PR-VER-02 v1.0                  Verification Process for SSC Pacific                           8/18/09


Process: Verification                                  Phase: Global
Process Owner: SSC Pacific Verification, Validation, Integration and Testing Integrated Product Team
Description: The purpose of Verification (VER) is to assure that selected work products meet their
specified requirements. Peer Reviews are one form of verification.
Entry Criteria:                                        Outputs:
• Overarching plans exist to plan this process,        • Verification plan and procedures
    establish integrated schedules, assign             • Verification and peer review results
    responsibilities, establish monitoring procedures,
                                                       • Non-compliance and corrective action reports
    and provide for improvement of this process
                                                       Exit Criteria:
• Adequate resources are committed to verification
                                                       • Evidence that the work products do or do not
Inputs:
                                                           meet their requirements has been collected
• Work product technical requirements or                   and reported
    specifications
• Project work products
   Roles:
• Project Manager (PM): Responsible for process performance and resource allocation
• Verification Team: One or more project members who perform verification tasks
• Configuration Management (CM): Controls designated work products of this process
• Quality Assurance (QA): Audits products and verification tasks
Assets/References: References (a) through (d) are available from http://sepo.spawar.navy.mil/
a. SSC Pacific Standard Process Assets Architecture Definition, DC-OPD-15, SSC Pacific
b. Project Management Plan Template, TM-PP-01, SSC San Diego
c. Project Technical Plan Template, TM-PP-03, SSC San Diego
d. Peer Review Process for SSC Pacific, PR-VER-01, SSC Pacific
e. Processes for Engineering a System, Electronic Industry Alliance (EIA) Standard 632, Jan 1999
f. Systems Engineering – System Life Cycle Processes, International Organization for Standardization
   (ISO)/International Electrotechnical Commission (IEC) 15288, ISO/IEC 15288:2002(E), Nov 2002
g. Software Life Cycle Processes, Institute of Electrical and Electronics Engineers (IEEE)/Electronic
   Industries Association (EIA) 12207.0, Mar 1998
Tasks:
1. Select work products for verification                 5. Conduct verification
2. Define strategy and acceptance criteria               6. Analyze results
3. Establish verification environment                    7. Communicate results and recommendations
4. Document plans and procedures
Measures:
• Effort and funds expended for each verification task
• Percent of requirements satisfactorily verified
• Number of corrective actions
• For peer reviews, provide peer review results including number of defects by priority, number of
   defects resolved, and any defect analysis results




                                                  1
PR-VER-02 v1.0                   Verification Process for SSC Pacific                              8/18/09


INTRODUCTION: This process is included in the SSC Pacific set of standard processes described in the
SSC Pacific Standard Process Assets Architecture Definition, reference (a). The tasks shown in Figure 1
are conducted in an iterative manner, performed at various levels and stages of work product
development. Responsibilities and acceptance criteria may vary with each stage.




                                   Figure 1. Verification Process Flow

TASKS:
1. Select work products for verification
The verification team identifies the work products that require verification. Selection of the work
products is based on analysis of project risks, requirements, and overall project objectives. The
verification team documents each selected product in a verification, project technical, or project
management plan. (See the Project Management Plan Template, reference (b) or Project Technical Plan
Template, reference (c) for examples of plans) In addition to work products integral to the deliverable
product, work products requiring verification may include those facilitating the product or service’s
maintenance, training, and other related support needs.
    2. Define strategy and acceptance criteria
The verification team determines the nature and scope of the verification strategy including verification
methods. Examples include, but are not be limited to the application of peer reviews, inspection, audit,
comparison, static test, dynamic test, regression tests, and demonstration. The strategy depends on
whether a model, prototype or actual work product is being verified, and on perceived risks such as safety
and security. Criteria for product acceptance are defined, based on the degree of satisfaction of the
specified requirements, and documented as described in Task 4.
3. Establish verification environment
   The verification team works with the PM to either acquire or develop the appropriate verification
   environment. This includes documenting the environment’s resource and architectural requirements
   (if applicable) and verification criteria in a plan to ensure appropriateness of the final environment.
   Example environments include conference rooms and materials for peer reviews, test beds, and
   enabling testing tools. The required verification environment operators are trained and the equipment
   and tools are prepared for the conduct of the verification.
    4. Document plans and procedures
The verification team documents the plans and procedures required by the verification strategy.
Documentation includes verification criteria to confirm that a product meets its intended requirements,
performance thresholds, applicable standards, cost/quality testing trade-offs, and requirements driven by
organizational policies. The verification team peer reviews the plans and procedures before providing



