Mission Support PC Refresh 2012 Closeout
Greg Podoba
10/11/2012
Project Results
OPS PC Deployment Project
– A four-year computer refresh cycle is needed in order for users to be productive and
efficient with new operating systems and productivity software (MS-Office)
– As of completion of this project:
• 20% of OPS computers are 4 years of age or older
• 36% of OPS computers are still on Windows XP.
 Project desired outcome and factors for success
253, 20%
246, 20%
392, 32%
347, 28%
OPS Computers as of April 28, 2012
Less than 2 years
Between 2 and 3 years
Between 3 and 4 years
Greater than 4 years
650, 52%
246, 20%
182, 15%
160, 13%
OPS Computers as of October 1, 2012
Less than 2 years
Between 2 and 3 years
Between 3 and 4 years
Greater than 4 years
Project Deliverables
– Created Project Plan showing weekly milestones
– Created Process, Checklists and Tools to be used during the deployment process
– Created communication plan to be used when replacing computers
– Reviewed list of computers being replaced and conducted software inventory using
SCCM
– Reviewed Argonne Tools (SCCM/ OSD/ USMT) and made needed adjustments as
necessary.
– Completed at least six hours of hardware stress testing on each computer before
passing.
– Provided bi-weekly 1-hour Windows 7 and Office 2010 transitional overview for
affected users
– Provided Satisfaction Survey for all affected users
Project Schedule and Milestones
 Project Dates (explain variance > 20%)
Planned Finish: 08/24/12 Actual Finish: 09/21/12
 Milestone Dates (explain variance > 20%)
Milestone 1 – 10% complete (40 machines)
Planned Finish: 04/06/12 Actual Finish: 04/06/12
Milestone 2 – 15% complete (60 machines)
Planned Finish: 04/13/12 Actual Finish: 04/13/12
Milestone 3 – 30% complete (120 machines)
Planned Finish: 05/11/12 Actual Finish: 05/21/12
Project Schedule and Milestones
 Milestone Dates (explain variance > 20%)
Milestone 4 – 45% complete (180 machines)
Planned Finish: 06/08/12 Actual Finish: 06/19/12
Milestone 5 – 60% complete (240 machines)
Planned Finish: 07/06/12 Actual Finish: 07/23/12
Milestone 5 – 75% complete (300 machines)
Planned Finish: 07/27/12 Actual Finish: 08/20/12
Milestone 7 – 90% complete (360 machines)
Planned Finish: 08/17/12 Actual Finish: 09/04/12
Milestone 8 – 100% complete (400 machines)
Planned Finish: 08/24/12 Actual Finish: 09/21/12
Actual vs. Forecasted Machines Completed
0
50
100
150
200
250
300
350
400
450
Actual # of Machines Completed
Forecasted # of Machines Completed
Project Resources
 Project team members and total hours effort (explain variance > 20%)
– Staff of 4 Kemtah Contractors
• Phil Panopio - Project Leader
• Imran Khawaja - Technician
• Chad Karkos - Technician
• Milissa Keene - Technician
– Greg Podoba – Project Manager
– Chris Waterman – Desktop Support Technician
– Matt Knor – ITSA/Tools Support
– Other CIS members to assist with specialized software installations when
needed
• S2 Support with a few applications
Budgeted Hours: 560 Actual Hours: 325
 Non CIS participants division and name (explain variance > 20%)
None
 Project materials and services cost (explain variance > 20%)
Budgeted Cost: $500,000 Actual Cost: $500,000 Computers/Contractors
Planned but Currently Unfinished Project Tasks
Typical Project Startup Planning Considerations _
Project and system risks Cyber Policies
Data security Architecture compliance
Backup processes Disaster recovery
Software libraries updated Release to production checklist
Training Communications to the division
Retiring hardware and software Records mgmt. for project docs
Location of project and system docs Customer acceptance
State of the Above Planned but Unfinished Project Considerations _
• Two Refreshes still remaining – WFO Application being replaced with InfoEd.
• Donna Cardia
• Rosemary Gonzalez
Project Results Summary
43
9
1
13
7
10
13
9
31
23
58
29
152
CIS TDC LEG HR HEW OPS/OTD PMA IAD CEP NWM ESQ OCF FMS
List of Computers Deployed by Division
Hardware Burn-In Results
7, 50%
5, 36%
1, 7%
1, 7%
3.5% Failure Detected by Burn-In
Bad Motherboard
Bad DVD Drives
Bad Memory
Bad Power Supply
Overall Migration Experience
36.6%, 11 users
26.7%, 8 users
13.3%, 4 users
16.7%, 5 users
6.7%, 2 users
66.7%, 68 users
18.6%, 19 users
6.9%, 7 users
3.9%, 4 users 3.9, 4 users
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
Very Satisfied Somewhat Satisfied Neutral Somewhat Dissatisfied Very Dissatisfied
2011 Survey
2012 Survey
• Total Number of Survey Responses
• 2011 – 30 Users
• 2012 – 102 Users
• Total Number of Very Satisfied and Somewhat Satisfied
• 2011 – 63.3%
• 2012 - 85.3%
• Increase of 22% in User Satisfaction with their Overall Migration Experience
• 56 Total Attendees to one-hour Windows 7 and Office 2010 Overview session
Lessons Learned and Noteworthy Accomplishments
 Lessons Learned
– Pre-migration/strategy meeting should be held with division contacts and SME prior
to start of deployments. This assists with mitigation of any risks associated with
culture, legacy software, hardware, and peripherals.
– A centralized location for media and installation instructions would help streamline
the installation of legacy software
– Communication invite sent to user needs to be rearranged to have “You must be
present for the delivery and installation of your new computer” in the 1st paragraph
– Cultural issue with users taking the time to learn
 Noteworthy Accomplishments
– Slimmed down on unnecessary software installed on the 400 newly deployed
machines
– 90% of delivery/installation/verification completed within an hour
– Windows 7 and Office 2010 Overview received good reviews from the 56 total
attendees
– Addition of 15 minute interview with user prior to migration aided with identifying
any possible pain points to watch out for
– Mandatory 24 to 48 hour follow up after the refresh was done for every user

