Project Monitoring and Problem Solving _Questionaire.docx
1. Project Monitoring and Problem Solving
1)When do we not monitor the Project
a) Start of the Project
b) End of the Project
c)Continuously
d)None of the above
2)Why do we not monitor the project status
a)To mitigate the risk
b)To detect the things
c)To know the project is going on schedule
d)none of the above
3)Formula to calculate Cost performance Index
a)EV-SV
b)SV-PV
c)EV/AC
d)None of the above
4)SPI value zero stands for
a)The assigned task is completed fully
b)The assigned task completed partially
c) Task is not started yet
d)None of the above
5) Which of the following technique is not used for monitoring the project status
a) Gant Chart
b)Mile stones
c)Hypothesis testing
d)Using Earned Value Analysis