OFFSHORE ASSOCIATED GASES
           PACKAGE 1
     DAS ISLAND FACILITIES



WEEKLY PRESENTATION
Mr.Wilson Contreras.SITE MANAGER
          OAG PROJECT.
INDEX
1.    ACTIVITIES OF THE WEEK
2.    MANPOWER STATUS
3.    CONCRETE STATUS (PIE / LINE GRAPH)
4.    WEEKLY PROGRESSIVE QUANTITY REPORT
      (CONCRETE)
5.    WEEKLY CONCRETE QUANTITIES
      FORECAST
6.    MONTHLY MANPOWER FORECAST
7.    STATUS OF PAR’s & PAU’s FOUNDATION
8.    WEEKLY HSE STATISTICS
9.    HSE PLAN
10.   HSE NEAR MISS TREND
11.   WEEKLY EXECUTIVE SUMMARY
12.   AREA OF CONCERN
13.   BLACK SOIL
14.   GEND IMPELLERS
ACTIVITIES OF THE WEEK
PODIUM AREA:
      Retaining Wall / Pipe Supports Valve Pits / VSD Building
      Booster Compressors (26-K-0401 & 26-K-0451) and
      Pipe Rack # PAR 101 to 106 & PAR 108 to 109
      Booster Compressor: 26-K-0401
      Booster Compressor: 26-K-0451
      Pipe Rack:
      Cable Trench (Podium/ Interconnecting / Offsite)
      ZAKUM / UMM SHAIF/ LNG MANIFOLD AREA :
      Reclamation Area /ADMA Flare Area:
      Road A1 – Bridge B – 7: Culvert
      Amenities Building
PROCESS AREA:
         Outstation Building # 14
         Substation Building # 11
         Feed Gas Compressor (I-K-401)
         Feed Gas Compressor (I-K-451)
         Train I & Train II:
         Pipe Rack Train 1 & 2:
         Manholes / Catch basin / Valve Pits
         Cable Trench / Duct Banks (Process/ Common Facilities)
ACTIVITIES OF THE WEEK
COMMON FACILITIES:
      PIPING:
      Process Area
      Interconnecting & Offsite Area:
      Podium Area:
      Fabrication Yard

TARGET Yard:
      Temporary Office & Lay down Area:
      Cathodic Protection for RC Foundations
MANPOWER STATUS AS OF 11.07.2008


S.                                 Manhours
         Company       Manpower                 Cum. Manhours
No.                               (this week)

1. MEPI                     36        2,095          85,520
2. Target                  804      52,490       1,676,438
3. Descon                  271      15,775           90,280
       Total on Site     1,111      70,360       1,852,238
CONCRETE CASTING




                                    Total Poured                Total
                                                              8086.18 m3
                                       28.78%




                                      Progress this               Total
                                                                671.50 m3
                                       week 2.39%
Remaining
                                       Total Concrete Poured 8757.68 m3
 68.83%
   Total
19335.32 m3




Total Poured   Progress this week   Remaining
CONCRETE CHART BASELINE SCHEDULE




                                                                                                                                                                                                                                              100
                                                                                                                                                                                                                                     98.73
             100




                                                                                                                                                                                                                        95.17
              90




                                                                                                                                                                                                           83.78
              80



              70




                                                                                                                                                                                              69.54
              60
PERCENTAGE




                                                                                                                                                                                58.15
                                                                                                                                8757.68 m3

              50




                                                                                                                                                                   47.50
                                                                                                                    8086.18 m3

              40                                                                               7327.68 m3

                                                                                    6837.43 m3




                                                                                                                                                      36.80
              30                                                             6771.43 m3




                                                                                                                                         31.17
                                                                                                                            28.78
                                                                                                            26.08
                                                                                                   24.34
                                                                         23.68


                                                                                      24.10
                                                                22.11




              20
                                                       21.62
                                              20.02
                                 18.34
                    17.24




              10



              0
                   18       19           20           21       22       23       24           25           26          27           28           31           36           40            44           49           53           58           62
                                                                             13/06/08 20/06/08 27/06/08 04/07/08 11/07/08
                                                                                                                                                                                        Actual                     Scheduled
                                                                                              WEEK NUMBER
WEEKLY PROGRESS QUANTITY REPORT(CONCRETE)




Discipline : Civil/ Structural                                                                                                     Date : July 04, 2008

                                                              Progress in Quantity                          Progress Percentage
                                                                                            Rem.
                                                                          Weekly Cum.       Balan       Daily       Weekly Cum.    R Balance
Sr.                                             U    Daily Progress        Progress          ce      Progress %     Progress %        %        Remarks
No                     ACTIVITY         EST.    ni
 .      Weeks        DESCRIPTION        QTY     t     Sch      Actl      Sch       Actl      Actl    Sch    Actl   Sch      Actl     Actl

         18th                          28,093   M3   969.78   419.58    6499.95   4842.33   23,251   3.45   1.49   23.14   17.24     82.76

                    Week (03/05/08-
         19th       09/05/08)                                                     309.50

                                      28,093                                      5151.83   22,941                         18.34     81.66

                    Week (10/05/08-
         20th       16/05/08)                                                     472.60

                                      28,093                                      5624.43   22,469                         20.02     79.98

                    Week (17/05/08-
         21st       23/05/08)                                                     448.75

                                      28,093                                      6073.18   22,020                         21.62     78.38

                    Week (24/05/08-
        22nd        30/05/08)                                                     138.00

                                      28,093                                      6211.18   21,882                         22.11     77.89

                    Week (31/05/08-
         23rd       05/06/08)
                        Weekly
                        Total =       28,093                   441.50             6652.68   21,440                         23.68     76.32
Discipline : Civil/ Structural                                                                                      Date : July 04, 2008

