SlideShare a Scribd company logo
1 of 33
Download to read offline
Optimizing Agency Funding to
Deliver SB 1 Projects
By DingXin (Ding) Cheng
Director of California Pavement Preservation Center
Professor of California State University, Chico
2018 Fall Asphalt Pavement Conference
October 24 - 25, Sacramento, CA
Objective of the Study
Evaluate the current pavement management program and
treatment types of Riverside County and provide
recommendations and cost performance measures for
improving the County’s pavement management system and
improve the overall pavement condition throughout the
County Road System.
2
Project Tasks
 Task 1- Collect information related to Riverside
County pavement management program.
 Task 2- Determine cost effective M&R Strategies
for the County.
 Task 3- Evaluate the County’s Pavement
Management System.
 Task 4- Evaluate different funding and project
selection scenarios.
 Task 5- Create summary report and presentation.
3
Background on Riverside
 4th most populous county in
California, with population
about 2.36 million
 Area = 7,303 square miles
 About 2,000 miles of county
maintained roadways
4
Road Miles by Functional Class (Paved Roads)
5
2017 Total
Sections
Total Center
Miles
Total
Lane
Miles PCI
Arterial 715 425.97 887.24 70
Collector 486 229.05 455.31 70
Residential/Local 4272 914.88 1,816.99 74
Rural Local (7) 60 38.53 75.52 74
Rural Major Collector (5) 320 204.43 412.01 71
Rural Minor Arterial (4) 2 0.27 0.54 79
Rural Minor Collector (6) 126 93.97 186.67 80
Urban Collector (5) 106 45.89 96.15 64
Urban Local (7) 3 1.04 1.28 79
Urban Minor Arterial (4) 1 0.70 1.40 62
Urban Principal Arterial-Other
(3) 19 11.57 52.30 70
Total 6110 1,966.32 3,985.41 72
PCI – Pavement Condition Index
PCI Breakdown
6
• PCI Value is based on a scale of 0 to
100 (100 being the best possible
condition of pavement).
• PCI breakpoints are used to
differentiate between different levels
of pavement conditions.
• PCI breakpoints are commonly
recommended by MTC.
Decision Tree
 A decision tree is a vital part of the Pavement
Management System.
 CP2 Center reviewed County’s current decision
tree.
 Working with the County, CP2 Center developed a
new decision tree based on County’s practice and
life cycle cost.
7
Decision Tree with LCC
 A Life Cycle Cost (LCC) analysis could be used to select the
best treatment for each pavement condition category and
functional class. The Equivalent Annual Cost (EAC) can be
calculated using unit cost, x $/yd2, and expected treatment
life, n years, and inflation rate of i%.
 The equivalent annual cost methodology allows to compare
the cost effectiveness of various treatments that have
unequal lifespans.
𝐸𝐸𝐸𝐸𝐸𝐸 =
𝑥𝑥 × 𝑖𝑖
1 − 1 + 𝑖𝑖 −𝑛𝑛
8
Budget Scenarios Analyzed
 Three time periods (5, 10, and 20 year) were analyzed with various
budget scenarios to determine the best ways to improve the average
network PCI.
9
Scenario 5-Year Scenarios 10-Year Scenarios 20-Year Scenarios
1
SB1 Funding with
20% - 40% PM
SB1 Funding with
20% - 40% PM
SB1 Funding with
20% - 40% PM
2
$20 Million with
20% - 40% PM
$20 Million with
20% - 40% PM
-
3
Target – Driven Scenario –
Maintain PCI of 72
Target – Driven Scenario –
Maintain PCI of 72
-
4
SB1 Funding with Increasing
Preventive Maintenance
-
5
SB1 Funding with
Decreasing Preventive
Maintenance
-
Determination Factors
The order in which the best scenarios were
determined:
 Network PCI
 Deferred Maintenance Cost
 Average Remaining Life of Pavement
 Total Overall Cost
10
5-Year Scenarios
11
• SB 1 Funding with 20% PM – 40% PM with 4%
Inflation
$135,000,000
$140,000,000
$145,000,000
$150,000,000
$155,000,000
$160,000,000
$165,000,000
$170,000,000
73.4
73.6
73.8
74
74.2
74.4
74.6
74.8
75
75.2
20% PM 25% PM 30% PM 35% PM 40% PM
DEFERREDMAINTENANCE
COST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
5-Year SB 1 Funding with 4% Inflation
Network PCI Deferred Maintenance Cost, $
5-Year Scenarios
12
• SB 1 Funding with 20% PM – 40% PM: GIS Results with 4% Inflation Rate
and 30% PM
Very good 4071
Good (Non-
load)
374
