1) A subcontractor was unpaid for road patching work it performed for Con Edison under a contract. It filed liens and sued Con Edison along with other parties.
2) The case involves complex issues around public improvement liens under New York's Lien Law, including questions around whether the work constituted a public or private improvement and whether valid liens were filed.
3) While the liens themselves may not be valid, the plaintiffs can still potentially recover against Con Edison through trust fund provisions of the Lien Law, as Con Edison received payments for the work and represented that funds would be held in trust for subcontractors.
Insurers' journeys to build a mastery in the IoT usage
Ā
Messy.mechanics.lien
1. Another Fine Mess
Copyright (C) 2013 Kevin J. Connolly
It is no secret that New Yorkās Lien Law is a complex statute. It has grown a
moss-like jurisprudential coating that confirms the statute as a minefield of
obscure traps that occasionally catches even the most distinguished of
construction counsel and their clients. Coupling this statute and its
jurisprudence with the cupidity of some contractors and the arrogance of some
developers has produced some extraordinary tales.
The most recent āperfect stormā appears to be found in Bergassi Group v
Consolidated Edison Company (2013 Ny Slip Opn 30398(U)). That case grew
out of Con Edās award of a contract for patching roads that Con Ed had opened
and trenched in laying utility lines. A subcontractor went unpaid, liens were
filed and off to court marched the parties.
The tale, as related in the pleadings, begins with the award by Con Ed to
Qualcom Construction of contracts to patch three roads--one in Westchester
and two in the Bronx--that had been opened for utility work. Qualcom awarded
a purchase order to NY Materials for the asphalt patch materials, as well as a
subcontract to MVM Construction to perform the patching work. Apparently,
the Con Ed contract required the issuance of payment and performance bonds,
which were placed by lead plaintiff Bergassi Group.
Something went wrong. MVM and other subcontractors were not timely paid.
They served lien notices on parties various and sundry, including Con Ed. Con
Ed held up payments to Qualcom pending the resolution or bonding of the
liens. It commenced an interpleader proceeding in Bronx County, and
dismissed the proceeding when MVM produced surety bonds that satisfied Con
Edās bureaucracy. Con Ed released some or all of the retained funds on the
strength of the lien discharge bonds.
The bonds turned out to be bogus. The contractorās principal appears to have
fled the jurisdiction shortly before a bankruptcy petition was filed.MVM, joined
by the material supplier and broker who placed the payment and performance
bonds, sued Con Ed on a variety of theories. Con Ed responded with a motion
to dismiss; plaintiff served an amended complaint; and Con Ed moved again for
dismissal before joining issue.
The Amended Complaint presented six causes of action:
1. Breach of Fiduciary Duty;
2. Negligence;
3. Conversion;
4. āViolation of Lien Law Article 3A;ā
5. Common Law Constructive Trust; and
6. Prima Facie Tort.
2. This is not the usual pattern. In private improvement lien litigation, we are
used to seeing the Unholy Trinity of Express Contract, Quantum Meruit, and
Enforcement of Lien. None of those causes of action is pleaded. In public lien
litigation, we still see those causes of action, though the enforcement
mechanism for a public lien is not a judgment of foreclosure and sale (as it can
be in private lien enforcement).
The Bonds
The bonds were, to be charitable, not quite right. There was a single bond,
addressing the claims of three lienors, covering properties in the Bronx and
Yonkers. To make matters more interesting, the bond was written to the
Queens County Clerk. To add to the mess, the surety on the bonds was
āOceanic Indemnity,ā a Bahamas corporation, and none of the supporting
documents--most notably a certificate of qualification under Insurance Law
1111--was present. Nevertheless, Con Ed, ostensibly relying on the bonds,
released the funds it was withholding and dismissed the 5239 Proceeding.
There was a time when all lien discharge proceedings required court
intervention. First, a special proceeding was brought to fix the amount of the
bond to be filed; then the owner or contractor would seek judicial approval of
the bond, which would be granted by way of an order of discharge. Now, the
amount of the bond is the principal amount of the claim plus ten per cent.; and
if the bond is accompanied by a Certificate of Qualification issued by the
insurance department, the discharge is effective as soon as the bond is filed.
Absent that certificate of qualification, the bond is not effective to discharge the
lien until it is approved by the Court. No proceeding was brought by Qualcom
to approve the bond. If any lien had been created, the bond was ineffective to
do anything.
Public or Private?
Much of the confusion here stems from the distinction between public
improvement liens and private improvement liens. Con Ed apparently believed
that the liens were invalid because they were not filed with the County Clerk.
Private improvement liens are so filed, while public improvement liens are filed
with the public owner and its financial comptroller(s). However, Con Ed also
put some faith in the bonds, which faith was misplaced.
The distinction is actually quite simple: āpublic improvementā is one performed
on realty that is owned by the State, or a public corporation. Work was being
performed on public roadways, and while the decision does not drill down to
the question of which public corporations are involved here, it is implicit in the
decision that the road work was a public improvement.
3. Sorting It Out
Justice Shenkmanās monumental memorandum decision is simply the best
discussion available of the Trust Fund provisions of the Lien Law. The liens
proper, on the other hand, are muddled (though not hopelessly).
The road work is a Public Improvement. Title to the roads is in the State or a
public corporation (such as the County or City). No further inquiry is needed,
and under Section 2(7) of the Lien Law, this is a Public Improvement.
To establish a Public Improvement Lien, one must file the notice of lien with
the head of the State agency or public corporation, and with the financial
officer of that entity in charge of the finances for the project.
None of the liens was filed with the State or public corporation. Unless these
lienors can make a timely re-filing with the public officers, the liens will fail.