                                                     Progress in Quantity                    Progress Percentage
S                                                                              Rem.                                     R
r                                                 Daily       Weekly Cum.      Balan      Daily      Weekly Cum.     Balance
.                                               Progress       Progress         ce     Progress %    Progress %         %      Remarks
N                                         U
o                  ACTIVITY        EST.   ni
.    Week        DESCRIPTION       QTY    t    Sch    Actl    Sch      Actl    Actl    Sch    Actl   Sch    Actl       Actl

     24th     Week (06/06/08- 12/06/08)

                Weekly Total =   28,093              118.75         6771.43   21,322                        24.10     75.90



     25th     Week (13/06/08- 19/06/08)

                Weekly Total =   28,093               66.00         6837.43   21,256                        24.34     75.66

     26th     Week (20/06/08- 26/06/08)

               Weekly Total =    28,093              490.25         7327.68   20,765                       26.08      73.92

     27th     Week (27/06/08- 03/07/08)

               Weekly Total =    28,093              758.50         8086.18   20,006                       28.78      71.22

     28th     Week (04/07/08- 10/07/08)

               Weekly Total =    28,093              671.50         8757.68   19,335                       31.17      68.83
WEEKLY CONCRETE QUANTITIES FORECAST
Updated as of :      11-July-08

                                 Date of Delivery of
Sl                                Modules at Das              Foundation                            Modules
.    Descripti                         Island                                     Foundation
                 Location                                                                                           Remarks
N      on                                                                         Completed
o.                                                                                               On
                                Baseline     Forecast     Baseline    Forecast                            On Site
                                                                                               Harbour

PAR's
1    PAR-012                    31/12/2008   17/12/2008               30/4/2008    11/4/2008

2    PAR-013                    31/12/2008   17/12/2008               14/6/2008    24/4/2008

3    PAR-014                    31/12/2008   17/12/2008               5/8/2008      5/6/2008
                  Common
4    PAR-016                    31/12/2008   17/11/2008   28/7/2008   24/6/2008
                  Facilities
5    PAR-017                    3/11/2008    17/11/2008               20/7/2008

6    PAR-018                    3/11/2008    17/12/2008               29/6/2008

7    PAR-019                    2/12/2008    17/12/2008               28/7/2008

8    PAR-001                    2/12/2008    18/10/2008               27/3/2008     7/5/2008

9    PAR-002                    2/12/2008    18/10/2008               21/5/2008    22/5/2008

10   PAR-003      Process       2/12/2008    18/10/2008               10/4/2008    21/5/2008
                 Area, Train-
11   PAR-009          1         31/12/2008   17/11/2008               27/3/2008    14/3/2008

12   PAR-010                    31/12/2008   17/11/2008               6/4/2008     13/3/2008

13   PAR-011                    31/12/2008   17/11/2008   10/6/2008   31/3/2008    24/5/2008

14   PAR-004                    2/12/2008    17/11/2008               7/5/2008

15   PAR-005                    2/12/2008    18/10/2008               23/6/2008
                  Process
16   PAR-006     Area, Train-   2/12/2008    19/10/2008               18/5/2008
                      2
17   PAR-007                    2/12/2008    17/11/2008               26/3/2008    14/3/2008

18   PAR-008                    2/12/2008    17/11/2008               8/4/2008     30/4/2008
Updated as of :    11-Jul-08

S                             Date of Delivery of
l.                             Modules at Das              Foundation                           Modules
     Descripti                      Island                                     Foundation
N                Location                                                                                      Remarks
       on                                                                      Completed
o                                                                                             On        On
.                             Baseline    Forecast     Baseline    Forecast
                                                                                            Harbour     Site

PAR's
19   PAR-101                  23/8/2008   17/9/2008                11/5/2008

20   PAR-104                  23/8/2008   17/9/2008                13/3/2008    15/3/2008
                  Booster
21   PAR-105     Compressor   23/8/2008   18/10/2008               12/3/2008    5/3/2008
                   -North
22   PAR-106                  23/8/2008   18/10/2008               27/3/2008
                                                        9/4/2008
23   PAR-108                              17/9/2008                27/3/2008

24   PAR-102                  23/8/2008   17/9/2008                26/3/2008    6/5/2008
                  Booster
25   PAR-103     Compressor   23/8/2008   17/9/2008                8/3/2008     5/3/2008
                   -South
26   PAR-109                              17/9/2008                27/3/2008    6/5/2008
27   PAR-107                               18/10/2008              6/5/2008    24/4/2008

28   PAR-201                   3/9/2008    17/7/2008               16/3/2008   26/4/2008

29   PAR-211   Interconnect   3/11/2008    17/8/2008               22/4/2008
                    ing
30   PAR-212                  3/11/2008    17/8/2008               18/3/2008   14/6/2008
                 Piperack-
31   PAR-216       East        3/9/2008    17/7/2008               27/4/2008   21/4/2008   20/06/08

32   PAR-217                   3/9/2008    17/7/2008               19/4/2008   8/6/2008    20/06/08

33   PAR-221                               17/8/2008               8/5/2008

34   PAR-213   Interconnect   3/11/2008    17/8/2008               10/4/2008
                    ing
35   PAR-214                  3/11/2008    17/8/2008               10/4/2008   14/6/2008
                 Piperack-
36   PAR-215       West       3/11/2008    17/8/2008               10/4/2008

37   PAR-202                   3/9/2008    17/7/2008    9/7/2008   22/3/2008   9/4/2008

38   PAR-203                  2/10/2008    17/7/2008               14/4/2008   28/4/2008

39   PAR-205                  2/10/2008    17/7/2008               2/4/2008    14/5/2008   20/06/08
               Interconnect
40   PAR-206        ing       2/10/2008    17/7/2008               2/4/2008    14/6/2008   20/06/08

41   PAR-207     Piperack-    2/10/2008    17/8/2008               27/3/2008   21/5/2008
                  Centre
42   PAR-208                  2/10/2008    17/12/2008              27/3/2008   17/5/2008