More Related Content

Viewers also liked

What kind of institution might distribute your media?
What kind of institution might distribute your media?What kind of institution might distribute your media?
What kind of institution might distribute your media?amelia_pickering
 
The power of human augmentation
The power of human augmentationThe power of human augmentation
The power of human augmentationcschnitzerling
 
Sculptures
SculpturesSculptures
Sculpturesiza201
 
TimBrownBankingExecutiveResume1-2
TimBrownBankingExecutiveResume1-2TimBrownBankingExecutiveResume1-2
TimBrownBankingExecutiveResume1-2Tim Brown
 
Learn at lunch Eportfolios
Learn at lunch EportfoliosLearn at lunch Eportfolios
Learn at lunch EportfolioshmillerSiena
 
Breaded the other side of colombia
Breaded the other side of colombiaBreaded the other side of colombia
Breaded the other side of colombiaeljoswarklcn
 
Keith - intro astro-Ecliptic Worksheet
Keith - intro astro-Ecliptic WorksheetKeith - intro astro-Ecliptic Worksheet
Keith - intro astro-Ecliptic WorksheetKeith Spencer
 
Euclid’ s geometry
Euclid’ s geometryEuclid’ s geometry
Euclid’ s geometrypawa9pawa
 
The Soa Brand Deck
The Soa Brand DeckThe Soa Brand Deck
The Soa Brand DeckAiyana Parks
 
Tugas 3 Matematika
Tugas 3 MatematikaTugas 3 Matematika
Tugas 3 Matematikacinjy
 
Pickup Systems LTD.odp
Pickup Systems LTD.odpPickup Systems LTD.odp
Pickup Systems LTD.odpHeidi Smithson
 
Early Grade Reading Activity Malawi (1)
Early Grade Reading Activity Malawi (1)Early Grade Reading Activity Malawi (1)
Early Grade Reading Activity Malawi (1)Sarah Bliss
 

Viewers also liked (19)

De thi hsg anh 6
De thi hsg anh 6De thi hsg anh 6
De thi hsg anh 6
 
What kind of institution might distribute your media?
What kind of institution might distribute your media?What kind of institution might distribute your media?
What kind of institution might distribute your media?
 
