SlideShare a Scribd company logo
1 of 1
Download to read offline
TECHNOLOGY                                                                                                                      BY KATHI KUBE
                                                                                                                                                      and does not mandate a speci c deadline.


From evolution to revolution
                                                                                                                                                      Cars made between now and the nal nal
                                                                                                                                                      rule will be grandfathered under the new
                                                                                                                                                      speci cations for 20 years, although some
                                                                                                                                                      existing tank cars must be prioritized for
Railroad engineering advances, challenges portend a wild ride                                                                                         discontinuance. T           will discuss tank
                                                                                                                                                      car designs in greater depth next month.
The average U.S. citizen likely still              territory. So it relies on human input, which including imposing di erent speed limits                 Meanwhile, less controversial technolo-
thinks dieselization was the only signi cant       can introduce errors. “ ere are potential for signaled (50 mph) and dark (30 mph)                  gies are likely to show up on railroads soon,
technological advance in railroading; mean-        solutions, but they remain to be developed,” territory, and a mandate to design and                including new designs for commuter cab
while, educated observers see change, albeit       Polivka says. TTCI has an Federal Railroad manufacture tank cars with puncture-resis-              cars. Several wrecks over the past 30 years
usually slow and plodding. Today, even             Administration-funded contract to develop tant shells capable of withstanding impact               involving cab cars and electric M.U. cars
“change” is changing. Progress in several          one of those approaches using a high-accu- at 25 mph and a tank-head puncture sys-                 have resulted in fatalities when the corner
scienti c disciplines, the continual need for      racy form of di erential GPS. Further, tem capable of withstanding impact at 30                    posts were breached. On June 18, 1998, a
improvement, and several horri c wrecks            sometimes PTC systems don’t receive key mph.                e proposed puncture-resistance         two-car South Shore Line M.U. commuter
have converged to herald an era of revolu-         messages over the radio due to interference standards would represent an increase in               train collided with a tractor-trailer truck at a
tionary as well as evolutionary change. But,       or several other factors. In these cases, the stringency of six and 10 times the current           grade crossing in Portage, Ind. A 19-ton
as is the case in all revolutions, change will     system can stop a train where no hazard ex- impact standards.                                      steel coil broke loose and penetrated the
not be easy: Several signi cant challenges         ists. ese conditions could conspire to slow         In its rule-making notice, FRA also pro-       lead car, killing three people. Michelle Müh-
remain and must be overcome.                       overall train velocities. During the next six posed that the 150,000 tank cars used in             langer, Patricia Llana, and David Tyrell, all
       e September 2008 Metrolink wreck in         years, T         will follow these challenges as hazmat service in the U.S. be replaced in         of the Volpe National Transportation Sys-
Chatsworth, Calif., that killed 25 people          PTC nears implementation.                        eight years a er the nal rule’s publication:      tems Center, designed and tested a state-of-
prompted a federal mandate to implement                Train control was one of many emerging Car builders would have two years to de-                the-art corner post that was able to absorb
positive train control systems nationwide by       technologies discussed in Pueblo, Colo., at sign, model, test, and build the new tank              about 137,000 foot-pounds of energy yet
Dec. 31, 2015. But PTC isn’t ready. Yes, the       TTCI’s 14th Annual Research Re-                              cars, then shippers would have to     deform only 7.5 inches, thereby preserving a
systems can and will stop a train short of a       view and the Joint Rail Confer-                              replace half their eet in the next    safe area for operators and passengers. FRA
target (control point, switch, etc.) but a vari-   ence hosted by associations for                              three years, and the remainder in     is using the test results in support of a new
ety of factors (weight, grade, humidity, leaves    mechanical, electrical, and civil                            the remaining three years. Con-       crashworthiness rule that Mühlanger ex-
on the tracks, and more) make it di cult to        engineers in March.                                          sidering that in 2006 the average     pects to be released later this year.
accurately predict the correct stopping dis-           Tank car design is another hot                           cost of a new tank car of a stan-         Standard wheel pro les are also likely to
tance, which might cause the systems to stop       issue. FRA, on Jan. 13, 2009, is-                            dard existing design was about        change this year. Wheel pro les last changed
trains a half-mile or more early.                  sued its nal rule on improving                               $81,000, replacing these tank cars    in the mid-1980s. Since that time, railroads
    “At Transportation Technology Center           tank car safety. Make that its -                             with yet-to-be-designed models        have begun running heavier railcars, and ad-
Inc., we have two Federal Railroad Adminis-        nal rule on an interim tank car                              would exceed $12 billion. is          justed their rail grinding and lubricating
tration-funded projects underway that have         design. On April 1, 2008, FRA Alan Polivka. T TCI            alone could be enough of a hin-       practices. “One small change might not make
developed some very promising solutions to         had issued a notice of proposed                              drance to force hazmat shipping       a di erence, but if enough add up, it creates a
the problem,” says Alan Polivka, TTCI assis-       rulemaking, in part as a response                            to the highways.                      new equilibrium,” says Nick Wilson, an engi-
tant vice president, communications and            to hazardous materials releases                                     e nal rule addressed some      neer in vehicle dynamics at TTCI.
train control. “ ey must undergo further           in train wrecks in Minot, N.D.,                              of these concerns. For example,           Speci cally, wheels and rails typically
analysis, simulation, and testing before           and Graniteville, S.C. Chemical                              the U.S. Department of Trans-         now have two severe contact points, which
they’ll be ready for prime time, however.”         companies, railroads, tank car                               porttion did not adopt the 30-        leads wheels to wear asymmetrically, can
    But that’s not the only challenge engi-        manufacturers, politicians, the                              mph speed limit for dark territo-     cause gauge spreading in the beginning
neers need to resolve. Technology can dis-         general public, and a host of oth-                           ry, and is not forcing technology     stage of service, and o en leads to prema-
cern which track a train is on once it starts      er interested parties responded                              with the signi cantly more strin-     ture wear of wheels and rail.
moving, but it can’t when the system is rst        quickly. Many believed the pro-                              gent designs — for now. Rather,           In her presentation, principal investiga-
acquiring the satellite link in multiple-track     posed rule had several problems, Nick Wilson. T TCI          this rule speci es interim designs,   tor Huimin Wu stated that TTCI expects
                                                                                                                                                      the Association of American Railroads to
                                                                                                                                                      recommend an interchange rule for the new
The sun will be setting on some tank car                                                                                                              wheel pro le this year. How apparent will
designs as the government and industry                                                                                                                the change be to the casual observer? “From
work to improve safety. TR A I NS : Kathi Kube                                                                                                        20 feet away, you won’t notice,” Wilson says.
                                                                                                                                                      “But people experienced in looking at
                                                                                                                                                      wheels will notice.”
                                                                                                                                                          In big ways and small ways, railroad
                                                                                                                                                      technology is changing.
                                                                                                                                                        >> TECHNOLOGY BRIEF