43   PAR-209                  2/10/2008    17/12/2008              27/3/2008   17/5/2008

44   PAR-210                  2/10/2008    17/08/2008              2/4/2008    21/5/2008
               Interconnect
                    ing
45   PAR-015                  31/12/2008   17/12/2008              10/4/2008   5/6/2008
                 Piperack-
                   West
45    TOTAL
Updated as of :   11-Jul-08

S                               Date of Delivery of
l.                               Modules at Das               Foundation                             Modules
     Descripti                        Island                                        Foundation
N                Location                                                                                          Remarks
       on                                                                           Completed
o                                                                                                  On       On
.                               Baseline     Forecast     Baseline     Forecast
                                                                                                 Harbour    Site

PAU's
1    PAU-001      Process       21/1/2009     21/1/2009                 14/5/2008

2    PAU-002     area-West      14/2/2009     21/1/2009                 20/5/2008

3    PAU-003       Process      14/10/2008   14/10/2008                 12/6/2008
                 area, Train-
4    PAU-004          1         18/11/2008   13/11/2008                 30/3/2008
                                                           10/6/2008
5    PAU-005                     2/2/2009     21/1/2009                 19/7/2008

6    PAU-006       Process      16/2/2009     16/2/2009                 19/7/2008
                 area, Train-
7    PAU-007          2         18/11/2008   13/11/2008                 28/7/2008

8    PAU-008                    18/11/2008   13/11/2008                  1/7/2008
8    TOTAL
Updated as of
                                                                                                         :                     11-Jul-08

S                              Date of Delivery of
l.                              Modules at Das                  Foundation                                   Modules
     Descripti                       Island                                            Foundation
N                Location                                                                                                      Remarks
       on                                                                              Completed
o                                                                                                           On         On
.                             Baseline      Forecast        Baseline      Forecast
                                                                                                          Harbour      Site

PAU AIRCOOLERS
1    PAU-051                    5/1/2009       22/12/2008

2    PAU-052                    5/1/2009       22/12/2008

3    PAU-053                    5/1/2009       22/12/2008

4    PAU-054      Process       5/1/2009       20/11/2008
                                                            10/6/2008    14/8/2008
5    PAU-055       area         5/2/2009       22/1/2009

6    PAU-056                    5/2/2009       22/1/2009

7    PAU-057                    5/2/2009       22/1/2009

8    PAU-058                    5/2/2009       20/11/2008

9    PAU-151A                  22/11/2008      2/10/2008

10   PAU-151B      Booster     22/11/2008      2/10/2008
                 compressor                                 27/4/2008    10/6/2008
11   PAU-152A       area       22/11/2008      2/10/2008

12   PAU-152B                  22/11/2008      2/10/2008
12    TOTAL




                     : Foundations already due to be completed as of report date as per recovery plan submitted by MEPI vide
                      letter no. L-1364 dated 26 March 2008

                     : Foundations completed
WEEKLY HSE STATISTICS
                        FROM 05.07.08 TO 11.07.08

 LTI         MTC        RTWD       First Aid         Near miss      Inspections         ASA    Drill        TBM
     0         0             1        0                 6                 6              3      0            77

                                   SAFETY TRAININGS CONDUCTED

                                                                                  Conducted        No. of
No.                              Title of Training
                                                                                     by          Attendees
 1       General HSE Training                                                         DESCON           05
 2       Heat Stress                                                                  TARGET           21
 3       Defensive Driving                                                            TARGET           09
 4       Working at Heights                                                           TARGET           04


                                                             Man Hours for the week                         70,360

                                                             Cumulative                                1,852,238
OAG PROJECT / HSE PLAN
                                            05/07/08 to 11/07/08

                 Activities Performed                                               Activities Planned
                      This Week                                                         Next Week
 Review and closures of unsafe observations stated in weekly    HSE Induction for new employees.
walk thru inspection.                                           Daily and weekly Site Inspection
 41 new employees have been inducted for safety.                Upadte Action Tracking system
 Weekly safety walk thru at Process, Interconnecting Pipe       Weekly supervisors meeting for Target and Descon
Rack and Podium area                                            TRA Meeting for Descon and Target.
 Monitoring of Site inspections reports.                        HSEMS and EMS Awareness Training for Staff
 Weekly HSE Coordination Meeting.                               Management safety weekly walk-thru
                                                                Weekly HSE Coordination Meeting
 Supervisor’s Weekly HSE Meeting.
                                                                Conduct ASA as per schedule
 Daily tool box meetings
                                                                Daily tool box meetings are attended by MEPI/Target/Descon staff as
 TRA Meeting                                                   per schedule
 Opening and close out Meeting with TUV & ADGAS Auditors.       Start month long HEAT STRESS campaign
 Conducted 4 ASA at site.                                       Action Plan :- On going
 The following inspections/verifications were conducted:        Scheduled Inspections :
                                                                              •Waste Management
               •Working at Heights
                                                                              •Housekeeping
               •Excavation Access                                             •Power Tools
               •Material Stacking                                             •Full Body Harness
                                                                              •Camp Inspection
 Training Conducted                                                           •Descon Yard
               •Defensive Driving - 09                          Training
               •Heat Stress – 21                                              •Heat Stress Management
                                                                              •Working at height
               •Work at Height – 04                                           •H2S Awareness
               •Emergency Response - 20                                       •HSEMS and EMS Awareness
               •General HSE Training – 05
              •PTW - 02
OAG PROJECT / HSE ACTIVITIES
                                       Near Miss Trend
                                      05/07/08 to 11/07/08

                                         Description                                                Status
Sub standard Practice– One MEPI supervisor climbed from the first stage of the scaffold to the   Unsafe act
second stage passing through handrail.

                                                                                                 Unsafe act
Sub standard Practice – DESCON trailer entered C-30 road, blocking the traffic for 30 minutes.

                                                                                                 Unsafe condition
Near Miss – Welding machine was found ON condition at podium at 08.30 PM.

