4. FRIENDSHIP
COMMUNITY CENTER
Washington, D.C.
Request for Proposals for a Design Build Contractor is
scheduled to be released the week of May 12, 2014.
The Design Build Contractor will be responsible for the
following:
Finalizing the playground design
Finalizing the splash pad design
Finalizing the Building design and
Construction
Where are we
in the project ?
5. FRIENDSHIP
COMMUNITY CENTER
Washington, D.C.
March SIT meeting
follow-up
• Beauvoir Playground
Total Project cost - $ 5 Million
$ 1 M - landscaping in front of school
$ 1 M - Retaining Walls
$ 3 M – Playground Equipment &
Installation
6. MEETING SCHEDULE
Friendship Park Upcoming Meeting Schedule
Meeting
Types
Spring 14 Summer 14 Fall 14 Winter 14
March April May June July Aug Sept Oct Nov Dec Jan Feb
SIT 5th 2nd
(cancelled)
7th 11th Email Email 3rd 1st 5th Email TBD TBD
Community Email 9th Email 18th Email Email 10th Email Email Email TBD TBD
7. May 2014 – to Completion
• Procurement for Design Build Contractor
• Design Build Contractor Selected
• SIT Meeting Every First Wednesday
• Community Meetings Quarterly (Second Wednesday)
• Construction
NEXT STEPS