El Realismo
El RealismoEl Realismo
El Realismo
 
The power of human augmentation
The power of human augmentationThe power of human augmentation
The power of human augmentation
 
Sculptures
SculpturesSculptures
Sculptures
 
Thirdpartylicensereadme
ThirdpartylicensereadmeThirdpartylicensereadme
Thirdpartylicensereadme
 
TimBrownBankingExecutiveResume1-2
TimBrownBankingExecutiveResume1-2TimBrownBankingExecutiveResume1-2
TimBrownBankingExecutiveResume1-2
 
Learn at lunch Eportfolios
Learn at lunch EportfoliosLearn at lunch Eportfolios
Learn at lunch Eportfolios
 
Breaded the other side of colombia
Breaded the other side of colombiaBreaded the other side of colombia
Breaded the other side of colombia
 
Graphics portfolio
Graphics portfolioGraphics portfolio
Graphics portfolio
 
Ingles
InglesIngles
Ingles
 
Keith - intro astro-Ecliptic Worksheet
Keith - intro astro-Ecliptic WorksheetKeith - intro astro-Ecliptic Worksheet
Keith - intro astro-Ecliptic Worksheet
 
Metro power
Metro powerMetro power
Metro power
 
Euclid’ s geometry
Euclid’ s geometryEuclid’ s geometry
Euclid’ s geometry
 
The Soa Brand Deck
The Soa Brand DeckThe Soa Brand Deck
The Soa Brand Deck
 
Tugas 3 Matematika
Tugas 3 MatematikaTugas 3 Matematika
Tugas 3 Matematika
 
Pickup Systems LTD.odp
Pickup Systems LTD.odpPickup Systems LTD.odp
Pickup Systems LTD.odp
 
Early Grade Reading Activity Malawi (1)
Early Grade Reading Activity Malawi (1)Early Grade Reading Activity Malawi (1)
Early Grade Reading Activity Malawi (1)
 
Expression of luxS
Expression of luxSExpression of luxS
Expression of luxS
 

Similar to 2012 PC Refresh Closeout

Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summaryguest524810
 
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)jmariani14
 
(Agile) software development in a nutshell
(Agile) software development in a nutshell(Agile) software development in a nutshell
(Agile) software development in a nutshellJuhana Huotarinen
 
Lean Solutions – Agile Transformation at the United States Postal Service
Lean Solutions  – Agile Transformation at the United States Postal ServiceLean Solutions  – Agile Transformation at the United States Postal Service
Lean Solutions – Agile Transformation at the United States Postal ServiceITSM Academy, Inc.
 
201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin TeohHui Qin Teoh, PMP®
 
Scrum in Distributed Teams
Scrum in Distributed TeamsScrum in Distributed Teams
Scrum in Distributed TeamsCprime
 
[AKC2021] SAFe case study digital experience(Pete Rim)
[AKC2021] SAFe case study digital experience(Pete Rim)[AKC2021] SAFe case study digital experience(Pete Rim)
[AKC2021] SAFe case study digital experience(Pete Rim)AgileKoreaConference Alliance
 
Continuous Improvement, make it visible - ICSPI 2006 - Ben Linders
Continuous Improvement, make it visible - ICSPI 2006 - Ben LindersContinuous Improvement, make it visible - ICSPI 2006 - Ben Linders
Continuous Improvement, make it visible - ICSPI 2006 - Ben LindersBen Linders
 
Survey Results: Common Problems with Microsoft Teams Call Quality
Survey Results: Common Problems with Microsoft Teams Call QualitySurvey Results: Common Problems with Microsoft Teams Call Quality
Survey Results: Common Problems with Microsoft Teams Call Qualitypanagenda
 
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...GoLeanSixSigma.com
 
Agile Network India | Event | Agile Implementation in distributed teams |
Agile Network India | Event | Agile Implementation in distributed teams | Agile Network India | Event | Agile Implementation in distributed teams |
Agile Network India | Event | Agile Implementation in distributed teams | AgileNetwork
 
Capfy09 Presentation V12
Capfy09 Presentation V12Capfy09 Presentation V12
Capfy09 Presentation V12scottsbiz
 
2015 JCP Year End Summary
2015 JCP Year End Summary2015 JCP Year End Summary
2015 JCP Year End SummaryHeather VanCura
 

Similar to 2012 PC Refresh Closeout (20)

Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)
IDG MarketPulse: Virtual Graphics Processing Unit (vGPU)
 
Blackbaud project kick off summary
Blackbaud project kick off summaryBlackbaud project kick off summary
Blackbaud project kick off summary
 
(Agile) software development in a nutshell
(Agile) software development in a nutshell(Agile) software development in a nutshell
(Agile) software development in a nutshell
 