Sub standard practice – No safety latch on the hook of 150 T crane at reclamation area.          Unsafe condition

Sub standard practice – Wire rope and spring of TRIPOD GRAB not working properly.                Unsafe condition

Near miss – TOYOTA HIACE, ADGAS vehicle found over speeding near plant-26.                       Unsafe act

Near miss- Rear door of the tipper truck was not locked while carrying pre-cast manhole.
                                                                                                 Unsafe condition




  * We have 03 unsafe condition and 06 unsafe act.
WEEKLY EXECUTIVE SUMMARY


                         Wt                      Weekly Progress %                            Cumulative Progress %
                                       Contr
                                                                                  Contrac
                                        act /                            Delta                                             Delta
Breakdown                                       Recov                                t/
                                       Baseli           Actu                                Recove               Delta
                 L2            L3                ery            Delta    (Rec.    Baselin             Actual              (Rec.Pl
                                         ne              al                                 ry Plan             (Plan)
                                                 Plan                    Plan)    e Early                                   an)
                                       Early
                                                                                   Plan
                                        Plan

Temporary                                                                                   100.00
                2.00%                  0.00%    0.00%   0.00%   0.00%    0.00%    98.00%              100.00%   2.00%     0.00%
Facilities                                                                                    %


Construction
& Pre-
                95.20%                 1.15%    2.12%   0.65%   -0.50%   -1.47%   58.13%    44.43%    31.78%    -26.35%   -12.66%
commission-
ing

Civil Works:                  64.94%   1.17%    3.09%   0.70%   -0.46%   -2.39%   82.13%    67.29%    48.12%    -34.01%   -19.17%

M.E.I. Works:                 35.06%   1.12%    0.32%   0.54%   -0.57%   0.22%    13.66%    2.09%     1.50%     -12.16%   -0.59%

Commission-
                2.20%                  0.00%    0.00%   0.00%   0.00%    0.00%    0.00%     0.00%     0.00%     0.00%     0.00%
ing

As Built
                0.60%                  0.00%    0.00%   0.00%   0.00%    0.00%    0.00%     0.00%     0.00%     0.00%     0.00%
Document

Total                 100%             1.09%    2.02%   0.62%   -0.48%   -1.40%   57.30%    44.30%    32.25%    -25.04%   -12.05%
ACTIVITIES FOR THE WEEK 11.07.2008

                           AREA OF CONCERN

1.   Construction & Commissioning Progress Site :
                                  Actual : 31.78 %, Delta     : - 12.65 %
                                           Before   Delta     : - 9.27 %
     Recovery Plant    : 44.43 %

     The Delta was increase and Need for Recovery Pour Concrete 1 200 M3
     every week for minimum during next 12 weeks.

     Delays by Aggregate / Bad Weather /Capacity of Harbour for UnLoad/Load .
     Planning and Coordination.

2.   Concrete poured last Thursday      10 July 2008 ------------ 84.0 M3
     Total concrete poured               This Week -------------- 671.5 M3
     Total Qty Concrete Poured until this Week ----------------  8757.68 M3

3.   ADGAS is looking for Additional Area for storage more Qty of Aggregates.
     On initial Area requested by MEPI is on process for approval
ACTIVITIES FOR THE WEEK 11.07.2008
                            AREA OF CONCERN


4.   Radios provided by MEPI have now 3 to 6 New channels and Target/MEPI will
     be contact Safeer for give to him all information that we request and test for direct
     communications with CCB / CCR. Ongoing.

5.   QHSE & QA / QC Audit was closed 10 July 2008 . Inform with conclusion
     and Actions will be sending after close Meeting in Abu Dhabi.
     QA/QC Engineer at Das expect on July 2008. Action by Ed - Livingston / C
     Foster.
     ADGAS is requesting MEPI for Filling remaining positions on Site, special
     on QA/QC, Planning and Piping Areas
ACTIVITIES FOR THE WEEK 11.07.2008
                      AREA OF CONCERN

6. Construction Jetty.
   Sea chart : Done. We have from Furgo / Constain. Survey was done in
   Dec 2005. TRA & MS. Done
   Integrity & Safety of Construction : 2 core drills was performed. Done
   Clean Debris : Started with Priority on Area that will be used by OAG-1. Ongoing.
   Temporary light : ADGAS Maintenance Stores have all parts for re - establish
   service. Ongoing.
   Mooring Anchor Blocks : Noble Denton Study provide another Mooring
   Anchor Concrete Block positions and coordinates. Some of there are the same of
   Existing Anchor Blocks on sea bed.
   Defenders : According with Noble Denton, we need take off old defenders and put
   New ones or if PPA accept, we can use old big Tired that we have and we used
   time before on Harbour ? Ongoing.
   Buoys : Purchasing. Ongoing.

7. Area Plant 19 :
   a. Reclamation / shore protection: ADGAS requested to MEPI Qty and Prices
      Drawing and scope of work was sent to MEPI.
   b. Area close to liquid Flare need level using excavated material. ADGAS will
      request ADMA permission for start to work.
ACTIVITIES FOR THE WEEK 11.07.2008
                       AREA OF CONCERN



8.   Flare Area: MEPI start the job. The area was demark with bonders for
     radiation.

9.   Modules :
     PAR 217 was Transported to Podium.
     PAR 216 will be Transported to Podium Today.
     205 & 206, are storage on Harbour Area from 27 June 2008 until after install of
     Modules 201/202/203 that arrived to Harbour.
     Gatching: Done.
     SPMT: Is OK.
     Foundations for Modules 217 & 216 are ready for receive Modules.
     DESCON 500t crane was assembled in Podium Area. Functional and Load
     Test were performed.
     A1 Route is ready for Transport of Modules.
     Permissions are ready for Transport of Modules PAR 217 / 216.
ACTIVITIES FOR THE WEEK 11.07.2008
                       AREA OF CONCERN

10. ADGAS Requesting to MEPI for re-start the welding work and back filling on
    Pipes Process Area sides East & West, there are two Lines 12 inches diameter
    Fresh Water and Fire Water are on open trenches from time ago. ONGOING.

