SlideShare a Scribd company logo
1 of 50
BUILDING QUÉBEC’S FIRST DIAMOND MINE
Corporate Update, June 19th 2015
Matt Manson Orin Baranowsky
President & CEO Director, Investor Relations
2
Forward-Looking Information
This presentation contains "forward-looking information" within the meaning of Canadian securities legislation and “forward-looking statements” within the meaning
of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as “forward-looking statements”,
are made as of the date of this presentation and the Company does not intend, and does not assume any obligation, to update these forward-looking statements,
except as required by law.
Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not
limited to, statements with respect to: (i) the amount of mineral resources and exploration targets; (ii) the amount of future production over any period; (iii) net
present value and internal rates of return of the mining operation; (iv) assumptions relating to recovered grade, average ore recovery, internal dilution, mining
dilution and other mining parameters set out in the Feasibility Study or Optimization Study; (v) assumptions relating to gross revenues, operating cash flow and
other revenue metrics set out in the Feasibility Study or Optimization Study; (vi) mine expansion potential and expected mine life; (vii) expected time frames for
completion of permitting and regulatory approvals and making a production decision; (viii) future exploration plans; (ix) future market prices for rough diamonds;
and (x) sources of and anticipated financing requirements. Any statements that express or involve discussions with respect to predictions, expectations, beliefs,
plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as “expects”, “anticipates”, “plans”,
“projects”, “estimates”, “assumes”, “intends”, “strategy”, “goals”, “objectives” or variations thereof or stating that certain actions, events or results “may”, “could”,
“would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and
may be forward-looking statements.
Forward-looking statements are made based upon certain assumptions and other important factors that, if untrue, could cause the actual results, performances or
achievements of Stornoway to be materially different from future results, performances or achievements expressed or implied by such statements. Such
statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which Stornoway will
operate in the future, including the price of diamonds, anticipated costs and Stornoway’s ability to achieve its goals. Certain important factors that could cause
actual results, performances or achievements to differ materially from those in the forward-looking statements include, but are not limited to: (i) required capital
investment and estimated workforce requirements; (ii) estimates of net present value and internal rates of return; (iii) receipt of regulatory approvals on acceptable
terms within commonly experienced time frames; (iv) anticipated timelines for the commencement of mine production; (v) market prices for rough diamonds and
the potential impact on the Renard Project’s value; and (vi) future exploration plans and objectives. Additional risks are described in Stornoway's most recently
filed Annual Information Form, annual and interim MD&As, and other disclosure documents available under the Company’s profile at: www.sedar.com.
When relying on our forward-looking statements to make decisions with respect to Stornoway, investors and others should carefully consider the foregoing factors
and other uncertainties and potential events. Stornoway does not undertake to update any forward-looking statement, whether written or oral, that may be made
from time to time by Stornoway or on our behalf, except as required by law.
Readers are referred to the technical report dated as of February 28th, 2013 entitled “The Renard Diamond Project, Québec, Canada, Feasibility Study Update, NI
43-101 Technical Report, February 28, 2013” in respect of the January 2013 Optimization Study, and the press release dated July 23, 2013 in respect of the July
2013 Mineral Resource estimate for further details and assumptions relating to the project. The Qualified Persons that prepared the technical reports and press
releases that form the basis for the presentation are listed in the Company’s AIF dated July 29, 2014. Disclosure of a scientific or technical nature in this
presentation has been reviewed and approved by Robin Hopkins, P.Geol. (NT/NU), Vice President, Exploration, a “qualified person” under NI 43-101.
3
Stornoway Diamond Corporation TSX:SWY
Notes:
1. Assuming a C$:US$ conversion rate of C$1.10 Project Site, March 24, 2015
100% Ownership in Renard,
Québec’s First Diamond Mine
Fully Permitted; Road Accessible;
Strong Social License; Excellent Cost Environment
Fully Financed and In Construction
July 8th 2014: C$946M1 project financing designed to
cover all project costs, contingencies, over-run facilities,
financing costs and working capital requirements.
On Budget
April 30, 2015: guiding for completion within
C$811m capital budget with construction 22.4%
complete compared to 21.7% planned.
On Schedule
Plant Commissioning 2H 2016. Commercial
Production 2Q 2017
4
Publicly Listed Diamond Producers, Developers and Explorers
Consensus Analyst Views on Value
Ticker
Price
(19/6/15)
Shares
O/S
(mm)
Market
Cap
($mm)
NAV/sh(1) Current
P/NAV(1) Target (1) % Return
to Target
Annual
Dividend
Diamond Producers
Dominion Diamonds DDC:T $18.55 85.1 $1,579.2 $30.80 0.6x $27.04 48% US$0.40/sh
Gem GEMD:LN £1.465 138.3 £202.6 £2.53 0.6x £2.25 56% US$0.05/sh
Lucara LUC:T $1.94 379.5 $736.3 $2.53 0.8x $2.76 44% $0.04/sh
Petra PDL:LN £1.586 512.1 £812.2 £2.40 0.7x £2.26 44% £0.02/sh
Diamond Developers
Firestone FDI:LN £0.33 309.0 £102.0 £0.70 0.5x £0.56 69% (n/a)
Mountain Province MPV:T $5.10 159.0 $810.7 $7.17 0.7x $6.55 28% (n/a)
Stornoway SWY:T $0.83 732.3 $607.8 $1.36 0.6x $1.14 37% (n/a)
Diamond Explorers
Kennady Diamonds KDI:LN $5.38 28.0 $150.5 (n/a) (n/a) (n/a) (n/a) (n/a)
North Arrow Minerals NAR:V $0.485 54.0 $26.2 (n/a) (n/a) (n/a) (n/a) (n/a)
Peregrine Diamonds PGD:T $0.245 282.7 $69.3 (n/a) (n/a) (n/a) (n/a) (n/a)
Shore Gold SGF:T $0.215 248.7 $53.5 (n/a) (n/a) (n/a) (n/a) (n/a)
Notes:
1. Bloomberg Analyst Consensus
All Currencies in C$ unless specified
55
Renard: Québec’s First Diamond Mine
6
The Renard Diamond Project
Québec’s First Diamond Mine
Chibougamau
Montréal
Toronto
800km
360km
Renard
1996: Start of initial regional exploration by Ashton & SOQUEM
2001: First kimberlite discovery
2001-08: Drilling, “mini-bulk” sampling, bulk sampling
2008-10: First NI 43-101 Resource and PEA
November 2011: Feasibility Study issued. First mineral reserve
December 2012: ESIA filed
February 2012: Road construction commences under Plan Nord
March 2012: “Mecheshoo Agreement” executed
Nov.-Dec.2012: Mining Lease and Québec Authorizations
issued
January 2013: Optimization Study issued
July 2013: Federal Canadian Authorizations Issued
September 2013: Road opens
April-July 2014: $C946m financing completed. Construction
commences
2Q 2017: Scheduled Commercial Production
2001: First Kimberlite Discovery
+7-9 Years: First NI 43-101 Resource and PEA
+16 Years: Commercial Production
+12 Years: Final Authorisations Issued
7
Lynx
R10
N
R7
R1Hibou
R4
R9
R2
R3
R65
R8
Kimberlite Bodies with
Measured and Indicated
Resources
Hibou
Lynx
R4
R9
R2
R3
R65
Kimberlite Bodies with
Resource Potential
R1Hibou
Lynx
Legend
Stornoway Properties
Hydro-Québec Facility
Renard Kimberlites
Kimberlitic Dyke
Regional Kimberlites
Hydro-Québec
Powerlines
Route 167 Extension/
Renard Mine Road
Road
Exploration/ Mining
Projects
LEGEND:
0 1 2
Kilometers
60 0 60 120
Kilometers
Renard
LG3LG2
LG4
Laforge 1
Laforge 2
Brisay
Foxtrot Property
Strateco
Eastmain MineWestern Troy
Troilus Mine
Eleonore
Temiscamie
Mistissini
Chibougamau
Matagami
Wemindji
Renard Kimberlite Bodies
Kimberlite Bodies with
Inferred Resources
8
The Feasibility: 11 years
of mining on 18mcarat
Mineral Reserve
(24mtonnes)
Permitting and Long
Term Plan
The Vision: Deposit still
Open
40
60
80
100
120
140
Millions
of Tonnes
20
0
TFFE High Range
Inferred Mineral Resource
TFFE Low Range
Indicated Mineral Resource
The Renard Diamond Project
A Large, High Value Diamond Resource with a Very Long Mine Life Potential
0m
100m
200m
400m
600m
700m
500m
300m
Renard 65
29/24cpht Renard 3
103/112cpht
Renard 2
104/119cpht
Renard 9
53cpht
Renard 4
60/50cpht
27 mcarat Indicated Mineral Resource
17 mcarat Inferred Mineral Resource
26-48 mcarat TFFE
Source: Stornoway, 2014
Grades illustrated are for Indicated and Inferred Mineral Resources respectively at a +1DTC sieve
size cut-off. Reserve and Resource categories are compliant with the "CIM Definition Standards on
Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have
demonstrated economic viability. The potential quantity and grade of any Exploration Target
(previously referred to as a “Potential Mineral Deposit”) is conceptual in nature, and it is uncertain if
further exploration will result in the target being delineated as a mineral resource.
Renard Mine Plan and Key Operating Assumptions
A Combined Open Pit and Underground Operation
0m
100m
200m
400m
600m
700m
500m
300m
Notes
1. Key Assumptions:C$1=US$1, Oil US$95/barrel, 2.5% real terms diamond price growth,
82.9% ore recovery, 23.8% mining and internal dilution, 0cpht dilution grade.
2. Expressed in May 2011 terms. Average price US$190/carat in March 2014 terms.
3. Expressed in October 2012 terms, as adjusted in October 2013 LNG FS. Includes
C$754m of costs and contingencies and C$57m of escalation allowance.
4. Expressed in October 2012 terms. Operating costs C$54/tonne in October 2013 LNG
FS terms. Excludes capitalized preproduction costs.
5. Before stream
Reserve and Resource categories are compliant with the "CIM Definition Standards on Mineral
Resources and Reserves". Mineral resources that are not mineral reserves do not have
demonstrated economic viability. The potential quantity and grade of any Exploration Target is
conceptual in nature, and it is uncertain if further exploration will result in the target being
delineated as a mineral resource.
Reserve Based Mine Plan1
(Jan 2013 FS Optimization and October 2013 LNG
Option FS)
Mine Life 11 years
Mineral Reserve 17.9 mcarats
Ave. Diamond Price2
$180/carat
Production Rate 2.2 mtonnes/yr
Ave. Diamond Production 1.6 mcarats/yr
Gross Revenue (C$M)2
$4,268
Initial Capital Costs3
$811m
Operating Cost4
$58/t ($76/carat)
Operating Margin5
67%
Payback 4.8 years
Resource Based Mine Plan
(Basis of December 2012 ESIA and Mine Permitting. Not
public disclosure consistent with NI 43-101)
Includes the mining of 2.3mcarats of Indicated
Resources within a Renard 65 open pit,
additional Inferred Resources in Renard 2, 3, 4
and 9, and an increased annual processing
capacity up to 2.6mtonnes/yr.
Increased project valuation and mine life.
Renard 65
Renard 2 Renard 3
Renard 4
Renard 9
9
10
490 m
asl
-275 m
asl
0 m
790 m
Ongoing Resource Expansion
Long Section Illustrating July 2013 NI 43-101 Mineral Resource
Renard 2 Renard 3 Renard 4 Renard 65 Renard 9
27 mcarat Indicated Mineral Resource
17 mcarat Inferred Mineral Resource
26-48 mcarat TFFE
Reserve and Resource categories are compliant with the "CIM Definition
Standards on Mineral Resources and Reserves". Mineral resources that are not
mineral reserves do not have demonstrated economic viability. The potential
quantity and grade of any Exploration Target (previously referred to as a
“Potential Mineral Deposit”) is conceptual in nature, and it is uncertain if further
exploration will result in the target being delineated as a mineral resource.
$10m 2014 drill program focussed
on Renard 2 below Mineral
Reserve at 600m.
Estimate of 9-12mTonnes 600m
to 1,000m depth.
>1 hectare at 1,000m. Open
below.
Resource update Summer 2015
Surface
600m Depth
1,000m Depth Renard 2
11
Renard’s Diamonds
Large Diamond Potential Not Included in Base Case Diamond Valuation Models
March 2014 Diamond Valuations
(WWW International Diamond Consultants Ltd.)
Kimberlite
Body
Size of
Valuation
Sample
(carats)
WWW March
2014 Sample
Price
(US$/carat)1
WWW March
2014 Base Case
Price Model
(US$/carat)1
Sensitivities
(Minimum to High)
Renard 2 1,580 $187 $197 $178 to $222
Renard 3 2,753 $179 $157 $146 to $192
Renard 4 2,674 $101 $106 ($155)2
$100 to $174
Renard 65 997 $262 $187 $175 to $211
Notes
1. All prices in US$/carat. Samples utilizing a +1 DTC sieve size cut-off.
2. Should the Renard 4 diamond population prove to have a diamond population with a size distribution
equal to the average of Renard 2 and 3, WWW have estimated that a base case diamond price model
of $155 per carat based on March 2014 pricing. Source: WWW March 2014 Valuation Update
Three Renard 65
diamonds: 9.78 ct and
6.41 ct diamonds
recovered from bulk
sampling and a 4 carat
stone discovered in
drillcore in 2003
Base Case Diamond Valuation
Estimates Using Best Practice
Methodology
Average diamond price estimate in
March 2014 for the Mineral Reserves
at US$190/ct (un-escalated)
compared to US$180/ct in the January
2013 Optimization Study.
High Quality Production with
Large Stone Potential
The Renard kimberlites have similar,
but marginally different diamond
populations exhibiting a high
incidence of large white gems.
Coarse Size Distribution in Renard 2
predicts three to six 50-100ct stones
and one to two +100ct stones every
100,000 carats (two weeks).
Substantial revenue potential from
large diamonds not accounted for in
the base case cash-flow model.
12
Stornoway will be a Significant Diamond Producer
Current and Future Diamond Producers
Source: Kimberly Process, WWW and Company Reports
Latest 12 Month Sales/ Forecast Future
Average Sales
1 De Beers (Anglo/Botswana) $7,114m
2 Alrosa (Russia) $4,901m
3 Dominion Diamond (TSX: DDC) $928m
4 Rio Tinto (ASE: RIO) $901m
5 Petra (L: PDL) $502m
6 Stornoway (note 2; TSX: SWY) $310m
7 Gem Diamonds (L: GEMD) $271m
8 Lucara (TSX: LUC) $266m
9 Mountain Province (note 2; TSX: MPV) $259m
10 Firestone (note 3; L: FDI) $123m
11 Others $3,025m
Total $18,600m
DeBeers
38%
Alrosa
26% Dominion
5%
RioTinto
5%
Petra
3%
SWY
2%
GEM
1%
LUC
1%
MPV
1%Firestone
1%
Others
16%
Notes:
1. Renard estimated at FS average annual diamond production of 1.63 million carats, and WWW March 2014 weighted diamond price of US$190/ct, un-escalated
2. Gahcho Kué estimated at 49% of Revised FS average annual production of 4.45 million carats, and average modeled diamond price of US$118/ct, un-escalated
3. Firestone estimated at FS average annual production of 1.15 million carats at an average price of US$107/ct un-escalated
6 Stornoway (note 1; TSX: SWY) $310m
13
Why Stornoway? Renard’s Cash Flow Potential
Based on Base Case Economics
Renard is Expected to Generate Substantial Cash Flow
over its first 11 years of Mining
After Tax, After Stream Operating Cash Flow of between
$150 and $250 million, or $0.20 to $0.30 per share
Assumptions
Mineral reserve case only, averaging 1.6mcarats per annum at US$190/carat
Capital and operating cost parameters as established in the January 2013 Optimization Study
and October 2013 LNG FS
Base case diamond pricing from March 2014; No “special” diamonds.
2.5% annual real diamond price escalation
C$:US$ conversion rate of C$1.10
