1308- The Sustainable Sugarcane Initiative (SSI) in India and Beyond
Site Manager Mr[1].Wilson Contreras Presentation Pdf
1. OFFSHORE ASSOCIATED GASES
PACKAGE 1
DAS ISLAND FACILITIES
WEEKLY PRESENTATION
Mr.Wilson Contreras.SITE MANAGER
OAG PROJECT.
2. INDEX
1. ACTIVITIES OF THE WEEK
2. MANPOWER STATUS
3. CONCRETE STATUS (PIE / LINE GRAPH)
4. WEEKLY PROGRESSIVE QUANTITY REPORT
(CONCRETE)
5. WEEKLY CONCRETE QUANTITIES
FORECAST
6. MONTHLY MANPOWER FORECAST
7. STATUS OF PAR’s & PAU’s FOUNDATION
8. WEEKLY HSE STATISTICS
9. HSE PLAN
10. HSE NEAR MISS TREND
11. WEEKLY EXECUTIVE SUMMARY
12. AREA OF CONCERN
13. BLACK SOIL
14. GEND IMPELLERS
3. ACTIVITIES OF THE WEEK
PODIUM AREA:
Retaining Wall / Pipe Supports Valve Pits / VSD Building
Booster Compressors (26-K-0401 & 26-K-0451) and
Pipe Rack # PAR 101 to 106 & PAR 108 to 109
Booster Compressor: 26-K-0401
Booster Compressor: 26-K-0451
Pipe Rack:
Cable Trench (Podium/ Interconnecting / Offsite)
ZAKUM / UMM SHAIF/ LNG MANIFOLD AREA :
Reclamation Area /ADMA Flare Area:
Road A1 – Bridge B – 7: Culvert
Amenities Building
PROCESS AREA:
Outstation Building # 14
Substation Building # 11
Feed Gas Compressor (I-K-401)
Feed Gas Compressor (I-K-451)
Train I & Train II:
Pipe Rack Train 1 & 2:
Manholes / Catch basin / Valve Pits
Cable Trench / Duct Banks (Process/ Common Facilities)
4. ACTIVITIES OF THE WEEK
COMMON FACILITIES:
PIPING:
Process Area
Interconnecting & Offsite Area:
Podium Area:
Fabrication Yard
TARGET Yard:
Temporary Office & Lay down Area:
Cathodic Protection for RC Foundations
5. MANPOWER STATUS AS OF 11.07.2008
S. Manhours
Company Manpower Cum. Manhours
No. (this week)
1. MEPI 36 2,095 85,520
2. Target 804 52,490 1,676,438
3. Descon 271 15,775 90,280
Total on Site 1,111 70,360 1,852,238
6. CONCRETE CASTING
Total Poured Total
8086.18 m3
28.78%
Progress this Total
671.50 m3
week 2.39%
Remaining
Total Concrete Poured 8757.68 m3
68.83%
Total
19335.32 m3
Total Poured Progress this week Remaining
12. Updated as of : 11-July-08
Date of Delivery of
Sl Modules at Das Foundation Modules
. Descripti Island Foundation
Location Remarks
N on Completed
o. On
Baseline Forecast Baseline Forecast On Site
Harbour
PAR's
1 PAR-012 31/12/2008 17/12/2008 30/4/2008 11/4/2008
2 PAR-013 31/12/2008 17/12/2008 14/6/2008 24/4/2008
3 PAR-014 31/12/2008 17/12/2008 5/8/2008 5/6/2008
Common
4 PAR-016 31/12/2008 17/11/2008 28/7/2008 24/6/2008
Facilities
5 PAR-017 3/11/2008 17/11/2008 20/7/2008
6 PAR-018 3/11/2008 17/12/2008 29/6/2008
7 PAR-019 2/12/2008 17/12/2008 28/7/2008
8 PAR-001 2/12/2008 18/10/2008 27/3/2008 7/5/2008
9 PAR-002 2/12/2008 18/10/2008 21/5/2008 22/5/2008
10 PAR-003 Process 2/12/2008 18/10/2008 10/4/2008 21/5/2008
Area, Train-
11 PAR-009 1 31/12/2008 17/11/2008 27/3/2008 14/3/2008
12 PAR-010 31/12/2008 17/11/2008 6/4/2008 13/3/2008
13 PAR-011 31/12/2008 17/11/2008 10/6/2008 31/3/2008 24/5/2008
14 PAR-004 2/12/2008 17/11/2008 7/5/2008