Good (Load) 47
Poor 144
Very Poor 420
Very good 3487
Good (Non-
load)
534
Good (Load) 339
Poor 464
Very Poor 223
5-Year Scenarios
13
• $20 Million with 20% - 85% PM with 4% Inflation
$245,000,000
$250,000,000
$255,000,000
$260,000,000
$265,000,000
$270,000,000
$275,000,000
$280,000,000
$285,000,000
67.4
67.6
67.8
68
68.2
68.4
68.6
68.8
69
69.2
20%
PM
25%
PM
30%
PM
35%
PM
40%
PM
45%
PM
50%
PM
55%
PM
60%
PM
65%
PM
70%
PM
75%
PM
80%
PM
85%
PM
DEFERREDMAINTENANCECOST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
5 Year $20 Million Funding with 4% Inflation
Network PCI Deferred Maintenance Cost
5-Year Scenarios
14
• $20 Million with 20% - 85% PM with 0% Inflation
$205,000,000
$210,000,000
$215,000,000
$220,000,000
$225,000,000
$230,000,000
$235,000,000
67
67.5
68
68.5
69
69.5
70
70.5
20%
PM
25%
PM
30%
PM
35%
PM
40%
PM
45%
PM
50%
PM
55%
PM
60%
PM
65%
PM
70%
PM
75%
PM
80%
PM
85%
PM
DEFERREDMAINTENANCECOST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
5 Year $20 Million Funding with 0% Inflation
Network PCI Deferred Maintenance Cost
5-Year Scenarios
15
• $20 Million with 20% - 85% PM: GIS Results with 4% Inflation and 70% PM
Very Good 3456
Good (Non-Load) 534
Good (Load) 347
Poor 487
Very Poor 232
Very good 3549
Good (Non- load) 490
Good (Load) 171
Poor 411
Very Poor 435
Summary of findings for 5-year scenarios
 SB 1 $240 million funding with 4% inflation will
increase PCI to 75
 SB 1 $240 million funding with 2018’s dollar will
increase PCI to 76
 Minimum funding of $20 million per year will
decrease the PCI to 69
 To maintain PCI of 72, it will need $170 million for
the five year period
16
10-Year Scenarios
17
SB 1 Funding with 4% Inflation in 2027
$0
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
75.4
75.6
75.8
76
76.2
76.4
76.6
76.8
77
77.2
10% PM 15% PM 20% PM 25% PM 30% PM 35% PM 40% PM
DEFERREDMAINTENANCE
COST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
10 Year SB 1 Funding with 4% Inflation
Network PCI Series2
10-Year Scenarios
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
77.5
78
78.5
79
79.5
80
80.5
81
81.5
82
82.5
20% PM 25% PM 30% PM 35% PM 40% PM
DEFERREDMAINTENANCE
COST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
10 Year SB 1 Funding with 2018's Dollar Value
Network PCI Deferred Maintenance Cost, $
18
SB 1 Funding with 2018’s Dollar Value in 2027
10-Year Scenarios
 SB 1 Funding with 20% PM with 4% Inflation in 2018 vs. 2027
Very Good 3524
Good (Non-Load) 531
Good (Load) 332
Poor 436
Very Poor 231
Very Good 4307
Good (Non-Load) 521
Good (Load) 91
Poor 0
Very Poor 133
10-Year Scenarios
 SB 1 Funding with 20% PM with 2018’s Dollar Value in 2018 vs. 2027
20
Very Good 3524
Good (Non-
Load)
531
Good (Load) 332
Poor 436
Very Poor 231
Very Good 4606
Good (Non-
Load)
378
Good (Load) 67
Poor 0
Very Poor 1
10-Year Scenarios
 $20 Million with 20% - 40% PM with 4% Inflation in 2027
21
$464,000,000
$466,000,000
$468,000,000
$470,000,000
$472,000,000
$474,000,000
$476,000,000
$478,000,000
$480,000,000
61.4
61.6
61.8
62
62.2
62.4
62.6
62.8
63
63.2
20% PM 25% PM 30% PM 35% PM 40% PM
DEFERREDMAINTENANCECOST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
10 Year $20 Million Funding with 4% Inflation
Network PCI Deferred Maintenance Cost
10-Year Scenarios
 $20 Million with 20% - 40% PM with 4% Inflation in 2018 vs. 2027
22
Very Good 3468
Good (Non-
Load)
532
Good (Load) 345
Poor 478
Very Poor 231
Very Good 3343
Good (Non-
Load)
631
Good (Load) 124
Poor 277
Very Poor 679
Summary of findings for 10-year scenarios
 SB 1 $540 million funding with 4% inflation will increase
PCI to 77.
 SB 1 $540 million funding with 2018’s dollar will increase
PCI to 82.
 Minimum funding of $20 million per year will decrease the
PCI to 63.
 To maintain PCI of 72, it will need $425 million for the 10
year period with a 4% inflation rate.
 To maintain PCI of 72, it will need $347 million for the 10
year period with 2018’s dollar.
23
20-YearScenarios
 SB 1 Funding with 20% - 40% PM
2037
Budget $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000
Network PCI 69 69 68 68 68
