SlideShare a Scribd company logo
1 of 26
County of Fairfax, Virginia
Department of Transportation
Proposed Bicycle Facilities
VDOT Summer 2015 Repaving
Mason District
March 25, 2015
County of Fairfax, Virginia
Department of Transportation
2
Overview
• Why are we here?
• What are we asking today?
• What projects are being proposed?
• Where are we in the process?
• What are the next steps?
County of Fairfax, Virginia
Why are we here?
• VDOT Summer repaving includes several roads in the Mount
Vernon District. Opportunity to review pavement markings and
street design. Project limited to restriping existing pavement.
• Opportunity to provide transportation options and improve
pedestrian safety
• Low to no cost for the County
Department of Transportation
3
County of Fairfax, Virginia
What are we asking today?
• Your input and feedback
– Support, questions, concerns, ideas
Department of Transportation
4
Photo Credit:
sundaystreetssf.com
County of Fairfax, Virginia
Project List
• Evergreen Lane
– From Columbia Pike to Little River Turnpike
• Annandale Road
– From Gallows Road to Arlington Boulevard
Department of Transportation
5
County of Fairfax, Virginia
Bicycle Master Plan
Department of Transportation
6
County of Fairfax, Virginia
Bicycle Master Plan (continued)
Department of Transportation
7
County of Fairfax, Virginia
Lane Diets
• A Lane Diet is generally described as narrowing travel
lanes from a roadway and utilizing the space for other
uses and travel modes. Does not involve reducing the
number of travel lanes.
• Benefits
– Providing transportation alternatives and options
– Increasing safety for non-motorized users
– Reduce speeding
Department of Transportation
8
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
Northern Section:
•Existing:
• Columbia Pike to Greenberry
Lane
• One lane in each
direction and Center turn
lane
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
Northern Section:
•Proposed:
• Columbia Pike to Greenberry
Lane
• One lane in each
direction, Center turn lane,
and bike lanes
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
Southern Section:
•Existing:
• Greenberry Lane to Little
River Turnpike
• 2 lanes in each direction
and center turn lane
• One lane in each
direction functions as a
turn lane
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
County of Fairfax, Virginia
Evergreen Lane
Columbia Pike to Little River Turnpike
Department of Transportation
Southern Section:
•Proposed:
• Greenberry Lane to Little
River Turnpike
• Two lanes in each
direction, Center turn lane,
and bike lanes
• One lane in each
direction functions as a
turn lane
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
Existing Conditions
•Most of corridor is 48’ curb to
curb
•Some sections 46’ curb to
curb
•1 travel lane in each direction
with parking
•Pinch point near Walnut
Manor Way
• 45’ curb to curb
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
Proposed Design
•Most of corridor is
approximately 48’ curb to
curb
•Some sections 46’ curb
to curb
•Pinch point near Walnut
Manor Way and
Beechview Drive
• 45’ curb to curb
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
• Options near Walnut Manor Way
• Shared Lane in both directions
• Climbing Lane in one direction
• Bike lanes in both directions
• 7’ parking lane, 4’ bike lane, 11’ travel lane
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
Shared Lane
•14’ shared travel lane
and 8.5’ parking lane
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
Climbing Lane
•11’ travel lanes
•5’ Bike lane
•Shared lane
•8’ parking lanes
County of Fairfax, Virginia
Annandale Road
Gallows Road to Arlington Boulevard
Department of Transportation
Bike Lanes
•11’ Travel lanes
•4’ Bike lane
•7’ Parking lane
County of Fairfax, Virginia
Where are we in the Process?
• Conceptual design underway
• Not proposing to change lane
configuration approaching intersections,
so no additional delay to vehicles
Department of Transportation
24
County of Fairfax, Virginia
What are the next steps?
• Gather community input tonight and over
next two weeks
– Comment Period: Open until April 10th
• Redesign plans as necessary
• Design completion: April 2015
• Projects go to construction Summer 2015
Department of Transportation
25
County of Fairfax, Virginia
Thank You
Questions/Comments?
adam.lind@fairfaxcounty.gov
Department of Transportation
26

More Related Content

What's hot

What's hot (20)

Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
 
Lee District 2017 VDOT Repaving
Lee District 2017 VDOT RepavingLee District 2017 VDOT Repaving
Lee District 2017 VDOT Repaving
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)
 
Student Free Fare Program Update and Recommendations
Student Free Fare Program Update and RecommendationsStudent Free Fare Program Update and Recommendations
Student Free Fare Program Update and Recommendations
 
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
 
Woodford Road Street Design Improvements Meeting
Woodford Road Street Design Improvements MeetingWoodford Road Street Design Improvements Meeting
Woodford Road Street Design Improvements Meeting
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the Beltway
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
 
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD TrailDesign Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
 
Dranesville District 2017 VDOT Repaving
Dranesville District 2017 VDOT RepavingDranesville District 2017 VDOT Repaving
Dranesville District 2017 VDOT Repaving
 
Citizens Information Meeting: North West Street and Great Falls Street Sidewalks
Citizens Information Meeting: North West Street and Great Falls Street SidewalksCitizens Information Meeting: North West Street and Great Falls Street Sidewalks
Citizens Information Meeting: North West Street and Great Falls Street Sidewalks
 
North Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements StudyNorth Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements Study
 
2017 VDOT Repaving and Restriping-Reston: Nov. 14, 2016
2017 VDOT Repaving and Restriping-Reston: Nov. 14, 20162017 VDOT Repaving and Restriping-Reston: Nov. 14, 2016
2017 VDOT Repaving and Restriping-Reston: Nov. 14, 2016
 
Mason District-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
Mason District-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...Mason District-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
Mason District-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
 
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
 
Transportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed FacilitiesTransportation Plan Map In County Comprehensive Plan-Completed Facilities
Transportation Plan Map In County Comprehensive Plan-Completed Facilities
 

Similar to Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mason District

Similar to Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mason District (20)

Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495
 
2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
 
Proposed Street Design Update - VDOT Summer 2015 Repaving Tysons
Proposed Street Design Update - VDOT Summer 2015 Repaving TysonsProposed Street Design Update - VDOT Summer 2015 Repaving Tysons
Proposed Street Design Update - VDOT Summer 2015 Repaving Tysons
 
Proposed Street Design Updates-VDOT Summer 2015 Repaving
Proposed Street Design Updates-VDOT Summer 2015 RepavingProposed Street Design Updates-VDOT Summer 2015 Repaving
Proposed Street Design Updates-VDOT Summer 2015 Repaving
 
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
 
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
 
Mason District 2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
Mason District 2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...Mason District 2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
Mason District 2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobi...
 
Metro to Mosaic Bikeway
Metro to Mosaic BikewayMetro to Mosaic Bikeway
Metro to Mosaic Bikeway
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
2017 Repaving and Restriping – Glade Dr., April 27th Meeting
2017 Repaving and Restriping – Glade Dr., April 27th Meeting2017 Repaving and Restriping – Glade Dr., April 27th Meeting
2017 Repaving and Restriping – Glade Dr., April 27th Meeting
 
Vienna Metro Station Bicycle Access Study
Vienna Metro Station Bicycle Access StudyVienna Metro Station Bicycle Access Study
Vienna Metro Station Bicycle Access Study
 
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
 
Vienna Metro Station Area Bicycle Access Study
Vienna Metro Station Area Bicycle Access StudyVienna Metro Station Area Bicycle Access Study
Vienna Metro Station Area Bicycle Access Study
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
Proposed Street Design Updates: VDOT Summer 2015 Repaving
Proposed Street Design Updates: VDOT Summer 2015 RepavingProposed Street Design Updates: VDOT Summer 2015 Repaving
Proposed Street Design Updates: VDOT Summer 2015 Repaving
 
Intersection Improvement Study at Spring Hill Road and Lewinsville Road - Com...
Intersection Improvement Study at Spring Hill Road and Lewinsville Road - Com...Intersection Improvement Study at Spring Hill Road and Lewinsville Road - Com...
Intersection Improvement Study at Spring Hill Road and Lewinsville Road - Com...
 