11. ADGAS is requesting, better protection for compact material on route, close to
    PAR 217. ONGOING.

12. ADGAS is requesting, What is the detail Plan for Install the Modules PAR 216 &
    217. DONE.

13. ADGAS is requesting, When will be start of construction assembling for PAR
    220/219/218.

14. ADGAS is very concern with Planning Activities for future Next Weeks and also
    very concern with Activities that were stopped long time ago and No re started
    again without any Technical Issue, example Open Trenches for Fire Water /
    Fresh Water Lines, Flare are dumped, Excavated Material, Erection Modules
    PAR 220/219/218. ONGOING.

15. ADGAS require MS for interconnection Piping & Modules.
Site Manager Mr[1].Wilson Contreras Presentation Pdf
Site Manager Mr[1].Wilson Contreras Presentation Pdf

More Related Content

Similar to Site Manager Mr[1].Wilson Contreras Presentation Pdf

Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmComparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmManuel Rojas Nadal
 
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmComparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmManuel Rojas Nadal
 
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...High frequency of abnormal high molecular weight glutenin alleles in Chinese ...
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...CIMMYT
 
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)Petrobras
 
Day 2 Energy Auditing of Heating and Water Heating Systems
Day 2 Energy Auditing of Heating and Water Heating Systems Day 2 Energy Auditing of Heating and Water Heating Systems
Day 2 Energy Auditing of Heating and Water Heating Systems RCREEE
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasiD.Pawan Kumar
 

Similar to Site Manager Mr[1].Wilson Contreras Presentation Pdf (7)

Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmComparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
 
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 AmComparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
Comparativo Temperatura Friccion Castrol 15w40 Vs Lubriquem 20w50 Am
 
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...High frequency of abnormal high molecular weight glutenin alleles in Chinese ...
High frequency of abnormal high molecular weight glutenin alleles in Chinese ...
 
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)
Webcast: Results Announcement - 2nd Quarter 2007 (Brazilian Corporate Law)
 
Day 2 Energy Auditing of Heating and Water Heating Systems
Day 2 Energy Auditing of Heating and Water Heating Systems Day 2 Energy Auditing of Heating and Water Heating Systems
Day 2 Energy Auditing of Heating and Water Heating Systems
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
 
1308- The Sustainable Sugarcane Initiative (SSI) in India and Beyond
1308- The Sustainable Sugarcane Initiative (SSI) in India and Beyond1308- The Sustainable Sugarcane Initiative (SSI) in India and Beyond
1308- The Sustainable Sugarcane Initiative (SSI) in India and Beyond
 