Deferred Maintenance
Cost $361,161,603 $334,414,197 $343,202,954 $350,355,032 $389,439,533
Average Remaining
Life 17.94 18.05 18.17 18.24 18.32
Total Cost $839,991,729 $839,979,811 $835,327,964 $828,632,678 $812,052,870
20 Year Analysis 4% Inflation
Year Summary 20% PM 25% PM 30% PM 35% PM 40% PM
20 Year Analysis 2018’s Dollar Value
Year Summary 20% PM 25% PM 30% PM 35% PM 40% PM
2037
Budget $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000
Network PCI 80 79 79 78 77
Deferred Maintenance
Cost $34,636,949 $27,181,367 $30,703,628 $39,845,654 $35,978,951
Average Remaining Life 23.08 22.89 22.65 22.29 21.90
Total Cost $837,584,425 $837,453,641 $829,253,015 $816,278,660 $800,269,044
20-Year Scenarios
 SB 1 - Funding with 20% - 40% PM
25
$300,000,000
$310,000,000
$320,000,000
$330,000,000
$340,000,000
$350,000,000
$360,000,000
$370,000,000
$380,000,000
$390,000,000
$400,000,000
67.4
67.6
67.8
68
68.2
68.4
68.6
68.8
69
69.2
20% PM 25% PM 30% PM 35% PM 40% PM
DEFERREDMAINTENANCE
COST
NETWORKAVERAGEPCI
PERCENT PREVENTIVE MAINTENANCE
20 Year SB 1 Funding with 4% Inflation
Network PCI Deferred Maintenance Cost, $
20-Year Scenarios
 SB 1 - Funding with 20% - 40% PM with 4% Inflation in 2018 vs. 2037
26
Very Good 3507
Good (Non-
Load)
532
Good (Load) 334
Poor 450
Very Poor 231
Very Good 3323
Good (Non-
Load)
1179
Good (Load) 267
Poor 179
Very Poor 106
20-Year Scenarios
 SB 1 - Funding with 20% - 40% PM with 2018’s Dollar Value in 2018 vs. 2037
27
Very Good 3507
Good (Non-
Load)
532
Good (Load) 334
Poor 450
Very Poor 231
Very Good 4367
Good (Non-
Load)
547
Good (Load) 116
Poor 21
Very Poor 1
Summary of findings for 20 year scenarios
 SB 1 funding of $540 million for the first 10 years +
$300 million for the second 10 years
 With 4% inflation, the average network PCI will
increase to 77 at year 2027, and then decrease to
69.
 With 2018’s dollar value, the average network PCI
will increase to 82 at year 2027, and then decrease
to 80.
28
Conclusions
29
1. After reviewing the decision tree and treatments used by Riverside
County, CP2 Center worked with the County engineer and
adjusted decision tree, PCI breakpoints, and treatments. A new
decision tree was developed based on life cycle cost.
2. Over 30 different budget scenarios were analyzed by the CP2
Center. The most beneficial budget scenarios are not either fixing
the worst first or performing pavement maintenance
(PM/preservation) only.
3. The $20 million per year budget is not enough to maintain the
current average network PCI. Based on this study, the PCI value
will continue to decrease with $20 million per year of funding.
Recommendations
1. Continually update the costs and service life for each
treatment in the decision tree.
2. A life cycle cost analysis should be used to select
proper treatments for future decision tree update.
3. SB 1 funding or other funding sources are necessary
to improve the average network pavement
conditions. Riverside County has a desired goal for
the PCI to reach 75 or higher after five years; the SB
1 funding will most likely help the County reach this
goal.
30
Recommendations
4. A properly balanced preservation and fixing the
worst will give the County the best solution.
5. A balanced budget between pavement preservation
(PM) and fixing the worst roads should be utilized to
improve the County’s pavement conditions. Keys to
achieve the desired PCI include the following:
 Optimize percentages for PM and Rehab (use lowest
deferred maintenance cost)
 Use innovative treatments that can improve life cycle
cost
31
Acknowledgement
 We appreciate the Transportation Division of
the Riverside County providing funding for this
meaningful study.
 Thanks Mr. Elmer Datum of the Riverside
County, who provided consistent support to
this study!
 Thanks students research assistants Kimberly
Joselin and Riley de Wit, who worked on the
project.
 Thanks Dr. R. Gary Hicks for his review.
32
Thank you very much!
Questions?
Contact Dr. DingXin Cheng: dxcheng@csuchico.edu
Phone: 530-898-5114
33
Today Decides Tomorrow