Bi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County RoadsBi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County Roads
 
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
 
Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018
Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018
Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018
 

More from Fairfax County

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
PsychicRuben LoveSpells
 

Recently uploaded (20)

Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 

Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mason District

  • 1. County of Fairfax, Virginia Department of Transportation Proposed Bicycle Facilities VDOT Summer 2015 Repaving Mason District March 25, 2015
  • 2. County of Fairfax, Virginia Department of Transportation 2 Overview • Why are we here? • What are we asking today? • What projects are being proposed? • Where are we in the process? • What are the next steps?
  • 3. County of Fairfax, Virginia Why are we here? • VDOT Summer repaving includes several roads in the Mount Vernon District. Opportunity to review pavement markings and street design. Project limited to restriping existing pavement. • Opportunity to provide transportation options and improve pedestrian safety • Low to no cost for the County Department of Transportation 3
  • 4. County of Fairfax, Virginia What are we asking today? • Your input and feedback – Support, questions, concerns, ideas Department of Transportation 4 Photo Credit: sundaystreetssf.com
  • 5. County of Fairfax, Virginia Project List • Evergreen Lane – From Columbia Pike to Little River Turnpike • Annandale Road – From Gallows Road to Arlington Boulevard Department of Transportation 5
  • 6. County of Fairfax, Virginia Bicycle Master Plan Department of Transportation 6
  • 7. County of Fairfax, Virginia Bicycle Master Plan (continued) Department of Transportation 7
  • 8. County of Fairfax, Virginia Lane Diets • A Lane Diet is generally described as narrowing travel lanes from a roadway and utilizing the space for other uses and travel modes. Does not involve reducing the number of travel lanes. • Benefits – Providing transportation alternatives and options – Increasing safety for non-motorized users – Reduce speeding Department of Transportation 8
  • 9. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation Northern Section: •Existing: • Columbia Pike to Greenberry Lane • One lane in each direction and Center turn lane
  • 10. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation
  • 11. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation Northern Section: •Proposed: • Columbia Pike to Greenberry Lane • One lane in each direction, Center turn lane, and bike lanes
  • 12. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation Southern Section: •Existing: • Greenberry Lane to Little River Turnpike • 2 lanes in each direction and center turn lane • One lane in each direction functions as a turn lane
  • 13. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation
  • 14. County of Fairfax, Virginia Evergreen Lane Columbia Pike to Little River Turnpike Department of Transportation Southern Section: •Proposed: • Greenberry Lane to Little River Turnpike • Two lanes in each direction, Center turn lane, and bike lanes • One lane in each direction functions as a turn lane
  • 15. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation Existing Conditions •Most of corridor is 48’ curb to curb •Some sections 46’ curb to curb •1 travel lane in each direction with parking •Pinch point near Walnut Manor Way • 45’ curb to curb
  • 16. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation
  • 17. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation
  • 18. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation Proposed Design •Most of corridor is approximately 48’ curb to curb •Some sections 46’ curb to curb •Pinch point near Walnut Manor Way and Beechview Drive • 45’ curb to curb
  • 19. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation
  • 20. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation • Options near Walnut Manor Way • Shared Lane in both directions • Climbing Lane in one direction • Bike lanes in both directions • 7’ parking lane, 4’ bike lane, 11’ travel lane
  • 21. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation Shared Lane •14’ shared travel lane and 8.5’ parking lane
  • 22. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation Climbing Lane •11’ travel lanes •5’ Bike lane •Shared lane •8’ parking lanes
  • 23. County of Fairfax, Virginia Annandale Road Gallows Road to Arlington Boulevard Department of Transportation Bike Lanes •11’ Travel lanes •4’ Bike lane •7’ Parking lane
  • 24. County of Fairfax, Virginia Where are we in the Process? • Conceptual design underway • Not proposing to change lane configuration approaching intersections, so no additional delay to vehicles Department of Transportation 24
  • 25. County of Fairfax, Virginia What are the next steps? • Gather community input tonight and over next two weeks – Comment Period: Open until April 10th • Redesign plans as necessary • Design completion: April 2015 • Projects go to construction Summer 2015 Department of Transportation 25
  • 26. County of Fairfax, Virginia Thank You Questions/Comments? adam.lind@fairfaxcounty.gov Department of Transportation 26