Based on terms of Financing Transaction closed on July 8th 2014
Assumes full conversion to equity of US$81million of Convertible
Debentures giving 825 million shares outstanding.
Significant Upside Potential from Resource,
Large Diamonds and Processing Capacity
1414
Renard Construction Progress
15
Project Well Prepared for Execution
Construction Commenced July 10th 2014
Project Site July 2014
Permitting and Social Licence in Place
Mecheshoo Agreement signed with Crees in March
2012, partnership agreements with Chibougamau and
Chapais in July 2012, Québec and Federal
Authorisations in Dec. 2012 and July 2013 respectively.
Access Infrastructure in Place
Renard Mine Road opened to traffic on Aug. 30th 2013.
Renard Aerodrome opened to landings Nov. 5th 2013.
Owner’s Team and EPCM in Place
Owner’s construction team located in Longueuil. EPCM
contract negotiated with SNC-Lavalin, DRA & AMEC.
LNG Power
LNG power option selected to utilize all-season road
and commercial LNG distribution network in Québec.
Favourable Construction Environment
Competitive cost environment and good contractor/
labour availability in Québec.
R65 Borrow Pit
Exploration Camp
Lac Lagopede
Ground Breaking Ceremony July 8th 2014
16
Jean-Charles
Dumont
VP Finance
SWY since 2011
Formerly Corporate
Controller of La
Mancha.
Ebe Scherkus
Chairman of the
Board
Stornoway’s Management Credentials
Experience in Building and Operating Major Projects
Matt Manson
President, CEO
& Director
Pat Godin
COO & Director
SWY since 2011
Formerly President
and COO of Agnico
Eagle Mines Ltd.
Executive Chairman
of Premier Gold
SWY since 2007
Formerly VP
Marketing/VP
Technical Services,
Aber Diamond Corp
(Dominion Diamond;
Diavik Project)
SWY since 2010
Formerly VP Project
Development Gmining
(Essakane Mine).
Successive mine
management and
project development
positions, Cambior
Ian Holl
VP Processing
SWY since 2014
20 years experience De
Beers in plant
construction,
commissioning and
operation (Victor, Snap
Lake, Jwaneng Mines) Yves Peron
VP Engineering
& Construction
SWY since 2012
Formerly VP Bus. Dev.
at Delsaer and Seneca.
Successive
management roles at
ArcelorMittal and
Xstrata.
Martin Boucher
VP Sustainable
Development
SWY since 2010
Formerly Canadian
Royalties (Nunavik
Project) and Xstrata
(Raglan, Gaspesia,
Koniambo Mines)
Brian Glover
VP Asset
Protection
SWY since 2012
Formerly Director
Security Operations
at Harry Winston
(Dominion Diamond).
More than 20 years
experience RCMP.
Robin Hopkins
VP Exploration
SWY since 2006
Formerly Aber
Resources and
discovery of the
Diavik Mine.
17
Site Progress
Site Overview by Week 48
Project Site March 24, 2015
Accommodation
Complex
R65 Pit
Project Site June 4, 2015
Mine Admin
Maintenance
Facility
Process Plant Power Plant
UG Mine Portal
R2-R3
R65
Garage
Administration Portal
Accommodation
Plant
Waste Rock
Ore Stockpile
PKC
Overburden
Stockpile
R2-R3 Pit
Contractors
Offices
18
Access Infrastructure In Place
The 240km long Route 167 Extension and the Clarence and Abel Swallow Airport
Eastmain River Bridge March 2015
March 2015July 2014
January 2015 Airport Naming Ceremony, March 2015
19
Process Plant at 6,000tpd (2.2Mtonnes per
annum) nameplate capacity, expandable to
7,000tpd (2.6Mtonnes per annum)
Optimization by DRA Americas Inc. has
allowed addition of Large Diamond
Recovery (“LDR”) capacity to the flow sheet
for no additional capital.
Flow sheet:
• Primary jaw crushing to < 230mm
• Twin DMS circuits at +1mm -19mm
• LDR circuit at +19mm -45mm, scalable
to -60mm
• Oversize +45mm to secondary cone
crusher
• LDR and DMS tails +6mm -19mm to
tertiary High Pressure Grinding Rolls
Cap-ex (Direct Costs, without Capitalized Op-ex)
• Jan 2013 Cap-ex without LDR: $162.7m
• Optimized Cap-ex with LDR: $147.1m
Thickening and centrifugal treatment of
fines and tails to create a truckable product
for dry-stack disposal.
Diamond Processing Plant
Represents Single Largest Cap-ex Item and Critical Path for Overall Construction
20
Site Progress
Live Updates on Process Plant Construction at www.stornowaydiamonds.com
Plant Footprint, Oct 21, 2014 First Concrete Pour, April 7, 2015
Project’s critical path item
Concrete (7 April) steel (14 June)
Building closure scheduled for
October 2015
Plant, June 4, 2015
21
Site Progress
Concrete Pouring on Major Facilities Commenced Ahead of Schedule April 2015
Maintenance Shed May 12, 2015
Maintenance Shed, April 20, 2015 Structural Steel Erection June 3, 2015
22
Open Pit Mining
Renard 2 – Renard 3 Pit Pre-stripping Commenced March 2015
R2-R3 Pre-Strip, March 5, 2015
Open Pit Mining Team, March 5, 2015
R2-R3
R65
Portal
R2-R3 Pit, May 23, 2015
Decline Ventilation, May 10, 2015R2-R3 Pit Pre-Strip, June 4, 2015
Mining Progress
as of Apr 30 2015 (FY15 Q4)
1.61m tonnes moved at R65 against plan of 1.21m (133%)
0.28m tonnes moved at R2-R3 against plan of 0.52m (54%)
23
Underground Mining
Renard 2 – Renard 3 Pit Pre-stripping Commenced March 2015
R2-R3 Pre-Strip, March 5, 2015
Jumbo in Decline, May 25, 2015 Decline Ventilation, May 10, 2015
R2-R3
R65
Portal
Decline Progress
as of Apr 30 2015 (FY15 Q4)
55m against plan of 95m (58%)
233m against plan of 295m by June 15 (79%)
24
Project Schedule
Based on Construction Mobilization July 10th 2014
Feasibility Study (Complete)
ESIA (Complete)
Public Hearings (Complete)
Reg. Authorizations (Complete)
Specific Operating Permits (50)
Road Construction (Complete)
Project Financing (Complete)
Detailed Engineering
Site Construction
Commissioning and Ramp-up
Commercial Production
2012
2H 2H 2H 2H2H 1H 1H 1H1H
2013 2014 2015 2016
2H1H
2017
Based on the Renard Diamond Project Construction Schedule, Plant
Commissioning is Planned for H2 2016 and Commercial Production in Q2 2017.
June 2015
First Vehicle Access
Completion Status
as of Apr 30 2015 (FY15 Q4)
Overall Construction: 22.4% (planned 21.7%)
Engineering Progress: 56% (planned 62%)
2525
Corporate Data
26
Shareholding
Share Price (TSX-SWY):
June 19, 2015
C$ $0.83
52 week High-Low C$ $0.46–$0.85
Average Daily Volume:
Last 12 Months
637,729
Average Daily Volume:
Since July 8th 2014
613,682
Market Capitalization: C$ 608 million
Total Shares Outstanding: 732 million
Total Options & Warrants Outstanding:
(28.2m Options $0.59-$5.36; 123.8m
warrants $0.90-$1.21)
152 million
Consolidated Cash1:
(as of April 30, 2015)
C$ 364 million
Consolidated Debt1:
(as of April 30, 2015)
C$ 208 million
Undrawn Financing Commitments2:
(Subject to Financing Agreement CPs)
C$ 352 million
Balance Sheet
Balance Sheet and Capital Structure
Notes
1. Audited
2. Assuming a C$:US$ conversion rate of C$1.10
Investissement Québec 28.6% 22.7%
Orion Mine Finance 19.5% 17.5%
CDPQ 6.1% 6.2%
Float 45.8% 53.6%
DilutedBasic
27
Sources and Uses of Funds to April 30, 2015(1)
On Current C$:US$ Exchange Rates
(all amounts in millions of C$) Assumed
Actual use
of Proceeds
to April 30,
2015
Renard Diamond Project
Capital Expenditures 811 177
Route 167 Extension (2) 70 70
Financing Costs, Interest during
Construction
58 18
Mine Closure Guarantee (2) 16 2
Pre-production Net Revenue (26) -
Total Project Costs 929 267
General Corporate Purposes
Equity fees and transaction costs 18 23
General working capital,
administrative and salary expenses
14 6
Total Uses 961 296
Costs
Notes
1. Unaudited
2. The total amount borrowed pursuant to the Renard Mine Road loan was $77 million, of which $70 million was used for construction of the Renard Mine Road and $7
million was used for civil works related to the airstrip. Costs related to the airstrip were included in the $811 million capital expenditures line in the table above.
3. Assuming a C$:US$ conversion rate of C$1.21
(all amounts in millions of C$)
Sources of Funds
Stream Deposits not yet received(3) 206
Senior Loan Facility, Tranche A 100
Senior Loan Facility, Tranche B 20
Cost Overrun Facility 28
Equipment Financing Facility(3) 18
Cash, cash equivalent and short term
investments
364
Receivables 16
Capital Resources Available 752
Estimated Cost to complete Renard Project,
including contingencies and escalation
(665)
Excess funding available including cost
overrun facilities – as at April 30, 2015
87
Sources and Uses
2828
Appendix 1: Stornoway’s C$946M Project Financing for Renard
29
Renard Project Financing Transaction Structure
Type
Amount
(% of Total)
Description
Common Equity C$374M (40%)
• C$132M marketed public equity offering of subscription receipts
• C$242M private placement to Orion (US$110M), RQ (C$100M) and Caisse (C$22M)
Diamond Stream US$250M (29%) • 20% diamond stream (Orion 16%, Caisse 4%) with ~US$56/ct(1) ongoing payment
Convertible Debentures US$81M (9%)
• Provided by Orion; 7 year, 6.25% coupon, 35% conversion premium to equity issue
price
Senior Debt C$120M (11%) • Provided by IQ; 7 year amortizing payment, Fixed (QC Bond)+5.75% or Prime +4.75%
Equipment Financing US$35M (4%) • Provided by Caterpillar
Cost Overrun Facility C$48M (5%)
• C$20M provided by IQ (same terms as senior debt)
• C$28M provided by Caisse (unsecured, 7 year term, 10% coupon)
Total C$946M (100%)
Assumes US$1.00 = C$1.10
1. Includes reimbursement of marketing expenses
Counter-Party
Amount
(% of Total)
Orion Mine Finance C$367M (39%)
Investissement Québec/
Ressources Québec
C$240M (25%)
Caisse de dépôt et
placement du Québec
C$105M (11%)
Caterpillar Financial C$39M (4%)
Public C$195M (21%)
Total C$946M (100%)
C$77M
C$811M
C$946M
C$70M
C$67M
Financing Funding Requirements
New
Financing
Existing
Financing
C$48M COF &
C$27M Working
Capital
Financing
Costs &
Interest During
Construction
Renard Mine
Road
Initial Capex &
Escalation
Allowance
30
Top 15 Equity Offerings 2015 YTD, 2014 and 2013
With the Exception of Barrick in 2013, 2014 Saw Larger Equity Financings Than 2013
2015 YTD 2014 2013
Source: Company disclosure.
Issuer Date Size ($ MM) Issuer Date Size ($ MM) Issuer Date Size ($ MM)
First Quantum May-15 C$1,437.5 Lundin Oct-14 C$674.2 Barrick Oct-13 US$3,000.2
Silver Wheaton Mar-15 US$800.0 Franco Nevada Aug-14 US$500.4 Detour Gold May-13 C$176.1
Romarco Jan-15 C$300.0 Primero Mar-14 C$224.3 Platinum Group Metals Dec-13 C$175.2
Yamana Jan-15 C$260.2 Fortress (Lundin Gold) Oct-14 C$200.0 Allied Nevada Apr-13 US$150.5
Osisko Royalties Jan-15 C$200.0 HudBay Jan-14 US$172.7 Ivanhoe Mines Sep-13 C$108.0
Detour Gold Jan-15 C$140.8 Detour Gold Feb-14 C$172.5 Guyana Goldfields Jan-13 C$100.0
Mountain Province Diamonds Mar-15 C$95.0 Torex Gold Jan-14 C$143.8 Paladin Energy Aug-13 C$81.6
SEMAFO Feb-15 C$50.3 Ivanhoe Mines May-14 C$143.8 Banro Corporation Mar-13 US$67.8
Asanko Gold Jan-15 C$40.0 Stornoway Apr-14 C$132.0 Trevali Mining Nov-13 C$46.0
Richmont Mines Jan-15 C$34.0 Rubicon Minerals Feb-14 C$115.1 SantacruzSilver Jan-13 C$40.4
Rubicon Minerals Mar-15 C$30.2 Platinum Group Metals Sep-14 US$113.8 Sulliden Gold Sep-13 C$40.1
First Majestic Apr-15 C$30.0 MAG Silver Jun-14 C$79.0 Colossus Minerals Jul-13 C$38.0
Kaminak Gold Feb-15 C$21.0 Mountain Province Diamonds Sep-14 C$75.0 NGEx Resources Jan-13 C$34.0
Trevali Mining May-15 C$20.0 Pretium Jul-14 US$69.0 Copper Mountain Mining Nov-13 C$30.1
Lydian International Jan-15 C$16.5 Altius Minerals Apr-14 C$65.0 Mountain Province Diamonds Nov-13 C$29.4
31
Issuer Date Size ($ MM) Coupon Rate (%) Term (Years) Description
Imperial Metals Sep-14 C$115.0 6.00% 6 Convertible Senior Unsecured Debentures
Stornoway Feb-14 US$81.3 6.25% 7 Convertible Unsecured Subordinated Debentures
Primero Mining Jan-15 US$75.0 5.75% 5 Convertible Unsecured Subordinated Debentures
5N Plus May-14 US$66.0 5.75% 5 Convertible Unsecured Subordinated Debentures
Banro Jun-14 US$40.0 8.00% 3.5 Convertible Preferred Shares
North American Palladium Apr-14 C$30.0 7.50% 5 Convertible Unsecured Subordinated Debentures
North American Palladium Mar-14 C$27.5 7.50% 5 Convertible Unsecured Subordinated Debentures
Argex Titanium Jan-14 C$7.5 8.00% 5 Convertible Unsecured Subordinated Debentures
Issuer Date Size ($ MM) Coupon Rate (%) Term (Years) Description
First Quantum Minerals May-14 US$850.0 7.25% 8 Senior Secured Notes
Lundin Oct-14 US$550.0 7.50% 6 Senior Secured Notes
Goldcorp Jun-14 US$549.3 3.63% 7 Senior Unsecured Notes
China Gold Jul-14 US$500.0 3.50% 3 Guaranteed Corporate Bond
Cameco Jun-14 US$499.8 4.19% 10 Senior Unsecured Debentures
Yamana Gold Jun-14 US$499.5 4.95% 10 Senior Unsecured Notes
Lundin Oct-14 US$450.0 7.88% 8 Senior Secured Notes
Goldcorp Jun-14 US$447.8 5.45% 30 Senior Unsecured Notes
Imperial Metals Mar-14 US$325.0 7.00% 5 Senior Unsecured Notes
AuRico Mar-14 US$304.1 8.50% 6 Senior Secured Second Lien Notes
HudBay Jul-14 US$181.9 9.50% 6 Senior Unsecured Notes
Stornoway Apr-14 C$120.0 Prime + 4.75% 10 Senior Secured Loan
Trevali Mining May-14 US$52.5 12.50% 5 Senior Secured Notes
Select Recent Debt & Convert Offerings
Debt Issuances
Convertible Debt Issuances
Source: Company disclosure.
32
Investor - Issuer Date Size ($ MM) Description
Franco-Nevada - Lundin Oct-14 US$648 Franco-Nevada to receive 68% of payable Au and Ag production until 720k oz Au and 12MM oz Ag are delivered
from 100% of Candelaria; thereafter reduces to 40% of LOM payable metals from 100% of the mine. Acquisition
financing package also consists of C$50MM private placement exclusive of stream value.
Orion Mine Finance & Caisse de dépôt -
Stornoway
Apr-14 US$250 Stream agreement for 20% interest on run of mine diamond production from certain kimberlite
bodies from the Renard Project. Investors to pay the Issuer in 3 deposits.
Gold Holding - Banro Aug-14 US$121 Streams on Banro's Tw angiza and Namoya mines for US$41MM and US$80MM, respectively. Investor to receive
40k oz Au from Tw angiza mine over 4 years. Investor to also receive 10% LOM Au production from Namoya
including Au processed at the site from other mines w ithin 20 km; maximum deliverable Au of 12k oz per annum.
Franco-Nevada & Sandstorm - True Gold Aug-14 Up to US$120 Franco-Nevada (75%) & Sandstorm (25%) to receive 100k oz Au over 5 years, and 6.5% LOM Au production
from True Gold's Karma Project thereafter. True Gold holds an 18 month option to increase funding by US$20MM
for an additional 30k oz Au. Ongoing payments of 20% of spot Au.
Royal Gold - Rubicon Feb-14 US$75 Royal Gold to receive 6.3% of Au production from Rubicon's Phoenix Project until 135k oz have been delivered
and 3.15% LOM Au production thereafter. Ongoing payments of 25% spot Au. Advance deposit payments from
Royal Gold payable in 5 installments.
Orion Mine Finance - Aldridge Aug-14 US$40 Consists of US$5MM private placement and US$35MM 2-year bridge loan facility. Bridge loan bears interest at
9% plus the greater of 3 month USD LIBOR and 1%. Aldridge also entered into offtake agreements w ith Orion for
~20% of Pb & ~50% of Au production over the first 10 years of the mine plan.
Franco-Nevada - Klondex Feb-14 US$35 Franco-Nevada to receive 38k oz Au by December 31, 2018, and a 2.5% NSR royalty on Klondex's Fire Creek
and Midas properties commencing 2019. Gold financing package provided to support Klondex's acquisition of the
Midas Mine and Mill Complex from New mont.
JMET - Santacruz Silver Sep-14 US$28 5-year pre-paid forw ard silver purchase agreement. JMET to receive 4.6MM oz Ag through August 2019 w ith no
ounces delivered over the first 12 months. Ongoing payments of spot Ag less an undisclosed fixed discount.