                                                                                                                                                        High-speed optics
                                                                                                                                                        detect joint bar cracks
                                                                                                                                                        ENSCO’s high-speed optical joint bar
                                                                                                                                                        inspection system combats broken or
                                                                                                                                                        cracked rail joiners by locating 1/4-
                                                                                                                                                        inch cracks at speeds up to 65 mph.


                                                                                                                                                              >> Learn more about new railroad
                                                                                                                                                               technologies at www.TrainsMag.
                                                                                                                                                                                                         www.TrainsMag.com   17

More Related Content

What's hot

P4 ken shirley tauranga transport and logistics forum 2012
P4  ken shirley tauranga transport and logistics forum 2012P4  ken shirley tauranga transport and logistics forum 2012
P4 ken shirley tauranga transport and logistics forum 2012
Greg Bold
 
Reports_Only_CM
Reports_Only_CMReports_Only_CM
Reports_Only_CM
John Fall
 
First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015
Norma Nun
 

What's hot (9)

Sustainable future through innovation
Sustainable future through innovationSustainable future through innovation
Sustainable future through innovation
 
SNC-Lavalin Ian Edwards' speech
SNC-Lavalin Ian Edwards' speechSNC-Lavalin Ian Edwards' speech
SNC-Lavalin Ian Edwards' speech
 
P4 ken shirley tauranga transport and logistics forum 2012
P4  ken shirley tauranga transport and logistics forum 2012P4  ken shirley tauranga transport and logistics forum 2012
P4 ken shirley tauranga transport and logistics forum 2012
 