Lean Solutions – Agile Transformation at the United States Postal Service
Lean Solutions  – Agile Transformation at the United States Postal ServiceLean Solutions  – Agile Transformation at the United States Postal Service
Lean Solutions – Agile Transformation at the United States Postal Service
 
2014 JCPYearEndSummary
2014 JCPYearEndSummary2014 JCPYearEndSummary
2014 JCPYearEndSummary
 
SAP sample
SAP sampleSAP sample
SAP sample
 
The Journey to DevOps
The Journey to DevOpsThe Journey to DevOps
The Journey to DevOps
 
201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh
 
A kanban scrum mashup to deliver fp projects
A kanban scrum mashup to deliver fp projectsA kanban scrum mashup to deliver fp projects
A kanban scrum mashup to deliver fp projects
 
Scrum in Distributed Teams
Scrum in Distributed TeamsScrum in Distributed Teams
Scrum in Distributed Teams
 
[AKC2021] SAFe case study digital experience(Pete Rim)
[AKC2021] SAFe case study digital experience(Pete Rim)[AKC2021] SAFe case study digital experience(Pete Rim)
[AKC2021] SAFe case study digital experience(Pete Rim)
 
TPM CYCLE C
TPM CYCLE CTPM CYCLE C
TPM CYCLE C
 
Continuous Improvement, make it visible - ICSPI 2006 - Ben Linders
Continuous Improvement, make it visible - ICSPI 2006 - Ben LindersContinuous Improvement, make it visible - ICSPI 2006 - Ben Linders
Continuous Improvement, make it visible - ICSPI 2006 - Ben Linders
 
Survey Results: Common Problems with Microsoft Teams Call Quality
Survey Results: Common Problems with Microsoft Teams Call QualitySurvey Results: Common Problems with Microsoft Teams Call Quality
Survey Results: Common Problems with Microsoft Teams Call Quality
 
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...
SUCCESS STORY: Reducing Lead Time for Fuel Reconciliation From 10 Hours to 30...
 
ODSA Workshop
ODSA WorkshopODSA Workshop
ODSA Workshop
 
Agile Network India | Event | Agile Implementation in distributed teams |
Agile Network India | Event | Agile Implementation in distributed teams | Agile Network India | Event | Agile Implementation in distributed teams |
Agile Network India | Event | Agile Implementation in distributed teams |
 
Capfy09 Presentation V12
Capfy09 Presentation V12Capfy09 Presentation V12
Capfy09 Presentation V12
 