Quintana - Arian Silver Oct-14 US$16 Quintana to receive 78.2% of Zn and Pb from San José until 32MMlbs and 38MMlbs, respectively, are delievered,
and 27.4% thereafter for 50 years. Issuer can buy 50% of stream for US$11MM before 2017. Investor also
acquires US$16MM of senior secured convertible notes to be restructured into new notes (8% interest).
Orion Mine Finance - Claude Mar-14 US$12 3.0% NSR royalty on Claude's Seabee Gold Operation. The NSR provides Claude w ith the option to repurchase
half of the NSR for US$12MM until December 31, 2016.
BlackRock - Avanco Jul-14 US$12 2.0% NSR royalty on Cu; 25.0% NSR royalty on Au and 2.0% NSR royalty on all other metals produced from the
Issuer's Antas North and Pedra Branca licensed areas. Additionally, BlackRock to receive a 2% NSR Royalty on
other discoveries w ithin Avanco's current licence portfolio.
Sprott - Veris Gold Apr-14 US$8 0.5% NSR royalty on Veris Gold's Jerritt Canyon mines and processing plant.
Select Recent Alternative Finance Agreements
Sourc: Company disclosure.
3333
Appendix 2: Renard Technical Data
34
Probable Mineral Reserve
Mining Recovery Factors Utilized in the Reserve
Calculation
Kimberlite
Grade
(cpht)
Tonnes
(millions)
Contained
Carats
(Millions)
Internal
Dilution
Mining
Recovery
Mining
Dilution
Renard 2 OP 95 1.31 1.24 0.0% 96.0% 7.1%
Renard 2 UG 80 17.03 13.62 7.0% 82.4% 20.2%
Renard 3 OP 93 0.72 0.67 0.0% 96.0% 10.5%
Renard 3 UG 84 1.00 0.84 21.1% 85.0% 14.0%
Renard 4 UG 42 3.72 1.58 1.4% 78.2% 14.0%
Total 75 23.79 17.95 5.9% 82.9% 17.9%
Notes: Reserve categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Totals may not add due to rounding. Grades are estimated at a
+1DTC sieve size cut-off.
R2 ,
83%
R3, 8%
R4, 9%
Revenue
R2 , 77%
R3, 7%
R4, 16%
Tonnage
R2 , 83%
R3, 8%
R4, 9%
Carats
NI 43-101 Probable Mineral Reserves
January 28th 2013
35
Notes: Resource categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have
demonstrated economic viability. Indicated Mineral resources are Inclusive of the Mineral Reserve. Totals may not add due to rounding. Grades are estimated at a +1DTC sieve size
cut-off.
Renard NI 43-101 Mineral Resources
July 23rd 2013
Kimberlite
Grade
(cpht)
Tonnes
(millions)
Contained
Carats
(Millions)
Renard 2 – Total 100 18.58 18.66
Renard 2 104 17.71 18.38
Renard 2 CRB-2a 32 0.87 0.28
Renard 3 103 1.76 1.82
Renard 4 60 7.25 4.31
Renard 65 29 7.87 2.30
Total Indicated 76.4 35.45 27.09
Renard 2 – Total 64 11.77 7.47
Renard 2 119 5.23 6.23
Renard 2 CRB 19 6.54 1.24
Renard 3 112 0.54 0.61
Renard 4 50 4.75 2.37
Renard 9 53 5.70 3.04
Renard 65 24 4.93 1.18
Lynx Dyke 107 1.80 1.92
Hibou Dyke 144 0.18 0.26
Total Inferred 56.8 29.67 16.85
36
Notes: The potential quantity and grade of any exploration target (previously referred to as “potential mineral deposit”) is conceptual in nature, and it is uncertain if further exploration
will result in the target being delineated as a mineral resource. The exploration upside for the Renard kimberlite pipes has been determined by projecting reasonable kimberlite
volumes from the base of the inferred Resource to a depth of 700m below surface. In the case of the Lynx and Hibou dykes, the exploration upside was established on the basis of
known drill intersections of kimberlite for which insufficient diamond sampling exists to adequately estimate a diamond resource grade.
Target for Further Exploration
July 23rd 2013. Changes to Previous January 2011 Estimates in Italics
Kimberlite
Grade
(cpht)
Tonnes
(millions)
Contained Carats
(Millions)
Renard 2 104 to 158 4.0 to 4.6 4.2 to 7.3
Renard 3 105 to 168 0.8 to 1.7 0.8 to 2.8
Renard 4 50 to 77 11.1 to 15.4 5.6 to 11.8
Renard 9 52 to 68 3.9 to 6.3 2.0 to 4.3
Renard 65 25 to 33 29.0 to 40.9 7.3 to 13.5
Lynx Dyke 96 to 120 3.1 to 3.2 3.0 to 3.8
Hibou Dyke 104 to 151 2.7 to 2.9 2.9 to 4.3
Total Exploration
Upside
54.6
(-0.8%)
to
74.9
(-0.8%)
25.7
(+9.1%)
to
47.8
(-1.4%)
37
Chronology of Renard Studies
Feasibility Study
Released on November 16th 2011. NI 43-101 Technical Report filed December 29 2011.
11 Year Mine Plan based on 18 Mcarat Mineral Reserve derived from January 2011 NI 43-101 Resource.
Long Term Business Plan
Companion study to the Feasibility Study with an extended mine plan incorporating the project`s 17.5 million carats of
Inferred Mineral Resources.
Basis of overall mine design and project permitting. Not part of the project`s public disclosure, consistent with Canadian
reporting standards
Optimization Study
Released on January 28th, 2013. NI 43-101 Technical Report filed March 2013.
Refined of Feasibility mine design, including shaft deferral and a modified underground mining sequence.
11 Year Mine Plan based on 17.9 million carat Mineral Reserve.
Resource Update
Released July 2013. NI 43-101 Resource update with 14% increase in Indicated Resource contained carats
LNG Feasibility Study
Released October 2013. Modified project Cap-ex and Op-ex for LNG powered gen-sets
38
January 2013 Optimization Study
Project Assumptions, Valuation and Pay-Back in the January 2013 FS Optimization Study
Key Assumptions in the Financial Model1
Mining
Parameters
Reserve Carats (M) 17.9
Tonnes Processed (M) 23.8
Recovered Grade (cpht) 75
Average Ore Recovery (%) 82.9%
Average Mining Dilution (%) 17.9%
Dilution Grade (cpht) 0
Processing Rate (Mtonnes/annum) 2.2
Mine Life (years) 11
Cost
Parameters
Initial Cap-ex (C$M)2 $752
LOM Cap-ex (C$M)4 $1,013
Oil Price (US$/barrel)2 $95
LOM Op-ex (C$/tonne)2 $57.63
LOM Op-ex (C$/carat)2 $76.63
Revenue
Parameters
Gross Revenue (C$M)2 $4,268
Marketing Costs 2.7%
DIAQUEM Royalty 2.0%
Cash Operating Margin (C$M)2 $2,693
% Operating Margin 67%
Income Tax, Mining Duties and IBA
Payments (C$M)1 $625
After Tax Net Cash Flow (C$M) $1,084
Diamond
Price
Parameters3
Renard 2 and Renard 3 (US$/carat) $182
Renard 4 (US$/carat) $164
Diamond Price Escalation 2.5%
Exchange rate 1C$=1US$
Schedule
Parameters
Effective Date for NPV Calculation Jan. 1 2013
Construction Mobilization/Early Works Aug. 1 2013
Plant Commissioning Commences Dec. 1 2015
Commercial Production Declared Jun. 1 2016
Valuation Results5
(C$m)
Pre-Tax After Tax
NPV5% $894 $537
NPV7% (Base Case) $683 $391
NPV9% $514 $274
IRR 20.4% 16.3%
Pay-Back (years) 4.69 4.82
Notes
1. Optimization Study, released January 28th 2013.
2. Expressed in October 2012 terms.
3. Expressed in May 2011 terms.
4. Expressed in nominal terms.
5. Expressed in de-escalated nominal terms.
39
Liquefied Natural Gas Power Plant
The Renard Diamond Project will be
powered using Liquid Natural Gas (“LNG”)
fuelled gen-sets, with daily supplies of
cryogenic LNG from GazMetro in Montreal
utilizing the Renard Mine Road.
The Renard LNG plant will comprise seven
2.1MW rated gas gen-sets, providing
sufficient power generation capacity for the
project’s normal operating specification of
9.5MW.
LNG has significant cost and environmental
advantages over traditional diesel powered
gen-sets and a Hydro-Quebec power-line
option.
Diesel will continue to be used for the mobile
mining fleet and construction activities.
40
Liquefied Natural Gas Power Plant
Feasibility Study Released October 2013
An LNG fuelled powerplant for Renard offers many advantages over diesel:
• Greatly reduced annual operating costs of $8m to $10m per year, for a small incremental
capital cost of $2.6m.
• Up to 43% less greenhouse gas emissions.
• stable supply market utilizing existing commercial distribution network within Québec.
• Elimination of on-site propane, as LNG will be used for building and underground mine
heating
Cost Improvements with LNG
2013 Optimization
Study with Diesel
2013 Optimization
Study with LNG
Unit Power Cost (C$/kWh) 1
$0.299 $0.188 (-37%)
Unit Operating Cost (C$/tonne) 1,2
$57.63 $53.84 (-7%)
Initial Capital Cost (C$m) 1
$752.1 $754.0 (+0.3%)
Life of Mine Capital Cost (C$m) 1,3
$1,013 $1,010 (-0.3%)
Annual Diesel Consumption (million litres) 27.5 5.9 (-79%)
Annual LNG Consumption (thousand m3
/annum) n/a 41.7
Annual Propane Consumption (thousand m3
/annum) 3.5 n/a
Notes
1. 2013 Optimization Study costs expressed in October 2012 terms.
2. Excludes capitalized preproduction costs.
3. Includes all initial, sustaining and deferred capital, contingencies and escalation
Key Assumptions
Based on the 11 year reserve-based mine life (17.9 mcarats) contained within
the 2013 Optimization Study, with a normal operating load of 9.49MW,
C$1=US$1, Oil US$95/barrel
4141
Appendix 3: The Diamond Market
42
Major Diamond Mines and Development Projects Worldwide
Few Enough Mines to Fit on One Map
South Africa
• Venetia (De Beers)
• Finsch, Cullinan, Kimberley (Petra Diamonds)
• Lace (DiamondCorp)
Tanzania
• Williamson (Petra Diamonds)
Russia
• Arkhangelsk District (Alrosa)
• Yakutia District (Alrosa)
• Grib (LUKOIL)
India
• Bunder (Rio Tinto)
Australia
• Argyle (Rio Tinto)
• Ellendale (Kimberly Diamonds)
Canada
• Ekati (Dominion)
• Diavik (Rio Tinto/Dominion)
• Victor, Snap Lake, Gahcho Kué (De Beers)
• Renard (Stornoway)
• Fort a la Corne (Shore Gold/Newmont)
Botswana
• Jwaneng, Orapa (De Beers)
• Ghaghoo (Gem Diamonds)
• Karowe (Lucara Diamonds)
Angola
• Catoca (Alrosa)
Democratic Republic of Congo
• Mbuyi-Mayi
Sierra Leone
• Koidu, (Steinmetz Group)
Lesotho
• Letseng (Gem Diamonds)
• Kao (Namakwa Diamonds)
• Liqhobong (Firestone)
• Mothae (Lucara)
43
The Diamond Pipeline
An Industry with Many Intermediaries
Source: Tacy
D.I.B. 2015
Mine Production Rough Trading and Diamond Polishing Diamond Jewelery
Production
Cost
Production
Value
Mine Sales to
Industry
Rough Sales
To Cutting
Centres
Value of
Polished
Produced
Value of
Diamonds in
Retail
Jewelery
Sales
Retail Sales
Of Diamond
Jewelery
Value in US$B
terms of each
stage of the
diamond
pipeline
$6.9B $16.5B $16.7B $16.7B
$22.3B
$23.0B
$78.5B
Estimated
Average Margins
after Costs (%)
Rough Mining: 0 to 50% Rough Dealing: 0 to 10%
Polishing:
-10 to 15%
Jewelery
Manufac: -10
to 10%
Jewelery
Retail: 20
to 50%
44
A Snapshot of Rough Diamond Supply
Industry Supply Themes
146mcarats produced in 2013
(US$18b)
No return to peak diamond production
of 176mcarats achieved in 2005
Maximum 20mcarats new production
on deck assuming all new projects
meet proponents published production
and schedule estimates
Consensus forecast of 2% supply
CAGR (in carat terms) to 2018,
declining thereafter
Potential or Actual New Projects
Rough Diamond Supply
Sources
The Global Diamond Report, December 2014: Bain & Co/Antwerp World Diamond Centre
The Diamond Insight Report, September 2014: McKinsey/De Beers
45
A Snapshot of Rough Diamond Demand
Rough Diamond Demand
Supply and Demand
Industry Demand Themes
Diamond jewelry/polished diamond demand
growth tied to GDP growth in principal
markets
Diamond jewelry sales strongly correlated to
market demographics (age, gender, wealth)
US still dominant polished diamond market
(40% in 2013, 2% CAGR 2008-13) with
China the growth market (15% in 2013, 20%
CAGR 2008-13)
Consensus forecast of c.5% rough demand
CAGR (in dollar terms) over next 10 years
Consensus forecasts of 2-4% real rough
diamond price CAGR over next 10 years
given supply/demand imbalance
Sources
The Global Diamond Report, December 2014: Bain & Co/Antwerp World Diamond Centre
The Diamond Insight Report, September 2014: McKinsey/De Beers
46
Rough Diamond Pricing 2009-2015
A tracking of the diamond market since the publication of the November 2011 FS and January 2013 Opt.
FS indicates rough diamond prices have generally remained within the bounds of sensitivities contained
within the FS financial model (May 2011 spot prices and a 2.5% real terms annual price escalator).
WWW Rough
Diamond Price
Index
COMEX Gold
May 2011 FS
Diamond Valuation
50
100
150
200
250
300
350
1-Jan-09 1-Jan-10 1-Jan-11 1-Jan-12 1-Jan-13 1-Jan-14 1-Jan-15
Indexto2009=100
WWW Rough Index, CPI Adjusted Renard Model Price Growth
FS 2.5% Price Model
(Nominal, adjusted
for CPI) with +/- 10%
Sensitivity
4747
Appendix 4: Management Biographies
48
Hume Kyle
Independent
Pat Godin
COO & Director
Matt Manson
President, CEO
& Director
John LeBoutillier
Independent/
IQ Designate
Monique Mercier
Independent/
IQ Designate
Peter Nixon
Independent
Ebe Scherkus
Independent/
Board Chairman
Executive Officers
Non-Executive Directors
Key Managers
Head Office: Longueuil, Québec
Exploration Office: North Vancouver, BC
Community Offices: Mistissini & Chibougamau Québec
Stornoway’s Board and Management Team
Serge Vézina
Independent
Yves Perron
VP Engineering
& Construction
Ghislain
Poirier
VP Public Affairs
Brian Glover
VP Asset
Protection
Martin Boucher
VP Sustainable
Development
Robin
Hopkins
VP Exploration
Orin
Baranowsky
Director, IR
Douglas Silver
Orion Designate
Ian Holl
VP Processing
Annie Torkia-
Lagacé
VP Legal Affairs
Gaston Morin
Independent/
IQ Designate
Jean-Charles
Dumont
VP Finance
Helene
Robitaille
Director, HR
49
Pat Godin
COO & Director
Biographies
Ebe Scherkus
Chairman of the
Board
Matt Manson was appointed President of Stornoway Diamond Corporation in March 2007 and subsequently
President & CEO in January 2009. Between 1999 and 2005 he was employed by Aber Diamond Corporation
(now Dominion Diamond Corporation) as VP Marketing and subsequently VP Technical Services & Control,
during which time he participated in the US$230m project financing for the Diavik Diamond Project and
oversaw Aber's technical and marketing operations. Mr. Manson is a graduate of the University of Edinburgh
(BSc Geophysics, 1987) and the University of Toronto (MSc Geology 1989 and PhD Geology, 1996), and has
over 18 years of experience in diamond exploration, development and production.
Pat Godin joined Stornoway as COO in May 2010. He was previously VP, Project Development for GMining
Services, responsible for the development of the Essakane Mine in Burkina Faso under contract to IAMGOLD,
VP Operations for Canadian Royalties, and President and General Manager of CBJ-CAIMAN S.A.S., a French
subsidiary of Cambior / IAMGOLD. For many years, he was involved in Cambior’s various Canadian properties
in Abitibi-Témiscamingue, through progressive management positions in project development and mine
management. He holds a bachelor’s degree in mining engineering from Université Laval in Québec and is a
member of the “Ordre des Ingénieurs du Québec”. He is the Chairman of the Board of Geomega Resources
and a director of Orbit-Garant Drilling.
Mr. Scherkus served as the President and Chief Operating Officer and a director of Agnico-Eagle from 2005 to
February 2012. Prior to his appointment as President and Chief Operating Officer in December 2005, Mr.
Scherkus served as Executive Vice-President and Chief Operating Officer from 1998 to 2005, as Vice-
President, Operations from 1996 to 1998, as a manager of Agnico Eagle LaRonde Division from 1986 to 1996
and as a project manager from 1985 to 1986. Mr. Scherkus is a graduate of McGill University (B.Sc.), a
member of the Association of Professional Engineers of Ontario and past president of the Québec Mining
Association. He is Chairman of the Board of Premier Gold Mines Ltd.
Matt Manson
President, CEO
& Director
50
Stornoway Diamond Corporation TSX:SWY
Head Office:
1111 Rue St. Charles Ouest,
Longueuil, Québec J4K 4G4
Tel: +1 (450) 616-5555
IR Contact:
Orin Baranowsky, CFA, Director IR
obaranowsky@stornowaydiamonds.com
Tel: +1 (416) 304-1026 x3
www.stornowaydiamonds.com
Info@stornowaydiamonds.com