More Related Content

Similar to Optimizing Agency Funding to Deliver SB1 projects

Pavement 101 Presentation 10 17 08
Pavement 101 Presentation 10 17 08Pavement 101 Presentation 10 17 08
Pavement 101 Presentation 10 17 08bucknam
 
Aguas Andinas Q2 Results Presentation
Aguas Andinas Q2 Results Presentation Aguas Andinas Q2 Results Presentation
Aguas Andinas Q2 Results Presentation AguasAndinas
 
Fixed Assets Turnover PowerPoint Presentation Slides
Fixed Assets Turnover PowerPoint Presentation SlidesFixed Assets Turnover PowerPoint Presentation Slides
Fixed Assets Turnover PowerPoint Presentation SlidesSlideTeam
 
Fixed Capital Evaluation PowerPoint Presentation Slides
Fixed Capital Evaluation PowerPoint Presentation SlidesFixed Capital Evaluation PowerPoint Presentation Slides
Fixed Capital Evaluation PowerPoint Presentation SlidesSlideTeam
 
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master Plan
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master PlanDon't Leave Your Facilities Needs to Chance: From Game Plan to Master Plan
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master PlanSightlines
 
TIM Results Presentation 4Q18
TIM Results Presentation 4Q18TIM Results Presentation 4Q18
TIM Results Presentation 4Q18TIM RI
 
Tim part results presentation 4 q18
Tim part   results presentation 4 q18Tim part   results presentation 4 q18
Tim part results presentation 4 q18TIM RI
 
Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Steven Quenzel
 
2 q18 earnings presentation 2018-07-26_final
2 q18 earnings presentation 2018-07-26_final2 q18 earnings presentation 2018-07-26_final
2 q18 earnings presentation 2018-07-26_finalinvestorrelationsdiscover
 
GMF 2016 Interim Results
GMF 2016 Interim ResultsGMF 2016 Interim Results
GMF 2016 Interim ResultsNick Ross
 
Tim meeting with investors - aug 2017
Tim   meeting with investors - aug 2017Tim   meeting with investors - aug 2017
Tim meeting with investors - aug 2017TIM RI
 
3 q 2017 operating results final
3 q 2017 operating results final3 q 2017 operating results final
3 q 2017 operating results finalUSCellular
 

Similar to Optimizing Agency Funding to Deliver SB1 projects (20)

California Carpet Stewardship Program Q2 2023 Results
California Carpet Stewardship Program Q2 2023 ResultsCalifornia Carpet Stewardship Program Q2 2023 Results
California Carpet Stewardship Program Q2 2023 Results
 
Pavement 101 Presentation 10 17 08
Pavement 101 Presentation 10 17 08Pavement 101 Presentation 10 17 08
Pavement 101 Presentation 10 17 08
 
CARE California Carpet Stewardship Program Q3 Results
CARE California Carpet Stewardship Program Q3 ResultsCARE California Carpet Stewardship Program Q3 Results
CARE California Carpet Stewardship Program Q3 Results
 
Aguas Andinas Q2 Results Presentation
Aguas Andinas Q2 Results Presentation Aguas Andinas Q2 Results Presentation
Aguas Andinas Q2 Results Presentation
 
2020 Budget Education Session
2020 Budget Education Session2020 Budget Education Session
2020 Budget Education Session
 
Fixed Assets Turnover PowerPoint Presentation Slides
Fixed Assets Turnover PowerPoint Presentation SlidesFixed Assets Turnover PowerPoint Presentation Slides
Fixed Assets Turnover PowerPoint Presentation Slides
 
Fixed Capital Evaluation PowerPoint Presentation Slides
Fixed Capital Evaluation PowerPoint Presentation SlidesFixed Capital Evaluation PowerPoint Presentation Slides
Fixed Capital Evaluation PowerPoint Presentation Slides
 