1 transportation vancouver island economic loss dec 02 2013
1 transportation  vancouver island economic loss dec 02 20131 transportation  vancouver island economic loss dec 02 2013
1 transportation vancouver island economic loss dec 02 2013
 
Reports_Only_CM
Reports_Only_CMReports_Only_CM
Reports_Only_CM
 
Costing of Australian urban passenger rail project 2000-2012
Costing of Australian urban passenger rail project 2000-2012Costing of Australian urban passenger rail project 2000-2012
Costing of Australian urban passenger rail project 2000-2012
 
Vision plan spur 11.30 presentation - hires
Vision plan   spur 11.30 presentation - hiresVision plan   spur 11.30 presentation - hires
Vision plan spur 11.30 presentation - hires
 
SMART Demonstrations Projects Presentation
SMART Demonstrations Projects PresentationSMART Demonstrations Projects Presentation
SMART Demonstrations Projects Presentation
 
First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015
 

Viewers also liked (13)

Ied Moda Lab
Ied Moda LabIed Moda Lab
Ied Moda Lab
 
Longchamps Paris
Longchamps ParisLongchamps Paris
Longchamps Paris
 
Pasteur
PasteurPasteur
Pasteur
 
Atlanta magazine
Atlanta magazineAtlanta magazine
Atlanta magazine
 
SC debe garantizar competencia en concesión de puertos
SC debe garantizar competencia en concesión de puertosSC debe garantizar competencia en concesión de puertos
SC debe garantizar competencia en concesión de puertos
 
Long Tall Sally
Long Tall SallyLong Tall Sally
Long Tall Sally
 
Trn Ft0709 Contest
Trn Ft0709   ContestTrn Ft0709   Contest
Trn Ft0709 Contest
 
Client Reference Video
Client Reference VideoClient Reference Video
Client Reference Video
 
Wer Bietet Mehr
Wer Bietet MehrWer Bietet Mehr
Wer Bietet Mehr
 
G4 Group
G4 GroupG4 Group
G4 Group
 
Atlanta Magazine\'s HOME
Atlanta Magazine\'s HOMEAtlanta Magazine\'s HOME
Atlanta Magazine\'s HOME
 
Master Bath Remodel
Master Bath RemodelMaster Bath Remodel
Master Bath Remodel
 
Get a grasp on the Bible
Get a grasp on the BibleGet a grasp on the Bible
Get a grasp on the Bible
 

Similar to Trn Tc0609 Ttci Preview

TH-Relics_Pickeral 9-14
TH-Relics_Pickeral 9-14TH-Relics_Pickeral 9-14
TH-Relics_Pickeral 9-14
David Pickeral
 
Straight out of Science Fiction: The Maglev
Straight out of Science Fiction: The MaglevStraight out of Science Fiction: The Maglev
Straight out of Science Fiction: The Maglev
RakhaArunaDewa
 
Thinking Highways - Congestion 4-12
Thinking Highways - Congestion 4-12Thinking Highways - Congestion 4-12
Thinking Highways - Congestion 4-12
David Pickeral
 
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CASocietal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Pablo Naoki Manzano Miura
 
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
gilbertkpeters11344
 

Similar to Trn Tc0609 Ttci Preview (20)

CYPcorridor_Paper
CYPcorridor_PaperCYPcorridor_Paper
CYPcorridor_Paper
 
Railway
RailwayRailway
Railway
 
TH-Relics_Pickeral 9-14
TH-Relics_Pickeral 9-14TH-Relics_Pickeral 9-14
TH-Relics_Pickeral 9-14
 
Hydrogen Super Highway - Seminar Report
Hydrogen Super Highway - Seminar Report Hydrogen Super Highway - Seminar Report
Hydrogen Super Highway - Seminar Report
 
Straight out of Science Fiction: The Maglev
Straight out of Science Fiction: The MaglevStraight out of Science Fiction: The Maglev
Straight out of Science Fiction: The Maglev
 
Publications
PublicationsPublications
Publications
 
Maglev Train Ppt 1
Maglev Train Ppt 1Maglev Train Ppt 1
Maglev Train Ppt 1
 
The State of Rail in Illinois
The State of Rail in IllinoisThe State of Rail in Illinois
The State of Rail in Illinois
 