15 PAR-005 2/12/2008 18/10/2008 23/6/2008
Process
16 PAR-006 Area, Train- 2/12/2008 19/10/2008 18/5/2008
2
17 PAR-007 2/12/2008 17/11/2008 26/3/2008 14/3/2008
18 PAR-008 2/12/2008 17/11/2008 8/4/2008 30/4/2008
13. Updated as of : 11-Jul-08
S Date of Delivery of
l. Modules at Das Foundation Modules
Descripti Island Foundation
N Location Remarks
on Completed
o On On
. Baseline Forecast Baseline Forecast
Harbour Site
PAR's
19 PAR-101 23/8/2008 17/9/2008 11/5/2008
20 PAR-104 23/8/2008 17/9/2008 13/3/2008 15/3/2008
Booster
21 PAR-105 Compressor 23/8/2008 18/10/2008 12/3/2008 5/3/2008
-North
22 PAR-106 23/8/2008 18/10/2008 27/3/2008
9/4/2008
23 PAR-108 17/9/2008 27/3/2008
24 PAR-102 23/8/2008 17/9/2008 26/3/2008 6/5/2008
Booster
25 PAR-103 Compressor 23/8/2008 17/9/2008 8/3/2008 5/3/2008
-South
26 PAR-109 17/9/2008 27/3/2008 6/5/2008
15. Updated as of : 11-Jul-08
S Date of Delivery of
l. Modules at Das Foundation Modules
Descripti Island Foundation
N Location Remarks
on Completed
o On On
. Baseline Forecast Baseline Forecast
Harbour Site
PAU's
1 PAU-001 Process 21/1/2009 21/1/2009 14/5/2008
2 PAU-002 area-West 14/2/2009 21/1/2009 20/5/2008
3 PAU-003 Process 14/10/2008 14/10/2008 12/6/2008
area, Train-
4 PAU-004 1 18/11/2008 13/11/2008 30/3/2008
10/6/2008
5 PAU-005 2/2/2009 21/1/2009 19/7/2008
6 PAU-006 Process 16/2/2009 16/2/2009 19/7/2008
area, Train-
7 PAU-007 2 18/11/2008 13/11/2008 28/7/2008
8 PAU-008 18/11/2008 13/11/2008 1/7/2008
8 TOTAL
16. Updated as of
: 11-Jul-08
S Date of Delivery of
l. Modules at Das Foundation Modules
Descripti Island Foundation
N Location Remarks
on Completed
o On On
. Baseline Forecast Baseline Forecast
Harbour Site
PAU AIRCOOLERS
1 PAU-051 5/1/2009 22/12/2008
2 PAU-052 5/1/2009 22/12/2008
3 PAU-053 5/1/2009 22/12/2008
4 PAU-054 Process 5/1/2009 20/11/2008
10/6/2008 14/8/2008
5 PAU-055 area 5/2/2009 22/1/2009
6 PAU-056 5/2/2009 22/1/2009
7 PAU-057 5/2/2009 22/1/2009
8 PAU-058 5/2/2009 20/11/2008
9 PAU-151A 22/11/2008 2/10/2008
10 PAU-151B Booster 22/11/2008 2/10/2008
compressor 27/4/2008 10/6/2008
11 PAU-152A area 22/11/2008 2/10/2008
12 PAU-152B 22/11/2008 2/10/2008
12 TOTAL
: Foundations already due to be completed as of report date as per recovery plan submitted by MEPI vide
letter no. L-1364 dated 26 March 2008
: Foundations completed
17. WEEKLY HSE STATISTICS
FROM 05.07.08 TO 11.07.08
LTI MTC RTWD First Aid Near miss Inspections ASA Drill TBM
0 0 1 0 6 6 3 0 77
SAFETY TRAININGS CONDUCTED
Conducted No. of
No. Title of Training
by Attendees
1 General HSE Training DESCON 05
2 Heat Stress TARGET 21
3 Defensive Driving TARGET 09
4 Working at Heights TARGET 04
Man Hours for the week 70,360
Cumulative 1,852,238
18. OAG PROJECT / HSE PLAN
05/07/08 to 11/07/08
Activities Performed Activities Planned
This Week Next Week
Review and closures of unsafe observations stated in weekly HSE Induction for new employees.