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master Plan
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master PlanDon't Leave Your Facilities Needs to Chance: From Game Plan to Master Plan
Don't Leave Your Facilities Needs to Chance: From Game Plan to Master Plan
 
Sqm corp pres 4q17_final
Sqm corp pres 4q17_finalSqm corp pres 4q17_final
Sqm corp pres 4q17_final
 
BVECD 2018 Compliance Report
BVECD 2018 Compliance ReportBVECD 2018 Compliance Report
BVECD 2018 Compliance Report
 
TIM Results Presentation 4Q18
TIM Results Presentation 4Q18TIM Results Presentation 4Q18
TIM Results Presentation 4Q18
 
Tim part results presentation 4 q18
Tim part   results presentation 4 q18Tim part   results presentation 4 q18
Tim part results presentation 4 q18
 
Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0
 
CA Carpet Stewardship Program Q1 2023 Results
CA Carpet Stewardship Program Q1 2023 ResultsCA Carpet Stewardship Program Q1 2023 Results
CA Carpet Stewardship Program Q1 2023 Results
 
2 q18 earnings presentation 2018-07-26_final
2 q18 earnings presentation 2018-07-26_final2 q18 earnings presentation 2018-07-26_final
2 q18 earnings presentation 2018-07-26_final
 
GMF 2016 Interim Results
GMF 2016 Interim ResultsGMF 2016 Interim Results
GMF 2016 Interim Results
 
Tim meeting with investors - aug 2017
Tim   meeting with investors - aug 2017Tim   meeting with investors - aug 2017
Tim meeting with investors - aug 2017
 
Matt Kwatinetz
Matt KwatinetzMatt Kwatinetz
Matt Kwatinetz
 
3 q 2017 operating results final
3 q 2017 operating results final3 q 2017 operating results final
3 q 2017 operating results final
 
3 q 2017 operating results final
3 q 2017 operating results final3 q 2017 operating results final
3 q 2017 operating results final
 

More from California Asphalt Pavement Association

National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...California Asphalt Pavement Association
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...California Asphalt Pavement Association
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024California Asphalt Pavement Association
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansCalifornia Asphalt Pavement Association
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolCalifornia Asphalt Pavement Association
 

More from California Asphalt Pavement Association (20)

Reducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industryReducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industry
 
Industry perspective on cold in-place recycling
Industry perspective on cold in-place recyclingIndustry perspective on cold in-place recycling
Industry perspective on cold in-place recycling
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Caltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavementsCaltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavements
 
Update on the latest research with regard to RAP
Update on the latest research with regard to RAPUpdate on the latest research with regard to RAP
Update on the latest research with regard to RAP
 
Pavement quality focus for local agencies in California
Pavement quality focus for local agencies in CaliforniaPavement quality focus for local agencies in California
Pavement quality focus for local agencies in California
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...
 
Utilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixesUtilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixes
 
Pavement Maintenance tools and technology update
Pavement Maintenance tools and technology updatePavement Maintenance tools and technology update
Pavement Maintenance tools and technology update
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiative
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industry
 
Asphalt industry EPD benchmarking update 2024
Asphalt industry EPD benchmarking update  2024Asphalt industry EPD benchmarking update  2024
Asphalt industry EPD benchmarking update 2024
 
Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials technicians
 
EPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt PlantEPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt Plant
 
EPD Benchmarks and lessons learned
EPD Benchmarks and lessons learnedEPD Benchmarks and lessons learned
EPD Benchmarks and lessons learned
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD tool
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