2015 JCP Year End Summary
2015 JCP Year End Summary2015 JCP Year End Summary
2015 JCP Year End Summary
 

2012 PC Refresh Closeout

  • 1. Mission Support PC Refresh 2012 Closeout Greg Podoba 10/11/2012
  • 2. Project Results OPS PC Deployment Project – A four-year computer refresh cycle is needed in order for users to be productive and efficient with new operating systems and productivity software (MS-Office) – As of completion of this project: • 20% of OPS computers are 4 years of age or older • 36% of OPS computers are still on Windows XP.  Project desired outcome and factors for success 253, 20% 246, 20% 392, 32% 347, 28% OPS Computers as of April 28, 2012 Less than 2 years Between 2 and 3 years Between 3 and 4 years Greater than 4 years 650, 52% 246, 20% 182, 15% 160, 13% OPS Computers as of October 1, 2012 Less than 2 years Between 2 and 3 years Between 3 and 4 years Greater than 4 years
  • 3. Project Deliverables – Created Project Plan showing weekly milestones – Created Process, Checklists and Tools to be used during the deployment process – Created communication plan to be used when replacing computers – Reviewed list of computers being replaced and conducted software inventory using SCCM – Reviewed Argonne Tools (SCCM/ OSD/ USMT) and made needed adjustments as necessary. – Completed at least six hours of hardware stress testing on each computer before passing. – Provided bi-weekly 1-hour Windows 7 and Office 2010 transitional overview for affected users – Provided Satisfaction Survey for all affected users
  • 4. Project Schedule and Milestones  Project Dates (explain variance > 20%) Planned Finish: 08/24/12 Actual Finish: 09/21/12  Milestone Dates (explain variance > 20%) Milestone 1 – 10% complete (40 machines) Planned Finish: 04/06/12 Actual Finish: 04/06/12 Milestone 2 – 15% complete (60 machines) Planned Finish: 04/13/12 Actual Finish: 04/13/12 Milestone 3 – 30% complete (120 machines) Planned Finish: 05/11/12 Actual Finish: 05/21/12
  • 5. Project Schedule and Milestones  Milestone Dates (explain variance > 20%) Milestone 4 – 45% complete (180 machines) Planned Finish: 06/08/12 Actual Finish: 06/19/12 Milestone 5 – 60% complete (240 machines) Planned Finish: 07/06/12 Actual Finish: 07/23/12 Milestone 5 – 75% complete (300 machines) Planned Finish: 07/27/12 Actual Finish: 08/20/12 Milestone 7 – 90% complete (360 machines) Planned Finish: 08/17/12 Actual Finish: 09/04/12 Milestone 8 – 100% complete (400 machines) Planned Finish: 08/24/12 Actual Finish: 09/21/12
  • 6. Actual vs. Forecasted Machines Completed 0 50 100 150 200 250 300 350 400 450 Actual # of Machines Completed Forecasted # of Machines Completed
  • 7. Project Resources  Project team members and total hours effort (explain variance > 20%) – Staff of 4 Kemtah Contractors • Phil Panopio - Project Leader • Imran Khawaja - Technician • Chad Karkos - Technician • Milissa Keene - Technician – Greg Podoba – Project Manager – Chris Waterman – Desktop Support Technician – Matt Knor – ITSA/Tools Support – Other CIS members to assist with specialized software installations when needed • S2 Support with a few applications Budgeted Hours: 560 Actual Hours: 325  Non CIS participants division and name (explain variance > 20%) None  Project materials and services cost (explain variance > 20%) Budgeted Cost: $500,000 Actual Cost: $500,000 Computers/Contractors
  • 8. Planned but Currently Unfinished Project Tasks Typical Project Startup Planning Considerations _ Project and system risks Cyber Policies Data security Architecture compliance Backup processes Disaster recovery Software libraries updated Release to production checklist Training Communications to the division Retiring hardware and software Records mgmt. for project docs Location of project and system docs Customer acceptance State of the Above Planned but Unfinished Project Considerations _ • Two Refreshes still remaining – WFO Application being replaced with InfoEd. • Donna Cardia • Rosemary Gonzalez
  • 9. Project Results Summary 43 9 1 13 7 10 13 9 31 23 58 29 152 CIS TDC LEG HR HEW OPS/OTD PMA IAD CEP NWM ESQ OCF FMS List of Computers Deployed by Division
  • 10. Hardware Burn-In Results 7, 50% 5, 36% 1, 7% 1, 7% 3.5% Failure Detected by Burn-In Bad Motherboard Bad DVD Drives Bad Memory Bad Power Supply
  • 11. Overall Migration Experience 36.6%, 11 users 26.7%, 8 users 13.3%, 4 users 16.7%, 5 users 6.7%, 2 users 66.7%, 68 users 18.6%, 19 users 6.9%, 7 users 3.9%, 4 users 3.9, 4 users 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 Very Satisfied Somewhat Satisfied Neutral Somewhat Dissatisfied Very Dissatisfied 2011 Survey 2012 Survey • Total Number of Survey Responses • 2011 – 30 Users • 2012 – 102 Users • Total Number of Very Satisfied and Somewhat Satisfied • 2011 – 63.3% • 2012 - 85.3% • Increase of 22% in User Satisfaction with their Overall Migration Experience • 56 Total Attendees to one-hour Windows 7 and Office 2010 Overview session
  • 12. Lessons Learned and Noteworthy Accomplishments  Lessons Learned – Pre-migration/strategy meeting should be held with division contacts and SME prior to start of deployments. This assists with mitigation of any risks associated with culture, legacy software, hardware, and peripherals. – A centralized location for media and installation instructions would help streamline the installation of legacy software – Communication invite sent to user needs to be rearranged to have “You must be present for the delivery and installation of your new computer” in the 1st paragraph – Cultural issue with users taking the time to learn  Noteworthy Accomplishments – Slimmed down on unnecessary software installed on the 400 newly deployed machines – 90% of delivery/installation/verification completed within an hour – Windows 7 and Office 2010 Overview received good reviews from the 56 total attendees – Addition of 15 minute interview with user prior to migration aided with identifying any possible pain points to watch out for – Mandatory 24 to 48 hour follow up after the refresh was done for every user