More Related Content

What's hot

Stornoway 2014 English AGM Presentation
Stornoway 2014 English AGM PresentationStornoway 2014 English AGM Presentation
Stornoway 2014 English AGM PresentationStornoway Diamonds
 
Stornoway PDAC 2016 Corporate Presentation
Stornoway PDAC 2016 Corporate PresentationStornoway PDAC 2016 Corporate Presentation
Stornoway PDAC 2016 Corporate PresentationStornoway Diamonds
 
Agm may 12 2017 final
Agm may 12 2017 finalAgm may 12 2017 final
Agm may 12 2017 finalPretiumR
 
Dalradian presentation feb 1 2016
Dalradian presentation feb 1 2016Dalradian presentation feb 1 2016
Dalradian presentation feb 1 2016DalradianResource
 
Pretivm european gold forum apr 2016
Pretivm   european gold forum apr 2016Pretivm   european gold forum apr 2016
Pretivm european gold forum apr 2016PretiumR
 
OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021CarolynGraham14
 
20210920 for corp_presentation
20210920 for corp_presentation20210920 for corp_presentation
20210920 for corp_presentationZhalaRahim
 
2021.12.20 prb presentation final
2021.12.20 prb presentation final2021.12.20 prb presentation final
2021.12.20 prb presentation finalProbe Gold
 
TriStar - August 2021 Corporate Presentation
TriStar - August 2021 Corporate PresentationTriStar - August 2021 Corporate Presentation
TriStar - August 2021 Corporate PresentationAdnet Communications
 
Stornoway Updated Mine Plan Support Materials March 30, 2016
Stornoway Updated Mine Plan Support Materials March 30, 2016Stornoway Updated Mine Plan Support Materials March 30, 2016
Stornoway Updated Mine Plan Support Materials March 30, 2016Stornoway Diamonds
 
Stornoway Corporate Presentation PDAC 2015
Stornoway Corporate Presentation PDAC 2015Stornoway Corporate Presentation PDAC 2015
Stornoway Corporate Presentation PDAC 2015Stornoway Diamonds
 
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017Stornoway Diamonds
 
BMO Capital Markets 26th Global Metals & Mining Conference
BMO Capital Markets 26th Global Metals & Mining ConferenceBMO Capital Markets 26th Global Metals & Mining Conference
BMO Capital Markets 26th Global Metals & Mining ConferencePretiumR
 
Ssr mining corp. pres. 081717
Ssr mining corp. pres.   081717Ssr mining corp. pres.   081717
Ssr mining corp. pres. 081717SilverStandard
 
European Gold Forum Presentation
European Gold Forum PresentationEuropean Gold Forum Presentation
European Gold Forum PresentationStornoway Diamonds
 
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...PretiumR
 
TriStar Gold Corporate Presentation
TriStar Gold Corporate PresentationTriStar Gold Corporate Presentation
TriStar Gold Corporate PresentationAdnet Communications
 
Pretium rodman renshaw sept 12 2017 final
Pretium rodman renshaw sept 12 2017 finalPretium rodman renshaw sept 12 2017 final
Pretium rodman renshaw sept 12 2017 finalPretiumR
 
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental MaterialsStornoway Diamond Corporation Q2 2017 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental MaterialsStornoway Diamonds
 

What's hot (20)

Stornoway 2014 English AGM Presentation
Stornoway 2014 English AGM PresentationStornoway 2014 English AGM Presentation
Stornoway 2014 English AGM Presentation
 
July 2021 mnd ir ppt
July 2021 mnd ir pptJuly 2021 mnd ir ppt
July 2021 mnd ir ppt
 
Stornoway PDAC 2016 Corporate Presentation
Stornoway PDAC 2016 Corporate PresentationStornoway PDAC 2016 Corporate Presentation
Stornoway PDAC 2016 Corporate Presentation
 
Agm may 12 2017 final
Agm may 12 2017 finalAgm may 12 2017 final
Agm may 12 2017 final
 
Dalradian presentation feb 1 2016
Dalradian presentation feb 1 2016Dalradian presentation feb 1 2016
Dalradian presentation feb 1 2016
 
Pretivm european gold forum apr 2016
Pretivm   european gold forum apr 2016Pretivm   european gold forum apr 2016
Pretivm european gold forum apr 2016
 
OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021
 
20210920 for corp_presentation
20210920 for corp_presentation20210920 for corp_presentation
20210920 for corp_presentation
 
2021.12.20 prb presentation final
2021.12.20 prb presentation final2021.12.20 prb presentation final
2021.12.20 prb presentation final
 
TriStar - August 2021 Corporate Presentation
TriStar - August 2021 Corporate PresentationTriStar - August 2021 Corporate Presentation
TriStar - August 2021 Corporate Presentation
 
Stornoway Updated Mine Plan Support Materials March 30, 2016
Stornoway Updated Mine Plan Support Materials March 30, 2016Stornoway Updated Mine Plan Support Materials March 30, 2016
Stornoway Updated Mine Plan Support Materials March 30, 2016
 
Stornoway Corporate Presentation PDAC 2015
Stornoway Corporate Presentation PDAC 2015Stornoway Corporate Presentation PDAC 2015
Stornoway Corporate Presentation PDAC 2015
 
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017
Stornoway q1 2017 earnings results presentation final 11.30pm monday 8 may 2017
 
BMO Capital Markets 26th Global Metals & Mining Conference
BMO Capital Markets 26th Global Metals & Mining ConferenceBMO Capital Markets 26th Global Metals & Mining Conference
BMO Capital Markets 26th Global Metals & Mining Conference
 
Ssr mining corp. pres. 081717
Ssr mining corp. pres.   081717Ssr mining corp. pres.   081717
Ssr mining corp. pres. 081717
 
European Gold Forum Presentation
European Gold Forum PresentationEuropean Gold Forum Presentation
European Gold Forum Presentation
 
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...
Ramping Up Brucejack Mine - Presented at the AFund Natural Resource Symposium...
 
TriStar Gold Corporate Presentation
TriStar Gold Corporate PresentationTriStar Gold Corporate Presentation
TriStar Gold Corporate Presentation
 
Pretium rodman renshaw sept 12 2017 final
Pretium rodman renshaw sept 12 2017 finalPretium rodman renshaw sept 12 2017 final
Pretium rodman renshaw sept 12 2017 final
 
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental MaterialsStornoway Diamond Corporation Q2 2017 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q2 2017 Earnings Release Supplemental Materials
 

Similar to Stornoway Corporate Update June 19, 2015

Stornoway Presentation at PDAC 2014
Stornoway Presentation at PDAC 2014Stornoway Presentation at PDAC 2014
Stornoway Presentation at PDAC 2014Stornoway Diamonds
 
Stornoway Corporate Presentation August 2014
Stornoway Corporate Presentation August 2014Stornoway Corporate Presentation August 2014
Stornoway Corporate Presentation August 2014Stornoway Diamonds
 
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...Stornoway Diamonds
 
Stornoway Corporate Update November 12, 2014
Stornoway Corporate Update November 12, 2014Stornoway Corporate Update November 12, 2014
Stornoway Corporate Update November 12, 2014Stornoway Diamonds
 
Stornoway Diamond Corporation Corporate Update Presentation
Stornoway Diamond Corporation Corporate Update PresentationStornoway Diamond Corporation Corporate Update Presentation
Stornoway Diamond Corporation Corporate Update PresentationStornoway Diamonds
 
Stornoway Corporate Presentation December 2015
Stornoway Corporate Presentation December 2015Stornoway Corporate Presentation December 2015
Stornoway Corporate Presentation December 2015Stornoway Diamonds
 
Presentation at the TD Securities Mining Conference
Presentation at the TD Securities Mining ConferencePresentation at the TD Securities Mining Conference
Presentation at the TD Securities Mining ConferenceStornoway Diamonds
 
PRB Corporate Presentation March 7, 2024
PRB Corporate Presentation March 7, 2024PRB Corporate Presentation March 7, 2024
PRB Corporate Presentation March 7, 2024Probe Gold
 
Renard Diamond Mine Financing Presentation
Renard Diamond Mine Financing PresentationRenard Diamond Mine Financing Presentation
Renard Diamond Mine Financing PresentationStornoway Diamonds
 
Great panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat Panther Silver Limited
 
Great panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat Panther Silver Limited
 
Corporate Presentation Sept 5, 2014
Corporate Presentation Sept 5, 2014Corporate Presentation Sept 5, 2014
Corporate Presentation Sept 5, 2014PretiumR
 
Corporate Presentation Sept 2014
Corporate Presentation Sept 2014Corporate Presentation Sept 2014
Corporate Presentation Sept 2014PretiumR
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate PresentationAvion Gold Corp
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate PresentationAvion Gold Corp
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate PresentationAvion Gold Corp
 
Stornoway 2015 Annual General Meeting Presentation
Stornoway 2015 Annual General Meeting PresentationStornoway 2015 Annual General Meeting Presentation
Stornoway 2015 Annual General Meeting PresentationStornoway Diamonds
 
Nan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNorthAmericanNickel
 
Avion Corporate Presentation - November 12
Avion Corporate Presentation - November 12Avion Corporate Presentation - November 12
Avion Corporate Presentation - November 12Avion Gold Corp
 

Similar to Stornoway Corporate Update June 19, 2015 (20)

Stornoway Presentation at PDAC 2014
Stornoway Presentation at PDAC 2014Stornoway Presentation at PDAC 2014
Stornoway Presentation at PDAC 2014
 
Stornoway Corporate Presentation August 2014
Stornoway Corporate Presentation August 2014Stornoway Corporate Presentation August 2014
Stornoway Corporate Presentation August 2014
 
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...
Stornoway Diamond Presentation at the Precious Metals Summit Beaver Creek, CO...
 
