2. EXECUTIVE SUMMARY
Location : JALAN CEMARA RAYA TAMAN YASMIN SEKTOR II - BOGOR JAWA BARAT
Land Area : 19.107,00 M2 (1,91 Ha )
Total House : 73 Unit
End User : EMPLOYE PERTAMINA CEPU & Generale
Time Execution : 24 Month
Developer : PT.BOTOS AMARI
SALESREVENUE
House T-60 : 26 Unit = 29.037.471.626Rp
House T-90 : 29 Unit 49.092.495.508Rp
House T-120 : 20 Unit = 49.416.398.218Rp
Total Reveu 127.546.365.352Rp
PROJECTFINANCING
LAND ACQUSITION
LAND ACQUISTION (19107 M2) : = 45.856.800.000Rp
Tax Purchase of land (BPHTB Lahan & Notaris) 3% = 1.375.704.000Rp
2% = 687.852.000Rp
Legal , Infrastruktur,Office & Marketing
Permit , Planing & Design & FS 1 % 1% = 637.731.827Rp
Facility & Infrastructure 1 ls 6.852.492.140Rp
Marketing Fee 2% = 2.550.927.307Rp
SGA 1% = 1.503.056.000Rp
2,5% = 3.188.659.134Rp
Contruction
House T-60 : 24 Unit 270.000.000Rp 6.480.000.000Rp
House T-90 : 29 Unit 405.000.000Rp 11.745.000.000Rp
House T-120 : 20 Unit 540.000.000Rp /Unit = 10.800.000.000Rp
Total = 91.678.222.407Rp
Recapilution Loss/ Profit
Income = 127.546.365.352Rp
Outcome = 91.678.222.407Rp
MARGIN = 35.868.142.944Rp
EXECUTIVESUMMARY
HOUSING IMPLEMENTATION PROJECT JASMINE VIEW RESIDENCE
TAMAN YASMIN - BOGOR
Land Title transfer Document (BN-SHGB ke
PT.BA 6 bulan )
Tax purchase of House (BPHTB Unit RUMAH)
3. Time Schedule
Sept 2018 Okt 2018 Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Jun 2019 Jul 2019 Agu 2018 Sep 2018 Okt 2018 Nov 2018
I I I I I I I I I I I I I I I
A. Facility & Infrastructure
1 Gate accses
2 Fence parimeter
3 Roadway contruction
4 Drainage
5 Lanscaping & Play ground
6 Water, electricity, Telephone (ground cable)
B Contruction
1 measurement land
2 Type 45' = 24 unit
3 Type 90' = 29 unit
4 Type 120' = 20 unit
5 Finisihing
REMARKNO Description Work