walk thru inspection. Daily and weekly Site Inspection
41 new employees have been inducted for safety. Upadte Action Tracking system
Weekly safety walk thru at Process, Interconnecting Pipe Weekly supervisors meeting for Target and Descon
Rack and Podium area TRA Meeting for Descon and Target.
Monitoring of Site inspections reports. HSEMS and EMS Awareness Training for Staff
Weekly HSE Coordination Meeting. Management safety weekly walk-thru
Weekly HSE Coordination Meeting
Supervisor’s Weekly HSE Meeting.
Conduct ASA as per schedule
Daily tool box meetings
Daily tool box meetings are attended by MEPI/Target/Descon staff as
TRA Meeting per schedule
Opening and close out Meeting with TUV & ADGAS Auditors. Start month long HEAT STRESS campaign
Conducted 4 ASA at site. Action Plan :- On going
The following inspections/verifications were conducted: Scheduled Inspections :
•Waste Management
•Working at Heights
•Housekeeping
•Excavation Access •Power Tools
•Material Stacking •Full Body Harness
•Camp Inspection
Training Conducted •Descon Yard
•Defensive Driving - 09 Training
•Heat Stress – 21 •Heat Stress Management
•Working at height
•Work at Height – 04 •H2S Awareness
•Emergency Response - 20 •HSEMS and EMS Awareness
•General HSE Training – 05
•PTW - 02
19. OAG PROJECT / HSE ACTIVITIES
Near Miss Trend
05/07/08 to 11/07/08
Description Status
Sub standard Practice– One MEPI supervisor climbed from the first stage of the scaffold to the Unsafe act
second stage passing through handrail.
Unsafe act
Sub standard Practice – DESCON trailer entered C-30 road, blocking the traffic for 30 minutes.
Unsafe condition
Near Miss – Welding machine was found ON condition at podium at 08.30 PM.
Sub standard practice – No safety latch on the hook of 150 T crane at reclamation area. Unsafe condition
Sub standard practice – Wire rope and spring of TRIPOD GRAB not working properly. Unsafe condition
Near miss – TOYOTA HIACE, ADGAS vehicle found over speeding near plant-26. Unsafe act
Near miss- Rear door of the tipper truck was not locked while carrying pre-cast manhole.
Unsafe condition
* We have 03 unsafe condition and 06 unsafe act.
20. WEEKLY EXECUTIVE SUMMARY
Wt Weekly Progress % Cumulative Progress %
Contr
Contrac
act / Delta Delta
Breakdown Recov t/
Baseli Actu Recove Delta
L2 L3 ery Delta (Rec. Baselin Actual (Rec.Pl
ne al ry Plan (Plan)
Plan Plan) e Early an)
Early
Plan
Plan
Temporary 100.00
2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 98.00% 100.00% 2.00% 0.00%
Facilities %
Construction
& Pre-
95.20% 1.15% 2.12% 0.65% -0.50% -1.47% 58.13% 44.43% 31.78% -26.35% -12.66%
commission-
ing
Civil Works: 64.94% 1.17% 3.09% 0.70% -0.46% -2.39% 82.13% 67.29% 48.12% -34.01% -19.17%
M.E.I. Works: 35.06% 1.12% 0.32% 0.54% -0.57% 0.22% 13.66% 2.09% 1.50% -12.16% -0.59%
Commission-
2.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ing
As Built
0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Document
Total 100% 1.09% 2.02% 0.62% -0.48% -1.40% 57.30% 44.30% 32.25% -25.04% -12.05%
21. ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERN
1. Construction & Commissioning Progress Site :
Actual : 31.78 %, Delta : - 12.65 %
Before Delta : - 9.27 %
Recovery Plant : 44.43 %
The Delta was increase and Need for Recovery Pour Concrete 1 200 M3
every week for minimum during next 12 weeks.