Stornoway Corporate Update November 12, 2014
Stornoway Corporate Update November 12, 2014Stornoway Corporate Update November 12, 2014
Stornoway Corporate Update November 12, 2014
 
Stornoway Diamond Corporation Corporate Update Presentation
Stornoway Diamond Corporation Corporate Update PresentationStornoway Diamond Corporation Corporate Update Presentation
Stornoway Diamond Corporation Corporate Update Presentation
 
Stornoway Corporate Presentation December 2015
Stornoway Corporate Presentation December 2015Stornoway Corporate Presentation December 2015
Stornoway Corporate Presentation December 2015
 
Presentation at the TD Securities Mining Conference
Presentation at the TD Securities Mining ConferencePresentation at the TD Securities Mining Conference
Presentation at the TD Securities Mining Conference
 
PRB Corporate Presentation March 7, 2024
PRB Corporate Presentation March 7, 2024PRB Corporate Presentation March 7, 2024
PRB Corporate Presentation March 7, 2024
 
Renard Diamond Mine Financing Presentation
Renard Diamond Mine Financing PresentationRenard Diamond Mine Financing Presentation
Renard Diamond Mine Financing Presentation
 
Corporate Presentation - July 14, 2016
Corporate Presentation - July 14, 2016Corporate Presentation - July 14, 2016
Corporate Presentation - July 14, 2016
 
Great panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qr
 
Great panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qrGreat panther silver limited corporate presentation july 14 2016_qr
Great panther silver limited corporate presentation july 14 2016_qr
 
Corporate Presentation Sept 5, 2014
Corporate Presentation Sept 5, 2014Corporate Presentation Sept 5, 2014
Corporate Presentation Sept 5, 2014
 
Corporate Presentation Sept 2014
Corporate Presentation Sept 2014Corporate Presentation Sept 2014
Corporate Presentation Sept 2014
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate Presentation
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate Presentation
 
Avion Corporate Presentation
Avion Corporate PresentationAvion Corporate Presentation
Avion Corporate Presentation
 
Stornoway 2015 Annual General Meeting Presentation
Stornoway 2015 Annual General Meeting PresentationStornoway 2015 Annual General Meeting Presentation
Stornoway 2015 Annual General Meeting Presentation
 
Nan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNan mines and money mining oct. corporate
Nan mines and money mining oct. corporate
 
Avion Corporate Presentation - November 12
Avion Corporate Presentation - November 12Avion Corporate Presentation - November 12
Avion Corporate Presentation - November 12
 

More from Stornoway Diamonds

Swy td conference 2019 presentation
Swy td conference 2019 presentationSwy td conference 2019 presentation
Swy td conference 2019 presentationStornoway Diamonds
 
Stornoway Second Quarter 2018 Earnings Results Presentation
Stornoway Second Quarter 2018 Earnings Results PresentationStornoway Second Quarter 2018 Earnings Results Presentation
Stornoway Second Quarter 2018 Earnings Results PresentationStornoway Diamonds
 
Stornoway Denver Gold Forum 2018 Presentation
Stornoway Denver Gold Forum 2018 PresentationStornoway Denver Gold Forum 2018 Presentation
Stornoway Denver Gold Forum 2018 PresentationStornoway Diamonds
 
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental MaterialsStornoway Diamond Corporation Q1 2018 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental MaterialsStornoway Diamonds
 
Stornoway q1 2018 earnings results presentation final
Stornoway q1 2018 earnings results presentation finalStornoway q1 2018 earnings results presentation final
Stornoway q1 2018 earnings results presentation finalStornoway Diamonds
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway Diamonds
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway Diamonds
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway Diamonds
 
Swy corporate presentation pdac investor exchange march 5 2018
Swy corporate presentation pdac investor exchange march 5 2018Swy corporate presentation pdac investor exchange march 5 2018
Swy corporate presentation pdac investor exchange march 5 2018Stornoway Diamonds
 
Swy corporate presentation bmo feb 25 28 2018
Swy corporate presentation bmo feb 25 28 2018Swy corporate presentation bmo feb 25 28 2018
Swy corporate presentation bmo feb 25 28 2018Stornoway Diamonds
 
A Dive into the International World of Diamonds
A Dive into the International World of DiamondsA Dive into the International World of Diamonds
A Dive into the International World of DiamondsStornoway Diamonds
 
Swy corporate presentation td securities mining conference jan 18 2017
Swy corporate presentation td securities mining conference jan 18 2017Swy corporate presentation td securities mining conference jan 18 2017
Swy corporate presentation td securities mining conference jan 18 2017Stornoway Diamonds
 
Stornoway Q3 2017 Earnings Results
Stornoway Q3 2017 Earnings Results Stornoway Q3 2017 Earnings Results
Stornoway Q3 2017 Earnings Results Stornoway Diamonds
 
Denver Gold Forum Presentation Sep 25 2017
Denver Gold Forum Presentation Sep 25 2017Denver Gold Forum Presentation Sep 25 2017
Denver Gold Forum Presentation Sep 25 2017Stornoway Diamonds
 
Stornoway Corporate Presentation July 13 2017
Stornoway Corporate Presentation July 13 2017Stornoway Corporate Presentation July 13 2017
Stornoway Corporate Presentation July 13 2017Stornoway Diamonds
 
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016Stornoway Diamonds
 

More from Stornoway Diamonds (20)

Swy td conference 2019 presentation
Swy td conference 2019 presentationSwy td conference 2019 presentation
Swy td conference 2019 presentation
 
Stornoway Second Quarter 2018 Earnings Results Presentation
Stornoway Second Quarter 2018 Earnings Results PresentationStornoway Second Quarter 2018 Earnings Results Presentation
Stornoway Second Quarter 2018 Earnings Results Presentation
 
Stornoway Denver Gold Forum 2018 Presentation
Stornoway Denver Gold Forum 2018 PresentationStornoway Denver Gold Forum 2018 Presentation
Stornoway Denver Gold Forum 2018 Presentation
 
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental MaterialsStornoway Diamond Corporation Q1 2018 Earnings Release Supplemental Materials
Stornoway Diamond Corporation Q1 2018 Earnings Release Supplemental Materials
 
Stornoway AGM 2018
Stornoway AGM 2018 Stornoway AGM 2018
Stornoway AGM 2018
 
Stornoway AGA 2018
Stornoway AGA 2018 Stornoway AGA 2018
Stornoway AGA 2018
 
Stornoway q1 2018 earnings results presentation final
Stornoway q1 2018 earnings results presentation finalStornoway q1 2018 earnings results presentation final
Stornoway q1 2018 earnings results presentation final
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation final
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation final
 
Stornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation finalStornoway q4 and fy 2017 earnings results presentation final
Stornoway q4 and fy 2017 earnings results presentation final
 
Swy corporate presentation pdac investor exchange march 5 2018
Swy corporate presentation pdac investor exchange march 5 2018Swy corporate presentation pdac investor exchange march 5 2018
Swy corporate presentation pdac investor exchange march 5 2018
 
Swy corporate presentation bmo feb 25 28 2018
Swy corporate presentation bmo feb 25 28 2018Swy corporate presentation bmo feb 25 28 2018
Swy corporate presentation bmo feb 25 28 2018
 
A Dive into the International World of Diamonds
A Dive into the International World of DiamondsA Dive into the International World of Diamonds
A Dive into the International World of Diamonds
 
Swy corporate presentation td securities mining conference jan 18 2017
Swy corporate presentation td securities mining conference jan 18 2017Swy corporate presentation td securities mining conference jan 18 2017
Swy corporate presentation td securities mining conference jan 18 2017
 
Stornoway Q3 2017 Earnings Results
Stornoway Q3 2017 Earnings Results Stornoway Q3 2017 Earnings Results
Stornoway Q3 2017 Earnings Results
 
Denver Gold Forum Presentation Sep 25 2017
Denver Gold Forum Presentation Sep 25 2017Denver Gold Forum Presentation Sep 25 2017
Denver Gold Forum Presentation Sep 25 2017
 
Stornoway Corporate Presentation July 13 2017
Stornoway Corporate Presentation July 13 2017Stornoway Corporate Presentation July 13 2017
Stornoway Corporate Presentation July 13 2017
 
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016
Matériel d'appui à la mise à jour du plan minier de mars 2016 - 30 mars 2016
 
AGA 2017 Presentation
AGA 2017 PresentationAGA 2017 Presentation
AGA 2017 Presentation
 
AGM 2017 Presentation
AGM 2017 PresentationAGM 2017 Presentation
AGM 2017 Presentation
 

Recently uploaded

Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024nicola_mining
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000Sapana Sha
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel Paul
 
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...Kumaran637735
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd
 
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书Fir La
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdftaxlinkcpa
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书Fir La
 
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书Fir La
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityJohanAspro
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCRSapana Sha
 

Recently uploaded (20)

Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
 
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCRCall Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
 
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Serviceyoung call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...
The resilient U.S. late-cycle expansion contributed to a stalling pattern in ...
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 23, 2024
 
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书
如何办理北卡罗来纳大学教堂山分校毕业证(文凭)UNC学位证书
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdf
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
如何办理东俄勒冈大学毕业证(文凭)EOU学位证书
 
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Serviceyoung  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
 
Model Call Girl in Uttam Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Uttam Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Uttam Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Uttam Nagar Delhi reach out to us at 🔝9953056974🔝
 
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Serviceyoung Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
 
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
如何办理密苏里大学堪萨斯分校毕业证(文凭)UMKC学位证书
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanity
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
 