                                                    2
PR-VER-02 v1.0                    Verification Process for SSC Pacific                             8/18/09


them to CM to be placed under configuration control. The conduct of peer reviews follows the Peer
Review Process, reference (d).
    5. Conduct verification
The verification team carries out the verification consistent with the plans and procedures in a manner
that ensures that verification actions, conditions and outcomes can be replicated. If the appropriate
verification method is a peer review, follow the guidance in reference (d). Records of verification actions
and outcomes are kept and provided to CM to be placed under configuration control. Defect data is
reported using the appropriate change request or trouble report mechanism.
    6. Analyze results
The verification team analyzes the collected verification data, using verification criteria from Task 3, to
identify non-conformance issues and determine needed corrective actions. Defects in the work product or
service’s requirements may be included if the verification team has the appropriate knowledge to make a
determination. Analysis methods, results, recommendations, and status are documented, peer reviewed,
and provided to CM to be placed under configuration control.
    7. Communicate results and recommendations
The PM and verification team communicate verification results and recommendations to appropriate
stakeholders.




                                                     3

More Related Content

What's hot

Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurancelakshmi1693
 
Software qualityassurance
Software qualityassuranceSoftware qualityassurance
Software qualityassurancesunilabj
 
Qualification & Validation Concept & Terminology
Qualification & Validation Concept & TerminologyQualification & Validation Concept & Terminology
Qualification & Validation Concept & TerminologyMuhammad Luqman Ikram
 
Qualification & validation concept & terminology
Qualification & validation concept & terminologyQualification & validation concept & terminology
Qualification & validation concept & terminologyMuhammad Luqman Ikram
 
Software quality assurance activites
Software quality assurance activitesSoftware quality assurance activites
Software quality assurance activitesGolu Gupta
 
Validation of friability test apapraturs
Validation of friability test apapratursValidation of friability test apapraturs
Validation of friability test apapratursRam Mohan S R
 
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10Scott Hamm
 
Qualification validation ppt_171116
Qualification validation ppt_171116Qualification validation ppt_171116
Qualification validation ppt_171116Somnath Banerjee
 
009 what are the systems validation protocol methods at atl 05 28-2015
009 what are the systems validation protocol methods at atl 05 28-2015009 what are the systems validation protocol methods at atl 05 28-2015
009 what are the systems validation protocol methods at atl 05 28-2015atlmarketing
 
Software Quality Framework Introduction
Software Quality Framework IntroductionSoftware Quality Framework Introduction
Software Quality Framework IntroductionDon Hough
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentationPRASHANT KSHIRSAGAR
 
Equipment Qualification by- Deepak Kumar
Equipment Qualification by- Deepak KumarEquipment Qualification by- Deepak Kumar
Equipment Qualification by- Deepak KumarDeepak Kumar
 

What's hot (20)

Qa qc
Qa qcQa qc
Qa qc
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Validation Part6
Validation Part6Validation Part6
Validation Part6
 
Software qualityassurance
Software qualityassuranceSoftware qualityassurance
Software qualityassurance
 
Qualification & Validation Concept & Terminology
Qualification & Validation Concept & TerminologyQualification & Validation Concept & Terminology
Qualification & Validation Concept & Terminology
 
Qualification & validation concept & terminology
Qualification & validation concept & terminologyQualification & validation concept & terminology
Qualification & validation concept & terminology
 
Software quality assurance activites
Software quality assurance activitesSoftware quality assurance activites
Software quality assurance activites
 
V Model
V ModelV Model
V Model
 
Validation of friability test apapraturs
Validation of friability test apapratursValidation of friability test apapraturs
Validation of friability test apapraturs
 
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10
Lilly Risk-Based CQ_ ISPE-CCPIE China Conference 2010_9-19-10
 
Qualification validation ppt_171116
Qualification validation ppt_171116Qualification validation ppt_171116
Qualification validation ppt_171116
 
009 what are the systems validation protocol methods at atl 05 28-2015
009 what are the systems validation protocol methods at atl 05 28-2015009 what are the systems validation protocol methods at atl 05 28-2015
009 what are the systems validation protocol methods at atl 05 28-2015
 