Site Manager Mr[1].Wilson Contreras Presentation Pdf

  • 1. OFFSHORE ASSOCIATED GASES PACKAGE 1 DAS ISLAND FACILITIES WEEKLY PRESENTATION Mr.Wilson Contreras.SITE MANAGER OAG PROJECT.
  • 2. INDEX 1. ACTIVITIES OF THE WEEK 2. MANPOWER STATUS 3. CONCRETE STATUS (PIE / LINE GRAPH) 4. WEEKLY PROGRESSIVE QUANTITY REPORT (CONCRETE) 5. WEEKLY CONCRETE QUANTITIES FORECAST 6. MONTHLY MANPOWER FORECAST 7. STATUS OF PAR’s & PAU’s FOUNDATION 8. WEEKLY HSE STATISTICS 9. HSE PLAN 10. HSE NEAR MISS TREND 11. WEEKLY EXECUTIVE SUMMARY 12. AREA OF CONCERN 13. BLACK SOIL 14. GEND IMPELLERS
  • 3. ACTIVITIES OF THE WEEK PODIUM AREA: Retaining Wall / Pipe Supports Valve Pits / VSD Building Booster Compressors (26-K-0401 & 26-K-0451) and Pipe Rack # PAR 101 to 106 & PAR 108 to 109 Booster Compressor: 26-K-0401 Booster Compressor: 26-K-0451 Pipe Rack: Cable Trench (Podium/ Interconnecting / Offsite) ZAKUM / UMM SHAIF/ LNG MANIFOLD AREA : Reclamation Area /ADMA Flare Area: Road A1 – Bridge B – 7: Culvert Amenities Building PROCESS AREA: Outstation Building # 14 Substation Building # 11 Feed Gas Compressor (I-K-401) Feed Gas Compressor (I-K-451) Train I & Train II: Pipe Rack Train 1 & 2: Manholes / Catch basin / Valve Pits Cable Trench / Duct Banks (Process/ Common Facilities)
  • 4. ACTIVITIES OF THE WEEK COMMON FACILITIES: PIPING: Process Area Interconnecting & Offsite Area: Podium Area: Fabrication Yard TARGET Yard: Temporary Office & Lay down Area: Cathodic Protection for RC Foundations
  • 5. MANPOWER STATUS AS OF 11.07.2008 S. Manhours Company Manpower Cum. Manhours No. (this week) 1. MEPI 36 2,095 85,520 2. Target 804 52,490 1,676,438 3. Descon 271 15,775 90,280 Total on Site 1,111 70,360 1,852,238
  • 6. CONCRETE CASTING Total Poured Total 8086.18 m3 28.78% Progress this Total 671.50 m3 week 2.39% Remaining Total Concrete Poured 8757.68 m3 68.83% Total 19335.32 m3 Total Poured Progress this week Remaining
  • 7. CONCRETE CHART BASELINE SCHEDULE 100 98.73 100 95.17 90 83.78 80 70 69.54 60 PERCENTAGE 58.15 8757.68 m3 50 47.50 8086.18 m3 40 7327.68 m3 6837.43 m3 36.80 30 6771.43 m3 31.17 28.78 26.08 24.34 23.68 24.10 22.11 20 21.62 20.02 18.34 17.24 10 0 18 19 20 21 22 23 24 25 26 27 28 31 36 40 44 49 53 58 62 13/06/08 20/06/08 27/06/08 04/07/08 11/07/08 Actual Scheduled WEEK NUMBER
  • 8. WEEKLY PROGRESS QUANTITY REPORT(CONCRETE) Discipline : Civil/ Structural Date : July 04, 2008 Progress in Quantity Progress Percentage Rem. Weekly Cum. Balan Daily Weekly Cum. R Balance Sr. U Daily Progress Progress ce Progress % Progress % % Remarks No ACTIVITY EST. ni . Weeks DESCRIPTION QTY t Sch Actl Sch Actl Actl Sch Actl Sch Actl Actl 18th 28,093 M3 969.78 419.58 6499.95 4842.33 23,251 3.45 1.49 23.14 17.24 82.76 Week (03/05/08- 19th 09/05/08) 309.50 28,093 5151.83 22,941 18.34 81.66 Week (10/05/08- 20th 16/05/08) 472.60 28,093 5624.43 22,469 20.02 79.98 Week (17/05/08- 21st 23/05/08) 448.75 28,093 6073.18 22,020 21.62 78.38 Week (24/05/08- 22nd 30/05/08) 138.00 28,093 6211.18 21,882 22.11 77.89 Week (31/05/08- 23rd 05/06/08) Weekly Total = 28,093 441.50 6652.68 21,440 23.68 76.32
  • 9. Discipline : Civil/ Structural Date : July 04, 2008 Progress in Quantity Progress Percentage S Rem. R r Daily Weekly Cum. Balan Daily Weekly Cum. Balance . Progress Progress ce Progress % Progress % % Remarks N U o ACTIVITY EST. ni . Week DESCRIPTION QTY t Sch Actl Sch Actl Actl Sch Actl Sch Actl Actl 24th Week (06/06/08- 12/06/08) Weekly Total = 28,093 118.75 6771.43 21,322 24.10 75.90 25th Week (13/06/08- 19/06/08) Weekly Total = 28,093 66.00 6837.43 21,256 24.34 75.66 26th Week (20/06/08- 26/06/08) Weekly Total = 28,093 490.25 7327.68 20,765 26.08 73.92 27th Week (27/06/08- 03/07/08) Weekly Total = 28,093 758.50 8086.18 20,006 28.78 71.22 28th Week (04/07/08- 10/07/08) Weekly Total = 28,093 671.50 8757.68 19,335 31.17 68.83
  • 11.
  • 12. Updated as of : 11-July-08 Date of Delivery of Sl Modules at Das Foundation Modules . Descripti Island Foundation Location Remarks N on Completed o. On Baseline Forecast Baseline Forecast On Site Harbour PAR's 1 PAR-012 31/12/2008 17/12/2008 30/4/2008 11/4/2008 2 PAR-013 31/12/2008 17/12/2008 14/6/2008 24/4/2008 3 PAR-014 31/12/2008 17/12/2008 5/8/2008 5/6/2008 Common 4 PAR-016 31/12/2008 17/11/2008 28/7/2008 24/6/2008 Facilities 5 PAR-017 3/11/2008 17/11/2008 20/7/2008 6 PAR-018 3/11/2008 17/12/2008 29/6/2008 7 PAR-019 2/12/2008 17/12/2008 28/7/2008 8 PAR-001 2/12/2008 18/10/2008 27/3/2008 7/5/2008 9 PAR-002 2/12/2008 18/10/2008 21/5/2008 22/5/2008 10 PAR-003 Process 2/12/2008 18/10/2008 10/4/2008 21/5/2008 Area, Train- 11 PAR-009 1 31/12/2008 17/11/2008 27/3/2008 14/3/2008 12 PAR-010 31/12/2008 17/11/2008 6/4/2008 13/3/2008 13 PAR-011 31/12/2008 17/11/2008 10/6/2008 31/3/2008 24/5/2008 14 PAR-004 2/12/2008 17/11/2008 7/5/2008 15 PAR-005 2/12/2008 18/10/2008 23/6/2008 Process 16 PAR-006 Area, Train- 2/12/2008 19/10/2008 18/5/2008 2 17 PAR-007 2/12/2008 17/11/2008 26/3/2008 14/3/2008 18 PAR-008 2/12/2008 17/11/2008 8/4/2008 30/4/2008
