Typical STOD tariff structure (weekday) 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9
  • 13. Production time shifting with active upstream storage 500kW plant, 150m head, 5000m3 storage 0 1 2 3 4 5 6 7 8 9 10 0 1000 2000 3000 4000 5000 6000 0 10 20 30 40 50 60 70 80 90 100 April flow duration and production from stored water Stored volume /m3 Movable production /kWh River Flow /m3s-1
  • 14. Production time shifting with active upstream storage 500kW plant, 150m head, 5000m3 storage 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 0 2 4 6 8 10 12 Peak time capacity factor Monthly capacity factors 1600h to 1900h No storage Monthly capacity factors 1600h to 1900h With storage
  • 15. Production time shifting with active upstream storage 500kW plant, 150m head, 10000m3 storage Value of shifting production £1300 p.a Derived from aiming at maximising production 1600h – 1900h on an all export STOD tariff Electricity value £1300 p.a. Derived from increasing likely TRIAD capacity factor from 91% to 99% TRIAD value £variable –c. £6300 p.a. in 22 area The presence of storage allows access to a banded DUoS tariff and optimisation of capacity factor in the red band. GDUoS value Significantly higher where there is on-site demand
  • 16. Total current value of storage 500kW plant, 150m head, 10000m3 storage Constraints • If you have a FiT accredited site designed to have Qdesign ≈ Qmean you cannot scale up the plant because you lose FiT accreditation • Reservoirs act volumes Capacity factor increase £17.1k Minimise wasted flow Marginal opportunity to eliminate start up volume as turbine can run efficiently intermittantly Generate at peak time £1.3k Generate at peak times Optimise hitting TRIADs and GDUoS £7.6k £26.0k Total benefit Minimise production loss from plant maintenance
  • 17. Other situations where storage is significantly more valuable Existing storage • If there is existing storage which can be adapted with relatively little additional regulatory and operational burden the benefit of storage can be enhanced On site usage • Larger differentials between off peak export and import prices, and more time at this differential make this more attractive than working simply on export price differentials Flashy catchment • Flashier catchments would usually lead to more than average spill and can benefit disproportionately from attenuating this Large design flow • Grid services • Potentially STOR market via aggregator
  • 18. Batteries • How come batteries are the in thing if we show that the business case for water storage is largely driven by gathering more FiTs • Current storage capacity dominated by Hydro, but lots of hype around batteries and other storage technology
  • 19. Storage – revenue streams Response • Enhanced Frequency Response • Firm Frequency Response Reserve • Fast reserve • Short Term Operating Reserve • Capacity Market Price / Time shift • Transmission or Distribution cost avoidance / payment • Own use • Curtailment Avoidance • Price arbitrage
  • 20. TRIAD changes • OFGEM open letter • TRIADs – the three max demand HH / year – result in apportionment of TNUoS charges • TRIADs encourage demand reduction, but prediction “getting too good”, high users perceived to avoid fair share • TRIAD avoidance via embedded diesel Distributed Generation (DG) at high users, and incentive not to just reduce on site demand, but export as much as possible • Government would like to encourage new CCGT via capacity Market which is currently outcompeted by diesel DG • But TRIADs are established and do lead to peak reduction, DNOs not clear on what latent demand there is • Conclusion – • probably difficult to change • probably hydro would not be badly hit by a broader base to transmission network charging
  • 21. Overall conclusion on storage • A combination of improved energy capture, plus better value for units generated makes storage on 100m head + sites worth considering • Water storage based storage can be cost effective especially with – High head, flashy watercourse – On site demand • If you are considering a project Renewables First are a capable partner for assessment, design, delivery 20
  • 22. 8th November 2016 Thanks for your attention