Stornoway Corporate Update June 19, 2015

  • 1. BUILDING QUÉBEC’S FIRST DIAMOND MINE Corporate Update, June 19th 2015 Matt Manson Orin Baranowsky President & CEO Director, Investor Relations
  • 2. 2 Forward-Looking Information This presentation contains "forward-looking information" within the meaning of Canadian securities legislation and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as “forward-looking statements”, are made as of the date of this presentation and the Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by law. Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: (i) the amount of mineral resources and exploration targets; (ii) the amount of future production over any period; (iii) net present value and internal rates of return of the mining operation; (iv) assumptions relating to recovered grade, average ore recovery, internal dilution, mining dilution and other mining parameters set out in the Feasibility Study or Optimization Study; (v) assumptions relating to gross revenues, operating cash flow and other revenue metrics set out in the Feasibility Study or Optimization Study; (vi) mine expansion potential and expected mine life; (vii) expected time frames for completion of permitting and regulatory approvals and making a production decision; (viii) future exploration plans; (ix) future market prices for rough diamonds; and (x) sources of and anticipated financing requirements. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as “expects”, “anticipates”, “plans”, “projects”, “estimates”, “assumes”, “intends”, “strategy”, “goals”, “objectives” or variations thereof or stating that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements. Forward-looking statements are made based upon certain assumptions and other important factors that, if untrue, could cause the actual results, performances or achievements of Stornoway to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which Stornoway will operate in the future, including the price of diamonds, anticipated costs and Stornoway’s ability to achieve its goals. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking statements include, but are not limited to: (i) required capital investment and estimated workforce requirements; (ii) estimates of net present value and internal rates of return; (iii) receipt of regulatory approvals on acceptable terms within commonly experienced time frames; (iv) anticipated timelines for the commencement of mine production; (v) market prices for rough diamonds and the potential impact on the Renard Project’s value; and (vi) future exploration plans and objectives. Additional risks are described in Stornoway's most recently filed Annual Information Form, annual and interim MD&As, and other disclosure documents available under the Company’s profile at: www.sedar.com. When relying on our forward-looking statements to make decisions with respect to Stornoway, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. Stornoway does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by Stornoway or on our behalf, except as required by law. Readers are referred to the technical report dated as of February 28th, 2013 entitled “The Renard Diamond Project, Québec, Canada, Feasibility Study Update, NI 43-101 Technical Report, February 28, 2013” in respect of the January 2013 Optimization Study, and the press release dated July 23, 2013 in respect of the July 2013 Mineral Resource estimate for further details and assumptions relating to the project. The Qualified Persons that prepared the technical reports and press releases that form the basis for the presentation are listed in the Company’s AIF dated July 29, 2014. Disclosure of a scientific or technical nature in this presentation has been reviewed and approved by Robin Hopkins, P.Geol. (NT/NU), Vice President, Exploration, a “qualified person” under NI 43-101.
  • 3. 3 Stornoway Diamond Corporation TSX:SWY Notes: 1. Assuming a C$:US$ conversion rate of C$1.10 Project Site, March 24, 2015 100% Ownership in Renard, Québec’s First Diamond Mine Fully Permitted; Road Accessible; Strong Social License; Excellent Cost Environment Fully Financed and In Construction July 8th 2014: C$946M1 project financing designed to cover all project costs, contingencies, over-run facilities, financing costs and working capital requirements. On Budget April 30, 2015: guiding for completion within C$811m capital budget with construction 22.4% complete compared to 21.7% planned. On Schedule Plant Commissioning 2H 2016. Commercial Production 2Q 2017
  • 4. 4 Publicly Listed Diamond Producers, Developers and Explorers Consensus Analyst Views on Value Ticker Price (19/6/15) Shares O/S (mm) Market Cap ($mm) NAV/sh(1) Current P/NAV(1) Target (1) % Return to Target Annual Dividend Diamond Producers Dominion Diamonds DDC:T $18.55 85.1 $1,579.2 $30.80 0.6x $27.04 48% US$0.40/sh Gem GEMD:LN £1.465 138.3 £202.6 £2.53 0.6x £2.25 56% US$0.05/sh Lucara LUC:T $1.94 379.5 $736.3 $2.53 0.8x $2.76 44% $0.04/sh Petra PDL:LN £1.586 512.1 £812.2 £2.40 0.7x £2.26 44% £0.02/sh Diamond Developers Firestone FDI:LN £0.33 309.0 £102.0 £0.70 0.5x £0.56 69% (n/a) Mountain Province MPV:T $5.10 159.0 $810.7 $7.17 0.7x $6.55 28% (n/a) Stornoway SWY:T $0.83 732.3 $607.8 $1.36 0.6x $1.14 37% (n/a) Diamond Explorers Kennady Diamonds KDI:LN $5.38 28.0 $150.5 (n/a) (n/a) (n/a) (n/a) (n/a) North Arrow Minerals NAR:V $0.485 54.0 $26.2 (n/a) (n/a) (n/a) (n/a) (n/a) Peregrine Diamonds PGD:T $0.245 282.7 $69.3 (n/a) (n/a) (n/a) (n/a) (n/a) Shore Gold SGF:T $0.215 248.7 $53.5 (n/a) (n/a) (n/a) (n/a) (n/a) Notes: 1. Bloomberg Analyst Consensus All Currencies in C$ unless specified
  • 6. 6 The Renard Diamond Project Québec’s First Diamond Mine Chibougamau Montréal Toronto 800km 360km Renard 1996: Start of initial regional exploration by Ashton & SOQUEM 2001: First kimberlite discovery 2001-08: Drilling, “mini-bulk” sampling, bulk sampling 2008-10: First NI 43-101 Resource and PEA November 2011: Feasibility Study issued. First mineral reserve December 2012: ESIA filed February 2012: Road construction commences under Plan Nord March 2012: “Mecheshoo Agreement” executed Nov.-Dec.2012: Mining Lease and Québec Authorizations issued January 2013: Optimization Study issued July 2013: Federal Canadian Authorizations Issued September 2013: Road opens April-July 2014: $C946m financing completed. Construction commences 2Q 2017: Scheduled Commercial Production 2001: First Kimberlite Discovery +7-9 Years: First NI 43-101 Resource and PEA +16 Years: Commercial Production +12 Years: Final Authorisations Issued
  • 7. 7 Lynx R10 N R7 R1Hibou R4 R9 R2 R3 R65 R8 Kimberlite Bodies with Measured and Indicated Resources Hibou Lynx R4 R9 R2 R3 R65 Kimberlite Bodies with Resource Potential R1Hibou Lynx Legend Stornoway Properties Hydro-Québec Facility Renard Kimberlites Kimberlitic Dyke Regional Kimberlites Hydro-Québec Powerlines Route 167 Extension/ Renard Mine Road Road Exploration/ Mining Projects LEGEND: 0 1 2 Kilometers 60 0 60 120 Kilometers Renard LG3LG2 LG4 Laforge 1 Laforge 2 Brisay Foxtrot Property Strateco Eastmain MineWestern Troy Troilus Mine Eleonore Temiscamie Mistissini Chibougamau Matagami Wemindji Renard Kimberlite Bodies Kimberlite Bodies with Inferred Resources
  • 8. 8 The Feasibility: 11 years of mining on 18mcarat Mineral Reserve (24mtonnes) Permitting and Long Term Plan The Vision: Deposit still Open 40 60 80 100 120 140 Millions of Tonnes 20 0 TFFE High Range Inferred Mineral Resource TFFE Low Range Indicated Mineral Resource The Renard Diamond Project A Large, High Value Diamond Resource with a Very Long Mine Life Potential 0m 100m 200m 400m 600m 700m 500m 300m Renard 65 29/24cpht Renard 3 103/112cpht Renard 2 104/119cpht Renard 9 53cpht Renard 4 60/50cpht 27 mcarat Indicated Mineral Resource 17 mcarat Inferred Mineral Resource 26-48 mcarat TFFE Source: Stornoway, 2014 Grades illustrated are for Indicated and Inferred Mineral Resources respectively at a +1DTC sieve size cut-off. Reserve and Resource categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have demonstrated economic viability. The potential quantity and grade of any Exploration Target (previously referred to as a “Potential Mineral Deposit”) is conceptual in nature, and it is uncertain if further exploration will result in the target being delineated as a mineral resource.
  • 9. Renard Mine Plan and Key Operating Assumptions A Combined Open Pit and Underground Operation 0m 100m 200m 400m 600m 700m 500m 300m Notes 1. Key Assumptions:C$1=US$1, Oil US$95/barrel, 2.5% real terms diamond price growth, 82.9% ore recovery, 23.8% mining and internal dilution, 0cpht dilution grade. 2. Expressed in May 2011 terms. Average price US$190/carat in March 2014 terms. 3. Expressed in October 2012 terms, as adjusted in October 2013 LNG FS. Includes C$754m of costs and contingencies and C$57m of escalation allowance. 4. Expressed in October 2012 terms. Operating costs C$54/tonne in October 2013 LNG FS terms. Excludes capitalized preproduction costs. 5. Before stream Reserve and Resource categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have demonstrated economic viability. The potential quantity and grade of any Exploration Target is conceptual in nature, and it is uncertain if further exploration will result in the target being delineated as a mineral resource. Reserve Based Mine Plan1 (Jan 2013 FS Optimization and October 2013 LNG Option FS) Mine Life 11 years Mineral Reserve 17.9 mcarats Ave. Diamond Price2 $180/carat Production Rate 2.2 mtonnes/yr Ave. Diamond Production 1.6 mcarats/yr Gross Revenue (C$M)2 $4,268 Initial Capital Costs3 $811m Operating Cost4 $58/t ($76/carat) Operating Margin5 67% Payback 4.8 years Resource Based Mine Plan (Basis of December 2012 ESIA and Mine Permitting. Not public disclosure consistent with NI 43-101) Includes the mining of 2.3mcarats of Indicated Resources within a Renard 65 open pit, additional Inferred Resources in Renard 2, 3, 4 and 9, and an increased annual processing capacity up to 2.6mtonnes/yr. Increased project valuation and mine life. Renard 65 Renard 2 Renard 3 Renard 4 Renard 9 9
  • 10. 10 490 m asl -275 m asl 0 m 790 m Ongoing Resource Expansion Long Section Illustrating July 2013 NI 43-101 Mineral Resource Renard 2 Renard 3 Renard 4 Renard 65 Renard 9 27 mcarat Indicated Mineral Resource 17 mcarat Inferred Mineral Resource 26-48 mcarat TFFE Reserve and Resource categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have demonstrated economic viability. The potential quantity and grade of any Exploration Target (previously referred to as a “Potential Mineral Deposit”) is conceptual in nature, and it is uncertain if further exploration will result in the target being delineated as a mineral resource. $10m 2014 drill program focussed on Renard 2 below Mineral Reserve at 600m. Estimate of 9-12mTonnes 600m to 1,000m depth. >1 hectare at 1,000m. Open below. Resource update Summer 2015 Surface 600m Depth 1,000m Depth Renard 2
  • 11. 11 Renard’s Diamonds Large Diamond Potential Not Included in Base Case Diamond Valuation Models March 2014 Diamond Valuations (WWW International Diamond Consultants Ltd.) Kimberlite Body Size of Valuation Sample (carats) WWW March 2014 Sample Price (US$/carat)1 WWW March 2014 Base Case Price Model (US$/carat)1 Sensitivities (Minimum to High) Renard 2 1,580 $187 $197 $178 to $222 Renard 3 2,753 $179 $157 $146 to $192 Renard 4 2,674 $101 $106 ($155)2 $100 to $174 Renard 65 997 $262 $187 $175 to $211 Notes 1. All prices in US$/carat. Samples utilizing a +1 DTC sieve size cut-off. 2. Should the Renard 4 diamond population prove to have a diamond population with a size distribution equal to the average of Renard 2 and 3, WWW have estimated that a base case diamond price model of $155 per carat based on March 2014 pricing. Source: WWW March 2014 Valuation Update Three Renard 65 diamonds: 9.78 ct and 6.41 ct diamonds recovered from bulk sampling and a 4 carat stone discovered in drillcore in 2003 Base Case Diamond Valuation Estimates Using Best Practice Methodology Average diamond price estimate in March 2014 for the Mineral Reserves at US$190/ct (un-escalated) compared to US$180/ct in the January 2013 Optimization Study. High Quality Production with Large Stone Potential The Renard kimberlites have similar, but marginally different diamond populations exhibiting a high incidence of large white gems. Coarse Size Distribution in Renard 2 predicts three to six 50-100ct stones and one to two +100ct stones every 100,000 carats (two weeks). Substantial revenue potential from large diamonds not accounted for in the base case cash-flow model.
  • 12. 12 Stornoway will be a Significant Diamond Producer Current and Future Diamond Producers Source: Kimberly Process, WWW and Company Reports Latest 12 Month Sales/ Forecast Future Average Sales 1 De Beers (Anglo/Botswana) $7,114m 2 Alrosa (Russia) $4,901m 3 Dominion Diamond (TSX: DDC) $928m 4 Rio Tinto (ASE: RIO) $901m 5 Petra (L: PDL) $502m 6 Stornoway (note 2; TSX: SWY) $310m 7 Gem Diamonds (L: GEMD) $271m 8 Lucara (TSX: LUC) $266m 9 Mountain Province (note 2; TSX: MPV) $259m 10 Firestone (note 3; L: FDI) $123m 11 Others $3,025m Total $18,600m DeBeers 38% Alrosa 26% Dominion 5% RioTinto 5% Petra 3% SWY 2% GEM 1% LUC 1% MPV 1%Firestone 1% Others 16% Notes: 1. Renard estimated at FS average annual diamond production of 1.63 million carats, and WWW March 2014 weighted diamond price of US$190/ct, un-escalated 2. Gahcho Kué estimated at 49% of Revised FS average annual production of 4.45 million carats, and average modeled diamond price of US$118/ct, un-escalated 3. Firestone estimated at FS average annual production of 1.15 million carats at an average price of US$107/ct un-escalated 6 Stornoway (note 1; TSX: SWY) $310m
  • 13. 13 Why Stornoway? Renard’s Cash Flow Potential Based on Base Case Economics Renard is Expected to Generate Substantial Cash Flow over its first 11 years of Mining After Tax, After Stream Operating Cash Flow of between $150 and $250 million, or $0.20 to $0.30 per share Assumptions Mineral reserve case only, averaging 1.6mcarats per annum at US$190/carat Capital and operating cost parameters as established in the January 2013 Optimization Study and October 2013 LNG FS Base case diamond pricing from March 2014; No “special” diamonds. 2.5% annual real diamond price escalation C$:US$ conversion rate of C$1.10 Based on terms of Financing Transaction closed on July 8th 2014 Assumes full conversion to equity of US$81million of Convertible Debentures giving 825 million shares outstanding. Significant Upside Potential from Resource, Large Diamonds and Processing Capacity