  • 13. Updated as of : 11-Jul-08 S Date of Delivery of l. Modules at Das Foundation Modules Descripti Island Foundation N Location Remarks on Completed o On On . Baseline Forecast Baseline Forecast Harbour Site PAR's 19 PAR-101 23/8/2008 17/9/2008 11/5/2008 20 PAR-104 23/8/2008 17/9/2008 13/3/2008 15/3/2008 Booster 21 PAR-105 Compressor 23/8/2008 18/10/2008 12/3/2008 5/3/2008 -North 22 PAR-106 23/8/2008 18/10/2008 27/3/2008 9/4/2008 23 PAR-108 17/9/2008 27/3/2008 24 PAR-102 23/8/2008 17/9/2008 26/3/2008 6/5/2008 Booster 25 PAR-103 Compressor 23/8/2008 17/9/2008 8/3/2008 5/3/2008 -South 26 PAR-109 17/9/2008 27/3/2008 6/5/2008
  • 14. 27 PAR-107 18/10/2008 6/5/2008 24/4/2008 28 PAR-201 3/9/2008 17/7/2008 16/3/2008 26/4/2008 29 PAR-211 Interconnect 3/11/2008 17/8/2008 22/4/2008 ing 30 PAR-212 3/11/2008 17/8/2008 18/3/2008 14/6/2008 Piperack- 31 PAR-216 East 3/9/2008 17/7/2008 27/4/2008 21/4/2008 20/06/08 32 PAR-217 3/9/2008 17/7/2008 19/4/2008 8/6/2008 20/06/08 33 PAR-221 17/8/2008 8/5/2008 34 PAR-213 Interconnect 3/11/2008 17/8/2008 10/4/2008 ing 35 PAR-214 3/11/2008 17/8/2008 10/4/2008 14/6/2008 Piperack- 36 PAR-215 West 3/11/2008 17/8/2008 10/4/2008 37 PAR-202 3/9/2008 17/7/2008 9/7/2008 22/3/2008 9/4/2008 38 PAR-203 2/10/2008 17/7/2008 14/4/2008 28/4/2008 39 PAR-205 2/10/2008 17/7/2008 2/4/2008 14/5/2008 20/06/08 Interconnect 40 PAR-206 ing 2/10/2008 17/7/2008 2/4/2008 14/6/2008 20/06/08 41 PAR-207 Piperack- 2/10/2008 17/8/2008 27/3/2008 21/5/2008 Centre 42 PAR-208 2/10/2008 17/12/2008 27/3/2008 17/5/2008 43 PAR-209 2/10/2008 17/12/2008 27/3/2008 17/5/2008 44 PAR-210 2/10/2008 17/08/2008 2/4/2008 21/5/2008 Interconnect ing 45 PAR-015 31/12/2008 17/12/2008 10/4/2008 5/6/2008 Piperack- West 45 TOTAL
  • 15. Updated as of : 11-Jul-08 S Date of Delivery of l. Modules at Das Foundation Modules Descripti Island Foundation N Location Remarks on Completed o On On . Baseline Forecast Baseline Forecast Harbour Site PAU's 1 PAU-001 Process 21/1/2009 21/1/2009 14/5/2008 2 PAU-002 area-West 14/2/2009 21/1/2009 20/5/2008 3 PAU-003 Process 14/10/2008 14/10/2008 12/6/2008 area, Train- 4 PAU-004 1 18/11/2008 13/11/2008 30/3/2008 10/6/2008 5 PAU-005 2/2/2009 21/1/2009 19/7/2008 6 PAU-006 Process 16/2/2009 16/2/2009 19/7/2008 area, Train- 7 PAU-007 2 18/11/2008 13/11/2008 28/7/2008 8 PAU-008 18/11/2008 13/11/2008 1/7/2008 8 TOTAL
  • 16. Updated as of : 11-Jul-08 S Date of Delivery of l. Modules at Das Foundation Modules Descripti Island Foundation N Location Remarks on Completed o On On . Baseline Forecast Baseline Forecast Harbour Site PAU AIRCOOLERS 1 PAU-051 5/1/2009 22/12/2008 2 PAU-052 5/1/2009 22/12/2008 3 PAU-053 5/1/2009 22/12/2008 4 PAU-054 Process 5/1/2009 20/11/2008 10/6/2008 14/8/2008 5 PAU-055 area 5/2/2009 22/1/2009 6 PAU-056 5/2/2009 22/1/2009 7 PAU-057 5/2/2009 22/1/2009 8 PAU-058 5/2/2009 20/11/2008 9 PAU-151A 22/11/2008 2/10/2008 10 PAU-151B Booster 22/11/2008 2/10/2008 compressor 27/4/2008 10/6/2008 11 PAU-152A area 22/11/2008 2/10/2008 12 PAU-152B 22/11/2008 2/10/2008 12 TOTAL : Foundations already due to be completed as of report date as per recovery plan submitted by MEPI vide letter no. L-1364 dated 26 March 2008 : Foundations completed
  • 17. WEEKLY HSE STATISTICS FROM 05.07.08 TO 11.07.08 LTI MTC RTWD First Aid Near miss Inspections ASA Drill TBM 0 0 1 0 6 6 3 0 77 SAFETY TRAININGS CONDUCTED Conducted No. of No. Title of Training by Attendees 1 General HSE Training DESCON 05 2 Heat Stress TARGET 21 3 Defensive Driving TARGET 09 4 Working at Heights TARGET 04 Man Hours for the week 70,360 Cumulative 1,852,238
  • 18. OAG PROJECT / HSE PLAN 05/07/08 to 11/07/08 Activities Performed Activities Planned This Week Next Week Review and closures of unsafe observations stated in weekly HSE Induction for new employees. walk thru inspection. Daily and weekly Site Inspection 41 new employees have been inducted for safety. Upadte Action Tracking system Weekly safety walk thru at Process, Interconnecting Pipe Weekly supervisors meeting for Target and Descon Rack and Podium area TRA Meeting for Descon and Target. Monitoring of Site inspections reports. HSEMS and EMS Awareness Training for Staff Weekly HSE Coordination Meeting. Management safety weekly walk-thru Weekly HSE Coordination Meeting Supervisor’s Weekly HSE Meeting. Conduct ASA as per schedule Daily tool box meetings Daily tool box meetings are attended by MEPI/Target/Descon staff as TRA Meeting per schedule Opening and close out Meeting with TUV & ADGAS Auditors. Start month long HEAT STRESS campaign Conducted 4 ASA at site. Action Plan :- On going The following inspections/verifications were conducted: Scheduled Inspections : •Waste Management •Working at Heights •Housekeeping •Excavation Access •Power Tools •Material Stacking •Full Body Harness •Camp Inspection Training Conducted •Descon Yard •Defensive Driving - 09 Training •Heat Stress – 21 •Heat Stress Management •Working at height •Work at Height – 04 •H2S Awareness •Emergency Response - 20 •HSEMS and EMS Awareness •General HSE Training – 05 •PTW - 02
  • 19. OAG PROJECT / HSE ACTIVITIES Near Miss Trend 05/07/08 to 11/07/08 Description Status Sub standard Practice– One MEPI supervisor climbed from the first stage of the scaffold to the Unsafe act second stage passing through handrail. Unsafe act Sub standard Practice – DESCON trailer entered C-30 road, blocking the traffic for 30 minutes. Unsafe condition Near Miss – Welding machine was found ON condition at podium at 08.30 PM. Sub standard practice – No safety latch on the hook of 150 T crane at reclamation area. Unsafe condition Sub standard practice – Wire rope and spring of TRIPOD GRAB not working properly. Unsafe condition Near miss – TOYOTA HIACE, ADGAS vehicle found over speeding near plant-26. Unsafe act Near miss- Rear door of the tipper truck was not locked while carrying pre-cast manhole. Unsafe condition * We have 03 unsafe condition and 06 unsafe act.