Urs,dq, iq,oq,pq
Urs,dq, iq,oq,pqUrs,dq, iq,oq,pq
Urs,dq, iq,oq,pq
 
Software Quality Framework Introduction
Software Quality Framework IntroductionSoftware Quality Framework Introduction
Software Quality Framework Introduction
 
Validation
ValidationValidation
Validation
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Validation qualification
Validation qualificationValidation qualification
Validation qualification
 
Validation boot camp 2
Validation boot camp 2Validation boot camp 2
Validation boot camp 2
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
 
Equipment Qualification by- Deepak Kumar
Equipment Qualification by- Deepak KumarEquipment Qualification by- Deepak Kumar
Equipment Qualification by- Deepak Kumar
 

Similar to Verification process

presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxAhmedAltantawi
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsQUONTRASOLUTIONS
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptAhtashamArshad4
 
Introduction To Software Quality Assurance
Introduction To Software Quality AssuranceIntroduction To Software Quality Assurance
Introduction To Software Quality Assuranceruth_reategui
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validationAJAYKUMAR4872
 
Pharmaceutical Validation.pdf
Pharmaceutical Validation.pdfPharmaceutical Validation.pdf
Pharmaceutical Validation.pdfGireesh Kumar Eri
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical
 
Health Care Project Testing Process
Health Care Project Testing ProcessHealth Care Project Testing Process
Health Care Project Testing ProcessH2Kinfosys
 
SQA Lecture 01 (Introduction) - Testing and SQA
SQA Lecture 01 (Introduction) - Testing and SQASQA Lecture 01 (Introduction) - Testing and SQA
SQA Lecture 01 (Introduction) - Testing and SQAsunena224
 
software engineering
software engineeringsoftware engineering
software engineeringshreeuva
 
4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and ConceptsSerdar Zeybek
 
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptx
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptxAUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptx
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptxShankar Maind Patil
 
Software_Verification_and_Validation.ppt
Software_Verification_and_Validation.pptSoftware_Verification_and_Validation.ppt
Software_Verification_and_Validation.pptSaba651353
 
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATION
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATIONValidation, scope of validation, URS , WHO GUIDELINES FOR VALIDATION
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATIONManikant Prasad Shah
 
Validation and calibration of master plan
Validation and calibration of master planValidation and calibration of master plan
Validation and calibration of master planPrinka Choudhary
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfabdo badr
 

Similar to Verification process (20)

presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptx
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutions
 
Introduction to CMMI-DEV v1.3 - Day 3
Introduction to CMMI-DEV v1.3  - Day 3Introduction to CMMI-DEV v1.3  - Day 3
Introduction to CMMI-DEV v1.3 - Day 3
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.ppt
 
Introduction To Software Quality Assurance
Introduction To Software Quality AssuranceIntroduction To Software Quality Assurance
Introduction To Software Quality Assurance
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
 
Pharmaceutical Validation.pdf
Pharmaceutical Validation.pdfPharmaceutical Validation.pdf
Pharmaceutical Validation.pdf
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & Validation
 
Health Care Project Testing Process
Health Care Project Testing ProcessHealth Care Project Testing Process
Health Care Project Testing Process
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
SQA Lecture 01 (Introduction) - Testing and SQA
SQA Lecture 01 (Introduction) - Testing and SQASQA Lecture 01 (Introduction) - Testing and SQA
SQA Lecture 01 (Introduction) - Testing and SQA
 
SQA_Class
SQA_ClassSQA_Class
SQA_Class
 
software engineering
software engineeringsoftware engineering
software engineering
 
4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts
 
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptx
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptxAUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptx
AUDITING OF QUALITY ASSURANCE AND ENGINEERING DEPARTMENT.pptx
 
Software_Verification_and_Validation.ppt
Software_Verification_and_Validation.pptSoftware_Verification_and_Validation.ppt
Software_Verification_and_Validation.ppt
 
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATION
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATIONValidation, scope of validation, URS , WHO GUIDELINES FOR VALIDATION
Validation, scope of validation, URS , WHO GUIDELINES FOR VALIDATION
 
Environmental Quality Assurance -- a primer
Environmental Quality Assurance -- a primerEnvironmental Quality Assurance -- a primer
Environmental Quality Assurance -- a primer
 