GE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of NetworksGE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of Networks
 
Tom Clements MOX Plutonium briefing 6.29.2012
Tom Clements MOX Plutonium briefing 6.29.2012Tom Clements MOX Plutonium briefing 6.29.2012
Tom Clements MOX Plutonium briefing 6.29.2012
 
Cost Benefit Analysis of Mobile Barriers MBT-1
Cost Benefit Analysis of Mobile Barriers MBT-1Cost Benefit Analysis of Mobile Barriers MBT-1
Cost Benefit Analysis of Mobile Barriers MBT-1
 
Thinking Highways - Congestion 4-12
Thinking Highways - Congestion 4-12Thinking Highways - Congestion 4-12
Thinking Highways - Congestion 4-12
 
NCDOT Rail Update
NCDOT Rail UpdateNCDOT Rail Update
NCDOT Rail Update
 
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CASocietal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
 
IRJET- Progress in the Proton Exchange Membrane Development and Application o...
IRJET- Progress in the Proton Exchange Membrane Development and Application o...IRJET- Progress in the Proton Exchange Membrane Development and Application o...
IRJET- Progress in the Proton Exchange Membrane Development and Application o...
 
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
3 2 2 Chapter 10 Managing IT Projects Discussion Questions.docx
 
Taxi Paper
Taxi PaperTaxi Paper
Taxi Paper
 
American Railroads: Decline and Renaissance in the Twentieth Century
American Railroads: Decline and Renaissance in the Twentieth CenturyAmerican Railroads: Decline and Renaissance in the Twentieth Century
American Railroads: Decline and Renaissance in the Twentieth Century
 
2013 Simultech newton
2013 Simultech newton2013 Simultech newton
2013 Simultech newton
 
Rail Technical Strategy, Key Capability 6 - More Space on Trains
Rail Technical Strategy, Key Capability 6 - More Space on TrainsRail Technical Strategy, Key Capability 6 - More Space on Trains
Rail Technical Strategy, Key Capability 6 - More Space on Trains
 

More from lorax210

Portfolio Presentation
Portfolio PresentationPortfolio Presentation
Portfolio Presentation
lorax210
 
Trn Tc1208 Switch Heaters
Trn Tc1208   Switch HeatersTrn Tc1208   Switch Heaters
Trn Tc1208 Switch Heaters
lorax210
 
Trn Ft0809 Airfanning
Trn Ft0809   AirfanningTrn Ft0809   Airfanning
Trn Ft0809 Airfanning
lorax210
 
Trn Tc0709 Beam
Trn Tc0709   BeamTrn Tc0709   Beam
Trn Tc0709 Beam
lorax210
 
Trn Tc0809 Ballast Sensor
Trn Tc0809   Ballast SensorTrn Tc0809   Ballast Sensor
Trn Tc0809 Ballast Sensor
lorax210
 
Trn Tc0409 Cleaning Hoppers
Trn Tc0409   Cleaning HoppersTrn Tc0409   Cleaning Hoppers
Trn Tc0409 Cleaning Hoppers
lorax210
 
Trn Tc0309 Wheel View
Trn Tc0309   Wheel ViewTrn Tc0309   Wheel View
Trn Tc0309 Wheel View
lorax210
 
Trn Ft1208 Winterfanning
Trn Ft1208  WinterfanningTrn Ft1208  Winterfanning
Trn Ft1208 Winterfanning
lorax210
 
Trn Ft0509 Depot Inn
Trn Ft0509   Depot InnTrn Ft0509   Depot Inn
Trn Ft0509 Depot Inn
lorax210
 
Trn Ft0409 Vacation
Trn Ft0409   VacationTrn Ft0409   Vacation
Trn Ft0409 Vacation
lorax210
 
Trn Ft0309 Spike Tower
Trn Ft0309   Spike TowerTrn Ft0309   Spike Tower
Trn Ft0309 Spike Tower
lorax210
 
Trn Ft0209 Alaska
Trn Ft0209   AlaskaTrn Ft0209   Alaska
Trn Ft0209 Alaska
lorax210
 

More from lorax210 (12)