Optimizing Agency Funding to Deliver SB1 projects

  • 1. Optimizing Agency Funding to Deliver SB 1 Projects By DingXin (Ding) Cheng Director of California Pavement Preservation Center Professor of California State University, Chico 2018 Fall Asphalt Pavement Conference October 24 - 25, Sacramento, CA
  • 2. Objective of the Study Evaluate the current pavement management program and treatment types of Riverside County and provide recommendations and cost performance measures for improving the County’s pavement management system and improve the overall pavement condition throughout the County Road System. 2
  • 3. Project Tasks  Task 1- Collect information related to Riverside County pavement management program.  Task 2- Determine cost effective M&R Strategies for the County.  Task 3- Evaluate the County’s Pavement Management System.  Task 4- Evaluate different funding and project selection scenarios.  Task 5- Create summary report and presentation. 3
  • 4. Background on Riverside  4th most populous county in California, with population about 2.36 million  Area = 7,303 square miles  About 2,000 miles of county maintained roadways 4
  • 5. Road Miles by Functional Class (Paved Roads) 5 2017 Total Sections Total Center Miles Total Lane Miles PCI Arterial 715 425.97 887.24 70 Collector 486 229.05 455.31 70 Residential/Local 4272 914.88 1,816.99 74 Rural Local (7) 60 38.53 75.52 74 Rural Major Collector (5) 320 204.43 412.01 71 Rural Minor Arterial (4) 2 0.27 0.54 79 Rural Minor Collector (6) 126 93.97 186.67 80 Urban Collector (5) 106 45.89 96.15 64 Urban Local (7) 3 1.04 1.28 79 Urban Minor Arterial (4) 1 0.70 1.40 62 Urban Principal Arterial-Other (3) 19 11.57 52.30 70 Total 6110 1,966.32 3,985.41 72 PCI – Pavement Condition Index
  • 6. PCI Breakdown 6 • PCI Value is based on a scale of 0 to 100 (100 being the best possible condition of pavement). • PCI breakpoints are used to differentiate between different levels of pavement conditions. • PCI breakpoints are commonly recommended by MTC.
  • 7. Decision Tree  A decision tree is a vital part of the Pavement Management System.  CP2 Center reviewed County’s current decision tree.  Working with the County, CP2 Center developed a new decision tree based on County’s practice and life cycle cost. 7
  • 8. Decision Tree with LCC  A Life Cycle Cost (LCC) analysis could be used to select the best treatment for each pavement condition category and functional class. The Equivalent Annual Cost (EAC) can be calculated using unit cost, x $/yd2, and expected treatment life, n years, and inflation rate of i%.  The equivalent annual cost methodology allows to compare the cost effectiveness of various treatments that have unequal lifespans. 𝐸𝐸𝐸𝐸𝐸𝐸 = 𝑥𝑥 × 𝑖𝑖 1 − 1 + 𝑖𝑖 −𝑛𝑛 8
  • 9. Budget Scenarios Analyzed  Three time periods (5, 10, and 20 year) were analyzed with various budget scenarios to determine the best ways to improve the average network PCI. 9 Scenario 5-Year Scenarios 10-Year Scenarios 20-Year Scenarios 1 SB1 Funding with 20% - 40% PM SB1 Funding with 20% - 40% PM SB1 Funding with 20% - 40% PM 2 $20 Million with 20% - 40% PM $20 Million with 20% - 40% PM - 3 Target – Driven Scenario – Maintain PCI of 72 Target – Driven Scenario – Maintain PCI of 72 - 4 SB1 Funding with Increasing Preventive Maintenance - 5 SB1 Funding with Decreasing Preventive Maintenance -
  • 10. Determination Factors The order in which the best scenarios were determined:  Network PCI  Deferred Maintenance Cost  Average Remaining Life of Pavement  Total Overall Cost 10
  • 11. 5-Year Scenarios 11 • SB 1 Funding with 20% PM – 40% PM with 4% Inflation $135,000,000 $140,000,000 $145,000,000 $150,000,000 $155,000,000 $160,000,000 $165,000,000 $170,000,000 73.4 73.6 73.8 74 74.2 74.4 74.6 74.8 75 75.2 20% PM 25% PM 30% PM 35% PM 40% PM DEFERREDMAINTENANCE COST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 5-Year SB 1 Funding with 4% Inflation Network PCI Deferred Maintenance Cost, $
  • 12. 5-Year Scenarios 12 • SB 1 Funding with 20% PM – 40% PM: GIS Results with 4% Inflation Rate and 30% PM Very good 4071 Good (Non- load) 374 Good (Load) 47 Poor 144 Very Poor 420 Very good 3487 Good (Non- load) 534 Good (Load) 339 Poor 464 Very Poor 223