Validation and calibration of master plan
Validation and calibration of master planValidation and calibration of master plan
Validation and calibration of master plan
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdf
 

More from JULIO GONZALEZ SANZ

Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
Cmmi hm 2008 sepg model changes for high maturity  1v01[1]Cmmi hm 2008 sepg model changes for high maturity  1v01[1]
Cmmi hm 2008 sepg model changes for high maturity 1v01[1]JULIO GONZALEZ SANZ
 
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]JULIO GONZALEZ SANZ
 
Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]JULIO GONZALEZ SANZ
 
Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]JULIO GONZALEZ SANZ
 
The need for a balanced measurement system
The need for a balanced measurement systemThe need for a balanced measurement system
The need for a balanced measurement systemJULIO GONZALEZ SANZ
 
Just in-time and lean production
Just in-time and lean productionJust in-time and lean production
Just in-time and lean productionJULIO GONZALEZ SANZ
 
History of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrHistory of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrJULIO GONZALEZ SANZ
 
Une 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioUne 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioJULIO GONZALEZ SANZ
 
An architecture for data quality
An architecture for data qualityAn architecture for data quality
An architecture for data qualityJULIO GONZALEZ SANZ
 
Sap analytics creating smart business processes
Sap analytics   creating smart business processesSap analytics   creating smart business processes
Sap analytics creating smart business processesJULIO GONZALEZ SANZ
 
Big data analytics, research report
Big data analytics, research reportBig data analytics, research report
Big data analytics, research reportJULIO GONZALEZ SANZ
 

More from JULIO GONZALEZ SANZ (20)

Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
Cmmi hm 2008 sepg model changes for high maturity  1v01[1]Cmmi hm 2008 sepg model changes for high maturity  1v01[1]
Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
 
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
 
Cmmi 26 ago_2009_
Cmmi 26 ago_2009_Cmmi 26 ago_2009_
Cmmi 26 ago_2009_
 
Creation use-of-simple-model
Creation use-of-simple-modelCreation use-of-simple-model
Creation use-of-simple-model
 
Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]
 
Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]
 
The need for a balanced measurement system
The need for a balanced measurement systemThe need for a balanced measurement system
The need for a balanced measurement system
 
Magic quadrant
Magic quadrantMagic quadrant
Magic quadrant
 
6 six sigma presentation
6 six sigma presentation6 six sigma presentation
6 six sigma presentation
 
Volvo csr suppliers guide vsib
Volvo csr suppliers guide vsibVolvo csr suppliers guide vsib
Volvo csr suppliers guide vsib
 
Just in-time and lean production
Just in-time and lean productionJust in-time and lean production
Just in-time and lean production
 
History of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrHistory of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfr
 
Using minitab exec files
Using minitab exec filesUsing minitab exec files
Using minitab exec files
 
Sga iso-14001
Sga iso-14001Sga iso-14001
Sga iso-14001
 
Cslt closing plenary_portugal
Cslt closing plenary_portugalCslt closing plenary_portugal
Cslt closing plenary_portugal
 
Une 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioUne 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julio
 
Swebokv3
Swebokv3 Swebokv3
Swebokv3
 
An architecture for data quality
An architecture for data qualityAn architecture for data quality
An architecture for data quality
 
Sap analytics creating smart business processes
Sap analytics   creating smart business processesSap analytics   creating smart business processes
Sap analytics creating smart business processes
 
Big data analytics, research report
Big data analytics, research reportBig data analytics, research report
Big data analytics, research report
 