Portfolio Presentation
Portfolio PresentationPortfolio Presentation
Portfolio Presentation
 
Trn Tc1208 Switch Heaters
Trn Tc1208   Switch HeatersTrn Tc1208   Switch Heaters
Trn Tc1208 Switch Heaters
 
Trn Ft0809 Airfanning
Trn Ft0809   AirfanningTrn Ft0809   Airfanning
Trn Ft0809 Airfanning
 
Trn Tc0709 Beam
Trn Tc0709   BeamTrn Tc0709   Beam
Trn Tc0709 Beam
 
Trn Tc0809 Ballast Sensor
Trn Tc0809   Ballast SensorTrn Tc0809   Ballast Sensor
Trn Tc0809 Ballast Sensor
 
Trn Tc0409 Cleaning Hoppers
Trn Tc0409   Cleaning HoppersTrn Tc0409   Cleaning Hoppers
Trn Tc0409 Cleaning Hoppers
 
Trn Tc0309 Wheel View
Trn Tc0309   Wheel ViewTrn Tc0309   Wheel View
Trn Tc0309 Wheel View
 
Trn Ft1208 Winterfanning
Trn Ft1208  WinterfanningTrn Ft1208  Winterfanning
Trn Ft1208 Winterfanning
 
Trn Ft0509 Depot Inn
Trn Ft0509   Depot InnTrn Ft0509   Depot Inn
Trn Ft0509 Depot Inn
 
Trn Ft0409 Vacation
Trn Ft0409   VacationTrn Ft0409   Vacation
Trn Ft0409 Vacation
 
Trn Ft0309 Spike Tower
Trn Ft0309   Spike TowerTrn Ft0309   Spike Tower
Trn Ft0309 Spike Tower
 
Trn Ft0209 Alaska
Trn Ft0209   AlaskaTrn Ft0209   Alaska
Trn Ft0209 Alaska
 

Recently uploaded

Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
instagramfab782445
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Recently uploaded (20)

Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Power point presentation on enterprise performance management
Power point presentation on enterprise performance managementPower point presentation on enterprise performance management
Power point presentation on enterprise performance management
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Rice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsRice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna Exports
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 