Delays by Aggregate / Bad Weather /Capacity of Harbour for UnLoad/Load .
Planning and Coordination.
2. Concrete poured last Thursday 10 July 2008 ------------ 84.0 M3
Total concrete poured This Week -------------- 671.5 M3
Total Qty Concrete Poured until this Week ---------------- 8757.68 M3
3. ADGAS is looking for Additional Area for storage more Qty of Aggregates.
On initial Area requested by MEPI is on process for approval
22. ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERN
4. Radios provided by MEPI have now 3 to 6 New channels and Target/MEPI will
be contact Safeer for give to him all information that we request and test for direct
communications with CCB / CCR. Ongoing.
5. QHSE & QA / QC Audit was closed 10 July 2008 . Inform with conclusion
and Actions will be sending after close Meeting in Abu Dhabi.
QA/QC Engineer at Das expect on July 2008. Action by Ed - Livingston / C
Foster.
ADGAS is requesting MEPI for Filling remaining positions on Site, special
on QA/QC, Planning and Piping Areas
23. ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERN
6. Construction Jetty.
Sea chart : Done. We have from Furgo / Constain. Survey was done in
Dec 2005. TRA & MS. Done
Integrity & Safety of Construction : 2 core drills was performed. Done
Clean Debris : Started with Priority on Area that will be used by OAG-1. Ongoing.
Temporary light : ADGAS Maintenance Stores have all parts for re - establish
service. Ongoing.
Mooring Anchor Blocks : Noble Denton Study provide another Mooring
Anchor Concrete Block positions and coordinates. Some of there are the same of
Existing Anchor Blocks on sea bed.
Defenders : According with Noble Denton, we need take off old defenders and put
New ones or if PPA accept, we can use old big Tired that we have and we used
time before on Harbour ? Ongoing.
Buoys : Purchasing. Ongoing.
7. Area Plant 19 :
a. Reclamation / shore protection: ADGAS requested to MEPI Qty and Prices
Drawing and scope of work was sent to MEPI.
b. Area close to liquid Flare need level using excavated material. ADGAS will
request ADMA permission for start to work.
24. ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERN
8. Flare Area: MEPI start the job. The area was demark with bonders for
radiation.
9. Modules :
PAR 217 was Transported to Podium.
PAR 216 will be Transported to Podium Today.
205 & 206, are storage on Harbour Area from 27 June 2008 until after install of
Modules 201/202/203 that arrived to Harbour.
Gatching: Done.
SPMT: Is OK.
Foundations for Modules 217 & 216 are ready for receive Modules.
DESCON 500t crane was assembled in Podium Area. Functional and Load
Test were performed.
A1 Route is ready for Transport of Modules.
Permissions are ready for Transport of Modules PAR 217 / 216.
25. ACTIVITIES FOR THE WEEK 11.07.2008
AREA OF CONCERN
10. ADGAS Requesting to MEPI for re-start the welding work and back filling on
Pipes Process Area sides East & West, there are two Lines 12 inches diameter
Fresh Water and Fire Water are on open trenches from time ago. ONGOING.
11. ADGAS is requesting, better protection for compact material on route, close to
PAR 217. ONGOING.
12. ADGAS is requesting, What is the detail Plan for Install the Modules PAR 216 &
217. DONE.
13. ADGAS is requesting, When will be start of construction assembling for PAR
220/219/218.
14. ADGAS is very concern with Planning Activities for future Next Weeks and also
very concern with Activities that were stopped long time ago and No re started
again without any Technical Issue, example Open Trenches for Fire Water /
Fresh Water Lines, Flare are dumped, Excavated Material, Erection Modules
PAR 220/219/218. ONGOING.
15. ADGAS require MS for interconnection Piping & Modules.