Verification process

  • 1. PR-VER-02 v1.0 Verification Process for SSC Pacific 8/18/09 Process: Verification Phase: Global Process Owner: SSC Pacific Verification, Validation, Integration and Testing Integrated Product Team Description: The purpose of Verification (VER) is to assure that selected work products meet their specified requirements. Peer Reviews are one form of verification. Entry Criteria: Outputs: • Overarching plans exist to plan this process, • Verification plan and procedures establish integrated schedules, assign • Verification and peer review results responsibilities, establish monitoring procedures, • Non-compliance and corrective action reports and provide for improvement of this process Exit Criteria: • Adequate resources are committed to verification • Evidence that the work products do or do not Inputs: meet their requirements has been collected • Work product technical requirements or and reported specifications • Project work products Roles: • Project Manager (PM): Responsible for process performance and resource allocation • Verification Team: One or more project members who perform verification tasks • Configuration Management (CM): Controls designated work products of this process • Quality Assurance (QA): Audits products and verification tasks Assets/References: References (a) through (d) are available from http://sepo.spawar.navy.mil/ a. SSC Pacific Standard Process Assets Architecture Definition, DC-OPD-15, SSC Pacific b. Project Management Plan Template, TM-PP-01, SSC San Diego c. Project Technical Plan Template, TM-PP-03, SSC San Diego d. Peer Review Process for SSC Pacific, PR-VER-01, SSC Pacific e. Processes for Engineering a System, Electronic Industry Alliance (EIA) Standard 632, Jan 1999 f. Systems Engineering – System Life Cycle Processes, International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC) 15288, ISO/IEC 15288:2002(E), Nov 2002 g. Software Life Cycle Processes, Institute of Electrical and Electronics Engineers (IEEE)/Electronic Industries Association (EIA) 12207.0, Mar 1998 Tasks: 1. Select work products for verification 5. Conduct verification 2. Define strategy and acceptance criteria 6. Analyze results 3. Establish verification environment 7. Communicate results and recommendations 4. Document plans and procedures Measures: • Effort and funds expended for each verification task • Percent of requirements satisfactorily verified • Number of corrective actions • For peer reviews, provide peer review results including number of defects by priority, number of defects resolved, and any defect analysis results 1
  • 2. PR-VER-02 v1.0 Verification Process for SSC Pacific 8/18/09 INTRODUCTION: This process is included in the SSC Pacific set of standard processes described in the SSC Pacific Standard Process Assets Architecture Definition, reference (a). The tasks shown in Figure 1 are conducted in an iterative manner, performed at various levels and stages of work product development. Responsibilities and acceptance criteria may vary with each stage. Figure 1. Verification Process Flow TASKS: 1. Select work products for verification The verification team identifies the work products that require verification. Selection of the work products is based on analysis of project risks, requirements, and overall project objectives. The verification team documents each selected product in a verification, project technical, or project management plan. (See the Project Management Plan Template, reference (b) or Project Technical Plan Template, reference (c) for examples of plans) In addition to work products integral to the deliverable product, work products requiring verification may include those facilitating the product or service’s maintenance, training, and other related support needs. 2. Define strategy and acceptance criteria The verification team determines the nature and scope of the verification strategy including verification methods. Examples include, but are not be limited to the application of peer reviews, inspection, audit, comparison, static test, dynamic test, regression tests, and demonstration. The strategy depends on whether a model, prototype or actual work product is being verified, and on perceived risks such as safety and security. Criteria for product acceptance are defined, based on the degree of satisfaction of the specified requirements, and documented as described in Task 4. 3. Establish verification environment The verification team works with the PM to either acquire or develop the appropriate verification environment. This includes documenting the environment’s resource and architectural requirements (if applicable) and verification criteria in a plan to ensure appropriateness of the final environment. Example environments include conference rooms and materials for peer reviews, test beds, and enabling testing tools. The required verification environment operators are trained and the equipment and tools are prepared for the conduct of the verification. 4. Document plans and procedures The verification team documents the plans and procedures required by the verification strategy. Documentation includes verification criteria to confirm that a product meets its intended requirements, performance thresholds, applicable standards, cost/quality testing trade-offs, and requirements driven by organizational policies. The verification team peer reviews the plans and procedures before providing 2
  • 3. PR-VER-02 v1.0 Verification Process for SSC Pacific 8/18/09 them to CM to be placed under configuration control. The conduct of peer reviews follows the Peer Review Process, reference (d). 5. Conduct verification The verification team carries out the verification consistent with the plans and procedures in a manner that ensures that verification actions, conditions and outcomes can be replicated. If the appropriate verification method is a peer review, follow the guidance in reference (d). Records of verification actions and outcomes are kept and provided to CM to be placed under configuration control. Defect data is reported using the appropriate change request or trouble report mechanism. 6. Analyze results The verification team analyzes the collected verification data, using verification criteria from Task 3, to identify non-conformance issues and determine needed corrective actions. Defects in the work product or service’s requirements may be included if the verification team has the appropriate knowledge to make a determination. Analysis methods, results, recommendations, and status are documented, peer reviewed, and provided to CM to be placed under configuration control. 7. Communicate results and recommendations The PM and verification team communicate verification results and recommendations to appropriate stakeholders. 3