  • 15. 15 Project Well Prepared for Execution Construction Commenced July 10th 2014 Project Site July 2014 Permitting and Social Licence in Place Mecheshoo Agreement signed with Crees in March 2012, partnership agreements with Chibougamau and Chapais in July 2012, Québec and Federal Authorisations in Dec. 2012 and July 2013 respectively. Access Infrastructure in Place Renard Mine Road opened to traffic on Aug. 30th 2013. Renard Aerodrome opened to landings Nov. 5th 2013. Owner’s Team and EPCM in Place Owner’s construction team located in Longueuil. EPCM contract negotiated with SNC-Lavalin, DRA & AMEC. LNG Power LNG power option selected to utilize all-season road and commercial LNG distribution network in Québec. Favourable Construction Environment Competitive cost environment and good contractor/ labour availability in Québec. R65 Borrow Pit Exploration Camp Lac Lagopede Ground Breaking Ceremony July 8th 2014
  • 16. 16 Jean-Charles Dumont VP Finance SWY since 2011 Formerly Corporate Controller of La Mancha. Ebe Scherkus Chairman of the Board Stornoway’s Management Credentials Experience in Building and Operating Major Projects Matt Manson President, CEO & Director Pat Godin COO & Director SWY since 2011 Formerly President and COO of Agnico Eagle Mines Ltd. Executive Chairman of Premier Gold SWY since 2007 Formerly VP Marketing/VP Technical Services, Aber Diamond Corp (Dominion Diamond; Diavik Project) SWY since 2010 Formerly VP Project Development Gmining (Essakane Mine). Successive mine management and project development positions, Cambior Ian Holl VP Processing SWY since 2014 20 years experience De Beers in plant construction, commissioning and operation (Victor, Snap Lake, Jwaneng Mines) Yves Peron VP Engineering & Construction SWY since 2012 Formerly VP Bus. Dev. at Delsaer and Seneca. Successive management roles at ArcelorMittal and Xstrata. Martin Boucher VP Sustainable Development SWY since 2010 Formerly Canadian Royalties (Nunavik Project) and Xstrata (Raglan, Gaspesia, Koniambo Mines) Brian Glover VP Asset Protection SWY since 2012 Formerly Director Security Operations at Harry Winston (Dominion Diamond). More than 20 years experience RCMP. Robin Hopkins VP Exploration SWY since 2006 Formerly Aber Resources and discovery of the Diavik Mine.
  • 17. 17 Site Progress Site Overview by Week 48 Project Site March 24, 2015 Accommodation Complex R65 Pit Project Site June 4, 2015 Mine Admin Maintenance Facility Process Plant Power Plant UG Mine Portal R2-R3 R65 Garage Administration Portal Accommodation Plant Waste Rock Ore Stockpile PKC Overburden Stockpile R2-R3 Pit Contractors Offices
  • 18. 18 Access Infrastructure In Place The 240km long Route 167 Extension and the Clarence and Abel Swallow Airport Eastmain River Bridge March 2015 March 2015July 2014 January 2015 Airport Naming Ceremony, March 2015
  • 19. 19 Process Plant at 6,000tpd (2.2Mtonnes per annum) nameplate capacity, expandable to 7,000tpd (2.6Mtonnes per annum) Optimization by DRA Americas Inc. has allowed addition of Large Diamond Recovery (“LDR”) capacity to the flow sheet for no additional capital. Flow sheet: • Primary jaw crushing to < 230mm • Twin DMS circuits at +1mm -19mm • LDR circuit at +19mm -45mm, scalable to -60mm • Oversize +45mm to secondary cone crusher • LDR and DMS tails +6mm -19mm to tertiary High Pressure Grinding Rolls Cap-ex (Direct Costs, without Capitalized Op-ex) • Jan 2013 Cap-ex without LDR: $162.7m • Optimized Cap-ex with LDR: $147.1m Thickening and centrifugal treatment of fines and tails to create a truckable product for dry-stack disposal. Diamond Processing Plant Represents Single Largest Cap-ex Item and Critical Path for Overall Construction
  • 20. 20 Site Progress Live Updates on Process Plant Construction at www.stornowaydiamonds.com Plant Footprint, Oct 21, 2014 First Concrete Pour, April 7, 2015 Project’s critical path item Concrete (7 April) steel (14 June) Building closure scheduled for October 2015 Plant, June 4, 2015
  • 21. 21 Site Progress Concrete Pouring on Major Facilities Commenced Ahead of Schedule April 2015 Maintenance Shed May 12, 2015 Maintenance Shed, April 20, 2015 Structural Steel Erection June 3, 2015
  • 22. 22 Open Pit Mining Renard 2 – Renard 3 Pit Pre-stripping Commenced March 2015 R2-R3 Pre-Strip, March 5, 2015 Open Pit Mining Team, March 5, 2015 R2-R3 R65 Portal R2-R3 Pit, May 23, 2015 Decline Ventilation, May 10, 2015R2-R3 Pit Pre-Strip, June 4, 2015 Mining Progress as of Apr 30 2015 (FY15 Q4) 1.61m tonnes moved at R65 against plan of 1.21m (133%) 0.28m tonnes moved at R2-R3 against plan of 0.52m (54%)
  • 23. 23 Underground Mining Renard 2 – Renard 3 Pit Pre-stripping Commenced March 2015 R2-R3 Pre-Strip, March 5, 2015 Jumbo in Decline, May 25, 2015 Decline Ventilation, May 10, 2015 R2-R3 R65 Portal Decline Progress as of Apr 30 2015 (FY15 Q4) 55m against plan of 95m (58%) 233m against plan of 295m by June 15 (79%)
  • 24. 24 Project Schedule Based on Construction Mobilization July 10th 2014 Feasibility Study (Complete) ESIA (Complete) Public Hearings (Complete) Reg. Authorizations (Complete) Specific Operating Permits (50) Road Construction (Complete) Project Financing (Complete) Detailed Engineering Site Construction Commissioning and Ramp-up Commercial Production 2012 2H 2H 2H 2H2H 1H 1H 1H1H 2013 2014 2015 2016 2H1H 2017 Based on the Renard Diamond Project Construction Schedule, Plant Commissioning is Planned for H2 2016 and Commercial Production in Q2 2017. June 2015 First Vehicle Access Completion Status as of Apr 30 2015 (FY15 Q4) Overall Construction: 22.4% (planned 21.7%) Engineering Progress: 56% (planned 62%)
  • 26. 26 Shareholding Share Price (TSX-SWY): June 19, 2015 C$ $0.83 52 week High-Low C$ $0.46–$0.85 Average Daily Volume: Last 12 Months 637,729 Average Daily Volume: Since July 8th 2014 613,682 Market Capitalization: C$ 608 million Total Shares Outstanding: 732 million Total Options & Warrants Outstanding: (28.2m Options $0.59-$5.36; 123.8m warrants $0.90-$1.21) 152 million Consolidated Cash1: (as of April 30, 2015) C$ 364 million Consolidated Debt1: (as of April 30, 2015) C$ 208 million Undrawn Financing Commitments2: (Subject to Financing Agreement CPs) C$ 352 million Balance Sheet Balance Sheet and Capital Structure Notes 1. Audited 2. Assuming a C$:US$ conversion rate of C$1.10 Investissement Québec 28.6% 22.7% Orion Mine Finance 19.5% 17.5% CDPQ 6.1% 6.2% Float 45.8% 53.6% DilutedBasic
  • 27. 27 Sources and Uses of Funds to April 30, 2015(1) On Current C$:US$ Exchange Rates (all amounts in millions of C$) Assumed Actual use of Proceeds to April 30, 2015 Renard Diamond Project Capital Expenditures 811 177 Route 167 Extension (2) 70 70 Financing Costs, Interest during Construction 58 18 Mine Closure Guarantee (2) 16 2 Pre-production Net Revenue (26) - Total Project Costs 929 267 General Corporate Purposes Equity fees and transaction costs 18 23 General working capital, administrative and salary expenses 14 6 Total Uses 961 296 Costs Notes 1. Unaudited 2. The total amount borrowed pursuant to the Renard Mine Road loan was $77 million, of which $70 million was used for construction of the Renard Mine Road and $7 million was used for civil works related to the airstrip. Costs related to the airstrip were included in the $811 million capital expenditures line in the table above. 3. Assuming a C$:US$ conversion rate of C$1.21 (all amounts in millions of C$) Sources of Funds Stream Deposits not yet received(3) 206 Senior Loan Facility, Tranche A 100 Senior Loan Facility, Tranche B 20 Cost Overrun Facility 28 Equipment Financing Facility(3) 18 Cash, cash equivalent and short term investments 364 Receivables 16 Capital Resources Available 752 Estimated Cost to complete Renard Project, including contingencies and escalation (665) Excess funding available including cost overrun facilities – as at April 30, 2015 87 Sources and Uses
  • 28. 2828 Appendix 1: Stornoway’s C$946M Project Financing for Renard
  • 29. 29 Renard Project Financing Transaction Structure Type Amount (% of Total) Description Common Equity C$374M (40%) • C$132M marketed public equity offering of subscription receipts • C$242M private placement to Orion (US$110M), RQ (C$100M) and Caisse (C$22M) Diamond Stream US$250M (29%) • 20% diamond stream (Orion 16%, Caisse 4%) with ~US$56/ct(1) ongoing payment Convertible Debentures US$81M (9%) • Provided by Orion; 7 year, 6.25% coupon, 35% conversion premium to equity issue price Senior Debt C$120M (11%) • Provided by IQ; 7 year amortizing payment, Fixed (QC Bond)+5.75% or Prime +4.75% Equipment Financing US$35M (4%) • Provided by Caterpillar Cost Overrun Facility C$48M (5%) • C$20M provided by IQ (same terms as senior debt) • C$28M provided by Caisse (unsecured, 7 year term, 10% coupon) Total C$946M (100%) Assumes US$1.00 = C$1.10 1. Includes reimbursement of marketing expenses Counter-Party Amount (% of Total) Orion Mine Finance C$367M (39%) Investissement Québec/ Ressources Québec C$240M (25%) Caisse de dépôt et placement du Québec C$105M (11%) Caterpillar Financial C$39M (4%) Public C$195M (21%) Total C$946M (100%) C$77M C$811M C$946M C$70M C$67M Financing Funding Requirements New Financing Existing Financing C$48M COF & C$27M Working Capital Financing Costs & Interest During Construction Renard Mine Road Initial Capex & Escalation Allowance
  • 30. 30 Top 15 Equity Offerings 2015 YTD, 2014 and 2013 With the Exception of Barrick in 2013, 2014 Saw Larger Equity Financings Than 2013 2015 YTD 2014 2013 Source: Company disclosure. Issuer Date Size ($ MM) Issuer Date Size ($ MM) Issuer Date Size ($ MM) First Quantum May-15 C$1,437.5 Lundin Oct-14 C$674.2 Barrick Oct-13 US$3,000.2 Silver Wheaton Mar-15 US$800.0 Franco Nevada Aug-14 US$500.4 Detour Gold May-13 C$176.1 Romarco Jan-15 C$300.0 Primero Mar-14 C$224.3 Platinum Group Metals Dec-13 C$175.2 Yamana Jan-15 C$260.2 Fortress (Lundin Gold) Oct-14 C$200.0 Allied Nevada Apr-13 US$150.5 Osisko Royalties Jan-15 C$200.0 HudBay Jan-14 US$172.7 Ivanhoe Mines Sep-13 C$108.0 Detour Gold Jan-15 C$140.8 Detour Gold Feb-14 C$172.5 Guyana Goldfields Jan-13 C$100.0 Mountain Province Diamonds Mar-15 C$95.0 Torex Gold Jan-14 C$143.8 Paladin Energy Aug-13 C$81.6 SEMAFO Feb-15 C$50.3 Ivanhoe Mines May-14 C$143.8 Banro Corporation Mar-13 US$67.8 Asanko Gold Jan-15 C$40.0 Stornoway Apr-14 C$132.0 Trevali Mining Nov-13 C$46.0 Richmont Mines Jan-15 C$34.0 Rubicon Minerals Feb-14 C$115.1 SantacruzSilver Jan-13 C$40.4 Rubicon Minerals Mar-15 C$30.2 Platinum Group Metals Sep-14 US$113.8 Sulliden Gold Sep-13 C$40.1 First Majestic Apr-15 C$30.0 MAG Silver Jun-14 C$79.0 Colossus Minerals Jul-13 C$38.0 Kaminak Gold Feb-15 C$21.0 Mountain Province Diamonds Sep-14 C$75.0 NGEx Resources Jan-13 C$34.0 Trevali Mining May-15 C$20.0 Pretium Jul-14 US$69.0 Copper Mountain Mining Nov-13 C$30.1 Lydian International Jan-15 C$16.5 Altius Minerals Apr-14 C$65.0 Mountain Province Diamonds Nov-13 C$29.4
  • 31. 31 Issuer Date Size ($ MM) Coupon Rate (%) Term (Years) Description Imperial Metals Sep-14 C$115.0 6.00% 6 Convertible Senior Unsecured Debentures Stornoway Feb-14 US$81.3 6.25% 7 Convertible Unsecured Subordinated Debentures Primero Mining Jan-15 US$75.0 5.75% 5 Convertible Unsecured Subordinated Debentures 5N Plus May-14 US$66.0 5.75% 5 Convertible Unsecured Subordinated Debentures Banro Jun-14 US$40.0 8.00% 3.5 Convertible Preferred Shares North American Palladium Apr-14 C$30.0 7.50% 5 Convertible Unsecured Subordinated Debentures North American Palladium Mar-14 C$27.5 7.50% 5 Convertible Unsecured Subordinated Debentures Argex Titanium Jan-14 C$7.5 8.00% 5 Convertible Unsecured Subordinated Debentures Issuer Date Size ($ MM) Coupon Rate (%) Term (Years) Description First Quantum Minerals May-14 US$850.0 7.25% 8 Senior Secured Notes Lundin Oct-14 US$550.0 7.50% 6 Senior Secured Notes Goldcorp Jun-14 US$549.3 3.63% 7 Senior Unsecured Notes China Gold Jul-14 US$500.0 3.50% 3 Guaranteed Corporate Bond Cameco Jun-14 US$499.8 4.19% 10 Senior Unsecured Debentures Yamana Gold Jun-14 US$499.5 4.95% 10 Senior Unsecured Notes Lundin Oct-14 US$450.0 7.88% 8 Senior Secured Notes Goldcorp Jun-14 US$447.8 5.45% 30 Senior Unsecured Notes Imperial Metals Mar-14 US$325.0 7.00% 5 Senior Unsecured Notes AuRico Mar-14 US$304.1 8.50% 6 Senior Secured Second Lien Notes HudBay Jul-14 US$181.9 9.50% 6 Senior Unsecured Notes Stornoway Apr-14 C$120.0 Prime + 4.75% 10 Senior Secured Loan Trevali Mining May-14 US$52.5 12.50% 5 Senior Secured Notes Select Recent Debt & Convert Offerings Debt Issuances Convertible Debt Issuances Source: Company disclosure.
  • 32. 32 Investor - Issuer Date Size ($ MM) Description Franco-Nevada - Lundin Oct-14 US$648 Franco-Nevada to receive 68% of payable Au and Ag production until 720k oz Au and 12MM oz Ag are delivered from 100% of Candelaria; thereafter reduces to 40% of LOM payable metals from 100% of the mine. Acquisition financing package also consists of C$50MM private placement exclusive of stream value. Orion Mine Finance & Caisse de dépôt - Stornoway Apr-14 US$250 Stream agreement for 20% interest on run of mine diamond production from certain kimberlite bodies from the Renard Project. Investors to pay the Issuer in 3 deposits. Gold Holding - Banro Aug-14 US$121 Streams on Banro's Tw angiza and Namoya mines for US$41MM and US$80MM, respectively. Investor to receive 40k oz Au from Tw angiza mine over 4 years. Investor to also receive 10% LOM Au production from Namoya including Au processed at the site from other mines w ithin 20 km; maximum deliverable Au of 12k oz per annum. Franco-Nevada & Sandstorm - True Gold Aug-14 Up to US$120 Franco-Nevada (75%) & Sandstorm (25%) to receive 100k oz Au over 5 years, and 6.5% LOM Au production from True Gold's Karma Project thereafter. True Gold holds an 18 month option to increase funding by US$20MM for an additional 30k oz Au. Ongoing payments of 20% of spot Au. Royal Gold - Rubicon Feb-14 US$75 Royal Gold to receive 6.3% of Au production from Rubicon's Phoenix Project until 135k oz have been delivered and 3.15% LOM Au production thereafter. Ongoing payments of 25% spot Au. Advance deposit payments from Royal Gold payable in 5 installments. Orion Mine Finance - Aldridge Aug-14 US$40 Consists of US$5MM private placement and US$35MM 2-year bridge loan facility. Bridge loan bears interest at 9% plus the greater of 3 month USD LIBOR and 1%. Aldridge also entered into offtake agreements w ith Orion for ~20% of Pb & ~50% of Au production over the first 10 years of the mine plan. Franco-Nevada - Klondex Feb-14 US$35 Franco-Nevada to receive 38k oz Au by December 31, 2018, and a 2.5% NSR royalty on Klondex's Fire Creek and Midas properties commencing 2019. Gold financing package provided to support Klondex's acquisition of the Midas Mine and Mill Complex from New mont. JMET - Santacruz Silver Sep-14 US$28 5-year pre-paid forw ard silver purchase agreement. JMET to receive 4.6MM oz Ag through August 2019 w ith no ounces delivered over the first 12 months. Ongoing payments of spot Ag less an undisclosed fixed discount. Quintana - Arian Silver Oct-14 US$16 Quintana to receive 78.2% of Zn and Pb from San José until 32MMlbs and 38MMlbs, respectively, are delievered, and 27.4% thereafter for 50 years. Issuer can buy 50% of stream for US$11MM before 2017. Investor also acquires US$16MM of senior secured convertible notes to be restructured into new notes (8% interest). Orion Mine Finance - Claude Mar-14 US$12 3.0% NSR royalty on Claude's Seabee Gold Operation. The NSR provides Claude w ith the option to repurchase half of the NSR for US$12MM until December 31, 2016. BlackRock - Avanco Jul-14 US$12 2.0% NSR royalty on Cu; 25.0% NSR royalty on Au and 2.0% NSR royalty on all other metals produced from the Issuer's Antas North and Pedra Branca licensed areas. Additionally, BlackRock to receive a 2% NSR Royalty on other discoveries w ithin Avanco's current licence portfolio. Sprott - Veris Gold Apr-14 US$8 0.5% NSR royalty on Veris Gold's Jerritt Canyon mines and processing plant. Select Recent Alternative Finance Agreements Sourc: Company disclosure.