Trn Tc0609 Ttci Preview

  • 1. TECHNOLOGY BY KATHI KUBE and does not mandate a speci c deadline. From evolution to revolution Cars made between now and the nal nal rule will be grandfathered under the new speci cations for 20 years, although some existing tank cars must be prioritized for Railroad engineering advances, challenges portend a wild ride discontinuance. T will discuss tank car designs in greater depth next month. The average U.S. citizen likely still territory. So it relies on human input, which including imposing di erent speed limits Meanwhile, less controversial technolo- thinks dieselization was the only signi cant can introduce errors. “ ere are potential for signaled (50 mph) and dark (30 mph) gies are likely to show up on railroads soon, technological advance in railroading; mean- solutions, but they remain to be developed,” territory, and a mandate to design and including new designs for commuter cab while, educated observers see change, albeit Polivka says. TTCI has an Federal Railroad manufacture tank cars with puncture-resis- cars. Several wrecks over the past 30 years usually slow and plodding. Today, even Administration-funded contract to develop tant shells capable of withstanding impact involving cab cars and electric M.U. cars “change” is changing. Progress in several one of those approaches using a high-accu- at 25 mph and a tank-head puncture sys- have resulted in fatalities when the corner scienti c disciplines, the continual need for racy form of di erential GPS. Further, tem capable of withstanding impact at 30 posts were breached. On June 18, 1998, a improvement, and several horri c wrecks sometimes PTC systems don’t receive key mph. e proposed puncture-resistance two-car South Shore Line M.U. commuter have converged to herald an era of revolu- messages over the radio due to interference standards would represent an increase in train collided with a tractor-trailer truck at a tionary as well as evolutionary change. But, or several other factors. In these cases, the stringency of six and 10 times the current grade crossing in Portage, Ind. A 19-ton as is the case in all revolutions, change will system can stop a train where no hazard ex- impact standards. steel coil broke loose and penetrated the not be easy: Several signi cant challenges ists. ese conditions could conspire to slow In its rule-making notice, FRA also pro- lead car, killing three people. Michelle Müh- remain and must be overcome. overall train velocities. During the next six posed that the 150,000 tank cars used in langer, Patricia Llana, and David Tyrell, all e September 2008 Metrolink wreck in years, T will follow these challenges as hazmat service in the U.S. be replaced in of the Volpe National Transportation Sys- Chatsworth, Calif., that killed 25 people PTC nears implementation. eight years a er the nal rule’s publication: tems Center, designed and tested a state-of- prompted a federal mandate to implement Train control was one of many emerging Car builders would have two years to de- the-art corner post that was able to absorb positive train control systems nationwide by technologies discussed in Pueblo, Colo., at sign, model, test, and build the new tank about 137,000 foot-pounds of energy yet Dec. 31, 2015. But PTC isn’t ready. Yes, the TTCI’s 14th Annual Research Re- cars, then shippers would have to deform only 7.5 inches, thereby preserving a systems can and will stop a train short of a view and the Joint Rail Confer- replace half their eet in the next safe area for operators and passengers. FRA target (control point, switch, etc.) but a vari- ence hosted by associations for three years, and the remainder in is using the test results in support of a new ety of factors (weight, grade, humidity, leaves mechanical, electrical, and civil the remaining three years. Con- crashworthiness rule that Mühlanger ex- on the tracks, and more) make it di cult to engineers in March. sidering that in 2006 the average pects to be released later this year. accurately predict the correct stopping dis- Tank car design is another hot cost of a new tank car of a stan- Standard wheel pro les are also likely to tance, which might cause the systems to stop issue. FRA, on Jan. 13, 2009, is- dard existing design was about change this year. Wheel pro les last changed trains a half-mile or more early. sued its nal rule on improving $81,000, replacing these tank cars in the mid-1980s. Since that time, railroads “At Transportation Technology Center tank car safety. Make that its - with yet-to-be-designed models have begun running heavier railcars, and ad- Inc., we have two Federal Railroad Adminis- nal rule on an interim tank car would exceed $12 billion. is justed their rail grinding and lubricating tration-funded projects underway that have design. On April 1, 2008, FRA Alan Polivka. T TCI alone could be enough of a hin- practices. “One small change might not make developed some very promising solutions to had issued a notice of proposed drance to force hazmat shipping a di erence, but if enough add up, it creates a the problem,” says Alan Polivka, TTCI assis- rulemaking, in part as a response to the highways. new equilibrium,” says Nick Wilson, an engi- tant vice president, communications and to hazardous materials releases e nal rule addressed some neer in vehicle dynamics at TTCI. train control. “ ey must undergo further in train wrecks in Minot, N.D., of these concerns. For example, Speci cally, wheels and rails typically analysis, simulation, and testing before and Graniteville, S.C. Chemical the U.S. Department of Trans- now have two severe contact points, which they’ll be ready for prime time, however.” companies, railroads, tank car porttion did not adopt the 30- leads wheels to wear asymmetrically, can But that’s not the only challenge engi- manufacturers, politicians, the mph speed limit for dark territo- cause gauge spreading in the beginning neers need to resolve. Technology can dis- general public, and a host of oth- ry, and is not forcing technology stage of service, and o en leads to prema- cern which track a train is on once it starts er interested parties responded with the signi cantly more strin- ture wear of wheels and rail. moving, but it can’t when the system is rst quickly. Many believed the pro- gent designs — for now. Rather, In her presentation, principal investiga- acquiring the satellite link in multiple-track posed rule had several problems, Nick Wilson. T TCI this rule speci es interim designs, tor Huimin Wu stated that TTCI expects the Association of American Railroads to recommend an interchange rule for the new The sun will be setting on some tank car wheel pro le this year. How apparent will designs as the government and industry the change be to the casual observer? “From work to improve safety. TR A I NS : Kathi Kube 20 feet away, you won’t notice,” Wilson says. “But people experienced in looking at wheels will notice.” In big ways and small ways, railroad technology is changing. >> TECHNOLOGY BRIEF High-speed optics detect joint bar cracks ENSCO’s high-speed optical joint bar inspection system combats broken or cracked rail joiners by locating 1/4- inch cracks at speeds up to 65 mph. >> Learn more about new railroad technologies at www.TrainsMag. www.TrainsMag.com 17