Justice Shenkmanās decision seems quietly to recognize that at this time, none
of the plaintiffs has a validly-filed lien. Whether they can redeem that problem
is discussed below.
Where plaintiffsā remedies lie, if at all, begin with Article 3-A of the Lien Law
and its Trust Fund provisions. The Trust Fund can arise even when the
claimant has no lien and no right to claim a lien.
In this case, the plaintiffs plead claims for breach Breach of Fiduciary Duty;
Negligence; Conversion; āViolation of Lien Law Article 3A;ā Common Law
Constructive Trust; and Prima Facie Tort. In short, they are pleading the
kitchen sink. The court held that the claim for prima facie tort was precluded
by plaintiffsā other claims and allegations, and dismissed the Article 3A
proceeding with leave to re-plead as a class action, and otherwise sustained the
complaint.
There are some significant obstacles to trust fund recovery. Among these are
the limited class of beneficiaries. If, as alleged, Con Ed received funds that were
earmarked for this project, then those funds were received in trust, for
Qualcom. The plaintiffsā claims as trust fund beneficiaries are against
Qualcom. Con Ed does not owe duties as an Article 3A trustee to the plaintiffs.
Con Ed also asserts that it paid out the balance of retained funds to Qualcom,
and therefore as a matter of law there was no diversion of trust funds. Payment
to a contractor or material supplier is a permitted use of trust funds, and Con
Ed had no duty to see to Qualcomās use of the $500,000 trust fund. Moreover,
as the āOwner,ā it did not receive funds from one of the seven sources
enumerated in Lien Law 70(5).
4. The problem in Con Edās argument lies in its not being the owner of the
property. It is a contractor. Although the contracts between Con Ed and the
Cities of Yonkers and New York have not been filed, there can be little doubt
but that Con Ed had a contract of some kind with the public bodies. Indeed, in
the absence of a ārootā contract with the State or public corporation, there can
be no public improvement lien.
Now What?
Letās suppose there is no contract with the Cities. Con Ed was performing this
work for its own benefit, in owning and operating steam distribution lines.
There might not be ANY public money here. In that case, since a lien cannot be
established against a public road, the claimant again hits a brick wall.
This overlooks the amendment of Lien Law Section 5, which now provides in
part:
Where no public fund has been established for the financing of a public
improvement with estimated cost in excess of two hundred fifty thousand
dollars, the chief financial officer of the public owner shall require the
private entity for whom the public improvement is being made to post, or
cause to be posted, a bond or other form of undertaking guaranteeing
prompt payment of moneys due to the contractor, his or her
subcontractors and to all persons furnishing labor or materials to the
contractor or his or her subcontractors in the prosecution of the work
on the public improvement.
There is no sign that Con Ed filed a payment bond or other undertaking. It
should have. That bond might have made the plaintiffs, or some of them,
whole. The lienors probably had a mandamus claim against the Chief Financial
Officers to require that the bond be posted. They may still have a valid
mandamus claim.
If there is or was a contract with the Cities, then there is a public fund and the
liens maybe valid. They do need to be re-filed, but that re-filing is timely until
thirty days after completion and acceptance of the work by the public owner.
The odds are that there is no ācompletion and acceptanceā by the City of Con
Edās work, and therefore these plaintiffs have unlimited time to re-file their
liens.
It is not to be expected that the liens will āstick.ā The āpublic money,ā if ever
there was any, is long gone. We are now deep into the thickets of the trust
fund.
The critical language from the Courts decision shows how the plaintiffsā trust
claims can still reach Con Edisonās pocket:
5. "Although an owner's liability pursuant to Lien Law article 3-A requires
the existence of an obligation on the part of the owner (see Lien Law 71
[3]), the obligation may be one either imposed by contract 'or as the
result of a mechanic's lien'" (Spectrum Painting Contr., Inc. v Kreisler
Borg Florman Gen. Constr. Co., 64 AD3d 565, 576 [2d Dept 2009],
quoting Quantum Corp. Funding v L.P.G. Assoc., Inc., 246 AD2d 320
[1st Dept 1995], Iv denied 91 NY2d 814 [1998]).[fn omitted] As noted by
one commentator, "since an owner who has notice of an subcontractor's
mechanic's lien may be required to pay twice if he makes payment to the
prime contractor after the lien is filed, the filing of a lien frequently stops
the flow of cash from the owner and can therefore operate as a significant
pressure device even before litigation is commenced" (4C NY Prac., Com.
Litig. in NY State Courts 104:20 [3d ed]).
Now the remaining question is whether the notice of lien served by the
plaintiffs is sufficient to trigger trust fund liability. The existing cases do not
provide much guidance. One factor to consider is the public policy underlying
the trust fund, which is to guarantee that those who do the work will be paid.
Remember, too, that the trust fund is broader than formal lien priority. Con Ed
certainly had notice of the plaintiffās claims. It undertook to hold the funds
subject to court direction, and then released them upon tender of patently
insufficient bonds. This may call for an investigation into just what sort of
improper blandishments may have induced Con Edās risk managers to have
made this mistake.
Here, too, the explicit undertakings and pleadings may have proven to be Con
Edās undoing. Justice Shenkman placed great weight on the interpleader
proceeding that Con Ed commenced, as well as on Con Edās representation
that the retained sums would be held in trust for distribution to the
subcontractors.
In short, we have here an epic saga in the making. There is more--much more--
to be mined from Justice Shenkmanās masterful opinion, and likely there will
be internecine proceedings.
Con Ed should be mindful that an award for breach of the trust fund will
support an award of attorneyās fees.