  • 20. WEEKLY EXECUTIVE SUMMARY Wt Weekly Progress % Cumulative Progress % Contr Contrac act / Delta Delta Breakdown Recov t/ Baseli Actu Recove Delta L2 L3 ery Delta (Rec. Baselin Actual (Rec.Pl ne al ry Plan (Plan) Plan Plan) e Early an) Early Plan Plan Temporary 100.00 2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 98.00% 100.00% 2.00% 0.00% Facilities % Construction & Pre- 95.20% 1.15% 2.12% 0.65% -0.50% -1.47% 58.13% 44.43% 31.78% -26.35% -12.66% commission- ing Civil Works: 64.94% 1.17% 3.09% 0.70% -0.46% -2.39% 82.13% 67.29% 48.12% -34.01% -19.17% M.E.I. Works: 35.06% 1.12% 0.32% 0.54% -0.57% 0.22% 13.66% 2.09% 1.50% -12.16% -0.59% Commission- 2.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% ing As Built 0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Document Total 100% 1.09% 2.02% 0.62% -0.48% -1.40% 57.30% 44.30% 32.25% -25.04% -12.05%
  • 21. ACTIVITIES FOR THE WEEK 11.07.2008 AREA OF CONCERN 1. Construction & Commissioning Progress Site : Actual : 31.78 %, Delta : - 12.65 % Before Delta : - 9.27 % Recovery Plant : 44.43 % The Delta was increase and Need for Recovery Pour Concrete 1 200 M3 every week for minimum during next 12 weeks. Delays by Aggregate / Bad Weather /Capacity of Harbour for UnLoad/Load . Planning and Coordination. 2. Concrete poured last Thursday 10 July 2008 ------------ 84.0 M3 Total concrete poured This Week -------------- 671.5 M3 Total Qty Concrete Poured until this Week ---------------- 8757.68 M3 3. ADGAS is looking for Additional Area for storage more Qty of Aggregates. On initial Area requested by MEPI is on process for approval
  • 22. ACTIVITIES FOR THE WEEK 11.07.2008 AREA OF CONCERN 4. Radios provided by MEPI have now 3 to 6 New channels and Target/MEPI will be contact Safeer for give to him all information that we request and test for direct communications with CCB / CCR. Ongoing. 5. QHSE & QA / QC Audit was closed 10 July 2008 . Inform with conclusion and Actions will be sending after close Meeting in Abu Dhabi. QA/QC Engineer at Das expect on July 2008. Action by Ed - Livingston / C Foster. ADGAS is requesting MEPI for Filling remaining positions on Site, special on QA/QC, Planning and Piping Areas
  • 23. ACTIVITIES FOR THE WEEK 11.07.2008 AREA OF CONCERN 6. Construction Jetty. Sea chart : Done. We have from Furgo / Constain. Survey was done in Dec 2005. TRA & MS. Done Integrity & Safety of Construction : 2 core drills was performed. Done Clean Debris : Started with Priority on Area that will be used by OAG-1. Ongoing. Temporary light : ADGAS Maintenance Stores have all parts for re - establish service. Ongoing. Mooring Anchor Blocks : Noble Denton Study provide another Mooring Anchor Concrete Block positions and coordinates. Some of there are the same of Existing Anchor Blocks on sea bed. Defenders : According with Noble Denton, we need take off old defenders and put New ones or if PPA accept, we can use old big Tired that we have and we used time before on Harbour ? Ongoing. Buoys : Purchasing. Ongoing. 7. Area Plant 19 : a. Reclamation / shore protection: ADGAS requested to MEPI Qty and Prices Drawing and scope of work was sent to MEPI. b. Area close to liquid Flare need level using excavated material. ADGAS will request ADMA permission for start to work.
  • 24. ACTIVITIES FOR THE WEEK 11.07.2008 AREA OF CONCERN 8. Flare Area: MEPI start the job. The area was demark with bonders for radiation. 9. Modules : PAR 217 was Transported to Podium. PAR 216 will be Transported to Podium Today. 205 & 206, are storage on Harbour Area from 27 June 2008 until after install of Modules 201/202/203 that arrived to Harbour. Gatching: Done. SPMT: Is OK. Foundations for Modules 217 & 216 are ready for receive Modules. DESCON 500t crane was assembled in Podium Area. Functional and Load Test were performed. A1 Route is ready for Transport of Modules. Permissions are ready for Transport of Modules PAR 217 / 216.
  • 25. ACTIVITIES FOR THE WEEK 11.07.2008 AREA OF CONCERN 10. ADGAS Requesting to MEPI for re-start the welding work and back filling on Pipes Process Area sides East & West, there are two Lines 12 inches diameter Fresh Water and Fire Water are on open trenches from time ago. ONGOING. 11. ADGAS is requesting, better protection for compact material on route, close to PAR 217. ONGOING. 12. ADGAS is requesting, What is the detail Plan for Install the Modules PAR 216 & 217. DONE. 13. ADGAS is requesting, When will be start of construction assembling for PAR 220/219/218. 14. ADGAS is very concern with Planning Activities for future Next Weeks and also very concern with Activities that were stopped long time ago and No re started again without any Technical Issue, example Open Trenches for Fire Water / Fresh Water Lines, Flare are dumped, Excavated Material, Erection Modules PAR 220/219/218. ONGOING. 15. ADGAS require MS for interconnection Piping & Modules.