  • 33. 3333 Appendix 2: Renard Technical Data
  • 34. 34 Probable Mineral Reserve Mining Recovery Factors Utilized in the Reserve Calculation Kimberlite Grade (cpht) Tonnes (millions) Contained Carats (Millions) Internal Dilution Mining Recovery Mining Dilution Renard 2 OP 95 1.31 1.24 0.0% 96.0% 7.1% Renard 2 UG 80 17.03 13.62 7.0% 82.4% 20.2% Renard 3 OP 93 0.72 0.67 0.0% 96.0% 10.5% Renard 3 UG 84 1.00 0.84 21.1% 85.0% 14.0% Renard 4 UG 42 3.72 1.58 1.4% 78.2% 14.0% Total 75 23.79 17.95 5.9% 82.9% 17.9% Notes: Reserve categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Totals may not add due to rounding. Grades are estimated at a +1DTC sieve size cut-off. R2 , 83% R3, 8% R4, 9% Revenue R2 , 77% R3, 7% R4, 16% Tonnage R2 , 83% R3, 8% R4, 9% Carats NI 43-101 Probable Mineral Reserves January 28th 2013
  • 35. 35 Notes: Resource categories are compliant with the "CIM Definition Standards on Mineral Resources and Reserves". Mineral resources that are not mineral reserves do not have demonstrated economic viability. Indicated Mineral resources are Inclusive of the Mineral Reserve. Totals may not add due to rounding. Grades are estimated at a +1DTC sieve size cut-off. Renard NI 43-101 Mineral Resources July 23rd 2013 Kimberlite Grade (cpht) Tonnes (millions) Contained Carats (Millions) Renard 2 – Total 100 18.58 18.66 Renard 2 104 17.71 18.38 Renard 2 CRB-2a 32 0.87 0.28 Renard 3 103 1.76 1.82 Renard 4 60 7.25 4.31 Renard 65 29 7.87 2.30 Total Indicated 76.4 35.45 27.09 Renard 2 – Total 64 11.77 7.47 Renard 2 119 5.23 6.23 Renard 2 CRB 19 6.54 1.24 Renard 3 112 0.54 0.61 Renard 4 50 4.75 2.37 Renard 9 53 5.70 3.04 Renard 65 24 4.93 1.18 Lynx Dyke 107 1.80 1.92 Hibou Dyke 144 0.18 0.26 Total Inferred 56.8 29.67 16.85
  • 36. 36 Notes: The potential quantity and grade of any exploration target (previously referred to as “potential mineral deposit”) is conceptual in nature, and it is uncertain if further exploration will result in the target being delineated as a mineral resource. The exploration upside for the Renard kimberlite pipes has been determined by projecting reasonable kimberlite volumes from the base of the inferred Resource to a depth of 700m below surface. In the case of the Lynx and Hibou dykes, the exploration upside was established on the basis of known drill intersections of kimberlite for which insufficient diamond sampling exists to adequately estimate a diamond resource grade. Target for Further Exploration July 23rd 2013. Changes to Previous January 2011 Estimates in Italics Kimberlite Grade (cpht) Tonnes (millions) Contained Carats (Millions) Renard 2 104 to 158 4.0 to 4.6 4.2 to 7.3 Renard 3 105 to 168 0.8 to 1.7 0.8 to 2.8 Renard 4 50 to 77 11.1 to 15.4 5.6 to 11.8 Renard 9 52 to 68 3.9 to 6.3 2.0 to 4.3 Renard 65 25 to 33 29.0 to 40.9 7.3 to 13.5 Lynx Dyke 96 to 120 3.1 to 3.2 3.0 to 3.8 Hibou Dyke 104 to 151 2.7 to 2.9 2.9 to 4.3 Total Exploration Upside 54.6 (-0.8%) to 74.9 (-0.8%) 25.7 (+9.1%) to 47.8 (-1.4%)
  • 37. 37 Chronology of Renard Studies Feasibility Study Released on November 16th 2011. NI 43-101 Technical Report filed December 29 2011. 11 Year Mine Plan based on 18 Mcarat Mineral Reserve derived from January 2011 NI 43-101 Resource. Long Term Business Plan Companion study to the Feasibility Study with an extended mine plan incorporating the project`s 17.5 million carats of Inferred Mineral Resources. Basis of overall mine design and project permitting. Not part of the project`s public disclosure, consistent with Canadian reporting standards Optimization Study Released on January 28th, 2013. NI 43-101 Technical Report filed March 2013. Refined of Feasibility mine design, including shaft deferral and a modified underground mining sequence. 11 Year Mine Plan based on 17.9 million carat Mineral Reserve. Resource Update Released July 2013. NI 43-101 Resource update with 14% increase in Indicated Resource contained carats LNG Feasibility Study Released October 2013. Modified project Cap-ex and Op-ex for LNG powered gen-sets
  • 38. 38 January 2013 Optimization Study Project Assumptions, Valuation and Pay-Back in the January 2013 FS Optimization Study Key Assumptions in the Financial Model1 Mining Parameters Reserve Carats (M) 17.9 Tonnes Processed (M) 23.8 Recovered Grade (cpht) 75 Average Ore Recovery (%) 82.9% Average Mining Dilution (%) 17.9% Dilution Grade (cpht) 0 Processing Rate (Mtonnes/annum) 2.2 Mine Life (years) 11 Cost Parameters Initial Cap-ex (C$M)2 $752 LOM Cap-ex (C$M)4 $1,013 Oil Price (US$/barrel)2 $95 LOM Op-ex (C$/tonne)2 $57.63 LOM Op-ex (C$/carat)2 $76.63 Revenue Parameters Gross Revenue (C$M)2 $4,268 Marketing Costs 2.7% DIAQUEM Royalty 2.0% Cash Operating Margin (C$M)2 $2,693 % Operating Margin 67% Income Tax, Mining Duties and IBA Payments (C$M)1 $625 After Tax Net Cash Flow (C$M) $1,084 Diamond Price Parameters3 Renard 2 and Renard 3 (US$/carat) $182 Renard 4 (US$/carat) $164 Diamond Price Escalation 2.5% Exchange rate 1C$=1US$ Schedule Parameters Effective Date for NPV Calculation Jan. 1 2013 Construction Mobilization/Early Works Aug. 1 2013 Plant Commissioning Commences Dec. 1 2015 Commercial Production Declared Jun. 1 2016 Valuation Results5 (C$m) Pre-Tax After Tax NPV5% $894 $537 NPV7% (Base Case) $683 $391 NPV9% $514 $274 IRR 20.4% 16.3% Pay-Back (years) 4.69 4.82 Notes 1. Optimization Study, released January 28th 2013. 2. Expressed in October 2012 terms. 3. Expressed in May 2011 terms. 4. Expressed in nominal terms. 5. Expressed in de-escalated nominal terms.
  • 39. 39 Liquefied Natural Gas Power Plant The Renard Diamond Project will be powered using Liquid Natural Gas (“LNG”) fuelled gen-sets, with daily supplies of cryogenic LNG from GazMetro in Montreal utilizing the Renard Mine Road. The Renard LNG plant will comprise seven 2.1MW rated gas gen-sets, providing sufficient power generation capacity for the project’s normal operating specification of 9.5MW. LNG has significant cost and environmental advantages over traditional diesel powered gen-sets and a Hydro-Quebec power-line option. Diesel will continue to be used for the mobile mining fleet and construction activities.
  • 40. 40 Liquefied Natural Gas Power Plant Feasibility Study Released October 2013 An LNG fuelled powerplant for Renard offers many advantages over diesel: • Greatly reduced annual operating costs of $8m to $10m per year, for a small incremental capital cost of $2.6m. • Up to 43% less greenhouse gas emissions. • stable supply market utilizing existing commercial distribution network within Québec. • Elimination of on-site propane, as LNG will be used for building and underground mine heating Cost Improvements with LNG 2013 Optimization Study with Diesel 2013 Optimization Study with LNG Unit Power Cost (C$/kWh) 1 $0.299 $0.188 (-37%) Unit Operating Cost (C$/tonne) 1,2 $57.63 $53.84 (-7%) Initial Capital Cost (C$m) 1 $752.1 $754.0 (+0.3%) Life of Mine Capital Cost (C$m) 1,3 $1,013 $1,010 (-0.3%) Annual Diesel Consumption (million litres) 27.5 5.9 (-79%) Annual LNG Consumption (thousand m3 /annum) n/a 41.7 Annual Propane Consumption (thousand m3 /annum) 3.5 n/a Notes 1. 2013 Optimization Study costs expressed in October 2012 terms. 2. Excludes capitalized preproduction costs. 3. Includes all initial, sustaining and deferred capital, contingencies and escalation Key Assumptions Based on the 11 year reserve-based mine life (17.9 mcarats) contained within the 2013 Optimization Study, with a normal operating load of 9.49MW, C$1=US$1, Oil US$95/barrel
  • 41. 4141 Appendix 3: The Diamond Market
  • 42. 42 Major Diamond Mines and Development Projects Worldwide Few Enough Mines to Fit on One Map South Africa • Venetia (De Beers) • Finsch, Cullinan, Kimberley (Petra Diamonds) • Lace (DiamondCorp) Tanzania • Williamson (Petra Diamonds) Russia • Arkhangelsk District (Alrosa) • Yakutia District (Alrosa) • Grib (LUKOIL) India • Bunder (Rio Tinto) Australia • Argyle (Rio Tinto) • Ellendale (Kimberly Diamonds) Canada • Ekati (Dominion) • Diavik (Rio Tinto/Dominion) • Victor, Snap Lake, Gahcho Kué (De Beers) • Renard (Stornoway) • Fort a la Corne (Shore Gold/Newmont) Botswana • Jwaneng, Orapa (De Beers) • Ghaghoo (Gem Diamonds) • Karowe (Lucara Diamonds) Angola • Catoca (Alrosa) Democratic Republic of Congo • Mbuyi-Mayi Sierra Leone • Koidu, (Steinmetz Group) Lesotho • Letseng (Gem Diamonds) • Kao (Namakwa Diamonds) • Liqhobong (Firestone) • Mothae (Lucara)
  • 43. 43 The Diamond Pipeline An Industry with Many Intermediaries Source: Tacy D.I.B. 2015 Mine Production Rough Trading and Diamond Polishing Diamond Jewelery Production Cost Production Value Mine Sales to Industry Rough Sales To Cutting Centres Value of Polished Produced Value of Diamonds in Retail Jewelery Sales Retail Sales Of Diamond Jewelery Value in US$B terms of each stage of the diamond pipeline $6.9B $16.5B $16.7B $16.7B $22.3B $23.0B $78.5B Estimated Average Margins after Costs (%) Rough Mining: 0 to 50% Rough Dealing: 0 to 10% Polishing: -10 to 15% Jewelery Manufac: -10 to 10% Jewelery Retail: 20 to 50%
  • 44. 44 A Snapshot of Rough Diamond Supply Industry Supply Themes 146mcarats produced in 2013 (US$18b) No return to peak diamond production of 176mcarats achieved in 2005 Maximum 20mcarats new production on deck assuming all new projects meet proponents published production and schedule estimates Consensus forecast of 2% supply CAGR (in carat terms) to 2018, declining thereafter Potential or Actual New Projects Rough Diamond Supply Sources The Global Diamond Report, December 2014: Bain & Co/Antwerp World Diamond Centre The Diamond Insight Report, September 2014: McKinsey/De Beers
  • 45. 45 A Snapshot of Rough Diamond Demand Rough Diamond Demand Supply and Demand Industry Demand Themes Diamond jewelry/polished diamond demand growth tied to GDP growth in principal markets Diamond jewelry sales strongly correlated to market demographics (age, gender, wealth) US still dominant polished diamond market (40% in 2013, 2% CAGR 2008-13) with China the growth market (15% in 2013, 20% CAGR 2008-13) Consensus forecast of c.5% rough demand CAGR (in dollar terms) over next 10 years Consensus forecasts of 2-4% real rough diamond price CAGR over next 10 years given supply/demand imbalance Sources The Global Diamond Report, December 2014: Bain & Co/Antwerp World Diamond Centre The Diamond Insight Report, September 2014: McKinsey/De Beers
  • 46. 46 Rough Diamond Pricing 2009-2015 A tracking of the diamond market since the publication of the November 2011 FS and January 2013 Opt. FS indicates rough diamond prices have generally remained within the bounds of sensitivities contained within the FS financial model (May 2011 spot prices and a 2.5% real terms annual price escalator). WWW Rough Diamond Price Index COMEX Gold May 2011 FS Diamond Valuation 50 100 150 200 250 300 350 1-Jan-09 1-Jan-10 1-Jan-11 1-Jan-12 1-Jan-13 1-Jan-14 1-Jan-15 Indexto2009=100 WWW Rough Index, CPI Adjusted Renard Model Price Growth FS 2.5% Price Model (Nominal, adjusted for CPI) with +/- 10% Sensitivity
  • 48. 48 Hume Kyle Independent Pat Godin COO & Director Matt Manson President, CEO & Director John LeBoutillier Independent/ IQ Designate Monique Mercier Independent/ IQ Designate Peter Nixon Independent Ebe Scherkus Independent/ Board Chairman Executive Officers Non-Executive Directors Key Managers Head Office: Longueuil, Québec Exploration Office: North Vancouver, BC Community Offices: Mistissini & Chibougamau Québec Stornoway’s Board and Management Team Serge Vézina Independent Yves Perron VP Engineering & Construction Ghislain Poirier VP Public Affairs Brian Glover VP Asset Protection Martin Boucher VP Sustainable Development Robin Hopkins VP Exploration Orin Baranowsky Director, IR Douglas Silver Orion Designate Ian Holl VP Processing Annie Torkia- Lagacé VP Legal Affairs Gaston Morin Independent/ IQ Designate Jean-Charles Dumont VP Finance Helene Robitaille Director, HR
  • 49. 49 Pat Godin COO & Director Biographies Ebe Scherkus Chairman of the Board Matt Manson was appointed President of Stornoway Diamond Corporation in March 2007 and subsequently President & CEO in January 2009. Between 1999 and 2005 he was employed by Aber Diamond Corporation (now Dominion Diamond Corporation) as VP Marketing and subsequently VP Technical Services & Control, during which time he participated in the US$230m project financing for the Diavik Diamond Project and oversaw Aber's technical and marketing operations. Mr. Manson is a graduate of the University of Edinburgh (BSc Geophysics, 1987) and the University of Toronto (MSc Geology 1989 and PhD Geology, 1996), and has over 18 years of experience in diamond exploration, development and production. Pat Godin joined Stornoway as COO in May 2010. He was previously VP, Project Development for GMining Services, responsible for the development of the Essakane Mine in Burkina Faso under contract to IAMGOLD, VP Operations for Canadian Royalties, and President and General Manager of CBJ-CAIMAN S.A.S., a French subsidiary of Cambior / IAMGOLD. For many years, he was involved in Cambior’s various Canadian properties in Abitibi-Témiscamingue, through progressive management positions in project development and mine management. He holds a bachelor’s degree in mining engineering from Université Laval in Québec and is a member of the “Ordre des Ingénieurs du Québec”. He is the Chairman of the Board of Geomega Resources and a director of Orbit-Garant Drilling. Mr. Scherkus served as the President and Chief Operating Officer and a director of Agnico-Eagle from 2005 to February 2012. Prior to his appointment as President and Chief Operating Officer in December 2005, Mr. Scherkus served as Executive Vice-President and Chief Operating Officer from 1998 to 2005, as Vice- President, Operations from 1996 to 1998, as a manager of Agnico Eagle LaRonde Division from 1986 to 1996 and as a project manager from 1985 to 1986. Mr. Scherkus is a graduate of McGill University (B.Sc.), a member of the Association of Professional Engineers of Ontario and past president of the Québec Mining Association. He is Chairman of the Board of Premier Gold Mines Ltd. Matt Manson President, CEO & Director
  • 50. 50 Stornoway Diamond Corporation TSX:SWY Head Office: 1111 Rue St. Charles Ouest, Longueuil, Québec J4K 4G4 Tel: +1 (450) 616-5555 IR Contact: Orin Baranowsky, CFA, Director IR obaranowsky@stornowaydiamonds.com Tel: +1 (416) 304-1026 x3 www.stornowaydiamonds.com Info@stornowaydiamonds.com