  • 13. 5-Year Scenarios 13 • $20 Million with 20% - 85% PM with 4% Inflation $245,000,000 $250,000,000 $255,000,000 $260,000,000 $265,000,000 $270,000,000 $275,000,000 $280,000,000 $285,000,000 67.4 67.6 67.8 68 68.2 68.4 68.6 68.8 69 69.2 20% PM 25% PM 30% PM 35% PM 40% PM 45% PM 50% PM 55% PM 60% PM 65% PM 70% PM 75% PM 80% PM 85% PM DEFERREDMAINTENANCECOST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 5 Year $20 Million Funding with 4% Inflation Network PCI Deferred Maintenance Cost
  • 14. 5-Year Scenarios 14 • $20 Million with 20% - 85% PM with 0% Inflation $205,000,000 $210,000,000 $215,000,000 $220,000,000 $225,000,000 $230,000,000 $235,000,000 67 67.5 68 68.5 69 69.5 70 70.5 20% PM 25% PM 30% PM 35% PM 40% PM 45% PM 50% PM 55% PM 60% PM 65% PM 70% PM 75% PM 80% PM 85% PM DEFERREDMAINTENANCECOST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 5 Year $20 Million Funding with 0% Inflation Network PCI Deferred Maintenance Cost
  • 15. 5-Year Scenarios 15 • $20 Million with 20% - 85% PM: GIS Results with 4% Inflation and 70% PM Very Good 3456 Good (Non-Load) 534 Good (Load) 347 Poor 487 Very Poor 232 Very good 3549 Good (Non- load) 490 Good (Load) 171 Poor 411 Very Poor 435
  • 16. Summary of findings for 5-year scenarios  SB 1 $240 million funding with 4% inflation will increase PCI to 75  SB 1 $240 million funding with 2018’s dollar will increase PCI to 76  Minimum funding of $20 million per year will decrease the PCI to 69  To maintain PCI of 72, it will need $170 million for the five year period 16
  • 17. 10-Year Scenarios 17 SB 1 Funding with 4% Inflation in 2027 $0 $50,000,000 $100,000,000 $150,000,000 $200,000,000 $250,000,000 75.4 75.6 75.8 76 76.2 76.4 76.6 76.8 77 77.2 10% PM 15% PM 20% PM 25% PM 30% PM 35% PM 40% PM DEFERREDMAINTENANCE COST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 10 Year SB 1 Funding with 4% Inflation Network PCI Series2
  • 18. 10-Year Scenarios $0 $20,000,000 $40,000,000 $60,000,000 $80,000,000 $100,000,000 $120,000,000 77.5 78 78.5 79 79.5 80 80.5 81 81.5 82 82.5 20% PM 25% PM 30% PM 35% PM 40% PM DEFERREDMAINTENANCE COST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 10 Year SB 1 Funding with 2018's Dollar Value Network PCI Deferred Maintenance Cost, $ 18 SB 1 Funding with 2018’s Dollar Value in 2027
  • 19. 10-Year Scenarios  SB 1 Funding with 20% PM with 4% Inflation in 2018 vs. 2027 Very Good 3524 Good (Non-Load) 531 Good (Load) 332 Poor 436 Very Poor 231 Very Good 4307 Good (Non-Load) 521 Good (Load) 91 Poor 0 Very Poor 133
  • 20. 10-Year Scenarios  SB 1 Funding with 20% PM with 2018’s Dollar Value in 2018 vs. 2027 20 Very Good 3524 Good (Non- Load) 531 Good (Load) 332 Poor 436 Very Poor 231 Very Good 4606 Good (Non- Load) 378 Good (Load) 67 Poor 0 Very Poor 1
  • 21. 10-Year Scenarios  $20 Million with 20% - 40% PM with 4% Inflation in 2027 21 $464,000,000 $466,000,000 $468,000,000 $470,000,000 $472,000,000 $474,000,000 $476,000,000 $478,000,000 $480,000,000 61.4 61.6 61.8 62 62.2 62.4 62.6 62.8 63 63.2 20% PM 25% PM 30% PM 35% PM 40% PM DEFERREDMAINTENANCECOST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 10 Year $20 Million Funding with 4% Inflation Network PCI Deferred Maintenance Cost
  • 22. 10-Year Scenarios  $20 Million with 20% - 40% PM with 4% Inflation in 2018 vs. 2027 22 Very Good 3468 Good (Non- Load) 532 Good (Load) 345 Poor 478 Very Poor 231 Very Good 3343 Good (Non- Load) 631 Good (Load) 124 Poor 277 Very Poor 679
  • 23. Summary of findings for 10-year scenarios  SB 1 $540 million funding with 4% inflation will increase PCI to 77.  SB 1 $540 million funding with 2018’s dollar will increase PCI to 82.  Minimum funding of $20 million per year will decrease the PCI to 63.  To maintain PCI of 72, it will need $425 million for the 10 year period with a 4% inflation rate.  To maintain PCI of 72, it will need $347 million for the 10 year period with 2018’s dollar. 23
  • 24. 20-YearScenarios  SB 1 Funding with 20% - 40% PM 2037 Budget $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 Network PCI 69 69 68 68 68 Deferred Maintenance Cost $361,161,603 $334,414,197 $343,202,954 $350,355,032 $389,439,533 Average Remaining Life 17.94 18.05 18.17 18.24 18.32 Total Cost $839,991,729 $839,979,811 $835,327,964 $828,632,678 $812,052,870 20 Year Analysis 4% Inflation Year Summary 20% PM 25% PM 30% PM 35% PM 40% PM 20 Year Analysis 2018’s Dollar Value Year Summary 20% PM 25% PM 30% PM 35% PM 40% PM 2037 Budget $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 Network PCI 80 79 79 78 77 Deferred Maintenance Cost $34,636,949 $27,181,367 $30,703,628 $39,845,654 $35,978,951 Average Remaining Life 23.08 22.89 22.65 22.29 21.90 Total Cost $837,584,425 $837,453,641 $829,253,015 $816,278,660 $800,269,044
  • 25. 20-Year Scenarios  SB 1 - Funding with 20% - 40% PM 25 $300,000,000 $310,000,000 $320,000,000 $330,000,000 $340,000,000 $350,000,000 $360,000,000 $370,000,000 $380,000,000 $390,000,000 $400,000,000 67.4 67.6 67.8 68 68.2 68.4 68.6 68.8 69 69.2 20% PM 25% PM 30% PM 35% PM 40% PM DEFERREDMAINTENANCE COST NETWORKAVERAGEPCI PERCENT PREVENTIVE MAINTENANCE 20 Year SB 1 Funding with 4% Inflation Network PCI Deferred Maintenance Cost, $
  • 26. 20-Year Scenarios  SB 1 - Funding with 20% - 40% PM with 4% Inflation in 2018 vs. 2037 26 Very Good 3507 Good (Non- Load) 532 Good (Load) 334 Poor 450 Very Poor 231 Very Good 3323 Good (Non- Load) 1179 Good (Load) 267 Poor 179 Very Poor 106
  • 27. 20-Year Scenarios  SB 1 - Funding with 20% - 40% PM with 2018’s Dollar Value in 2018 vs. 2037 27 Very Good 3507 Good (Non- Load) 532 Good (Load) 334 Poor 450 Very Poor 231 Very Good 4367 Good (Non- Load) 547 Good (Load) 116 Poor 21 Very Poor 1
  • 28. Summary of findings for 20 year scenarios  SB 1 funding of $540 million for the first 10 years + $300 million for the second 10 years  With 4% inflation, the average network PCI will increase to 77 at year 2027, and then decrease to 69.  With 2018’s dollar value, the average network PCI will increase to 82 at year 2027, and then decrease to 80. 28
  • 29. Conclusions 29 1. After reviewing the decision tree and treatments used by Riverside County, CP2 Center worked with the County engineer and adjusted decision tree, PCI breakpoints, and treatments. A new decision tree was developed based on life cycle cost. 2. Over 30 different budget scenarios were analyzed by the CP2 Center. The most beneficial budget scenarios are not either fixing the worst first or performing pavement maintenance (PM/preservation) only. 3. The $20 million per year budget is not enough to maintain the current average network PCI. Based on this study, the PCI value will continue to decrease with $20 million per year of funding.
  • 30. Recommendations 1. Continually update the costs and service life for each treatment in the decision tree. 2. A life cycle cost analysis should be used to select proper treatments for future decision tree update. 3. SB 1 funding or other funding sources are necessary to improve the average network pavement conditions. Riverside County has a desired goal for the PCI to reach 75 or higher after five years; the SB 1 funding will most likely help the County reach this goal. 30
  • 31. Recommendations 4. A properly balanced preservation and fixing the worst will give the County the best solution. 5. A balanced budget between pavement preservation (PM) and fixing the worst roads should be utilized to improve the County’s pavement conditions. Keys to achieve the desired PCI include the following:  Optimize percentages for PM and Rehab (use lowest deferred maintenance cost)  Use innovative treatments that can improve life cycle cost 31
  • 32. Acknowledgement  We appreciate the Transportation Division of the Riverside County providing funding for this meaningful study.  Thanks Mr. Elmer Datum of the Riverside County, who provided consistent support to this study!  Thanks students research assistants Kimberly Joselin and Riley de Wit, who worked on the project.  Thanks Dr. R. Gary Hicks for his review. 32
  • 33. Thank you very much! Questions? Contact Dr. DingXin Cheng: dxcheng@csuchico.edu Phone: 530-898-5114 33 Today Decides Tomorrow